Professional Documents
Culture Documents
! !
" "! "#
&'( )*"
+(" &,-$./012-)$3
!
45+
45
( 6*"
(" &(*" (-$./012 7
, 2
34
$
! "
#
$
5
%
&'()))** 6
# 347 !4
3
$ +
)**',!,*-.. '1))),
/0 +
)**',!(*-1 $ )8,',-)!!!,
/0 +
)8,',-)!--(
* 4'#' 2
! 4'#' 2
94&4
:; 4 + =
$
5
9 54 34#4'(-),,
3#
$ +
)8(!',-!)).1
< 24# /0 +
)8(!',-!.)!
4'1*!))! /0')8-',!))(..
- 5 4 # 8 2
25 > 3
"
7
&& && $
5
$ +
)*-.,',),,!!) 6
# 347 14 /
?'
&
/0 +
)*-.,',),.,( & %
&'())).
$ +
)**',**(),)8
( #5
1 4 =5 =
25 $
: $:
= "?
"
5
@
?
+
?
A#
B
+
,
',.
3 ?+ "##',,))
$ +
),!',-(18
/0 +
),!',-(.*,
. 2
=5
) 4'#' 2
== = 2
6
5
3'. D## @#
? 26 $
6@
% + 24'))8 %
&'()))-!
$ +
,81-,1!*
/0 +
,8,8-,!-,- ,8-*8.)
4'#' 2
, 4'#' 2
+$
+<
+$ 34 +< =
50
=
50 @#
?
'**
4
+ 24 ' )))* /
' ,))* <
* 4
5
@
/
Voltage
State/ Executing Transmission Circuit Length Commissioning
Level (in Quarter
Sector Agency Lines Type (Ckm) Month
KV)
Ranchi -
Medinipur
POWERGRID line (PM-JTL- 765 D/C 538 Feb-21 Q4
TBCB)
LILO of both
ckts. of
Chandithala -
Central
Kharagpur at
Sector POWERGRID 400 D/C 148 Feb-21 Q4
Medinipur
(PM-JTL-
TBCB)
Darbhanga -
POWERGRID Sitamarhi 400 D/C 80 Mar-21 Q4
(New) line
Voltage
State/ Executing Transmission Circuit Length Commissioning
Level (in Quarter
Sector Agency Lines Type (Ckm) Month
KV)
(Ckt.-I) (Triple
Snowbird)
(ERSS XXITL
- TBCB)
LILO of both
Ckts. of
Nabinagar-II -
Gaya (Q) line
POWERGRID 400 D/C 6 Mar-21 Q4
at Chandauti
(ERSS
XXITL-
TBCB)
Re-
Conducting
POWERGRID of Rangpo - 400 D/C 220 Mar-21 Q4
New Siliguri
line
Sitamarhi
(New) -
Motihari line
(Triple Q1 of
POWERGRID Snowbird) FY
400 D/C 171 Apr-21
(ERSS 2021-
22
XXITL-TBCB)
Private
NIL
Sector
LILO of Joda- Q1 of
TTPS line at FY
Odisha OPTCL 220 D/C 29 May-21
Telkoi 2021-
22
Subashgram
(PG) - 220 D/C 64 Jan-21 Q4
Baruipur
West LILO of
WBSETCL
Bengal Arambag -
Rishra at N. 220 D/C 31 Mar-21 Q4
Chanditala
2.2 Following substations/ICTs have been commissioned in the Eastern Region during Q4
of 2020-21 and Q1 of 2021-22:
Extn. at Rourkela
POWERGRID S/stn. (ICT-II) 400/220 315 Feb-21 Q4
1 220 kV These lines are not N-1 compliant. 1. Planning of additional 220 kV
Buddhipadar- This issue has been observed with transmission lines from 400/220
Lapanga D/C, very high injection from Vedanta kV Rourkela substation (2 X630
220 kV Captive plant ( 250-300 MW) on a MVA ICTs being evacuated
Buddhipadar persistent basis. Further, it has through two 220 kV lines (500
Vedanta D/C and been enhanced with the retirement MW maximum).
Sl.
Corridor Description of the constraints Remedial Action Plan :
No
2 220 kV Waria- 220 kV Bidhan Nagar (Durgapur) is Included in Agenda Item no. 6
Bidhan Nagar D/C a Major load centre in West Bengal
Area. With nearby generating plant
of DVC feeding these load due to
low impedance path is resulting in
higher loading of the220 kV Waria-
Bidhan Nagar D/C. In addition to
these, the 220 kV Bus at Bidhnagar
is operated in split mode due to
high fault level by opening of 220
kV bus coupler. Further, the
400/220 kV Waria-Parulia (D/C)
has been made LILO at 400/220 kV
DSTPS and one of the 400/220 kV
ICT are in service making these
circuits a low impedance path and
thus their overloading.
Sl.
Corridor Description of the constraints Remedial Action Plan :
No
7 220 kV Rajarhat- These lines are not N-1 compliant. 1. Commissioning of Rajarhat
Newtown D/C and In this qtr, 220 kV Shubhasgram- (POWERGRID) – New Town
220 kV EMSS loading is low however it is AA2 220 kV D/c, Rajarhat
Subhasgram- more during the summer season. (PGCIL) – Barasat/Jeerat 220
EMSS D/C kV D/c and Subashgram
(PGCIL) – Baraipur 220 kV D/c.
2. Load trimming scheme has
been implemented by CESC for
(n-1) contingency on 220 kV
Subhasgram-EMSS D/C.
9 220 kV Gaya- These lines are not N-1 compliant. With commissioning of 400/220 kV
(PG) -Bodhgaya substation at Chandauti by LILO of
D/C Gaya-NPGC 400kV D/C line at 400
kV Chandauti and shifting of some
load from Bodhgaya to this new
substation loading of this line is
expected to be reduced.
10 220 kV These lines are not N-1 compliant. Baruipur 220 kV substation was
Shubhasgram- planned. This will have 220 kv
Lakshmikantpur Shubhasgram-Baruipur D/C and
D/C loads from Lakshmikantpur will be
shifted to Baruipur.
11 220 kV These lines are not N-1 compliant. Additional 220 kV Lines from
BuddhipadarLapa 400/220 kV Raurkela substation
nga D/C, 220 kV need to be planned.
Buddhipadar
Vedanta D/C and
220 kV Rourkela-
Tarkera D/C
ICT constraints:
● Planning of Bus
● Antitheft charging of 400 kV
Reactor at WBPDCL
Bheramara-Behrampur 2nd D/C
400 kV ● Generating Plant
Less generation at Farakka
Bahrampur, (Kolaghat,
4 and Sagardighi and light
Farakka NTPC, Sagardighi,
loading of lines from Farakka
Sagardighi Bakreshwar) for
and Sagardighi during lean
voltage support in low
hours
generation and lean
hours.
S. No. Nodes Description of the Constraints Remedial Actions:
6.4 Chief Engineer (PSPA-II) stated that this is an operational issue and ERLDC
may convene a meeting with both parties to resolve this matter. ERLDC
conducted a meeting with DVC and WBSETCL on 24.05.2021 (enclosed at
Annexure-II) regarding high loading on 220 kV Durgapur (PG)-Parulia (DVC)
D/C line.
6.5 The matter was discussed in the Joint Study meeting held on 14.06.2021
(minutes of the meeting enclosed at Annexure-III), it was agreed that till the
commissioning of 3rd ICT at Bidhannagar, 220 kV Durgapur TPS – Waria TPS
line may be kept open. After commissioning of 3 rd ICT at Bidhannagar, 220kV
Waria TPS – Bidhannagar (WBSETCL) D/c line can be opened. Further,
WBSETCL may prepare long-term solution to the observed constraint like
termination of Waria TPS – Bidhannagar line at some other place instead of
Bidhannagar.
6.6 Members may discuss.
7.3 In the 3rd meeting of ERPCTP, ERLDC reported the constraint of high loading
of 400 kV Maithon-B – Raghunathpur line therefore, the proposal of DVC may
affect power flow in various lines and the fault level at Bidhan Nagar. In the
meeting it was opined to restudy the proposal along with fault level studies with
the revised inputs.
7.4 The issue was discussed in the joint study meeting held on 14.06.2021 wherein
it was agreed that the proposed scheme proposed by DVC will resolve the issue
of N-1 reliability criteria in 220 kV Maithon-Dhanbad D/C and 220 kV Maithon-
Kalyaneshwari D/C lines.
7.5 Members may discuss.
8. Line Reactor in Biharsharif – Lakhisarai 400kV D/c line and new bus
reactor at Biharsharif
8.1 The 400kV Biharsharif – Kahalgaon D/c (Twin Moose) line (about 201km) was
commissioned in 1989 along with 50MVAr single phase line reactors (in each
circuit) installed at Biharsharif end. The said line was LILOed for establishment
of 400/132kV Lakhisarai (POWERGRID) S/s under ERSS-III in the year 2014.
After the LILO, new sections formed are as mentioned below:
a. 400kV Biharsharif – Lakhisarai D/c line (about 89km)
b. 400kV Lakhisharai – Kahalgaon D/c line (about 145km)
8.2 Upon LILO of the Biharsharif – Kahalgaon line at Lakhisarai S/s, the 50MVAr
line reactor (in each circuit) was retained in the Biharsharif – Lakhisarai line at
Biharsharif end and were converted to switchable line reactors due to
overcompensation issues. Further, while split bus arrangement was being
carried out at Biharsharif S/s at 400kV level, some of the 400kV lines were
reconfigured at the substation. Thus, presently one 50MVAr line reactor is
installed in Biharsharif – Sasaram ckt-1 and other 50MVAr is installed in
Biharsharif – Lakhisarai ckt-2. No line reactors are installed at Biharsharif end
in Biharsharif – Sasaram ckt-2 and Biharsharif – Lakhisarai ckt-1.
8.3 It is understood from POWERGRID that after serving the transmission system
for about 32 years, the line reactors are giving frequent trouble in O&M and the
service support is also not easily available since the design has now become
obsolete. Accordingly, it is proposed by POWERGRID to decommission the
said 50MVAr single phase switchable line reactors installed in Biharsharif –
Sasaram ckt-1 and other 50MVAr is installed in Biharsharif – Lakhisarai ckt-2.
8.4 Biharshariff – Lakhisarai 400kV line is about 89km and with 420kV, 50MVAr
switchable line reactor at Biharsharif end, the line is about 84% compensated.
Biharsharif – Sasaram 400kV line is about 210km and with 420kV 50MVAr
switchable line reactor at Biharsharif end & 420kV, 63MVAr switchable line
reactor at Sasaram end, the line is about 81% compensated. From studies it is
observed that the said 2x50MVAr switchable line reactors at Biharsharif end
are not required for line operation purposes.
8.5 Upon splitting of Biharsharif 400kV bus, the section-A has 2x125MVAr +
1x50MVAr bus reactors and the section-B has 1x80MVAr bus reactor. In last
one year, bus voltage in section-B is generally observed to be on higher side
with maximum being about 422kV and average being 406kV. Further, the
50MVAr line reactor (proposed to be decommissioned) associated with
Biharsharif – Lakhisarai ckt-2 is also on section-B. Thus, considering system
voltages, proposed decommissioning of 50MVAr switchable line reactor and
contingency of existing 80MVAr bus reactor, it is proposed to install a new
420kV, 125MVAr bus reactor at Biharsharif in bus section-B. POWERGRID has
confirmed regarding availability of space for the same.
8.6 In view of the above, proposal of CTU is as below:
(a) De-commissioning of 420kV, 50MVAr single phase switchable line reactors
presently installed at Biharsharif end in 400kV Biharsharif – Sasaram ckt-1
and 400kV Biharsharif – Lakhisarai ckt-2.
(b) Installation of new 420kV, 125MVAr bus reactor along with associated bay
in bus section-B (Bus-1 & 2) at Biharsharif (POWERGRID) S/s.
Teesta VI HEP – Rangpo (POWERGRID) 220kV D/c line with twin moose
conductor (conductor temp. 85°C) along with associated line bays at both ends:
Under the scope of generation developer.
14.5 Connectivity Granted to Teesta-IV
NHPC Ltd. was granted Connectivity of 520MW for its upcoming Teesta-IV HEP
(520MW) through LILO of Teesta-III HEP – Rangpo 400kV D/c (Quad) line at
Teesta-IV HEP (to be built under ISTS) vide intimation dated 01-01-2021 after
deliberations in the 2nd meeting of ERPC-TP. Subsequent to grant of
Connectivity, NHPC Ltd. signed the Transmission Agreement on 02/03/2021
for taking up the system under ISTS. But they failed to submit the Construction
Bank Guarantee (26 Cr.) as per CERC Connectivity Regulations within
stipulated time even after multiple reminders. Accordingly, CTUIL vide letter
dated 23-06-2021 has revoked the said Connectivity granted to NHPC Ltd. for
its Teesta-IV HEP.
14.6 Members may note.
15.1 In few cases generation projects were commissioned ahead of the anticipated
commissioning of the associated transmission system. In such cases,
generation projects were given temporary connectivity through loop-in & loop-
out (LILO) of nearby transmission lines so as to enable them connect with the
grid. The temporary connectivity through LILO was to be withdrawn after
commissioning of the associated transmission system. Associated
transmission system of some of such generation projects have been
commissioned and their temporary connectivity through LILO has been
disconnected; however, some generators are still connected through LILO
arrangement. CERC in its order dated 07-102015 on Petition No.112/TT/13 and
dated 28-09-2016 in Petition no. 30/MP/2014 has directed that the interim
(LILO) arrangement has to be removed.
15.2 The progress of associated transmission system of IPPs and the deliberations
in the 3rd ERPC(TP) meeting is summarized as below:
Generation Project in ER connected through temporary LILO arrangement
Present Final Anticipated
Sl. Generation IC
Connectivity through LILO Connectivity Completion
No. Project (MW)
Arrangement Schedule
Sneha LILO of one LILO of one circuit of December
Kinetic circuit of Teesta-III – Dikchu pool – Singhik 2021, by
Power Rangpo 400kV D/c line at D/c (Twin Moose) line Sikkim.
1 2x48
Projects Pvt. Dikchu (220kV line operated at
Ltd. (Dikchu (granted in Dec’14 by 132kV) at Dikchu HEP
HEP) CERC)
LILO of one circuit of Tashiding – Legship December
Shiga Energy
Rangpo-New Melli 220kV Pool 220kV D/c 2021, by
Pvt. Ltd.
2 2x48.5 D/c line at Tashiding line Sikkim.
(Tashiding
through Tashiding-Legship
HEP)
Pool-New Melli 220kV D/c
15.3 E&P Dept., Govt. of Sikkim may provide status update on above matters.
16. Status of downstream 220kV or 132kV network by STUs from the various
commissioned and under-construction ISTS substations
16.1 Numbers of ISTS sub-stations have been commissioned and some are under
construction for which the downstream system is being implemented by the
STUs. Based on the information provided by the states in 3rd meeting of
ERPCTP, updated information on planned/under-construction downstream
system is as follows:
A. Existing Substations:
c. To be implemented by Jharkhand:
Updated
Sl. Transformation Completion
Substation/Location Date of Award
No. Capacity/ Element Schedule
1) Daltonganj 400/220/132kV
Daltonganj
i) (POWERGRID) – 220kV D/c Dec, 21
Latehar
Daltonganj
ii) (POWERGRID) – 220kV D/c commissioned
Garhwa (New)
Daltonganj
iii) (POWERGRID) – 132kV D/c Dec, 21
Chatarpur
2) Chaibasa 400/220kV
Chaibasa
i) (POWERGRID) – 220kV D/c No update
Jadugoda (JUSNL)
JUSNL may update
d. To be implemented by Bihar:
Updated
Sl. Transformation Completion
Substation/Location Date of Award
No. Capacity/ Element Schedule
1) Sitamarhi 400/220/132kV
Sitamarhi (New) – Commissioned
i) 220kV D/c
Motipur (BSPTCL)
Sitamarhi (New) – 220kV D/c Mar, 2021
ii) Raxaul (New) (Twin Moose)
Sitamarhi (New) – Commissioned
iii) 132kV D/c
Runni Saidpur
LILO of Benipatti –
iv) Pupri132kV S/c at 132kV S/c Feb, 2021
Sitamarhi (New)
2) Chandauti 400/220/132kV
LILO of Gaya 220 KV
(POWERGRID) – Chandauti(New)-
Sonenagar 220kV D/c Sonenagar I & II
at Chandauti (New) Commissioned.
220 KV
Chandauti-
i) 220kV D/c Bodhgaya-I & II
Antitheft
Charged (LILO
at Bodhygaya is
under
implementation
by BSPTCL.
LILO of Chandauti
(BSPTCL) – Rafiganj
ii) 132kV S/c Mar, 2021
132kV S/c at
Chandauti (New)
LILO of Chandauti
(BSPTCL) –
iii) 132kV S/c Mar, 2021
Sonenagar 132kV S/c
at Chandauti (New)
BSPTCL may update
Updated
Sl. Transformation Completion
Substation/Location Date of Award
No. Capacity/ Element Schedule
1) Saharsa 400/220/132kV July 2021
Saharsa (New) – Mar, 2021
i) 220kV D/c
Khagaria
Saharsa (New) – Jul, 2021
ii) 220kV D/c
Begusarai
Saharsa (New) –
Saharsa 132kV D/c line
formed by LILO of
iii) Saharsa – Banmankhi 132kV D/c Feb, 2021
and Saharsa – Uda
Kishanganj 132kV S/c
lines
2) Dhanbad 400/220kV July 2021
LILO of the 220 kV
Tenughat – Govindpur (Approval
i) D/c line at Jainamore 220kV expected in 2024-25
and at Dhanbad. next budget)
17.1 Following 400kV substations have been approved in the previous meetings
under intra-state strengthening schemes in ER. Status of
completion/commissioning as per information provided in the 3rd meeting of
ERPCTP is given below:
A. Bihar (to be implemented by BSPTCL/BGCL)
Sl. Transformation Completion
Substation/Location Date of Award Schedule
No. Capacity/ Element
400/220/132/33kV,
2x500MVA + Dec, 21
I Naubatpur GIS 26.04.2018
2x160MVA +
2x80MVA
2x500 MVA +2x160
a) Naubatpur MVA+2x80 MVA Dec, 21
400/220/132 kV S/S
LILO of circuits 3 & 4 of Patna
(PG)-Balia 400 kV D/c (Quad) Dec, 21
b) 400 kV 2x D/C
line at Naubatpur 400 kV 2x
D/C
LILO of both circuits of Ara
(PG) – Khagaul (BSPTCL) line Dec, 21
c) 220 kV 2xD/C
at Naubatpur (New) 220 kV
2xD/C
Naubatpur (New)-Bihta Dec, 21
d) 220kV D/c
(BSPTCL)
Naubatpur (New)-Bhusaula Dec, 21
e) 220kV D/c
(New)
f) Naubatpur (New)- Paliganj 132kV D/c Dec, 21
Naubatpur (New)- Masaurhi Dec, 21
g) 132kV D/c
(existing)
400/220/132kV,
II Bakhtiyarpur GIS: 2x500MVA + 26.11.2019 Dec, 21
2x160MVA
Bakhtiyarpur 2x500 MVA +2x160 Dec, 21
a) MVA 400/220/132 kV
GIS S/S
LILO of both circuits of Barh –
Patna (PG) 400kV D/c (Quad)
b) line-1 at Bakhtiyarpur 400 kV 400kV 2xD/c Dec, 21
2xD/C
Bakhtiyarpur (New) - 220 kV D/C Dec, 21.
c) Sheikhpura (New)
Bakhtiyarpur (New) - Hathidah 220 kV D/C Dec, 21
d) (New)
Bakhtiyarpur (New) - Fatuha 220 kV D/C Dec, 21
e) (BSPTCL)
Bakhtiyarpur (New) - Harnaut 132 kV D/C Dec, 21
f) (BSPTCL)
Bakhtiyarpur (New) - 132 kV D/C Dec, 21
g) Baripahari (BSPTCL)
LILO of 132 kV S/C Line
h) Baripahari – Harnaut at 132kV S/c Dec, 21
Bakhtiyarpur
Jakkanpur GIS 400/220/132/33kV, 26.04.2018 Dec, 21
2x500MVA +
III
3x160MVA +
4x80MVA
Jakkanpur 2x500 MVA +3x160 Dec, 21
a) MVA+3x80 MVA
Sl. Transformation Completion
Substation/Location Date of Award Schedule
No. Capacity/ Element
400/220/132/33 kV
GIS S/S
LILO of both circuits of Dec, 21
Nabinagar-II – Patna (PG) 400 kV 2xD/C
b) 400kV D/c at Jakkanpur 400
kV 2xD/C
LILO of both circuits of Sipara
(BSPTCL)-Bihta (BSPTCL) 2x220 kV D/C Dec, 21
c) line at Jakkanpur (new) 2x220
kV D/C
LILO of Khagaul (BSPTCL) -
Sipara (BSPTCL) 220 kV S/C 220 kV D/C Dec, 21
d) line at Jakkanpur (New) 220
kV D/C
LILO of both circuits of
Jakkanpur-Sipara line at
e) Jakkanpur New (being 2x132 kV D/C Dec, 21.
reconductored with HTLS by
BSPTCL) 2x132 kV D/C
LILO of 132 KV S/C
Jakkanpur/Mithapur-Fatuha
f) line at Jakkanpur New (being 132kV S/c Dec, 21
re-conductored with HTLS by
BSPTCL) 132 kV D/C
IV Chappra (New):
Establishment of 2x500 MVA
+2x200 MVA 400/220/132/kV 400/220/132/kV
GSS S/S at Chhapra
LILO of 400 kV Barh (NTPC)
- Motihari (DMTCL) D/C
(Quad) transmission line at 400 kV
Chappra (about 40 km)
220 kV Chhapra (New) -
Gopalganj DCDS (about 100 220 kV Funds not yet 2022-23
km) tied up
220 kV Chhapra(New) -
Amnour DCDS (about 25 km) 220 kV
132 kV Chhapra(New) -
Maharajganj DCDS (about 132 kV
45 km)
132 kV Chhapra(New) -
Raghunathpur DCDS (about 132 kV
80 km)
BSPTCL may update
No agenda points.
MoP vide OM dated 20th May, 2021 amended ToR of NCT (copy enclosed at
Annexure-I) This OM further mention that:
“The Regional Power Committees (Transmission Planning) can make
meaningful recommendations only regarding their own Region. They cannot
decide on transfers across region.”
In compliance of the above OM, we may not discuss Inter-regional transmission
system in the meeting.
-
Annexure-I (Page 1 of 2)
No.15/3/2018-Trans-Pt(5)
Government of India
Ministry of Power
Shram Shakti Bhawan, Rafi Marg, New Del~ hi
2. Further!. NCT, while considering the Transmission P·Janning shall also keep In
mind the follow1ng aspects:
(ii') For enabling growth of Renewable Energy (RE) capacity areas which have high
solar/ ·w ind energy potential, w'ill need to be identified and connected to bulk
power evacuation systems so that capacity can come up there. This is a
national mission as a part of our energy transit~ion goal.
3. This issues with the approva'l of the Honlble ~Minister of State (Independent
Charge) for P'ower and New & Renewable Energy and Minister of State for Skin
Development and Entrepreneurship.
· . . . · · ~
.(Bihari~ · rt~dl
Lal :; I '
Under Secretary to the Govt. of l,ndia
Tetefax: 23325242
Email: transdesk-mop@nic.in
To
{i) All Members of NCT.
(ii) Secretary, Ministry of New & Renewable Energy, Govt. of India.
{iii) Chairperson,, CEA, New Delhi.
(iv) CMD, POSOCO, New Delhi
(v) CM ~ Ds of all CPSEs under the Mintstry of Power, Govt. of India.
-
Annexure-IV (Page 2 of 2)
-~-
(vi) Heads of all autonomous bodies under the Ministry of Power, Govt. of India.
(vii) Finance/ Budget Section, Ministry of Power.
•
(viii) Power/ Energy Secretaries of all States/UTs.
(ix) Chief Executives of all State Power Transmission Utilities.
(x) CEO, NITI Aayog, New Delhi.
Copy to:
-·
- I
,.-
•
Annexure-II (Page 1 of 4)
MoM for meeting on High loading on 220 kV Durgapur (PG) – Parulia (DVC) D/C line
1. In 3rd ERPCTP meeting it was decided that ERLDC will call a separate meeting with DVC and
WBSETCL for High loading on 220 kV Durgapur (PG) – Parulia (DVC) D/C line. In line with the
decision taken, a meeting was called on 24-May-2021 from 11:00 Hrs to dicuss the issue. Both
DVC as well as WBSETCL were requested to come up with all relevant data/information so that
fruitful discussion could take place.
2. WBSETCL representatives could not attend the meeting, this list of participants is as follows
o ERLDC
▪ S. Mondal, DGM ERLDC
▪ S. Sahay, CM ERLDC
▪ C. Kumar, Manager ERLDC
o DVC
▪ Subrata Ghosh, CE, SPE, DVC
▪ Jayanta Dutta, DCE, DVC
▪ Aditi Sen Pradhan, SE, SLDC DVC
3. ERLDC representative presented the current 220 kV snapshot of in and around Durgapur
substation, same is shown below.
Annexure-II (Page 2 of 4)
4. Post commissioning of both the 315 MVA 400/220 kV ICTs at DSTPS and charging of 220 kV DSTPS-
Parulia(DVC), D/C loading of 220 kV Durgapur(PG)-Parulia(DVC) has been reduced significantly.
Most of the time this loading remains below 100 MW.
5. Although 220 kV DSTPS-DTPS(Waria) D/C has also been commissioned but DVC cannot keep it in
loaded condition, as it results in very high loading of both the lines (close to its thermal loading
limit). Further N-1 contingency of 315 MVA ICTs at DSTPS are also not satisfied during that
condition.
6. One of the reasons for such high flow in 220 kV DSTPS-DTPS(Waria) D/C (when connected) is high
export to Bidhannagar (WB) from DTPS(Waria) through 220 kV DTPS(Waria)- Bidhannagar (WB)
D/C Line. WBSETCL Bidhannagar is connected at 400KV to Durgapur(PG), PPSP and New
Chanditala, from where the Voltage level is stepped down to 220KV through 2 Nos’ 315MVA
400KV/220KV ICTs and different 220KV Interconnections are maintained at 220KV Level. It has
been observed that with the introduction of 2 No’s 315MVA 400/220KV ICT at DSTPS, appreciable
load of WBSETCL Bidhannagar is feed through 220KV D/C DTPS – WBSETCL Bidhannagar tie Line
thereby overloading the 220KV D/C DTPS – DSTPS Line and defeating the n-1 contingency of ICT
at DSTPS.
7. In the earlier configuration, DTPS(Waria) was receiving power from Parulia(DVC), through 220 kV
Parulia-DTPS D/C. Latter this line was LILO ed at 400/220 kV DSTPS and 220 kV DSTPS-DTPS section
is kept open due to its high loading. This resulted in loss of one major infeed to 220 kV DTPS and
subsequently high loading of remaining infeed which is 220 kV Mejia-A - DTPS(Waria) D/C. At
present at instances N-1 Contingency criteria is not satisfied for the above 220 kV Mejia-A -
DTPS(Waria) D/C.
8. 220 kV Mejia-A has very high fault level, thus normally it runs in bus split mode. As informed by
DVC SLDC during the meeting, running Mejia-A in split mode results in skewed loading in 220 kV
Mejia-A - DTPS(Waria) D/C due to non - availability of equal number of generators in 2 segregated
buses ( usually 5 out of the 6 Units are in service at MTPS ‘ A) . Here it is to mention that with 4
nos of units running at Mejia-A, it can be operated in single bus mode, but beyond that split bus
is preferable considering the fault level.
9. DVC SLDC shared that with commissioning of 220 kV Parulia-Burdhman D/C line loading of DSTPS-
DTPS(Waria) D/C is expected to reduced somewhat, however even after that it will not be possible
to keep the line in service.
10. ERLDC stated that in the radius of around 30 kMs three 400/220 kV substation i.e Durgapur(PG),
DSTPS(DVC) and Bidhannagar (WB) is located with total transformation capacity of 7 x 315 MVA,
approximately 2000 MVA. However, utilization of these became very skewed post commission of
400/220 kV ICTs at DSTPS and subsequently LILO of 220 kV lines there.
11. ERLDC is further of the view that for proper utilization of ICTs at Durgapur(PG) and control of
loading of underlying 220 kV network, West Bengal may plan to one double ckt infeed from
Durgapur(PG) to some nearby 220 kV substation of WBSETCL.
12. Participant felt that both long term and short-term plan need to be chalked out for talking this
problem.
13. One of the short-term measure could be opening of 220 kV DTPS(Waria)- Bidhannagar (WB) D/C,
however before opening it need to be ensured that same is not causing any additional constraint
Annexure-II (Page 3 of 4)
in either DVC system or WBSETCL system. Further both DVC as well as ERLDC felt that opening of
tie line should be done only as last resort, and before that WBSETCL should explore possibility of
network reconfiguration in and around Bidhannagar so that loading of D/C 220KV DTPS –
Bidhannagar Tie line can be reduced and opening of 220KV D/C DTPS – DSTPS Line can be avoided.
14. Draft MoM was shared with DVC as well as WBSETCL, comments received from Additional CE,
WBSLDC through mail on 2-June-2021 is attached in Annexure-I
Annexure-II (Page 4 of 4)
Annexure-1
1. No representative from WBSETCL was there in the meeting, as various meetings took
place on the same day as preventive actions for the cyclone "Yaash", which was expected
to affect some part of the state on and from 25th May. So, on receipt of the MOM we are
sharing the view of WB SLDC here.
2. In ref to last point (No 13) of the minutes opening of 220 kV DTPS(Waria)-Bidhannagar
(WB) D/C as short term measure can not be possible till commissioning of 3rd 315 MVA
ICT at Durgapur(Bidhannagar) 400 kV Sub-stn. It's target time of Commissioning is June
2022.
3.Moreover I have been directed to convey that WBSETCL doesn't agree to open the
Bidhannagar-Waria 220 kV D/C tie line even after commissioning of 3rd 315 MVA ICT at
Bidhannagar . In view of the problem faced by DVC for overloading the DSTPS-DTPS
segment in case of closing these D/C lines, WBSETCL is trying to work out some
alternative plan to use these tie lines with different connectivities for proper utilisation of
the asset.
4. Also to mention that the entire portion of the Bidhannagar connected network is
operated in loop. So no network rearrangement can reduce the loading of Waria-
Bidhannagar flow. It's important to mention here that this flow depends on several factors
like numbers of units running in DPL, BKTPP etc.
On point 11 (last but two in the MOM) CPD, WBSETCL will share their view after due
consideration of the proposal and the feasibility. Also on the point (3) above, you may
take up the matter with the concerned department of WBSETCL, i.e. with CPD,
WBSETCL.
File No.CEA-PS-12-15/2/2018-PSPA-II Division-Part(1) 498
Annexure-III (Page 1 of 9)
I/16095/2021
भारत सरकार
Government of India
विद्युत मंत्रालय
Ministry of Power
के न् द्री य वि द्यु त प्रा धि क र ण
Central Electricity Authority
वि द्यु त प्र णा ली यो ज ना ए वं मू ल् यां क न प्र भा ग - I I
Power System Planning & Appraisal Division-II
Sub : Minutes of the Joint Study meeting on issues referred by 3rd Eastern
Region Power Committee (Transmission Planning) (ERPCTP).
महोदय/ Sir,
भवदीय/Yours faithfully,
सेवा भवन, आर. के . पुरम-I, नई दिल्ली-110066 टेलीफै क्स: 011-26732325 ईमेल: cea-pspa2@gov.in वेबसाइट: www.cea.nic.in
Sewa Bhawan, R.K Puram-I, New Delhi-110066 Telefax: 011-26792325 Email: cea-pspa2@gov.in Website: www.cea.nic.in
File No.CEA-PS-12-15/2/2018-PSPA-II Division-Part(1) 499
Annexure-III (Page 2 of 9)
I/16095/2021
List of addressee:
Chief Engineer (PSPA-II), CEA welcomed all the participants and stated that in the
3rd meeting of Eastern Region Power Committee (Transmission Planning)
(ERPCTP) held on 9th February, 2021, few issues were referred for joint study.
Accordingly, the Joint Study meeting was held on 14 th June, 2021. List of
Participants is enclosed at Annexure-I. Issue wise discussion is given below:
1. Connectivity to Teesta-IV HEP (520 MW), Sikkim of NHPC Limited:
1.1. Director (PSPA-II), CEA stated that in the 2 nd meeting of ERPCTP connectivity of
Teesta-IV HEP with ISTS was agreed. In the 3 rd meeting of ERPCTP, ERLDC
stated that at Teesta-IV switchyard, one and half breaker scheme may be
implemented instead of double bus single breaker scheme. He also suggested
that 400 kV LILO of Teesta-III – Rangpo D/C line to be terminated at Teesta-IV in
such a way that in any contingency at switchyard, the line can be bypassed
through Tie Circuit Breaker. Further, there should not be any limiting constraint on
account of cables used.
1.2. Representative of NHPC presented the SLD of Teesta-IV HEP switchyard (SLD is
enclosed at Annexure-II). He stated that the switchyard has been planned in
open space, therefore, evacuation lines will be terminated to the GIS bus, without
cables. He further stated that due to space constraint, one and half breaker
scheme cannot be implemented.
1.3. ERLDC stated that in case of outage of a bus section, power evacuation from
Teesta-III HEP may get affected. NHPC replied that in case of fault in one bus
section, power will be handled by the second bus section.
1.4. ERLDC proposed that a scheme in generation switchyard, prior to bus connection,
may be implemented such that the 400 kV LILO of Teesta-III – Rangpo D/C line
can be bypassed through an isolator arrangement. To implement this, adjacent
feeders shall be from different sides of the LILO. This will provide operational
flexibility and avoid blockage for power evacuation from Teesta-III, if fault takes
place at any of the feeder.
1.5. Representative of NHPC stated that due to space constraint, bypassing
arrangement through isolator is not feasible to implement.
1.6. Representative of CTU suggested that at LILO tower, some arrangement of
bypassing the power from one circuit to another circuit may be made.
1.7. CE (PSPA-II), CEA stated that as per NHPC bypassing arrangement at
generation switchyard is not feasible, therefore, connections at LILO tower can be
File No.CEA-PS-12-15/2/2018-PSPA-II Division-Part(1) 501
Annexure-III (Page 4 of 9)
I/16095/2021
arranged in such a manner that it can be bypassed in minimum time. Further, the
LILO has been agreed for implementation under ISTS, as such, the provision
need to be flagged for incorporation in RfP documents.
1.8. After the deliberation, it was agreed that arrangement at LILO tower would be
carried out in such a manner that in case of major issue in Teesta-IV switchyard,
the LILO can be bypassed in minimum time.
Waria TPS – Bidhannagar (WBSETCL) D/c line may be opened only after
installation of 3rd ICT at Bidhannagar to make it N-1 reliant. To control the fault
level, they are using bus coupler at Bidhannagar and rearranging the loads. He
also stated that further studies need to be done at their end. They will also plan to
terminate Waria end to another substation.
2.7. After deliberation, it was agreed that till the commissioning of 3rd ICT at
Bidhannagar, 220 kV Durgapur TPS – Waria TPS line may be kept open. After
commissioning of 3rd ICT at Bidhannagar, 220kV Waria TPS – Bidhannagar
(WBSETCL) D/c line can be opened. Further, WBSETCL may prepare long-term
solution to the observed constraint like termination of Waria TPS – Bidhannagar
line at some other place instead of Bidhannagar.
3. Non-compliance of N-1 contingency criteria on 220 kV Maithon-Dhanbad D/C
and 220 kV Maithon-Kalyaneshwari D/C line.
3.1. Director (PSPA-II), CEA stated that the issue was discussed in the 3 rd meeting of
ERPCTP wherein DVC proposed following schemes to meet the substantial
Power Demand of Barjora, Durgapur, CTPS & downstream connectivity’s of that
region and relieving congestion by reduction of power flow of 400KV S/C RTPS –
Maithon (PG), 220KV D/C Kalyaneswari – Maithon (PG), 220KV D/C Parulia
(DVC) – Parulia (PG) & 220KV D/C Dhanbad – Maithon (PG):
A. Establishment of 220KV infrastructure at existing Raghunathpur Thermal Power
Station (RTPS) along with associated lines
Presently, RTPS is having two units (U # 1 & 2 : 600 MW x 2) which are
connected to 400KV grid system. DVC proposed for:
a. Establishment of 220KV side connectivity of 2 x 315MVA 400/220KV ICT
(already in service) along with 04 nos. of 220KV line bays for the connectivity
of item b.
b. D/C LILO of 220KV Chandrapura TPS – Kalyaneswari line to RTPS
B. Construction of 400KV (AIS)/220KV (GIS) infrastructure at existing Mejia Thermal
Power Station (MTPS) along with associated lines
MTPS (U # 1 to 6 : 210 MW x 4 + 250 MW x 2, U # 7 & 8 : 500 MW x 2) is having
no electrical connectivity between the 400 kV and 220 kV system. DVC proposed
for:
a. Installation of 2 x 315MVA 400/220KV ICT along with controlling bays at both
sides and 04 nos. of 220KV line bays for the connectivity of item b & c.
b. Shifting of 220KV D/C MTPS-A – Barjora Line from MTPS – A to MTPS – B
Switchyard
c. Tie connection between MTPS – A & MTPS – B at 220KV level.
File No.CEA-PS-12-15/2/2018-PSPA-II Division-Part(1) 504
Annexure-III (Page 7 of 9)
I/16095/2021
Annexure-I
Sl.
No. Name Designation
400KV
BUS1, 3150A
S.A.
BUS
COUPLER
BUS- I PT
3 PHASE
400kV
BUS-II, 3150A
S.A.
BUS- II PT S.A. S.A. S.A. S.A.
3 Phase, 80 MVAR
BUS REACTOR-1
BUS REACTOR-2
S.A. (OPTIONAL) S.A. (OPTIONAL) S.A. (OPTIONAL) GSU Tr. S.A. (OPTIONAL)
GSU Tr. GSU Tr. GSU Tr.
3 x 53 MVA
11/ 400 KV
LEGEND:-
SC PTSP SC PTSP SC PTSP SC PTSP
ISOLATOR SURGE SA SA SA SA
CIRCUIT BREAKER ARRESTOR
FOR
EARTHING METERING &
CURRENT TR. PROTECTION
SWITCH PT PT PT PT
V.T. DUCT CONNECTION FOR
WAVE TRAP BUSHING CT PT PT PT PT DVR DUPLICATE
PROTECTION
XLPE CABLE
HIGH SPEED
EARTHING SWITCH XLPE CABLE TERMINATION
BUS REACTOR
Note:
1. Bus-bar & Switchyard Equipments current rating in 400 KV GIS shall
be 3150A and short circuit Current rating shall be of 63KA for 1 sec .
2. 400 KV Line conductor shall be of ACSR QUAD MOOSE Conductor.
4. Future Bays are not considered due to Space Constraint in Pothead yard area . GENERAL SINGLE LINE DIAGRAM
64G1 64G1 64G1 64G1
NGT 64G2 NGT 64G2 NGT 64G2 NGT 64G2
Tel No. :033-24239651. 24239650 FAX No. :033-24239652. 24239653 Web : www.eruc.e:ov.in
To
Sir,
11
With reference to above, it is to inform you that the subjected matter of Replacement of existing
SO MVAR LR of 400 kV Maithon-Gaya-1 with new SO MVAR LR (Natural Ester Oil) at Maithon S/s"
was placed for discussion in 1781h OCC Meeting of ERPC held on 20.04.2021.
During deliberation of the agenda in the meeting, POWERGRID explained the features and
characteristics of natural ester oi l vis-a-vis mineral oil and stated that the commissioning of 400 kV SO
MVAR switchable LR with ester oi l is first of its kind in India and had been undertaken as a R&D project
by their O&M wing. They also clarified that the entire cost for this new LR would be met from their
internal fund and there would not be any cost implication on the beneficiaries.
After detailed deliberation, OCC agreed for replacement of the switchable SO MVAR LR of 400 kV
Maithon-Gaya-1 line at Maithon end and the existing SO MVAR LR would be kept as spare Reactor.
Further, OCC referred the proposal to ERPCTP (standing committee on transmission planning of ER)
for approval.
The detail agenda item along with the corresponding deliberation in 1781h OCC meeting is enclosed at
Annexure-! for your reference.
Further Powergrid vide e-mail dated 09/06/2021 informed that new SO MVAR line reactor has already
been received at Maithon 5/s and requested for necessary shutdown of the elements for the
replacement work.
As this is a first kind of R&D project which uses natura l Ester oi l as coo ling medium and the comp lete
cost would be borne by Powergrid, it is requested to consider for in-principa l approval of ERPCTP so
that the replacement work could be done at the earliest.
Thanking You,
Yours faithfully,
Encl: As above
~~o:LI
Member Secretary
Copy to:
1. Chief General Manager(AM), POWERGRID, ER-2, New Town, Bidhan Nagar, Kolkata -7001S6
Annexure-IV (Page 2 of 4)
Annexure-I
shutdown application nor the outage of the main bays after returning of the shutdown was intimated
to ERLDC and stated that it is a violation of grid code.
WBSETCL informed that it is a clear case of violation of standard procedure for taking continuous
shutdown of any elements and stated that in case of any contingency there would be serious
consequence during this period of ongoing assembly election.
OCC took serious note of the above negligence and opined that this type of action is detrimental
for reliability and security of the grid and advised Powergrid to take necessary action so as not to
repeat similar kind of event in future.
Powergrid informed that the issue has been taken by them seriously and already necessary
directives have been communicated to concerned dept/personnel for strict compliance.
Powergrid informed that the main bay would be brought into service after getting the necessary
bus & ICT shutdown at Subhasgram.
OCC advised all the utilities that while availing and returning the shutdown for any elements they
should avail or return the complete elements i.e. with all its associated equipment and in case of
any issues in any part of the equipment they shall intimate ERLDC with written communication.
ITEM NO. B.8: Replacement of existing 50 MVAR LR of 400 kV Maithon-Gaya-I with new
50 MVAR LR (Natural Ester Oil) at Maithon S/s.
Presently, 400 KV Maithon-Gaya-I Line is having switchable Line Reactor (50 MVAR) installed
at Maithon end. Generally, all the oil filled equipment’s (Transformer/Reactors) at EHV
switchyards are filled with conventional mineral oil. However, considering latest technological
advancements in the field of cooling medium and further increasing materials which are more
eco-friendly in nature, first 400 KV class Reactor with natural ester oil is developed as per
POWERGRID design with 50 MVAR capacity.
Few salient features of Easter oil over mineral oil are given in tabular forms for understanding.
10
Annexure-IV (Page 3 of 4)
For subject replacement, existing 50 MVAR LR will be dismantled and kept at spare foundation
as spare Reactor, while, the new asset will be commissioned as 50 MVAR switchable LR of
GAYA-I.
For above activity following S/D’s will be required (Dates are tentative, S/D will be taken only
after receipt of Reactor at Maithon):-
This is first of its kind for such equipment to be charged in India and performance of the same shall be
updated also for future references such that system improvement steps along with eco-friendly measure
can maximize the benefit for the users.
Powergrid representative explained the features and characteristics of natural ester oil vis-a-vis
mineral oil and stated that the commissioning of 400 kV 50 MVAR switchable LR with ester oil is
first of its kind in India and had been undertaken as a R& D project by their O&M wing.
On a query from OCC, they clarified that the entire cost for this new LR would be met from their
internal fund and there would not be any cost implication on the beneficiaries.
ERLDC opined that as the commissioning of LR with ester oil is first of its kind in India, it can be
considered as a pilot project and accordingly the same should get the approval of CEA/CTU.
OCC appreciated the initiatives of Powergrid for adopting the latest technological advancements
in cooling field using eco-friendly ester oil.
11
Annexure-IV (Page 4 of 4)
After detailed deliberation, OCC agreed for replacement of the switchable 50 MVAR LR of 400 kV
Maithon-Gaya-I line at Maithon end and the existing 50 MVAR LR would be kept as spare Reactor.
OCC referred the proposal to ERPCTP (standing committee on transmission planning of ER) for
approval.
ITEM NO. B.9: Assessment of O&M activities for Repetitive Tripping of lines
In recent months, frequent tripping on various lines on account of RoW issues has been observed.
This directly impacts the Eastern regional grid reliability and security.
The below Tables provides a list of such lines where such issues have been observed from July
2020 to March 2021.
It is important to find the real cause of these events and the need for taking preventive action and
remedial measures to avoid such tripping. Due care must be taken by Line owners to ensure such
events are reduced.
No of
Name of Transmission Line Remarks Owner
tripping
All single-phase fault, and 5 times at a
400 kV PPPSP-Bidhannagar-2 12 distance of 140 km approx. from PPSP WBSETCL
end
400 kV Meeramundali-Bolangir 10 All single-phase fault, 5 times B-earth PGCIL
All single-phase fault, and 7 times at a
400 kV-Meramundali-Lapanga 2 10 distance of 170 km approx. from OPTCL
Meramundali end
400 kV Meramundali-Lapanga 1 8 All single-phase fault OPTCL
All at a distance of 30-33 km from
400 kV-Kharagpur-Kolaghat-1 8 WBSETCL
Kolaghat
No of
Name of Transmission Line Remarks Owner
tripping
220 kV Chandil- No A/R at STPS and mostly faults at 90 WBSETCL/
23
STPS(WBPDCL) km from Chandil end. JUSNL
Many times, A/R successful only from
220 kV Khagaria-New Purnea-2 18 Purnea end, but no A/R from Khagaria BSPTCL
which could have avoided tipping
Generally high resistive fault, with OPTCL/
220 kV Joda-Ramchandrapur 14
delayed clearance and no A/R . JUSNL
7-time fault at a distance of 70 km from
220 kV Begusarai-New Purnea-1 11 BSPTCL
Purnea.
JUSNL/BS
220 kV Tenughat-Bihar Sharif 11 Fault mostly in JUSNL portion
PTCL
Fault at a distance of 85 km from fstpp
220 kV Farakka-Lalmatia 11 NTPC
.
Multiple tripping either on fault or due
OPTCL/
220 kV Budhipadar-Korba-2 10 to bus bar mal operation at
CSPTCL
Buddhipadar
12
~ ''f"h!CI? I"'
Annexure-V (Page 1 of 4)
G ove mm e n t of India
~ +4'511 <:."1 "-"'1
Mi n i stry o f Povve r
~ e-l?f'R;i ~ +I ~Rt
Eastern Regional Power Committee i5ll{ ~ail' g 9001-2015
14.~ ~ ~. c:. t &ft Ji Gl.cn"lc-l<hl¢1 1 7 0003:3 ISO : : 9001-2015
14 Gol f C l ub Road. To ll ygunj. 1-<.o l kata-700033
To
With reference to above, it is to inform that the fol lowing agenda items were discussed in the
previous OCC meetings of ERPC and after detailed deliberation, OCC referred the proposal to ERPCTP
(Standing Committee on transmission planning of ER) for further discussion and approval.
1. Arrangement for 33 kV Power Supply to Dulanga Mines from Darlipali STPP of NTPC.
(Discussed in 1781h OCC Meeting held on 20.04.2021)
2. Restoration of 400 kV TSTPS-Meramundu/i-2 to its original length. (Discussed in 1771h OCC
Meeting held on 17.03.2021)
The detail agenda item along w ith the corresponding deliberation in OCC meetings is enclosed at
Annexure-! for your reference.
It is requested to consider the above two issues for discussion in the forthcoming 4th ERPC TP meeting.
Thanking You,
Yours faithfully,
Encl : As above
~JH(::to~l
M~~}J1f (
(N.S.
Member Secretary
Copy to :
Annexure-I
NTPC vide email informed that in-principle approval has been accorded by GRIDCO,
Bhubaneswar, Odisha for availing 15 MVA power supply connection from Darlipali
STPP by Dulanga Coal Mine of NTPC Ltd as a consumer of local DISCOM i.e.
WESCO(presently TPWODL) for mining operation at Dulanga Coal Mine which will be
treated as part of drawl of Odisha share from Darlipali STPP.
Accordingly, two number 33 kV feeders have been envisaged for providing power
supply to Dulanga for mining operation.
In replying to WESCO's query on the subject, M/s GRICO has opined vide their letter
no 106 dated 20.01.2021 to get approval from ERPC/ERLDC regarding the
connectivity and the metering scheme for availing the power supply connection as
Darlipali STPP is a central generating power station.
In 178th OCC meeting of ERPC, NTPC elaborated the issue and informed that
GRIDCO has accorded approval for availing power supply from Darlipali STPP to
Dulanga coal Mines of NTPC Ltd as a consumer of Local Discom.
Accordingly, 2 nos. of 33 kV feeders have been envisaged for supply of power from
Darlipali STPP to Dulanga mines.
On a query from ERPC secretariat, NTPC representative informed that the length of
33kV feeders is 10KM and clarified that the flow through the 33 kV feeders shall be
accounted for as GRIDCO drawal and DSTPP injection and shall not be accounted for
in the auxiliary consumption or as a part of station load of Darlipali STPP.
GRIDCO representative stated that they have given in-principal approval to the
arrangement as proposed by NTPC for evacuation of power from Darlipali STPP
through 33 kV feeders to Dulanga coal mines. The power so evacuated would be
considered as GRIDCO share of drawal and to be consumed by NTPC in the capacity
of being a consumer of local Discom. They submitted that Darlipalli STPP being a
central generating station, the necessary metering arrangement and accounting for the
above scheme needs to be approved by ERPC/ERLDC.
Annexure-V (Page 3 of 4)
ERLDC informed that as the 33 kV feeders are evacuating GRIDCO power and
connected to ISGS and state control area the same should be considered as a tie line.
Accordingly, they stated that the scheme needs to be approved by the standing
committee on transmission planning of ER. However, OCC opined that since the flow
through 33kV feeders shall be accounted for as drawal of Odisha and NTPC intends
to draw power through these feeders as consumer of WESCO (a DISCOM of Odisha),
these feeders can be treated as part of Distribution system.
ERPC Secretariat expressed that the power supply to Dulanga mines shall be totally
separated from Station Transformer of Darlipalli STPP and separate ABT compliant
Special Energy meters to be installed at both end of the 33kV feeders for energy
accounting. Further, if these two feeders are dedicatedly supplying power to Dulanga
Mines, it can be treated at par with auxiliary power drawl of Powergrid Sub-station in
Eastern Region for Accounting purpose.
After detailed deliberation, OCC agreed for the above scheme of power supply to
Dulanga mines from Darlipalli STPP through 2 nos. of 33 kV feeders and the energy
drawl from these two feeders shall be considered as GRIDCO drawl and DSTPP
injection.
Further, OCC advised NTPC to submit the details of above scheme along with
SLD/Sketch details to ERPC Secretariat so that the scheme can be referred to
ERPCTP for necessary approval.
• They stated that due to mismatch in line length, overloading is being observed
in 400KV TSTPS-Meramunduli-1 after tripping of the pole of HVDC Talcher.
The loading of 400KV TSTPS-Meramunduli-2 remains at 60 % of 400KV
TSTPS-Meramunduli-1 during such conditions.
Odisha informed that the bypass arrangement can be shifted from Anugul switchyard
to starting point of the LILO section of 400KV TSTPS-Meramunduli-2 line so that the
electrical length would be equal to its original length and the power flow would be equal
for both the circuits.
It was also proposed by them to upgrade the capacity of existing 220 kV TSTPS-
Meramundali line instead of building a new line.
After detailed deliberation, OCC opined that study need to be carried out by OPTCL
regarding the proposal of constructing new line from Talcher STPP to Odisha system
and decided to refer the issue to standing committee on transmission planning for
further discussion.
File No.CEA-PS-12-15/17/2018-PSPA-II Division 22
I/15962/2021 Annexure-II (Page 1 of 6)
भारत सरकार
Government of India
विद्युत मंत्रालय
Ministry of Power
कें द्री य वि द्यु त प्रा धि क र ण
Central Electricity Authority
वि द्यु त प्र णा ली यो ज ना ए वं मू ल् यां क न प्र भा ग - I I
Power System Planning & Appraisal Division-II
महोदय/ Sir,
भवदीय/Yours faithfully,
सेवा भवन, आर. के परु म-I, नई दिल्ली-110066 टे लीफोन : 011-26732325 ईमेल: cea-pspa2@gov.in वेबसाइट: www.cea.nic.in
Sewa Bhawan, R.K Puram-I, New Delhi-110066 Telephone: 011-26732325, Email: cea-pspa2@gov.in Website: www.cea.nic.in
File No.CEA-PS-12-15/17/2018-PSPA-II Division 23
I/15962/2021 Annexure-II (Page 2 of 6)
1. Director (PSPA-II), CEA stated that Railways has approached CEA for getting ISTS
connectivity at Sasaram (Pasauli) for their Eastern Dedicated Freight Corridor
project. The issue was discussed in 19 th Standing Committee on Power System
Planning of Eastern Region held on 01.09.2017 and Special meeting was held at
Kolkata on 16.07.2018, where Eastern Region constituents had raised concerns over
non-utilization/underutilization of assets created by states and sub-optimal utilization
of RoW & space at ISTS substations.
The issue was further discussed in 1 st meeting of Eastern Region Power Committee
(Transmission Planning) held on 14.02.2020 wherein Railways presented their
response to the concern raised by ER constituents. During discussion on the subject
certain legal, regulatory, operational and transmission planning related issues were
raised.
Subsequently, Ministry of Railways vide letter dated 17.03.2021 has furnished para-
wise comments on the issues raised in ERPCTP meeting, and requested CEA to
resolve the issue of ISTS connectivity at Sasaram (Pusauli) for commissioning of
EDFC (Eastern Dedicated Freight Corridor) as per schedule. To facilitate and resolve
this issue, a meeting inviting CTU, NLDC, ERLDC and Railways was scheduled on
09th April, 2021. However, as no representative from Railways turned up, the meeting
was closed. Railways vide email dated 12.04.2021 requested to re-schedule the
meeting and as such we are having this meeting now.
and Sasaram (Pasauli) out of which ISTS connectivity at Abdullapur and Meerut have
already been granted; however, at Sasaram (Pasauli) it is yet to be granted. The
work of connecting with Pusauli has already been awarded to POWERGRID but as
the issue remains unresolved, the work is yet to be started.
3. He stated that Indian Railways, as deemed licensee under the Electricity Act 2003, is
drawing traction power in the States of Punjab, Haryana, U.P., Bihar and DVC area
through the grid connectivity with respective STUs. In U.P, Traction Substations
(TSSs) in Dadri - Naini section are connected to CTU and is drawing 105MW power
at UP-ISTS.
4. Director (PSPA-II), CEA stated that as per Electricity Act, 2003, transmission licensee
has to give non-discriminatory open access to its transmission system for use by
others. Therefore, if Railways are transmission licensee under the Electricity Act,
then all the duties and responsibilities of a transmission licensee as prescribed in the
Electricity Act, would be applicable to them. This was discussed in detail in 1 st
meeting of ERPCTP. Also, if Railway is a transmission licensee, then its transmission
planning would be carried out by CTU/STU and transmission charges should be
determined by CERC or SERC.
5. Railways stated that they may be treated as special case as they are deemed
licensee recognised by MoP and CERC. They are different from Transmission and
Distribution licensee. Their proposal for EDFC was already discussed in the 39 th
meeting of NR planning meeting held in 2017.
6. Chief Engineer (PSPA-II), CEA stated that the issue of connectivity at Sasaram
(Bihar) will be decided in the meeting of ER planning committee. As per our
understanding, all transmission licensees have to follow all the rules and
responsibilities provided in the Electricity Act, 2003. If any relaxation is being sought
by Railways as a special case, they may kindly approach to MoP.
“4. …….In this regard, it is clarified that Indian Railways constructs the ISTS/STU
connectivity lines as electric supply lines under provisions of Indian Railways Act,
1989 to serve its own loads.”
Further, as Railways are allowed to construct electric supply lines under Railways
Act, 1989 to serve its own loads, granting connectivity to ISTS can be considered to
construct electricity supply line under Indian Railways Act 1989 instead of a licensee
under Electricity Act 2003. But in that case, Railway should not insist to implement
this connectivity line as deemed licensee under Electricity Act 2003.
7. Regarding the question of whether Railways need to apply for connectivity under
provisions of CERC regulations, CTU stated that the connectivity application
File No.CEA-PS-12-15/17/2018-PSPA-II Division 25
I/15962/2021 Annexure-II (Page 4 of 6)
8. Chief Engineer (PSPA-II), CEA opined that Railways cannot be treated as STU as
there are responsibilities of STU that needs to be fulfilled which Railways cannot. It
cannot be treated as Bulk customer as their load is not more than 100 MW which is
the minimum requirement as per CERC. Therefore, Railways being government
organization and having responsibility to construct electricity supply line under
Railways Act, they may not require to submit connectivity application under
regulations of CERC. However, other requirements of connectivity like equipments
information, connectivity agreement etc need to be signed by Railways as per
Central Electricity Authority (Technical Standards for Connectivity to the Grid)
Regulations, 2007 and amendments thereof.
9. CTU stated that the proposal needs to be discussed in the ERPCTP forum and they
would grant the connectivity only after ERPCTP decision.
10. Member (PS), CEA enquired about proposed load of railways from Sasaram.
Railways informed that load of DFCCIL at Sasaram will be initially 30 MVA which will
increase to 60 MVA by 2030.
11. ERLDC stated that at Sasaram s/s, 2x500 MVA transformation capacity is available
and at peak, loading of about 400-450 MW have been observed.
12. CTU stated that 220 kV bays are available at Sasaram for connectivity with Railways
but the ICTs continue to operate at high loading. However, railways load is not very
high and some augmentations can be planned considering future demand
requirement of Bihar.
13. After deliberations, it was agreed that the issue would be taken up in the forthcoming
meeting of ERPCTP for discussion. On the request of Railways to hold the ERPCTP
meeting early, CE (PSPA-II), CEA assured to convene the meeting within one month.
***
File No.CEA-PS-12-15/17/2018-PSPA-II Division 26
I/15962/2021 Annexure-II (Page 5 of 6)
Annexure-I
Sl.
Name Designation
No.
CTU
POSOCO
Sl.
Name Designation
No.