Professional Documents
Culture Documents
Kurma 8 Iatmi-Psc GS, Introduction
Kurma 8 Iatmi-Psc GS, Introduction
UNIVERSITAS TRISAKTI
JAKARTA
Syamsul Irham
PSC GROSS SPLIT - INTRODUCTION
OUTLINE
Background
Objectives
Basic Principle
Case Discussion
Background
Objectives
Basic Principle
Case Discussion
Background 3 : Data
History 2006-2016,
PNBP ↓↓↓
PPH ↓
CT ↓
CR ↑↑↑
Background 3 : Data
History 2006-2016,
PNBP ↓↓↓
PPH ↓
CT ↓
CR ↑↑↑
Background 3 : Data
History 2006-2016,
PNBP ↓↓↓
PPH ↓
CT ↓
CR ↑↑↑
Background 3 : Data
History 2006-2016,
PNBP ↓↓↓
PPH ↓
CT ↓
CR ↑↑↑
Background 3 : Data
History 2006-2016,
PNBP ↓↓↓
PPH ↓
CT ↓
CR ↑↑↑
Background 3 : Data
History 2006-2016,
PNBP ↓↓↓
PPH ↓
CT ↓
CR ↑↑↑
Background
Objectives
Basic Principle
Case Discussion
Background
Objectives
Basic Principle
Case Discussion
Non-konvensional 16%
VARIABLE 6 Kandungan CO2
1 Status Lapangan <5 0%
POD I 5% 5≤x<10 1%
POD II 3% 10≤x<20 1%
20≤x<40 2%
NO POD 0%
40≤x<60 2%
2 Lokasi Lapangan x≥60 4%
Onshore 0% 7 Kandungan H2S (ppm)
Offshore (0<h<20) 8% <100 0%
Offshore (20<h<50) 10% 100≤x<1000 1%
Offshore (50<h<150) 12% 1000≤x<2000 2%
Offshore (150<h<1000) 14% 2000≤x<3000 3%
3000≤x<4000 4%
Offshore (h>1000) 16%
x≥4000 5%
3 Kedalaman res (m) 8 SG
≤2500 0% <25 1%
>2500 1% ≥25 0%
4 Ketersediaan Infrastruktur Pendukung 9 TKDN
Well Developed 0% 30≤x<50 2%
New Frontier Offshore 2% 50≤x<70 3%
70≤x<100 4%
New Frontier Onshore 4%
10 Tahapan Produksi
5 Jenis reservoir Primer 0%
Konvensional 0% Sekunder 6%
Non-konvensional 16% Tersier 10%
PROGRESSIVE
1 Harga Minyak Bumi (US$/bbl)
(85-ICP)x0.25/100
E.T.S
F.T.P
I.C
F.T.P
C.R
Equity Share
Equity share
DMO DMO
TAX
Background
Objectives
Basic Principle
Case Discussion
• WK “XY” akan
GROSS REVENUE GROSS REVENUE
berakhir kontrak 912.80 912.80
dengan pilihan
menggunakan
sistem kontrak RESULT : CT PSC-GS > CT PSC-CR
PSC-CR atau
PSC-GS
PSC-CR atau
PSC-GS RESULT : Contractor Econ Indicator PSC-GS > PSC-CR
$150.00
$100.00 Cost Recovery
$50.00 Gross Split
$0.00
60% 80% 100% 120% 140%
Sensitivity
$100.00
TOTAL
Year
MM$ CAPEX sensitivity to Contractor NPV
2018 35.61
2019 85.97 $140.00
2020 4.55
2021
$120.00
NPV, MMUSD
2022 2.31 $100.00
2023
$80.00
2024
2025 $60.00 Cost Recovery
2026 $40.00
2027
$20.00 Gross Split
2028
2029 $0.00
2030
2031 60% 80% 100% 120% 140%
TOTAL 128.44
Sensitivity
$150.00
$100.00
Cost Recovery
$50.00
Gross Split
$0.00
60% 80% 100% 120% 140%
Sensitivity
References