Professional Documents
Culture Documents
Civil Engineers
Bridge Engineering 158
June 2005 Issue BE2
Pages 63 –69
Paper 13989
Received 13/10/2004
Accepted 31/01/2005
Keywords:
bridges/composite structures/ Oliver John Riches Neil Alexander Carstairs Anthony E. K. Jones
design methods & aids Senior Engineer, Arup Scotland, Associate, Arup, Newcastle Associate Director, Arup Research
West Lothian, Scotland upon Tyne and Development, London
Fully integral composite bridges provide a cost-effective skew span varying from 33.0 m to 34.7 m. The bridge
solution in many situations. The connection between the deck is 27 m wide, with 2 m verges and a carriageway up to
steel girders and a reinforced concrete abutment at the 23 m wide.
position of maximum shear, moment and axial force does
however pose a significant design challenge. Following This paper describes the development and implementation of this
earlier experience with checking a design using the connection detail, using Boathouse Bridge as a case study for its
method described in SCI report 180, the authors have design, fabrication and construction.
developed an alternative connection detail, which has so
far been successfully used on two projects. This greatly
simplifies the transfer of forces at the connection and 2. BEAM – ABUTMENT CONNECTION LOAD PATHS
improves buildability significantly. Further research by
The transfer of bending moments, shear and axial forces from the
the authors was carried out to identify the pitfalls
deck to the abutment and the interaction of these load effects is
when designing to current practice and to develop
complex and the authors recognised that this would best be
rigorous analysis, design and detailing rules that
justified using a strut-and-tie analysis of the load paths through
ensure the effectiveness of the design of this new
the connection.
connection. This paper describes the connection and its
application to Boathouse Bridge over the A66 in
Schlaich and Schaefer1,2 have proposed a unified design
Stockton-on-Tees.
approach for reinforced concrete structures that recognises that
classic beam theory used for design of elements is only valid for
certain regions of the structure. Simple rules are provided to
1. INTRODUCTION identify ‘B’ regions (standing for Bernoulli or beam) where beam
Composite steel girder concrete deck bridges are a cost-effective theory is valid and ‘D’ regions (discontinuity), for which beam
solution for medium spans (e.g. motorway and dual carriageway theory is not valid (i.e. a linear distribution of strain across the
bridges). This form of construction offers additional advantages section cannot be assumed). The connection between the deck
including easy assembly of girders on site, rapid erection and and abutment clearly falls into the category of a ‘D’ region
construction and the minimisation of disruption to traffic. (Fig. 2). Schlaich and Schaefer also propose simple strut-and-tie
Further benefits can be achieved by providing a fully integral models to model the behaviour at these ‘D’ regions in a
bridge, such as minimising long-term maintenance requirements, manner analogous to the Morsch strut-and-tie models used for
and reducing the extent of foundation works. the ultimate limit state design of beams for bending and shear.
Reinforcement is provided along the lines of the ties and
Connecting steel girders to a reinforced concrete abutment at the anchored within or past the nodes in the model and the struts go
position of maximum shear, moment and axial force does pose a through the concrete. The size of the struts and the areas of
significant design challenge. To this end an innovative reinforcement can be calculated directly from the forces in
connection detail has been developed which ensured a robust and the model.
effective design and simplified construction on site for Boathouse
Bridge a single-span composite, integral bridge. For a reinforced concrete deck to abutment connection a simple
strut-and-tie model can transfer the loads through this region
Boathouse Bridge is part of a grade-separated interchange (Fig. 3).
and carries the South Stockton Link Road over the existing
A66 dual two-lane carriageway and a slip road. It was For the composite deck beam to abutment connection, the design
designed for Birse Civils Ltd by Arup as part of a successful method in SCI Report 1803 relies on shear connectors and
design-and-build tender for Stockton-on-Tees Borough Council transverse reinforcement to transfer the bottom compressive
for Phase 2 of the link road, which included another highway flange forces into the concrete and then transfers the
bridge, twin railway tunnels through a road embankment, and concentrated bending moment applied by the beams into a
associated retaining walls and embankments. Boathouse Bridge uniform moment on the abutment wall using torsion in the
(Fig. 1) crosses the A66 at an 188 skew, with a single clear concrete.
Bridge Engineering 158 Issue BE2 A simplified integral composite bridge connection Riches et al. 63
Downloaded by [ Newcastle University] on [24/09/16]. Copyright © ICE Publishing, all rights reserved.
Fig. 1. Construction of Boathouse Bridge
d1 d1
D B D
d2
B d2
D d2
Fig. 2. Typical ‘B’ and ‘D’ regions in an integral bridge Fig. 4. Proposed connection detail
64 Bridge Engineering 158 Issue BE2 A simplified integral composite bridge connection Riches et al.
Downloaded by [ Newcastle University] on [24/09/16]. Copyright © ICE Publishing, all rights reserved.
connection within the boundary can then be clearly defined and
used to justify a robust, well-detailed deck abutment connection.
This also leads to significant reductions in reinforcement density Top flange tie
and complexity at the connection.
The model used assumes that the shear forces found at the
boundary are transferred to the abutment by a tension tie to the
Top flange tie
top flange at the end of the girder. This approach allows a simple
and safe model to be developed which has the following
advantages.
(a) It simplifies the arrangement of struts at the node behind the Fig. 6. Plan view of transfer of compression force in flange to
bearing plate and allows the vertical component of the shear reinforcement in deck
to be transferred to the concrete below the top flange, instead
of in the highly stressed area at this node.
(b) It utilises the web in tension, similar to the tension field 3.3. Resolving forces behind the bearing plate
action assumed by BS 5400 Part 35 to calculate the ultimate The zone behind the bearing plate is highly stressed and care is
shear capacity of the web. required to accurately identify the principal stresses resulting
from the various struts that converge on this zone.
In three dimensions, the diagonal struts are inclined to spread the
concentrated loads from the bearing plate into uniform load on To this end the node has been split as shown in Fig. 7 and
the reinforcement in the abutment wall and deck, with a tie described in detail by Schlaich and Schaefer.2 Note that the split
formed by transverse reinforcement at the top of the abutment has to be perpendicular to one of the adjacent struts (reactions)
wall (Fig. 6). which itself joins the node at a face perpendicular to its direction.
This is permissible as long as the vertical and horizontal
The change in the force in the girder top flange, going from stresses are the principal stresses and hence there is no shear
tension (due to bending) to compression (due to the horizontal across the cut.
component of the tie carrying shear in the web), is transferred
conventionally through shear connectors and transverse
reinforcement into the longitudinal deck reinforcement. In the Sc
strut-and-tie model this transfer of load is modelled by a truss. SF
SFH
SFV
3(a)
SB
3(b)
SGV
SGH SG
SD
Fig. 5. Detailed strut-and-tie model Fig. 7. Split node behind bearing plate—all forces compressive
Bridge Engineering 158 Issue BE2 A simplified integral composite bridge connection Riches et al. 65
Downloaded by [ Newcastle University] on [24/09/16]. Copyright © ICE Publishing, all rights reserved.
Figure 7 demonstrates the split node, and shows a simple which allows a reduction in the requirement for reinforcement on
arrangement of the critical struts to model the internal node the back of the abutment to be justified.
forces which are aligned in the direction of the principal stresses.
SFV
A (1) B
SB
(2)
SGV C
SGH SG
TD
66 Bridge Engineering 158 Issue BE2 A simplified integral composite bridge connection Riches et al.
Downloaded by [ Newcastle University] on [24/09/16]. Copyright © ICE Publishing, all rights reserved.
4.2. Strut-and-tie analysis
Scale: 1:14·6049
2D Stress, Max
The forces obtained from the grillage model were then applied to
Stresses are at MIDDLE of element
170·000 N/mm2
150·000 N/mm2
a strut-and-tie model analysed on a plane frame grillage using
100·000 N/mm2
4·00000 N/mm2 bar elements (i.e. elements that are only able to carry direct
3·00000 N/mm2
2·00000 N/mm2
1·00000 N/mm2
compression and tension forces).
0·0 N/mm2
-2·00000 N/mm2
-4·00000 N/mm2
-6·00000 N/mm2
-8·00000 N/mm2
-10·0000 N/mm2
The following procedure was utilised.
-100·000 N/mm2
-150·000 N/mm2
-170·000 N/mm2
Case: A4 "SLS Max My" (a) The initial geometry of the strut-and-tie model was defined
by the geometry and location of the reinforcement and
steelwork and an arbitrary effective width of the compression
node behind the bearing plinth.
(b) The internal boundary load effects (moment, axial load and
shear) and external forces applied to the connection within
y the boundary were applied to the strut-and-tie model.
x
(c) The vertical stresses in the node were checked and the strut-
Fig. 10. Minimum (tensile) projected stresses and-tie geometry revised accordingly until compliant
stresses were achieved.
80 l
mina te
m no
20 m ent of pla
A 650 edm te
emb o concre
int
Haunches
250
25
6
50
150
25
8 8 15 mm fillet
250 Haunch
weld
plate
250
600
GRD line 25
11 11
50
700
10 10 250
25 Bottom
150
flange
250
50 End Haunch
plate plate
6
150 25
70 No. holes for M36
400 End- 25
holding-down bolts
Horizontal plate
girders 2, 3, 6, 7 only 250
bracing cL T16
Reinforcement
bars
Detail 7 Section 8-8
(Scale 1:10) (Scale 1:10)
200
250 250 50
Web of girder 18 web
Web of girder Full butt
9 No. 30 mm holes
Beam
275 50
25 web
15 mm Hole cut into
50 50 50
continuous fillet web of beam
welds all round 9 No. 30 mm
600 50 50 holes for T16
Bottom
reinforcement
flange
50 50 50 Web replaced Bottom
200
End-plate with 50 mm
25 flange
thick haunch plate
welded to end-plate
End-plate
700 ¥ 600 ¥ 50 mm thick 400 Varies, for setting
out see detail 7
Bridge Engineering 158 Issue BE2 A simplified integral composite bridge connection Riches et al. 67
Downloaded by [ Newcastle University] on [24/09/16]. Copyright © ICE Publishing, all rights reserved.
The procedure was repeated for all critical load combinations and
the reinforcement and steelwork designed and detailed using the
enveloped resolved forces of the strut-and-tie model.
Fig. 12. Erection of main girders Fig. 14. Bracket detail before concreting
68 Bridge Engineering 158 Issue BE2 A simplified integral composite bridge connection Riches et al.
Downloaded by [ Newcastle University] on [24/09/16]. Copyright © ICE Publishing, all rights reserved.
6. CONCLUSIONS
The current trend towards integral bridges in the UK, to deliver
durable and low-maintenance solutions, has posed a significant
challenge particularly with regard to providing cost-effective,
buildable and technically sound connections.
REFERENCES
it could be removed during single lane closures of the road. 1. SCHLAICH J. and SCHAEFER K. Design and detailing structural
Bracing cast in to the abutments transferred load from the deck concrete using strut-and-tie models. The Structural Engineer,
down to the bottom flanges. To stabilise the bottom flange 1991, 69, No. 6, 113 –125.
under hogging moment, single sets of permanent K bracing 2. SCHLAICH J. and SCHAEFER K. Konstruieren im Stahlbetonbau.
were provided at about 6 m from each end of the deck. The Beton-Kalender (EIBL J. (ed.)), Ernst & Sohn Verlag, Berlin,
other bracing visible in Fig. 13 provides temporary restraint 1993, Part II.
to the forces from the cantilever formwork/working 3. STEEL CONSTRUCTION INSTITUTE . Integral Steel Bridges, Design of
platform. a Single-span Bridge—Worked Example. SCI, Berkshire,
Publication Number: P180, 1997.
The deck concrete was poured in advance of the connection 4. AMERICAN CONCRETE INSTITUTE COMMITTEE 318. Building
concrete, to minimise hogging moments due to dead load. Code Requirements for Structural Concrete and Commentry
(ACI 318R-02). ACI, Framington Hills, MI, 2002, cl R11.6.4.
5. BRITISH STANDARDS INSTITUTION . Steel Concrete and Composite
5.3. Casting the connection Bridges—Part 3: Code of Practice for Design of Steel Bridges.
Figure 14 shows the bracket detail in position with all BSI, London, 2000, BS 5400-3: 2000.
the surrounding reinforcement placed, and Fig. 15 6. BRITISH STANDARDS INSTITUTION . Steel Concrete and Composite
demonstrates the lack of congestion in the reinforcement prior to Bridges—Part 4: Code of Practice for Design of Concrete
concreting. Bridges. BSI, London, 1990, BS 5400-4: 1990.
Bridge Engineering 158 Issue BE2 A simplified integral composite bridge connection Riches et al. 69
Downloaded by [ Newcastle University] on [24/09/16]. Copyright © ICE Publishing, all rights reserved.