no Question Answer
Business related

1. Give me an example of strategic Smart city Mission is newly introduced by Union Govt in
plan you have created. 2015 where exactly our existence is predominant.
1. How did the need for this Considering massive upcoming development in this
come about? sector, to record our dominance & expertise in the field,
2. What data did you analyze precisely we focused on one of the green field Amaravati
to create this? (Look for capital city projects covering 217 Sq.km area. To make it
competitor analysis) happen we have made a strategic plan to get order book
3. How did you go about to the tune of 6000 + Crs (six packages) against estimated
gaining buy in for this? development cost of 15,647 Crs and completing the same
4. What was the result in 3 years.

1.Since there are lot of competitors in the market, drawing


a strategic plan is highly inevitable to understand “Where
to compete & How to compete”.

2. By doing SWOT analysis and Comparison with


competition, Customer estimate & benefits, value creation,
relationship management, operational excellence.

3. At the very initial stage itself, we had a close network


with client and identified the customer needs & desires,
competitor actions, events in operating environment. With
all those efforts, we successfully attained our strategic
plan by getting order book worth of 6000 Crs by partnering
with Transportation IC.

4. Successfully become a L1 for 6 packages and executed


contract agreement. Had good opportunity to show our in-
house design competence and operation excellence.
2 Tell me about time when you Almost a year before the official announcement of capital
identified & capitalized on a city, we started collaborating with customer and revealed
business opportunity. our expertise in this field.
1. How did you spot this? 1. Through healthy relationship management with
2. What were your initial customer, we got insights of upcoming capital city works.
steps?

Sensitivity: LNT Construction Internal Use


3. How did you evaluate the 2. Understood the customer costs & benefits and informed
viability of the option? about our value creation, operational excellence, and
4. How did you gain buy in Comparison with competitor
from stakeholders for this?
5. What was the outcome of 3. Since the projects are decided to award in EPC mode,
your efforts? we believed that with our in-house design setup we could
6. What is your key learning strongly meet customer requirement.
here?
4. Through this healthy relationship, we have well
established our expertise and promoted new technologies
available across the countries to adopt it.

6. Without looking for immediate result if we closely work


with customer will certainly result in long term gain.
3. Give me an example of a time Considering long term perspective, assigned a BD team to
when you took a particularly long- serve client in finalizing the concepts, latest technologies,
term decision. estimations, etc.,
1. What was the thinking at
the time? 1.We are not sure about awarding job to us but technically
2. How did you decide on this assisting them in needy time will create a space for future
course of action? job.
3. What factors did you
consider in this case? 2. Since this is a first green field capital city project in large
4. In hindsight, what worked & scale in India and customer also aiming to compete world
what could have been class cities, we took this as a good opportunity.
improved?
5. How did you implement 3. We have very competent in-house design by which we
these learnings since then? can create value addition to the customer & company.

4. Demonstrated our expertise and latest technology


across the word which overwhelmed customer. Integration
issues of network design with each package could have
been analyzed properly.

5.Extended technical support to the customers though we


are not currently associated with them so that it will pave a
way for future projects.
4. Tell me about latest innovative Metal Crusher and Project site is in opposite bunds of
idea you have implemented? Krishna river. Hence, logistics of 100 lac MT (incl TI IC)

Sensitivity: LNT Construction Internal Use


1. How did the idea occur to aggregate become a bottleneck of the project. 80km
you? distance through road & hence adopted barge which is a
2. What did you have to do to distance 25Km only.
gain buy in for this?
3. What steps did you take in 1.Small size barge was in operation for local public
ensuring a successful movement and by seeing this we decided to engage large
implementation? scale barge exclusively for our aggregate transportation.
4. What was the value this
added to the team / 2.Negotiated with authorities for approval and barge
department/ business? vendor and logistics vendor.

3.Made a special barge logistics team (TI IC) which will


ensure 10 trips /day and 20 Vehicles / trip to ensure
optimum usage.

4. Would have been saved nearly 20 Cr during completion


of Amaravati project by good coordination between
crusher team to end user team, resulted scheduled
progress in supply of aggregates.

5. Tell me about time when you used  Online information 


external market data to decide on  Government Magazine, consultants
a way forward.  Project Lakshya perspective 2026
 Where did you get this data  L&T awareness service – internal circulation mail
from? about the projects – Domestic & international
 What steps did you taken  Steps taken to analyses the external data are
in your analysis? correct, cross checking with known sources of the
 How did you arrive at data captured & past trends about the companies,
recommendations using recently gained experience etc.
this?  Arrived conviction on correctness data,
 What was the outcome of recommended for implementation.
your analysis?  Outcome is securing the project with Striking rate
 What is your key learning is 30% or more.
from this  By collecting & analyzing reliable market data will
definitely decide the result of securing projects.

Sensitivity: LNT Construction Internal Use


Personal development

8 Tell me about time when you took In 2008- MDP – IIM Bangalore
conscious steps to learn a new In 2009 -MDP – IIM Calcutta
skill or task? In 2010- L&T Institute of Project Management – Senior
 What prompted you to do Management program on projects – Level 2
so? In 2012- Strategic Project and Program Management
 How did you go about -Level 3 in association with George Washing ton
learning this skill or task? University, USA
 What support did you seek In 2019 – International project visit to Dubai – to
& where did you find this? understand international project management skill &
 What helped you learn this practices- Jebel ALI STP Project.
new task or skill? In 2020-21, Online certificate programs in L&T Next
 How long did it take What Digital platform
is your key take away from  Critical thinking
this experience?  Vision & values – The standing pillars of
organization
 Synergistic customer
 Organizational leadership
 Global Strategic mindsets

25
Give me an example of a time Mr. Karthikeyan was average performer in Jaipur cluster
when you turned around the office. He was under stress due to personal problems.
performance of a poor/ average 1.I observed there was a decline in work quality, became
team member. lonely & I enquired immediately to address the problems.
 What was the situation at 2. Set goals – given opportunity to turn around his
the time? performance – developed work improvement plan –
 How did you identify this identified his requirements of resources, tools & support
team members key that are available.
development areas? 3. Providing feedback - on his improvement on regular
 What steps did you take to basis, ask his challenges & hurdles facing during the
coach the team member? process and support required to perform & documented
 How did you keep track of his improved plan
the progress this individual 4. Rewarding with prize / memento for his improvement
was making? and further guidance to scale further.
Now he is a project Manager for sewerage package worth
of 350 cr.

Sensitivity: LNT Construction Internal Use


26 Tell me about a time when you Recently a new team member Mr. Abdul Mohamed Riaz
had to intervene to resolve a team has joined in planning department.
issue involving newer team 1.He was not familiar with our systems & culture followed
members! in our company
 What was the issue at 2. After many months he was not able to cope with our
hand? team & literally he is struggling to mix with team
 According to you, what 3. I deployed as my coordinator
were the key factors 4. I analyzed his behavioral issues & sent him to site to
contributing this? start discussing the site team to discuss progress & issues
 How did you go about problems. Gradually made him dialogues with the staff, &
resolving these issues? developed trust between them and created confident
 What helped in gaining slowly in his actions.
buy-in-from all team 4. Learnings – By continuous supporting and mentoring
members on this? can develop new comer also a potential candidate for the
 What is your learning from project performance.
this experience?

Customer oriented
9 Tell me about recent instance Due to tough schedule and milestone, quick decision
where you developed a solution making become inevitable to avoid any delays. Customer
jointly with the customer (internal also very much focused to Fast-track on the work
& external) progress.
 Who was the customer in
this case? 1.APCRDA, ADCL external customer& TI IC were the
 What was the need you are internal partner & there was s suggestion from customer to
trying to address? delegate the power to next level people.
 How did you approach the
co- creation of the solution 2.All the time Project Director used to attend progress
with your customer? meetings with PGMC, PMC, Client, Vendors, Top
 What specifically helped management, Design team, technology providers, etc.
you in doing so? which resulted delay in decision making which affected
 What was the feedback progress.
you received in this case?
What were the net results 3.We learnt that by delegating CMs to take some of the
decisions as a promotional initiative as PM (informal) for
each package to take quick decisions.

Sensitivity: LNT Construction Internal Use


4.CMs took ownership and acted like PM in resolving
many issues which pushed project progress.

5.Customer was very satisfied with the decision and result.


Easy to access PMs for day-to-day problems solving.
10 Give me an example of a time During the year 2020-21 we have targeted to take
when you leveraged informal industrial development projects at Krishnapatnam (1000cr)
structures to your advantage? & at Chittoor -500cr under APIIC in AP.
Self-met the right person informally to discuss &
1. How did this come out? understand the ground reality, competition, etc in the
2. What steps did you take in projects in first sitting.
this case? In second sitting I could be able to smell the competitor
3. How did you build on these strength & weakness
informal structures to gain Subsequent meeting, I could influence with our strength&
advantage? further information about the political situation & risks.
4. What challenge did you Finally arrived winning formula to secure order
face here? unfortunately the projects are still yet to come for NIT. Still
5. What was the net result follow up is on.

13 Give me an instance of a time Initially, there were lot of complications in finalizing the
when you leveraged your TCS by accommodating 7 utilities within ROW. TCS
understanding of your (internal & finalization is the first & foremost activity for utility works.
external) customer to advise them
on what should be done. 1.APCRDA, PMC & Program consultant & in house
1. Who was the customer in Engineering Team
this case?
2. What were their immediate 2. Short term requirement is to finalize the TCS to kick
& long-term needs? start the construction work and long-term need was ease
3. How did you identify the for O&M.
best solution for them in
this case? 3.Accomodating the major utilities out of main carriage
4. What steps did you to take way could help to achieve faster progress.
to convince them of your
approach? 4.To achieve fast track progress, we should aim to keep
5. What resistance did you very minimum utility in carriage way.
face?
6. How did it all work out? 5.Initially, client was not ready to use MF zone for utilities
What is your key take away from by anticipating clashes between the networks.

Sensitivity: LNT Construction Internal Use


this experience?
6.On an experimental basis, we made clash analysis using
BIM by accommodating 6 out of 7 utilities in the MF zone
and final accepted our idea & benefitted

7.We should do constructability study with engineering


team with the intention to ease the construction works.
29 Give me an example of a time Customer asked us to take back the material from site.
when you took great efforts to
deliver a challenging customer The request delivery was challenging because of the huge
request. quantum of pipe to be taken back which was already
 What made the request invoiced and paid by the customer.
delivery to challenging?
 How did you approach I have attended meetings with Commissioner and
this? approached minister of Urban Development and had made
 What steps did you take him understand the criticality in the customer request.
towards?
delivering on this request? However, I have circulated the available pipe material list
 What support did you to the entire IC so as to utilize the pipe elsewhere. Shifted
require from other in this? 45 km of pipe in view of the larger wastage of materials
 What was the end due to Project Halt. The project specific pipe retained and
outcome? taken the right stand with the client to take over the
 What feedback did you material.
receive from the customer?
The Client has agreed to take over the materials and also
agreed to set off the outstanding with the Mobilization
advance that we are holding which is an amicable win win
to both the parties.

Feedback from the customer has been positive as we


have adjusted the materials.

30 Tell me about a time when you An Executive Engineer (Customer) was not happy with a
had to take steps to receive from a Project Manager assigned to a particular Job and that was
customer complaint. creating hurdles to the Project Progress.
 What was the issue in this In that instance I had intervened and met the officials and
case? understood the concerns of the EE and Team Lead of the
 What was the impact on PMC.
the customers that made

Sensitivity: LNT Construction Internal Use


them complaint? I initially planned to improve the rapport between the PM
 What did you do upon and EE by making both understand the importance of
being alerted to this issue? them working together towards the project progress. I then
(Look for ownership of the called the Project Manager personally and advised him to
issue) be in good terms with the client and made him understand
 How did you plan to the complaints from the client.
recover this?
 What was your course of However, after persistent complaints the PM was
action? replaced. I chose an eligible person within the available
What feedback did you finally staff and elevated him to the level of Project Manager and
receive from the customer on this? ensured the Client relationship and the project progress.

After the replacement, the client in several forum gave


good positive feedback about the new PM and have also
cleared the pending approvals. There upon the entire
power delegation was given to the PM, so that the client
would convey anything and everything to the PM but not
approach the higher management unless its highly
required.

People oriented

11. Give me an example of a time Amaravati project is located adjacent to the Krishna riverbed.
when you challenged your team to Water table was higher than our anticipation, hence closing &
push themselves to deliver greater coming out of the trenches for power duct & sewer line depth
results. of 10-13m was a tough task. I pushed my team to find the
1. What was the situation at way to meet our targets.
the time?
2. What let you to believe 1. Actual rate of progress was just half of our budgeted
that there was a scope for target.
additional value to be
delivered? 2.Instead of carrying out in conventional way, if we apply
3. How did you energize to some new techniques will increase our performance.
deliver this?
4. What specifically did you 3.I conducted root cause analysis and motivated my team to
do leverage your find out a better solution by doing brainstorming & out of box
relationship with them in thinking.

Sensitivity: LNT Construction Internal Use


achieving this?
5. What was the end 4.Positoned myself as easy to approach, carefully listening
outcome? and valuing every team member’s opinion and motivating
them.

5.Finally, our team found a systematic solution like adopting


continuous dewatering system, moving shutter formwork
systems, modified excavation profile and all those contributed
to double the rate of progress.

16. Give me an example of a team Mr. Vijayanand, Construction Manager of ADCL


member who you encouraged to package has been encouraged to take Project
take a larger responsibility. Manager role in newly awarded AGC project.

1. What led you to believe in 1.Systematic approach towards any kind of


this team member? work/problem.
2. What did you do encourage
this individual? 2.Appreciating his potential to grow further to
3. What support did you achieve greater heights and arranged leadership
provide in this case? trainings to know about company’s objectives,
4. How did you keep track of policy & standards.
his/her progress?
5. What was the result of your 3.Delegating works, guiding, and supporting in
efforts? tougher situations to achieve committed results.

4.Comparing his actual performance against


budgeted targets and improvement in operational
excellence.

5.Finally, promoted as a Project Manager for


1000 Cr project and successfully delivering the
results
17. Share an instance where you To foster ‘First time right’ culture, in quality,
actively encouraged ideas from encouraged my team to come up with support

Sensitivity: LNT Construction Internal Use


your team. which they need to uphold it.
1. What was the need for this
at the time? 1.To maintain ‘First time right’ culture, need more
2. What steps did you take to clarity.
encourage your team?
3. What were their reactions to 2.Asked constructive feedback of team members
this? about what support they need to achieve it.
4. How did you ensure they
had the support to deliver on 3.They appropriately suggested that all network
these ideas? layouts should bring into one platform which
5. What was the result of this should be in 3D to easy understanding of utilities
and avoiding reworks.

4.Immediately taken up with EDRC team and


managed to get 3D modeled underground utilities
by our In-house team through civil 3D for site
execution.

5.Executoin team took advantage to fast-track the


progress by avoiding referring 6 different layouts
at a time.

18. Tell me about the last brainstorming Due to the change in government and its
activity you lead in your team prioritization, there may be a chance of de-
scoping. Hence, we had a brainstorming session
1. What was the issue being with all the cross functional department to figure
discussed? out the impact.
2. What were the ideas that
were suggested? 1.Issue discussed – descoping of utilities -If de-
3. How did you evaluate these scope happens, what would be the financial
suggestions when arriving at impact on Margin and difficulties in construction
a final way forward? sequence.
4. What did you do specifically 2. one person is engaged for guiding the
to encourage participation discussion & encouraged everyone to contribute
from all team members? 3.Allowing everyone to share their opinion and
5. What was the result of this? motivating them to think it in different angle.
4. Many ideas came out whether practical or
impractical &
explored all the possible options to assess the

Sensitivity: LNT Construction Internal Use


impact.
5.Comprehensive analysis made to choose
between options
6. During this process no criticism
7.Assessed the impact which likely to happen and
ready with our decisions to negotiate with
customer.
20. Tell me about a time when you While job getting pace, resource mobilization
helped empower a team member to become a critical area to uphold the speed in
succeed. larger scale.
1. What was the situation at
the time? 1.One point of time, there was an immediate
2. How did you go about requirement additional 1000+ labors.
empowering this individual?
3. What were the challenges 2.Made a dedicated team for mobilizing
you faced in doing so? manpower and empowering them to take end to
4. How did support your team end responsibility.
member here?
5. What was the outcome in 3.Lack of coordination was there in mobilizing
this case? manpower.

4.Gave full support to have end to end


responsibility like negotiations, mobilizing, camp
arrangements, one-time allocation, ensuring
timely work front / bills / payments and other
concerns if any.

5.Comparatively, we had a good response in


mobilizing required manpower in line with the
project requirement.

21 Tell me about a time when you 1.Setting up a Design team at site


helped your team deliver on any 2.Usually design jobs are carried at HQ.
initiative, they had taken. Considering 6 no of packages, it is understood
 What was the initiative in design team at HQ will be hectic job in getting
this case? approvals from various stakeholders & hence
 How did you support them decided to set up complete design team of 8
to deliver on this? people from various discipline.
3.Major swift taken place afterwards, daily review

Sensitivity: LNT Construction Internal Use


 What specifically did you do meeting with design team for any issue in
to encourage and motivate drawings or any constrain with clients, it is
them? discussed with concerned authorities to make the
 What was the result of your approvals fast.
efforts?
 What is your key learning
from this experience?
22 Tell me about a recent instance
when you helped a team members Identifying young competent engineers to handle key
professional growth. responsibilities in future for the sustainable growth of
 How did you identify this our organization.
need?  
 What steps did you take to 1.One of the success mantra for any organization is
guide this individual? ‘’Sustainable Growth”. Hence, formulating tomorrows
 What resistance did you leader is becoming mandatory.
face?  
 How did you overcome this? 2.Based on their interest on learnings, performance
 What was the outcomes of on current role, willingness to accept bigger
these actions responsibilities and professional competency, I
selected four competent engineers and trained them
to personally through proper delegation of work,
recognizing and rewarding their efforts and motivated
them on tough situations.
 
3.Along with the practical learnings, some additional
professional learnings also must.
 
4.I nominated them for IPM offered “Planning for
Project Excellence” course and they completed as
well.
 
5.They have gained significant knowledge on
Contracts Management, Project Management, Costing
and Risk Management.

Sl.no Questions Answers

Sensitivity: LNT Construction Internal Use


23 Give me an example of a time when you In typical project environment 20-25 %
supported a millennial in a team. staff are millennials
 What was the background in this 1.As millennials are technology lovers &
case? they want to be always online, engaged in
 What did you do to build rapport & implementation of digitalization initiatives
help this team member? in all the departments to monitor the
 What specific challenges did you status/ progress.
face in doing this? 2.Empower them with autonomy &
 How did you ensure you kept responsibilities to make decision on their
yourself updated when dealing own. Offering flexibility & work from home
with these individuals? facilities. They always tend to work as
 What feedback did you receive group & keep engaged in many aspects of
from this team member or other the business.
stakeholders? 3.They will not respond immediately but
come with the superior solution
4. Self - keep always updated with latest
technology, innovation, and information to
support their ideas.

5.Feedback received from our team was


really encouraging & continue to support in
all the initiatives.
24 Tell me about a time when you 1.Typically the structure of the project
consciously took steps to build leadership team consists of planning, execution &
pipeline in the team. cross functional departments
 What was the structure of the team 2.There were situation to take care of more
then? no. of packages, second line leadership is
 What let you to identifying a need must to manage the projects without
for a second leadership line? compromising the quality, safety, financial
 How did go about doing this? matrix & customer requirements.
 What steps specifically helped you 3. Identified N1, N2 leaders, deployed
in developing your team them into my role to understand the
members? process, policy & values of the company
 What was the outcome of your 4. Focused on development & inform
efforts? everything transparent to gain trust.
5. Identify their strengths & weakness,
given training and development programs
to strengthen their skill gaps
6. Review & monitor their performance

Sensitivity: LNT Construction Internal Use


with the desired matrix , encouraged to
take additional responsibilities with
authority
7. Toady one of my leader is taking care of
entire responsibility & I move into next
position.

Sl.n Questions Answers


o
27 Give me an example of a time when There was acute shortage of manpower for the
you developed the skills of a team execution works and created a big challenge to me
member through active delegation. how to organise.
 What was the need you 1.Nominated one of my team member Mr.
identified in this team member? Visvanathan, senior member, engaged in resource
 How did you go about mobilization.
identifying the tasks that would 2. Discussed timelines and deadlines
address this need? 3. Agreed on a schedule of checkpoints at which
 What support did you offer the will reviewed.
team member through this?
 What was the outcome you 3.clearly articulated the desired outcome
witnessed?
4.Clearly defined the constrains & boundaries -
Where are the lines of authority, responsibility, and
accountability
4. Empowered him with authority & decision
making
5. Provided adequate support & ensure through
proper communication and monitoring as well as
provision of resources.
6. Allowed to control his own methods and
processes. This facilitates success and trust.
7. Built strong motivation and commitment.
Discussed how success will impact financial
rewards, future opportunities, informal recognition,
and other desirable consequences. Provided

Sensitivity: LNT Construction Internal Use


recognition where deserved.

Finally he was able to mobilized the targeted no of


people for the work.

28 Give me an instance of a time when Mr. Anand Thiagarajan, PD of AIIMS Project


you helped a team member or peer located 20 km form our job.
who approached you for support. He approached for two reasons 1. For supporting
 What was the need for the concrete supply & 2. To accommodate his
support that was requested workmen in our labour colony
for? 2. I checked with known sources about his
 What did you do to gain a genuine requirement.
better understanding of the 3. Analyzed our requirement to meet our schedule
situation? (look for probing) & supported with the available resources.
 How did you go about 4.Ecellent feedback received for timely sharing the
providing this support? resources which helped to achieve his target.
 What was the feedback you
received?

Technology
15. Give me an example of a time when During execution phase, before start of any activity
you used digital solution at work? getting approval of SEC card for the workmen was
mandatory. It used to consume significant time of
1. What was the issue you were applying & approving persons. To curtail this, we
trying to address? provided our input to the safety department and
2. What was the issue you were finally got digital solution “Safe Armz”.
trying to address?
3. What was the existing 1.Improving the efficiency of available resources.
process?
4. How did you arrive at the 2. To avoid manually filling, approving &
solution you recommended? maintaining the day-to-day documents.
5. What business results did this
bring in? 3.Manually filling the SEC cards which used to
What is your key learning from this? have 4-5 pages.

4.Fast-track the applying & approving process was

Sensitivity: LNT Construction Internal Use


everyone demand.

5. Not much waiting period to start the work, from


anywhere you can apply & get the approval, no
documentation of physical documents, etc.

6.Approaching problems in a different perspective


without compromising our standards.
19. Tell me about a process you re- 1.As per the contract, 9000 no’s sewer manholes
engineered or modified using to be casted in situ method in one year which is
automation to improve quality or practically not possible and critical & deciding
reduce time. activity for the project completion
1. What was the existing 2.We should go for a mass production by
process? automation & the solution was precasting
2. What made you feel the need 3. We have revised the design for precast
to edit this? manholes with the in-house Engineering team &
3. How did you begin the got approved with client
automation? 4. Engaged 3 precast making factories in and
4. What resistance did you face around to produce 500 no’s each per month
from others? 5. There was resistance from our supply chain
5. How did you overcome this? department for the approval regarding
What was the result of your efforts? transportation of manholes
6. Convinced with the detailed estimate with the
factory-made quality & availability of manhole in
time
7. Sewerage network was completed on schedule
& released the front to our partner.

Innovation
4. Tell me about latest innovative idea Metal Crusher and Project site is in opposite bunds of Krishna
you have implemented? river. Hence, logistics of 100 lac MT (incl TI IC) aggregate become
5. How did the idea occur to you? a bottleneck of the project. 80km distance through road & hence
6. What did you have to do to adopted barge which is a distance 25Km only.
gain buy in for this?

Sensitivity: LNT Construction Internal Use


7. What steps did you take in 1.Small size barge was in operation for local public movement and
ensuring a successful by seeing this we decided to engage large scale barge exclusively
implementation? for our aggregate transportation.
What was the value this added to the
team / department/ business? 2.Negotiated with authorities for approval and barge vendor and
logistics vendor.

3.Made a special barge logistics team (TI IC) which will ensure 10
trips /day and 20 Vehicles / trip to ensure optimum usage.

4. Would have been saved nearly 20 Cr during completion of


Amaravati project by good coordination between crusher team to
end user team, resulted scheduled progress in supply of
aggregates.

14. Tell me about how you encourage 1.Encourage staff to think about innovation every day and to take
innovation in your team. ownership and responsibility for new ideas and solutions.
1. When did happen recently? 2.Empower employees to think about tough problems. 3.Adopt a
2. What was the need for a new non-hierarchical management approach.
approach here?
3. How did you find out about 4.. Develop an innovation strategy - and use it -. By developing an
this ? innovation strategy, leadership provides employees with certainty about
4. What did you do to support the core role of innovation and reinforces the idea that innovation is
your team in this case? everyone’s responsibility. - Developing an innovation strategy also
5. What resistance did you face forces senior management to think about what innovation means to
from others? them, and to state in clear terms how their employees should contribute
6. How did you overcome this? new ideas for products, systems, and services
What results did your team achieve as
a consequence of this?
Accept failure and make it the norm

.
6 Willingness to experiment

7. Embrace co-creation and open innovation opportunities- When it


comes to innovation, don’t be afraid to get your customers involved, too.

Sensitivity: LNT Construction Internal Use


8. Open communication – Be Transparent

9. Staff wellbeing - Recognize and reward successful innovations

10. Ensure staff psychological safety- After all, employees do not


want to feel like attempts at innovation could threaten their jobs if it goes
wrong.

1.It happened two years back.

2.In Amaravathy Trunk infra project ,10 Km RCC power duct to be


constructed in underground for a depth of 10-15 m with the water
table of 3.50 m from the ground within 6 months to accommodate
HT/LT cable

3.Considering the high ground water table, reducing the span of


working at deeper trenches was the need of the hour. Operational
excellence is the key factor to succeed in schedule, cost & quality.

4.Encouraged my team to adapt moving formwork system to


reduce fixing & removing of form wok which consumes 60% of
time.

5.Due to depth & slope variance, the system may not get success
in these kinds of work.

6.Noted all the feedback, engineering needs and designed an


adjustable moving formwork system which can fit for any slope &
depth.

7.Through the innovative idea, the team achieved greater


productivity, reduced cycle time from 25 days to 10 days. resulted
in saving cost & time.