Training Day 7 Accomplishment Summary

Date July 12, 2021

Training Location / Site Makati/WFH Description of Daily Training


Bill of Quantities Avery House Unit
Activity

Industry / Company Name / Architectural, Interior Design, Engineering, Construction and Fit-out / D3ID/ 498-A Boni Ave, Mandaluyong, 1550 Metro Manila,
Address Philippines

Name and Signature of


Supervisor

Duration 4-6 weeks Number of Hours 10

Itemization of materials and labor/Calculation of costs including the Summary of Cost and BOQ Breakdown
Details of Training Activity
Pictures of Evidences
Training Day 8 Accomplishment Summary
Date July 13, 2021

Training Location / Site Makati/WFH Description of Daily Training


Bill of Quantities Canary House Unit
Activity

Industry / Company Name / Architectural, Interior Design, Engineering, Construction and Fit-out / D3ID/ 498-A Boni Ave, Mandaluyong, 1550 Metro Manila,
Address Philippines

Name and Signature of


Supervisor

Duration 4-6 weeks Number of Hours 10

Itemization of materials and labor/Calculation of costs including the Summary of Cost and BOQ Breakdown
Details of Training Activity
Pictures of Evidences
Training Day 9 Accomplishment Summary
Date July 14, 2021

Training Location / Site Makati/WFH Description of Daily Training


Bill of Quantities Holly House Unit
Activity

Industry / Company Name / Architectural, Interior Design, Engineering, Construction and Fit-out / D3ID/ 498-A Boni Ave, Mandaluyong, 1550 Metro Manila,
Address Philippines

Name and Signature of


Supervisor

Duration 4-6 weeks Number of Hours 10

Itemization of materials and labor/Calculation of costs including the Summary of Cost and BOQ Breakdown
Details of Training Activity
Pictures of Evidences
Training Day 10 Accomplishment Summary
Date July 15, 2021

Training Location / Site Makati/WFH Description of Daily Training


Bill of Quantities Lauren House Unit
Activity

Industry / Company Name / Architectural, Interior Design, Engineering, Construction and Fit-out / D3ID/ 498-A Boni Ave, Mandaluyong, 1550 Metro Manila,
Address Philippines

Name and Signature of


Supervisor

Duration 4-6 weeks Number of Hours 10

Itemization of materials and labor/Calculation of costs including the Summary of Cost and BOQ Breakdown
Details of Training Activity
Pictures of Evidences
Training Day 11 Accomplishment Summary
Date July 16, 2021

Training Location / Site Makati/WFH Description of Daily Training


Bill of Quantities Madison House Unit
Activity

Industry / Company Name / Architectural, Interior Design, Engineering, Construction and Fit-out / D3ID/ 498-A Boni Ave, Mandaluyong, 1550 Metro Manila,
Address Philippines

Name and Signature of


Supervisor

Duration 4-6 weeks Number of Hours 10

Itemization of materials and labor/Calculation of costs including the Summary of Cost and BOQ Breakdown
Details of Training Activity
Pictures of Evidences
Training Day 12 Accomplishment Summary
Date July 17, 2021

Training Location / Site Makati/WFH Description of Daily Training Rechecking/Adjusting Bill of Quantities of
Activity 5 House Unit and Summary of Quotation

Industry / Company Name / Architectural, Interior Design, Engineering, Construction and Fit-out / D3ID/ 498-A Boni Ave, Mandaluyong, 1550 Metro Manila,
Address Philippines

Name and Signature of


Supervisor

Duration 4-6 weeks Number of Hours 10

Rechecking/Adjusting: Itemization of materials and labor/Calculation of costs including the Summary of Cost and BOQ
Details of Training Activity Breakdown and Summary of Quotation
Pictures of Evidences