DELHI METRO RAIL CORPORATION LIMITED

No. DMRC/20/III-502/2018 Date: 11.05.2021

Correction Slip No. 2


Sub.: Correction Slip No. 2 to General Conditions of Contract (Nov, 2019)

Sub-Clause 11.3.1 of Clause No. 11.3 (Provisional Payment Against Material at Site) is revised as
follows:
Clause No. Sub- Existing Clause Revised Clause
Clause

11.3 11.3.1 A provisional payment on account of A provisional payment on account of


(Provisional main construction materials required main construction materials required
Payment for the Permanent Works, shall be for the Permanent Works, shall be
Against paid on request of the Contractor paid on request of the Contractor
Material at after these materials are brought to after these materials are brought to
Site) Site, against an Indemnity Bond in a Site, against an Indemnity Bond in a
form acceptable to Employer is duly form acceptable to Employer is duly
executed. The payment shall be executed. The payment shall be
limited to 80% of the actual value or limited to 80% of the actual value or
assessed value of these materials assessed value of these materials
and the total of such provisional and the total of such provisional
payment on account of construction payment on account of construction
materials at a time shall be limited to materials at a time shall be limited
three percent of Original Contract to three percent of Original Contract
Value or likely average consumption Value or likely average consumption
of such materials for three months, of such materials for three months,
whichever is less and at any time whichever is less and at any time
the total outstanding provisional the total outstanding provisional
payment against material at site payment against material at site
shall not exceed four percent of the shall not exceed four percent of the
Original Contract Value. The Original Contract Value. The
valuation of the average valuation of the average
consumption of such main consumption of such main
construction materials shall be construction materials shall be
approved by the Engineer, whose approved by the Engineer, whose
decision shall be final. Materials decision shall be final.
which are of perishable nature should
be adequately insured.

This is issued with the approval of MD.

(R. K. Gupta)
Sr.GM/Contract
1. All EDs, PDs, CGMs, HODs, CPMs, CVO & GM/Legal
2. GM/IT: For uploading on intranet please

Copy to:
1. DP, DW, DF, DE, DBD, DO & DRS.
2. OSD to MD- For kind information to MD please.