This document provides an engineer's estimate for revitalizing a 4-phase traffic light intersection. It includes replacing the traffic light controller, cables, LED displays, painting poles, and horizontal drilling. The total estimated cost is 199,386,000 Indonesian Rupiah, which includes the materials, labor, and 10% value added tax.
This document provides an engineer's estimate for revitalizing a 4-phase traffic light intersection. It includes replacing the traffic light controller, cables, LED displays, painting poles, and horizontal drilling. The total estimated cost is 199,386,000 Indonesian Rupiah, which includes the materials, labor, and 10% value added tax.
This document provides an engineer's estimate for revitalizing a 4-phase traffic light intersection. It includes replacing the traffic light controller, cables, LED displays, painting poles, and horizontal drilling. The total estimated cost is 199,386,000 Indonesian Rupiah, which includes the materials, labor, and 10% value added tax.
No Uraian Pekerjaan Satuan Volume Harga Satuan Harga Total
A. Revitalisasi Traffic Light Simpang 4
a. Pekerjaan 1 Pergantian Controller Traffic Light 4 Phase modul 1.00 50,000,000.00 50,000,000.00 2 Pergantian Kabel m 42.00 30,000.00 1,260,000.00 3 Pergantian Aspek 30 cm LED buah 8.00 5,500,000.00 44,000,000.00 4 Pengecatan Tiang buah 4.00 500,000.00 2,000,000.00 5 Pengeboran Horizontal m 42.00 2,000,000.00 84,000,000.00 Jumlah 181,260,000.00 PPN 10% 18,126,000.00 Harga Total 199,386,000.00