In light of the above, National Education Trust Ltd on behalf of the Ministry of
Education, Youth and Information has decided to:
I. Respond to Clarifications
Clarifications were sought and are address according:
1. “We are seeking clarification on the extent of the on-lot sewage treatment
referred to in the RFP document; does it entail;
- connecting to an existing on-lot treatment facility along with modifications as
relevant?
- or the provision of a new central wastewater treatment plant?
- rationalization of the existing sewage collection system and connection to
sewerage from the proposed new blocks?
NET’s Response:
Provisions for 'connection' into the existing Sewage Disposal Design/Layout will
need to be considered in particular from the Administrative Block e.g. from a MH
or TGB
No modification or rationalization required to the existing Sewage Disposal
Design
No provision for a new Central Waste Water Treatment plant will be required
(Please see Sewage Disposal Design uploaded)
NET’s Response:
The current student population is 1000. The institution is not intending to add
students to its cohort as the current expansion is to treat with/create adequate
space for the existing population.