INTERNAL ASSESSMENT EXAM III - May 2021

Subject Code & Name : CS8602 – SOFTWARE ENGINEERING Date : 08-05-2021


Branch : CSE Sem : IV
PART - A (5 X 2 = 10 Marks)
ANSWER ALL THE QUESTIONS
1 What is the difference between verification and validation? Which types of CO4 Analyze
testing address verification? Which type of testing address validation? Understa
2 Why does software fail after it has passed from acceptance testing? Analyze
CO4
Understa
3 Assume that the size of an organic type software product has been estimated to be Analyz
32,000 lines of source code. Determine the effort required to develop the software CO5 &Evalu
product.
4 What are the different types of productivity estimation measures? Analyz
CO5
&Evalu
5 Compare Project Risk vs Business Risk. Analyze
CO5
Understa
PART - B (5 X 8 = 40 Marks)
ANSWER ALL THE QUESTIONS
6 Describe about the various Integration and Debugging strategies followed in
Rememb
Software development. What is integration testing? Discuss all the method in CO4
Underst
detail.
7 i. Compare and contrast alpha and beta testing.(2) Analy
ii. List the phases in software Reengineering process model and explain each CO4 & Unders
phase. (6)
8 i) Suppose you are managing a software development project. The project is
expected to be completed in 6 months at a cost of $10,000 per month. After 3
Analy
months, you realize that the project is 20 percent completed at a cost of $30,000.
CO5 &
You need to determine whether the project is on-time and on-budget after 3
Evalua
months.
ii) Explain the COCOMO II model for estimation.
9 i)An application has the following:10 low external inputs ,8 high external outputs,13CO5 Analy
low internal logical files,17 high external interface files,11 average external inquiries &
and complexity adjustment factor of 1.10.What are the unadjusted and adjusted Evalua
function point counts?
ii)consider 7 functions with their estimated LOC given:fun1-2340,fun2-
5380,fun3-6800,fun4-3350,fun5-4950,fun6-2140,fun7-8400.By historical data
average productivity is 620/m and labour rate is 8000/m. Calculate total
estimated project cost and total estimated project effort?
10

Analyze
CO5
Evalua

Perform an analysis of the project status at week 13 ,using EVA. Use the CPI and
SPI to determine project efficiency .Explain the process involved and organize
the solution as follows:
1. Drawing the Gantt chart of the plan
2. Drawing the Gantt chart of the actual plan (progress status)
3. Perform the analysis (plot PV, AC, EV, CPI, SPI)
Duration : 1 hour 30 Minutes Max Marks: 50