Professional Documents
Culture Documents
iii)
c) Once the desired land is purchased, than the same shall be communicated to the local
government for their information and records. Forest land a) Diversion of forest is required and
permission from regional MoEF is required if the land is < 5 Ha and if the land is more than 5
Ha then clearance from central MoEF is required. For details please refer Annexure-A
4) Environmental Clearance for Power Plant, Dam, Coal Mines and other requirement etc. a.
State Pollution Conservation board (SCPB). If the investment involved in the Green field project
is less than Rs.100.00 Crore or project cost of expansion of existing plant is less than 50 crore
than in that case only State Pollution Conservation Board Clearance is sufficient and we need
not to go to MoEF for environmental clearance, however, if the project cost is more than 100
Crore or cost of expansion of existing plant is more than 50 Crore or the location of plant
involves two or more states or forest land is coming under the circumference of 25 kms from the
project site then in that case MoEF clearance is required. b. Ministry of Environment and Forest
(MoEF). For MOEF clearance following procedures has to be done i. Phase-I Screening :
Submit the application for Site clearance to MoEF. If the site clearance is not granted than
search for alternative site and again submit the application for site clearance. ii. The site
clearance provided by MoEF have certain conditions, if the site selected meet all the conditions
than proceed for Environmental Clearance Phase-II (Siting, EIA report Preparation, public
hearing etc) iii. Phase-II:1. Step-1 Base line data collection 2. Step-2 EIA report preparation and
other approvals including Central Regulation Zone (CRZ) for coastal area. a. If Diversion of
Forest < 5 Ha is involved than apply for regional MoEF however , for forest area > 5 Ha apply
to Central MoEF clearance. b. If use of ground water is involved than a hydrological report is to
be submitted along with EC applicatio. c. Obtain Approvals for Electricity, Water Supply
(Ground Water Board or irrigation Department or Municipal Corporation etc.) and Explosives
Storage/Hazardous substances (if applicable) d. Finalize Application and Environmental
Appraisal Questionnaire 3. Step 3 a. Public Hearing required b. Submit requisite number of
copies of executive summary.
iv. Phase-III 1. Step-1 a. Submission of Documents (EIA– 20 copies, EMP, NOC, Public
Hearing details, DPR) to MoEF 2. Step 2 a. Review by IAA b. If IAA feels that the data
provided in sufficient than, the expert committee will submit their assessment over the report and
application. 3. Step- 3 a. Expert committee will submit their recommendation to IAA. 4. Step- 4
a. If the project is accepted than MoEF clearance is granted for 5 years, however, if the case is
rejected than case is closed. Reconsideration may be considered in some cases. 5. Step 1 to 3
requires approx 90 days and step 4 requires approx 30 days. 3. Water Drawl Permission. a.
Drawl from Perennial River:- Approval from State Govt in which river is falling. Data such as
Water feasibility Report, Guage Discharge and Index MAP indicating the location of Power
Plant, River pump house etc. to be submitted to Principal Secretary, Water Resource Department
for state clearance. b. If, more than one state is involved in drawl of water from the river then in
such case permission from Central Water Commission (CWC) is required. c. If construction of
Dam is required, Construction of Dam Permission, Water Drawl Permission, Royalties to be paid
etc. 4. Fuel Linkage Clearance a. If coal is to brought from outside agency i.e. no captive coal
mine is allocated than permission for coal linkage is required, which involves following
procedures i. Permission for railway sidings in case rail transportation is required from the
nearest railway line. ii. Way of right for railway sidings iii. Three Party agreement etc. b.
Allotment of coal blocks as per the requirement from Coal Ministry, Govt of India. c. Coal
Mining Plan is to be prepared and approved from State Govt.
5. Civil Aviation Clearance for construction of any sky rise building including chimney from
Airport Authority of India. 6. Permission from State Govt for Construction Power. 7. Permission
from State Govt for Construction Water. 8. Permission for Use for explosives 9. Consent to
Establish from the State Environmental Board for setting up the thermal Power Plant.
10.Consent to Operate and maintain from the State Environmental Board for setting up the
thermal Power Plant.
List of Clearances Required for Power Projects Sl.N o ITEM AGENCY REMARKS
2.
Reasonableness of the Scheme Site location for optimum utilisation of fuel resources, distance
from load centres, transportation facilities, water availability and environmental considerations.
State Govts Section 29 clause (2),(3),(4) and (6) ES Act, 1948State Govts.
3.
4.
Interaction between State Govt.=s Deptts & CWC required.Relevant Irrigation Act of the
Sl.N o
ITEM
AGENCY
REMARKS
FOREST CLEARANCE
8. 9.
Sl.N o
ITEM
AGENCY
REMARKS
STATUTORY CLEARANCES Petroleum & Natural Gas 16. FINANCING CEA, Deptt. of
Power, Deptt of Eco. Affairs,Financi al Institutions Deptt of Coal,Min. of Petroleum & Natural
Gas, Ministry of Railways, Shipping & Surface Transport
17
TRANSPORTATION OF FUEL
* Not required any more