Professional Documents
Culture Documents
https://doi.org/10.1007/s40998-017-0034-4
RESEARCH PAPER
A. Abdollahi1 • M. Rashidinejad1
Received: 10 August 2016 / Accepted: 21 July 2017 / Published online: 19 September 2017
Shiraz University 2017
123
306 Iran J Sci Technol Trans Electr Eng (2017) 41:305–317
Constants 1 Introduction
xi The weighting factor of scenario i
ltiDnm Bid for mth block of nth demand in scenario i and In the past, centralized models addressed the network
year t expansion problem aimed at minimizing the investment
ti
lGhj Offer for jth block of hth generator scenario i and cost (Romero et al. 2002; Rahmani et al. 2013a, b). With
year t restructuring of electricity industry, new expansion models
cpq;r Transposed vector of the investment costs of new have been introduced. In these models, some issues such as
transmission lines the market participants’ strategies [generation companies
chj Transposed vector of the investment costs of new (GENCOs), load serving entities (LSEs), and transmission
generating units companies (TRANSCOs)], congestion, and security criteria
a Adjustment factor for costs of planning and are considered as the main components of the long-term
operation planning problem (Khodaei et al. 2010; Alguacil et al.
xpq Reactance of corridor p - q 2003). Therefore, generation and transmission expansion
0 Transmission line in the initial topology
npq planning considering the entire network social welfare
M Big enough positive constant maximization is one of the most challenging and decision-
max
fpq Maximum power flow in one of the lines in corridor making activity problems in power system (Hooshmand
p-q et al. 2012; Roh et al. 2009), and it plays an important role
max
pGhj Size of jth block of hth generator in operation-based tools, which are the core of a power
pmax Maximum generation of hth generator system (Pourakbari-Kasmaei and Rashidi-Nejad 2011).
Gh
e In a restructured electric industry, generation and
kpq A binary parameter presenting contingency in
transmission expansion are usually handled by a central-
condition e
ized entity (e.g., ISO) to obtain the most economical and
Ue A binary parameter of allocation FSC for existing
reliable expansion (Roh et al. 2009). In other words,
lines
transmission systems should be developed to remove
Up A binary parameter of allocation FSC for candidate
transmission congestion and provide fair access for all
lines
market participants (Shrestha and Fonseka 2004). Con-
pa Compensation level of ath FSC for corresponding
structing new transmission lines is difficult due to geo-
lines
graphical problems, high investment cost, and severe
Ca Ratio of ath FSC’s investment cost to investment
reduction in social welfare (de la Torre et al. 2008).
cost of corresponding line
Power system planning is the science of determining the
I Discount rate
optimal place, size, and time for adding new facilities to
t0 Base year
power systems. In the previous literature, different models
have been proposed to solve transmission expansion
Sets
planning (TEP) problem (Rahmani et al. 2013a, b). Orfanos
E Set of all system conditions, i.e., e0 normal condition,
et al. (2013) proposed an efficient approach for proba-
e1 contingency occurred on existing lines, and e2
bilistic transmission expansion planning that considers load
contingency occurred on prospective lines
and wind power generation uncertainties. The Benders
e01 Set of all corridors that includes contingency in
decomposition algorithm in conjunction with Monte Carlo
existing lines
simulation is used to tackle the proposed probabilistic TEP.
e1 Set of all corridors that includes contingency in
In Akbari and Tavakoli-Bina (2014), TEP is solved using
prospective lines
the AC optimal power flow (AC-OPF) to provide accurate
cc Set of all scenarios
picture of power flow compared to the DC optimal power
cN Set of all nodes of network
flow. Also, uncertainties about future electricity demand,
ck Set of all transmission lines, existing and prospective
fuel prices, greenhouse gas emissions, as well as possible
cr Set of all prospective transmission lines in corridor
disruptions can be incorporated in the planning models
p-q
(Seddighi and Ahmadi-Javid 2015). Improved heuristic
ch Set of all blocks of hth generating unit
algorithms have been used for the solution of the power
cG Set of indices of the generating units
system planning. In Georgilakis (2010), market-based
cn Set of all blocks of nth demand
transmission expansion planning as a complex mixed
cD Set of indices of the demands
integer non-linear programming problem is solved via
A Set of all candidate FSCs indexed by a
improved differential evolution algorithm. The main
T Set of all years of the planning horizon
objective is to obtain the optimal decision to minimize the
123
Iran J Sci Technol Trans Electr Eng (2017) 41:305–317 307
overall generation and transmission cost for market par- necessity of constructing parallel transmission lines with
ticipants considering pricing and investment. The global high investment cost (Rahmani et al. 2013a, b). In other
optimum solution is obtained through the proposed algo- words, FSCs can redistribute the power flow to use the
rithm with some improvements to increase the diversity of remaining capacity of transmission lines and increase
population and prevent the premature convergence. In competition between market participants. Considering
some works, short-term operating problems are incorpo- FSCs in transmission planning results in a different grid
rated in long-term planning problems. In Koltsaklis and topology at much lower cost due to better utilization of the
Georgiadis (2015) unit commitment problem is incorpo- whole transfer capacity of the network, meaning that, with
rated into the long-term planning horizon to determine the a small investment in FSCs, significant improvement in
optimal capacity additions, electricity market clearing social welfare can be achieved.
prices, and daily operational planning of the studied power Several flexible AC transmission systems (FACTS) can
system. The heuristic-based algorithms, such as simulated be used to redistribute the power in the transmission system
annealing and genetic algorithm have been widely used to but among them FSCs are cost-effective and more suit-
solve GTEP problem (Da Silva et al. 2000; Sun and Yu able for redistributing the power in transmission system
2000; Braga and Saraiva 2005; Kandil et al. 2001). The (Rahmani et al. 2013a, b). In Rahmani et al. (2013a, b),
power system planning models are mixed integer linear besides considering some of the benefits and drawbacks of
programming. Therefore, there is a wide tendency to solve FSCs, the effects of their installation on planning project,
these problems based on mathematical optimization, such in monopoly environment, have been investigated. In
as linear programming, Bender’s decomposition, and bi- deregulated environment, ISO can install FSCs along with
level optimization (Sanchez-Martin et al. 2005; Garver transmission planning for better utilization of existing
1970; Lee et al. 1974; Choi et al. 2005a, b; Lu et al. 2005). transmission infrastructures and lowering the overall
Some issues such as reliability and security constraints and transmission investments. However, these problems have
uncertainties were considered in market-based power sys- feasible solutions, and with technological advances in
tem planning (Buygi et al. 2004a, b, c, d), where the protection system, there is no fear of using series com-
stochastic planning is also one of the most important issues pensation in a transmission system.
in power system planning (Akbari et al. 2011). In some In this paper, a dynamic (multi-year) model for the
works such as Shayeghi et al. (2008), new points of view transmission expansion problem considering inclusion of
have been taken into account, a decimal codification FSCs in a pool-based electric energy market is presented.
genetic algorithm (DCGA) has been used to consider the In this model, the network topology, generator offers, and
inflation rate and load growth factor on network losses, demand bids are taken into account. Moreover, the
where the social welfare and better expansion planning can improvement of social welfare as a result of transmission
be a byproduct. expansion planning via inclusion of FSCs is investigated.
Nowadays, some short-term practical issues such as FSCs as a short-term solution for the power system prob-
transmission switching and installing compensation devi- lems are integrated in the multistage transmission expan-
ces can be considered for better utilization of the existing sion planning, when the horizon of planning is divided in
transmission network, delaying the construction of new several stages (Escobar et al. 2004). In each planning stage,
lines, and even improving social welfare (Khodaei et al. FSCs can be integrated into the system to increase com-
2010). In Blanco et al. (2009), a new framework is pre- petition between market participants as well as to lower the
sented for assessing flexible investment within the trans- necessity of constructing many transmission lines, which
mission expansion planning under uncertainties. In this results in a significant decrease in both the investment cost
model, gaining flexibility by investing in FACTS devices, and the construction time.
the expansion investments in transmission lines are defer- This paper proposes a mixed integer linear programming
red. In other words, a suitable combination between lines for multi-period framework in which market-based GTEP
and FACTS devices can lead to flexible investment in along with FSC allocation is considered. The main con-
small scale, instead of large investments in transmission tributions of this paper are as follows:
expansion projects. In Miasaki and Romero (2007), a
1. To consider integrated generation and transmission
developed mathematical model of TEP considers the
expansion planning. In this paper new generating units
installation of series compensation devices. In this model,
are constructed so that the profits of LSEs and
the solution obtained by a specialized genetic algorithm
GENCOs are maximized.
supplies the amount and the location where new trans-
2. To propose a robust mixed-integer linear programming
mission lines and series compensation devices must be
model for multi-period GTEP. In this model three
installed. However, installing fixed series compensators
operating periods are incorporated with different
(FSCs) in new transmission lines can eliminate the
123
308 Iran J Sci Technol Trans Electr Eng (2017) 41:305–317
Demand Coefficient
term planning related to FSC lifetime, and (c) long-
term transmission expansion planning.
The rest of this paper is organized as follows. Section 2
presents the model features. In Sect. 3 the mathematical
model for dynamic generation-transmission expansion plan-
ning incorporating FSC is described. Section 4 describes
Scenario 1
Scenario 2
Scenario 3
Scenario 4
some metrics to analyze the solution of expansion with respect
to using FSCs. The proposed methodology is applied to case
studies in Sect. 5. Section 6 provides the concluding remarks.
Time
8ðpqÞ2c 8r2c
;
k k
123
Iran J Sci Technol Trans Electr Eng (2017) 41:305–317 309
dtie0
utpq;r;a ut1
pq;r;a 0; f8ðpqÞ 2 ck ; 8ðtÞ 2 T g ð5Þ pq;a
n0pq uðtÞ0 max
pq;a fpq ;
xpq pa
ðtÞ0
upq;a utpq;r;a 1 ntpq;r ; f8i 2 cc ; 8e 2 E; 8ðpqÞ 2 ck ; for ðpqÞ 6¼ e0l ; 8ðtÞ 2 Tg
ð6Þ
f8ðpqÞ 2 ck ; r ¼ 1; 8a 2 A; 8ðtÞ 2 T g ð20Þ
tie0
t d
upq;r1;a utpq;r;a 1 ntpq;r ; pq;a
ð7Þ n0pq 1 uðtÞ0 max
pq;a fpq ;
f8ðpqÞ 2 ck ; 8a 2 A; 8ðtÞ 2 Tg xpq pa
ntpq;r1 ntpq;r 0; f8ðpqÞ 2 ck ; 8ðtÞ 2 Tg ð8Þ f8i 2 cc ; 8e 2 e1 ; 8ðpqÞ 2 ck ; for ðpqÞ ¼ e0l ; 8ðtÞ 2 Tg
ð21Þ
ntpq;r nt1
pq;r 0; f8ðpqÞ 2 ck ; 8ðtÞ 2 Tg ð9Þ
X
tie tie tie tie
ythj yt1
hj 0; f8j 2 ch ; 8i 2 cc ; 8ðtÞ 2 Tg ð10Þ xpq fpq;r dpq;a;r hp hq M 1 ntpq;r ;
! a2A
XX f8ðpqÞ 2 ck ; 8i 2 cc ; 8r 2 cr ; 8e 2 E; for ðpqÞ 6¼ el ; 8ðtÞ
ntpq;r þ n0pq 1 0; f8ðpqÞ 2 ck ; 8ðtÞ 2 Tg 2 Tg
t2T r2ck
ð22Þ
ð11Þ
X X X
ntpq;r ¼ 0; f8ðpqÞ 2 ck g ð12Þ e
tie
xpq fpq;r dtie
pq;a;r h tie
p h tie
q 1k pq M 1n t
pq;r ;
t2ðt1 ;t2 ;...;tg Þ r2ck a2A
X X X X X f8ðpqÞ 2 ck ;8i 2 cc ;8e 2 e2 ; for ðpqÞ ¼ el ;8ðtÞ 2 Tg
tie tie te0
fpqr fpqr þ fpq þ ptie
Gh ¼ ptie
Dn ;
8p¼s 8q¼s 8ðpqÞ2ck 8h2cG 8n2cD ð23Þ
fqie
s ; 8i 2 cc ; 8s 2 cN ; 8e 2 E; 8ðtÞ 2 Tg tie
fpq;r ntpq;r fpq
max
;
ð13Þ
X f8i 2 cc ; 8ðpqÞ 2 ck ; 8e 2 E; for ðpqÞ 6¼ el ; 8ðtÞ 2 Tg
tie0
xpq fpq dtie0
pq;a ¼ n0pq ðhtie
p htie
q Þ; f8ðpqÞ 2 ck ; 8i ð24Þ
a2A
2 cc ; 8e 2 E; for ðpqÞ 6¼ e0l ; 8ðtÞ 2 Tg tie e
fpq;r 1 kpq ntpq;r fpq
max
;
ð14Þ f8i 2 cc ; 8ðpqÞ 2 ck ; 8e 2 e2 ; for ðpqÞ ¼ el ; 8ðtÞ ð25Þ
X 2 Tgð24Þ
tie0
xpq fpq dtie0 0 tie tie
pq;a ¼ ðnpq 1Þðhp hq Þ;
a2A dtie
f8ðpqÞ 2 ck ; 8i 2 cc ; 8e 2 e1 ; for ðpqÞ ¼ e0l ; 8ðtÞ 2 Tg tie pq;r;a
fpq;r 1 utpq;r;a fpq
max
;
xpq pa
ð15Þ
f8i 2 cc ; 8ðpqÞ 2 ck ; 8e 2 E; for ðpqÞ 6¼ el ; 8ðtÞ 2 Tg
tie0
fpq n0pq fpq
max
; ð26Þ
f8i 2 cc ; 8e 2 E; 8ðpqÞ 2 ck ; for ðpqÞ 6¼ e0l ; 8ðtÞ 2 Tg
dtie
tie pq;r;a e
ð16Þ fpq;r 1 kpq 1 utpq;r;a fpq
max
;
xpq pa
tie0 f8i 2 cc ; 8ðpqÞ 2 ck ; 8e 2 e2 ; for ðpqÞ ¼ el ; 8ðtÞ 2 Tg
fpq ðn0pq 1Þfpq
max
; f8i 2 cc ; 8e 2 e1 ; 8ðpqÞ
2 ck ; for ðpqÞ ¼ e0l ; 8ðtÞ 2 Tg ð27Þ
ð17Þ dtie
pq;r;a
utpq;r;a fpq
max
;
tie0 xpq pa ð28Þ
tie0 dpq;a
fpq ðn0pq Þð1 ut0 max
pq;a Þfpq ; f8i 2 cc ;8ðpqÞ 2 ck ;8e 2 E; for ðpqÞ 6¼ el ;8ðtÞ 2 Tg
xpq pa
f8i 2 cc ; 8e 2 E; 8ðpqÞ 2 ck ; for ðpqÞ 6¼ e0l ; 8ðtÞ 2 Tg dtie
pq;r;a e
1 kpq utpq;r;a fpq
max
;
ð18Þ xpq pa
ð29Þ
tie0 f8i 2 cc ; 8e 2 ce ; for ðpqÞ ¼ el ; 8ðpqÞ 2 ck ; 8e
tie0 dpq;a
fpq n0pq 1 1 uðtÞ0 max
pq;a fpq ; 2 e2 ; 8ðtÞ 2 T
xpq pa X
f8i 2 cc ; 8e 2 e1 ; 8ðpqÞ 2 ck ; for ðpqÞ ¼ e0l ; 8ðtÞ 2 Tg ptie
Gh ¼ ptie
Ghj ; f8h 2 cG ; 8i 2 cc ; 8ðtÞ 2 Tg ð30Þ
8j2ch
ð19Þ
123
310 Iran J Sci Technol Trans Electr Eng (2017) 41:305–317
0 ptie t max
Ghj yhj pGhj ; f8j 2 ch ; 8i 2 cc ; 8ðtÞ 2 Tg ð31Þ operative during the whole planning horizon. Due to lack
of information for the line lengths in the system data, FSCs
0 ptie max
Gh pGh ; f8h 2 cG ; 8i 2 cc ; 8ðtÞ 2 Tg ð32Þ are installed in the lines with a reactance greater than 0.05
X
ptie ptie pu. Therefore, Ue and Up, as binary parameters, are set to 1
Dn ¼ Dnm ; f8n 2 cD ; 8i 2 cc ; 8ðtÞ 2 Tg ð33Þ
8m2cn if the reactance of the corresponding line is greater than
0.05 pu.
0 ptie max
Dnm pDnm ; f8m 2 cn ; 8i 2 cc ; 8ðtÞ 2 T g ð34Þ Constraints (6) and (7) enforce installing the same
FSCs in the existing and prospective lines for power flow
tie
hp htie
q h; f8ðpqÞ 2 ck ; 8i 2 cc ; 8ðtÞ 2 Tg ð35Þ
balancing in parallel lines. Constraint (6) is applied to the
corridors with the existing lines in base topology, i.e.,
tie
hp htie e
q hþMkpq ;
ð36Þ n0pq 1. Constraint (6) ensures that no FSC is installed in
f8i 2 cc ; 8e 2 e1 ; 8ðpqÞ 2 ck ; 8ðtÞ 2 Tg candidate lines without installing FSC in similar existing
tie lines. In addition, note that constraint (7) enforces the
hp htie
q hþM 1 npq;r ;
t
ð37Þ same FSCs installation in similar prospective lines in a
f8i 2 cc ; 8e 2 e0 ; 8ðpqÞ 2 ck ; 8ðtÞ 2 Tg corridor.
tie
hp htie
q h þ M 1 n t
pq;r 1 k e
pq ;
3.2.2 Prospective Line Installation Constraints
ð38Þ
f8i 2 cc ; 8e 2 e2 ; 8ðpqÞ 2 ck ; 8ðtÞ 2 T g
Constraint (8) guarantees installing prospective lines
sequentially. Constraints (9) and (10) guarantee that an
3.1 Objective Function of Proposed Model
installed line and generating unit remain operative during
the planning horizon. Constraint (11) expresses that by a
In (1), the total social welfare is maximized under normal and
line outage, sum of the other lines (existing and prospec-
contingency conditions and is weighted for different scenarios
tive) in corridor p - q must be greater than or equal to
over the planning horizon. Total social welfare is comprised of
zero. Constraint (12) enforces that no new lines can be built
two main terms: (a) market social welfare (i.e., the aggregated
during the first g years of the planning horizon.
demand bid function minus the aggregated generator offer
function) and (b) investment costs of new lines and FSCs. The
3.3 Contingency-Dependent Constraints
market social welfare is considered for one typical operation
year, while investments are considered over the planning
3.3.1 Power Flow Constraints
horizon. Therefore, a simulates the ratio between the invest-
ments and the annual scenario-weighted social welfare and
Ið1þIÞtt0
Constraint (13) satisfies power balance in all nodes under
makes them comparable using ð1þIÞtt0 1
. In Rahmani et al. normal and contingency conditions and in scenario i. qie s,
(2013a, b), a global investment cost has been considered for as a dual variable of the power balance constraint, is the
FSCs in US$/MW that contains the cost of capacitors. To nodal price at bus s in scenario i, in normal condition of
calculate the Ca, as a constant coefficient, the cost of FSCs is the system. Constraints (14) and (15) enforce the Kirch-
divided by the cost of the line as follows: hoff’s voltage law (KVL) to non-outage existing trans-
FSC investment cost per km mission lines under all conditions, and existing
Ca ¼ : ð39Þ transmission lines in contingency conditions, respectively,
Line investment cost per km
in scenario i.
The third term of the objective function stands for cal- In constraints (14) and (15), FSC reduces line reactance
culating the cost of FSCs, multiplying Ca by transmission as follows:
line investment cost for the existing and candidate lines. The
objective function is subjected to the following constraints. n0pq htie
p htie
q
tie0
fpq ¼ P : ð40Þ
xpq 1 s2S pa ut0 pq;a
3.2 Contingency Independent Constraints
Equation (40) can be re-rewritten as follows:
3.2.1 FSC Installation Constrains X
tie0 tie0 tie tie
xpq fpq xpq fpq pa ut0
pq;a ¼ n 0
pq h p h q : ð41Þ
Constraints (2) and (4) ensure that one of the FSCs with s2S
123
Iran J Sci Technol Trans Electr Eng (2017) 41:305–317 311
0 SWFSC;GTEP SWB
k1 ¼ P P P ð44Þ
tt0
8t2T 8r2ck cpq;r ntpq;r þ chj ythj þ Ca cpq;r utpq;r;a þ 8ðpqÞ2ck Ca cpq n0pq ut0
pq;a =ð1 þ IÞ
where contingency has occurred. M is assumed as a big where SWGTEP and SWFSC;GTEP are the optimal social
value that ensures the constraint is relaxed when welfare considering GTEP without and with FSCs incor-
npq,r = 0; but when npq,r = 1, this value is not important poration, respectively. SWB is the aggregated social wel-
and KVL is enforced for the corresponding transmission fare for the base topology. k1 shows the improvement of
line. the optimal social welfare for each dollar invested in
Constraints (24) and (25) express the power flow limits.
transmission expansion, while k01 expresses the improve-
In constraints (25), (27), and (29), to model line contin-
e ment of the optimal social welfare for each dollar invested
gency in condition e and scenario i, a binary parameter, kpq ,
e
in transmission expansion as well as installing FSCs. It is
is defined. It can be seen that, when kpq is 1, node p will be clear that investing in new facilities is reasonable if metrics
isolated from node q.
123
312 Iran J Sci Technol Trans Electr Eng (2017) 41:305–317
240 80 MW ISO can use FSC through GTEP for increasing utiliza-
5 1 tion of the existing lines, which results in lowering trans-
mission and generating investment. Therefore, from an
operation point of view, this paper proposes a metric (de-
fined as (45)) which takes into account the effect of new
3 facilities in congestion of existing lines.
40 MW X fpq max
fpq
l¼ max
ð45Þ
8pq2c
fpq
l
240 MW Similar to (43) and (44), metric (45) can also be defined
2 for GTEP considering FSC using l0 . In fact, metrics l and
l0 are defined to investigate the effect of FSC through
GTEP on congestion of the existing lines. The small value
of the metric shows that the lines carry more power,
6 4 resulting in better utilization of the existing lines.
160MW
(43)–(44) are greater than one. Similarly, metrics (43)–(44) 5.1 Introduction
can be defined to measure the change in welfare obtained
by the generators ðk2 ; k02 Þ, the demands ðk3 ; k03 Þ; and the The Garver and IEEE 24-bus systems are used as case
studies. In this paper, three types of FSCs with different
market operator ðk4 ; k04 Þ for each situation. Note that all
compensation percentages can be installed in a transmis-
metrics can be obtained in terms of declared surplus,
sion line as P1 = 20% with C1 = 10%, P2 = 30% with
resulting from clearing market.
C2 = 15%, and P3 = 50% with C3 = 20% (Rahmani et al.
2013a, b). Based on the pool-based market structure,
123
Iran J Sci Technol Trans Electr Eng (2017) 41:305–317 313
Table 2 Characteristics of the different scenarios scenario 1 has a weight of 0.412 with demand coefficient of
Scenario Weight Demand coefficient
0.47 that means in 41.2% of the hours of a year, the amount of
load level for corresponding scenarios is 47% of its peak
1 0.4120 0.47 load.
2 0.3597 0.85 The proposed method is applied to the Garver’s system
3 0.1172 1.20 for the following cases.
4 0.1111 1.70
Case 1 Solving the proposed method without considering
FSC.
generators’ offering blocks and demands’ bidding blocks In this case, proposed model is solved considering
are submitted by generating units and demands, respec- upq;r;a ¼ 0 and ut0
t
pq;a ¼ 0. The optimal solution provides the
tively, to attain their maximum profits. GTEP will be following lines and generating units with present value of
solved considering submitted bidding and offering data to the investment costs of $263 M.
maximize the social welfare. Here, linear cost functions are
used for modeling generators’ operation costs that contain • Year 1: lines n26 ¼ 3; n15 ¼ 2; n46 ¼ 2 and gener-
a set of blocks. The constant marginal cost is assumed for ating units U1, U2, and U4,
each block. Each generating unit submits one block of the • Year 2: generating unit U5,
offered power to the market and the price declared is the • Year 4: line n46 ¼ 1.
marginal cost corresponding to that block. Different sce- As expected, new lines connect inexpensive generator in
narios are assigned in which different levels of demand are node 6 to the nodes with high demand (2 and 4).
consumed for a number of hours during the target year. The Table 3 presents economic results of expansion in case
main difference among the scenarios is the level of 1. Note that, in all cases, the total social welfare is obtained
demand. Each scenario is weighted in the objective func- summing up surpluses of the generators, consumers, and
tion to correctly consider their relative relevance. The planner while subtracting investment cost of new facilities.
weight of each scenario is calculated by dividing the
number of hours a scenario occurs by the total number of Case 2 Solving the proposed method along with FSC
hours for the whole year. Moreover, size of each demand allocation.
blocks is different in every scenario (De la Torre et al. In this case, proposed model is solved and the following
2008; Aguado et al. 2012). In this paper, an annual growth results are obtained.
of generation and demand of 3.1% and annual growth of • Year 1: lines n26 ¼ 2; n15 ¼ 2; n46 ¼ 1 and gener-
offer and bids of 5% are considered (Aguado et al. 2012). ating units U1, U2, and U4,
• Year 2: generating unit U5,
5.2 Garver’s System • Year 4: line n46 ¼ 1;
• Year 14: u34;1;3 ¼ 1, u26;2;3 ¼ 1, and u26;3;3 ¼ 1;
Figure 2 shows the initial topology of Garver’s system.
This system has six transmission lines and six buses with where u0pq;a and upq;r;a show the ath installed FCS in
three generators and five loads. The base data of the Gar- existing line and rth prospective line in corridor p - q,
ver’s system are given in (Garver 1970). The planning respectively. The present value of investment cost is
horizon and discount rate are 15 years and 10%, respec- $223 M. Table 4 shows the economic results of expansion
tively. The bidding blocks for existing and new generators along with FSC for the market participants. Comparing
and demands are shown in Table 1. According to Table 1, Tables 3 and 4, it can be observed that optimal allocation
seven generating units are considered to be installed. of FSCs increases the total social welfare by up to $61 M.
Table 2 shows the weight of each scenario and corre- Table 5 shows metrics presented in Sect. 4 for cases 1
sponding demand coefficient. According to this table, and 2.
123
314 Iran J Sci Technol Trans Electr Eng (2017) 41:305–317
123
Iran J Sci Technol Trans Electr Eng (2017) 41:305–317 315
123
316 Iran J Sci Technol Trans Electr Eng (2017) 41:305–317
123
Iran J Sci Technol Trans Electr Eng (2017) 41:305–317 317
Garver L (1970) Transmission network estimation using linear systems. Energy Convers Manag 52:2854–2860. doi:10.1016/j.
programming. IEEE Trans Power Appar Syst PAS enconman.2011.02.018
89:1688–1697. doi:10.1109/TPAS.1970.292825 Rahmani M, Romero R, Rider MJ (2013a) Strategies to reduce the
Georgilakis PS (2010) Market-based transmission expansion planning number of variables and the combinatorial search space of the
by improved differential evolution. Electr Power Energy Syst multistage transmission expansion planning problem. IEEE
32:450–456. doi:10.1016/j.ijepes.2009.09.019 Trans Power Syst 28:2164–2173. doi:10.1109/TPWRS.2012.
Hooshmand R, Hemmati R, Parastegari M (2012) Combination of AC 2223241
transmission expansion planning and reactive power planning in Rahmani M, Vinasco G, Rider MJ, Romero R, Pardalos PM (2013b)
the restructured power system. Energy Convers Manag Multistage transmission expansion planning considering fixed
55:26–35. doi:10.1016/j.enconman.2011.10.020 series compensation allocation. IEEE Trans Power Syst
Kandil MS, El-Debeiky SM, Hasanien NE (2001) A hybrid mathe- 28:3795–3805. doi:10.1109/TPWRS.2013.2266346
matical and rule-based system for transmission network planning Roh JH, Shahidehpour M, Wu L (2009) Market-based generation and
in a deregulated environment. Power Eng Soc Summer Meet transmission planning with uncertainties. Power Syst IEEE Trans
3:1451–1456. doi:10.1109/PESS.2001.970289 24:1587–1598. doi:10.1109/TPWRS.2009.2022982
Khodaei A, Shahidehpour M, Kamalinia S (2010) Transmission Romero R, Monticelli A, Garcia A, Haffner S (2002) Test systems
switching in expansion planning. Power Syst IEEE Trans and mathematical models for transmission network expansion
25:1722–1733. doi:10.1109/TPWRS.2009.2039946 planning. IEE Proc Gener Transm Distrib 149:27–36. doi:10.
Koltsaklis NE, Georgiadis MC (2015) A multi-period, multi-regional 1049/ip-gtd:20020026
generation expansion planning model incorporating unit com- Sanchez-Martin P, Ramos A, Alonso JF (2005) Probabilistic midterm
mitment constraints. Appl Energy 158:310–331. doi:10.1016/j. transmission planning in a liberalized market. IEEE Trans Power
apenergy.2015.08.054 Syst 20:2135–2142. doi:10.1109/TPWRS.2005.856984
Lee STY, Hicks KL, Hnyilicza E (1974) Transmission expansion by Seddighi AH, Ahmadi-Javid A (2015) Integrated multiperiod power
branch-and-bound integer programming with optimal cost– generation and transmission expansion planning with sustain-
capacity curves. Power Appar Syst IEEE Trans PAS ability aspects in a stochastic environment. Energy 86:9–18.
93:1390–1400. doi:10.1109/TPAS.1974.293869 doi:10.1016/j.energy.2015.02.047
Lu M, Dong ZY, Saha TK (2005) A framework for transmission Shayeghi H, Jalilzadeh S, Mahdavi M, Hadadian H (2008) Studying
planning in a competitive electricity market. In: Transmission influence of two effective parameters on network losses in
and distribution conference and exhibition: Asia and Pacific, transmission expansion planning using DCGA. Energy Convers
IEEE/PES, 2005, pp 1–6. doi:10.1109/TDC.2005.1547025 Manag 49:3017–3024. doi:10.1016/j.enconman.2008.06.013
Miasaki CT, Romero R (2007) A specialized genetic algorithm Shrestha GB, Fonseka PAJ (2004) Congestion-driven transmission
applied to transmission expansion planning model with alloca- expansion in competitive power markets. IEEE Trans Power
tion of series compensation devices. Controle Autom Syst 19:1658–1665. doi:10.1109/TPWRS.2004.831701
18:210–222. doi:10.1590/S0103-17592007000200007 Sun H, Yu DC (2000) A multiple-objective optimization model of
Orfanos GA, Georgilakis PS, Hatziargyriou ND (2013) Transmission transmission enhancement planning for independent transmis-
expansion planning of systems with increasing wind power sion company (ITC). Power Eng Soc Summer Meet IEEE
integration. IEEE Trans Power Syst 28:1355–1362. doi:10.1109/ 4:2033–2038. doi:10.1109/PESS.2000.866959
TPWRS.2012.2214242
Pourakbari-Kasmaei M, Rashidi-Nejad M (2011) An effortless hybrid
method to solve economic load dispatch problem in power
123