PROCESS AND RESPONSIBILITY MATRIX: DILG 13 (REGIONAL OFFICE) PROCUREMENT PROCEDURES

(GUIDE FOR PUBLIC BIDDING of GOODS AND SERVICES: > Php 500K)

BAC Documentary
END-USER BAC MEMBER BAC TWG HOPE
SECRETARIAT Requirements/Requisites

I. PREPARATION OF BIDDING DOCUMENTS


Prepares and facilitates Treats approved  BAC Minutes of Meeting
approval of Purchase purchase request and  Bidding Documents (by the end user)
Start
Request (PR) & Bidding determines mode of
Documents procurement

II. INVITATION TO BID


2.1 Pre-procurement Conference Calls for a Pre-procurement  Minutes of Pre-procurement Conference
conference (may not be required  Bidding Documents
Prepares Bidding
for ABC Php2M & below)
Documents

2.2 Advertise/Posting Post Invitation to Bid (for 7 days) in:  Invitation to Bid
Post bid bulletin/supplemental
Newspaper (not required for ABC  Final Bidding Documents for Posting
bid (if any) 7 days before the
Php2M & below), PhilGeps, website  Copy (Abstract) of PhilGeps Posting
& Conspicuous place deadline of submission of bids

2.3 Pre-bid Conference Conducts Pre-bid Conference (12 cd  Invitation letters for the Observer
before deadline of submission of bids  Minutes of Pre-bid Conference
(required for ABC Php1M and above)  Bid Bulletin

III. RECEIPTS AND OPENING OF BIDS Receives and Open quotations of at least  Invitation letters for the Observer
3 bidders (determine presence/ absence  Receipt and Attendance Sheets
of required documents  BAC Minutes (Bid Opening)

Conducts bid evaluation (within 7cd  Abstract of Bids


IV. BID EVALUATION Assist the BAC in the initial  Bid Evaluation Report (BER)
Assist the BAC in upon the deadline of the receipt of
preparation of bid proposal) to ascertain eligibility evaluation of the bid
Abstract of Bids & lowest calculated bid and (calculation & specification)
prepares abstract of bids

1
PROCESS AND RESPONSIBILITY MATRIX: DILG 13 (REGIONAL OFFICE) PROCUREMENT PROCEDURES

END-USER BAC Documentary


BAC MEMBER BAC TWG HOPE
SECRETARIAT Requirements/Requisites

VI. POST QUALIFICATION  Notice to LCB re conduct of post qualification


Conduct post qualification (within & submission of documents (within 3cd upon
1 7cd after determination of LCB to receipt of notice): Latest Income & Business
determine responsiveness of bid Tax; PhilGeps Registration
 Post Qualification Report

VII. AWARD, IMPLEMENTATION AND TERMINATION OF THE CONTRACT  BAC Resolution recommending award
7.1 Contract Award Prepares Resolution Determines & with supporting documents: Abstract of
Recommending to HOPE recommends lowest Bids, duly approved delivery schedule,
the awarding of Contract calculated & responsive Sub-allotment or other appropriate
to the LCRB document
bid
 Notice to Award (requires LCRB to post
Prepares delivers Notice of Approves BAC Resolution
performance security)
Award to the LCRB (also (within 7 cd) and signs Notice
requires LCRB to post of Award to the LCRB
performance security)

7.2 Contract Signing and Issuance of Notice to Proceed


Upon submission of the LCRB of the  Purchase Order (by GSS) with attachment:
performance security, signs Bidding documents, winning bidder’s bid
Contract/PO (within 10 cd upon receipt
(eligibility/technical and financial
of NOA) with the winning bidder
proposal), Performance Security, NOA)
 Notice to Proceed (with copy of the
Post Notice to Proceed &
contract/PO)
End Contract/PO (within 3dc Issues Notice to Proceed (within
at PhilGeps, website & 3cd) to the winning bidder
conspicuous place

NOTE: For submission to COA:


1. Copy of Contract or PO (within 5 working days from execution of the Contract).
2. Copy of Bid documents (of all bidders) in case of failure of bidding.