TCPL – 1X63.

75 MW POWER PLANT, GUMMIDIPOONDI


Doc. Ref : LMI /OPR/09 Date of issue: 11/02/05 Rev:1 page:1 of 1

EQUIPMENT CHANGEOVER SCHEDULE

Equipments are to be changeover as per the following weekly schedule to ensure


uniform wear and tear:

MONDAY SEAL AIR FAN


BFP*
MULSIFIER SYSTEM COMPRESSOR

TUESDAY CEP
CCCW PUMP
HVAC / BLUE STAR

WEDNESDAY AIR COMPRESSOR


DEP
OIL VAPOUR EXTRACTOR

THURSDAY HFO PUMP & HEATER


DRY VACUUM PUMP
CT PUMP
CRUSHER, SCREEN
VENTING FAN

FRIDAY FLUIDISING BLOWER


RAW WATER PUMP
FF JOCKEY PUMP

SATURDAY GLAND STEAM BLOWER

*BFP to be changeover once in a month.

Issued by Works manager