TING TAI KONSTRUKSI INDONESIA


EMBEDMENT LIST OF SLIPFORM WORK
Project : PROJECT EPC TUBAN JETTY UPGRADE AND ITS ANCILLARY PRODUCTION & TRANSPORTASION FACILITIES PROJECT
Page : 1/21
Building : BLENDING SILO
Doc. No. : HST-R-PY-001-R00

RADIUS/ POSITION
NO ELEVATION DIMENSION INSIDE / ITEM SHAPE QUANTITY SIGN REMARKS
DEGREE
(M) OUTSIDE

Opening Access road


Loading area
(4000x4000)
(See Drawing TPJC-TQ1-
1 EL. + 30,300 8,450 Out / In 240° 1 By: PT. Ting Tai
DW-C3-391-3S02-001
TPJC-TQ1-DW-C6-391-
3S02-004) : Install frame
opening

Column Opening 4000x


2 EL. + 30,300 8,450 Out / In 240° 2 By: PT. HK
4000

3 EL. + 30,300 7,650 INSIDE 30°; 240° & 180° Column CCI 3 By: PT. HK

Rebar Vertical (Luar &


D32 @100
4 EL. + 30,300 8,450 Out / In 0° - 360° 528 By: PT. HK
dalam)
PT.TING TAI KONSTRUKSI INDONESIA
EMBEDMENT LIST OF SLIPFORM WORK
Project : PROJECT EPC TUBAN JETTY UPGRADE AND ITS ANCILLARY PRODUCTION & TRANSPORTASION FACILITIES PROJECT
Page : 2/21
Building : BLENDING SILO
Doc. No. : HST-R-PY-001-R00

RADIUS/ POSITION
NO ELEVATION DIMENSION INSIDE / ITEM SHAPE QUANTITY SIGN REMARKS
DEGREE
(M) OUTSIDE

Rebar Horizontal (Luar &


5 EL. + 30,300 8,450 Out / In 0° - 360° dalam) 91 By: PT. HK

D19 @100

Opening 1260x1260
EL. + 33,375
(See Drawing TPJC-TQ1-
DW-C3-391-3S02-001
6 EL. + 31,040 8,450 Out / In 145° 1 By: PT. HK
TPJC-TQ1-DW-C6-391-
3S02-004) : Additional
rebar For Opening
EL. + 31,965

EL. + 31,040

EL. + 33,375
Opening Φ740 (See
Drawing TPJC-TQ1-DW-
C3-391-3S02-001
7 EL. + 31,810 8,450 Out / In 105° EL. + 32,635 1 By: PT. HK
TPJC-TQ1-DW-C6-391-
3S02-004) : Install Add
Rebar For Opening
EL. + 31,810

Opening 1260x1260
(See Drawing TPJC-TQ1-
DW-C3-391-3S02-001
8 EL. + 32,040 8,450 Out / In 145° 1 By: PT. Ting Tai
TPJC-TQ1-DW-C6-391-
3S02-004) : Install frame
opening
PT.TING TAI KONSTRUKSI INDONESIA
EMBEDMENT LIST OF SLIPFORM WORK
Project : PROJECT EPC TUBAN JETTY UPGRADE AND ITS ANCILLARY PRODUCTION & TRANSPORTASION FACILITIES PROJECT
Page : 3/21
Building : BLENDING SILO
Doc. No. : HST-R-PY-001-R00

RADIUS/ POSITION
NO ELEVATION DIMENSION INSIDE / ITEM SHAPE QUANTITY SIGN REMARKS
DEGREE
(M) OUTSIDE

150 150

IPL - 4

150

150
9 EL. + 32,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9

2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

Opening Φ740 (See


Drawing TPJC-TQ1-DW-
C3-391-3S02-001
10 EL. + 32,560 8,450 Out / In 105° 1 By: PT. Ting Tai
TPJC-TQ1-DW-C6-391-
3S02-004) : Install frame
opening

150 150

IPL - 4
150

150
11 EL. + 34,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 34,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

Opening Access road


Loading area
(4000x4000) EL. + 34,375
Outside & (See Drawing TPJC-TQ1-
12 EL. + 34,375 8,450 240° 1 By: PT.HK
Inside DW-C3-391-3S02-001
TPJC-TQ1-DW-C6-391-
3S02-004) : Install Add
Rebar For Opening
PT.TING TAI KONSTRUKSI INDONESIA
EMBEDMENT LIST OF SLIPFORM WORK
Project : PROJECT EPC TUBAN JETTY UPGRADE AND ITS ANCILLARY PRODUCTION & TRANSPORTASION FACILITIES PROJECT
Page : 4/21
Building : BLENDING SILO
Doc. No. : HST-R-PY-001-R00

RADIUS/ POSITION
NO ELEVATION DIMENSION INSIDE / ITEM SHAPE QUANTITY SIGN REMARKS
DEGREE
(M) OUTSIDE

EL. + 34,850

Stek Lipat For Canopy


(Beam dan slab) Rebar
13 EL. + 34,850 8,450 Outside 240° 1 By: PT.HK
D16 dan D13 @150

EL. + 38,575

Opening 3000x2500 (See


Drawing TPJC-TQ1-DW-
C3-391-3S02-001
14 EL. + 35,000 8,450 Out / In 113,6° 1 By: PT.HK
TPJC-TQ1-DW-C6-391-
3S02-004) : Install Add EL. + 35,925
Rebar For Opening
EL. + 35,000

Opening 3000x2500 (See


Drawing TPJC-TQ1-DW-
113,6° (Center C3-391-3S02-001
15 EL. + 36,000 8,450 Out / In 1 By: PT. Ting Tai
Line Air Slide) TPJC-TQ1-DW-C6-391-
3S02-004) : Install frame
opening
PT.TING TAI KONSTRUKSI INDONESIA
EMBEDMENT LIST OF SLIPFORM WORK
Project : PROJECT EPC TUBAN JETTY UPGRADE AND ITS ANCILLARY PRODUCTION & TRANSPORTASION FACILITIES PROJECT
Page : 5/21
Building : BLENDING SILO
Doc. No. : HST-R-PY-001-R00

RADIUS/ POSITION
NO ELEVATION DIMENSION INSIDE / ITEM SHAPE QUANTITY SIGN REMARKS
DEGREE
(M) OUTSIDE

150 150

IPL - 4

150

150
16 EL. + 36,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 36,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

150 150

IPL - 4

150

150
17 EL. + 38,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 38,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

500
700

IPL - 16
(Embedded For Floor EL. + 38,670
18 EL. + 38,670 7,650 Inside Column 6 By: PT.HK
EL.+39.370 TOC)
500 x 700 x 16

Detail In Column

450
450

67°, 82°, 123°, IPL-10, embedded for


19 EL. + 38,845 7,650 Inside 158°, 202°, 240°, Slab EL.+39.070 (TOC) EL. + 38,845 8 By: PT.HK
267°, 306° Posisi dinding silo

67°, 82°, 123°,


158°, 202°, 240°,
267°, 306°
PT.TING TAI KONSTRUKSI INDONESIA
EMBEDMENT LIST OF SLIPFORM WORK
Project : PROJECT EPC TUBAN JETTY UPGRADE AND ITS ANCILLARY PRODUCTION & TRANSPORTASION FACILITIES PROJECT
Page : 6/21
Building : BLENDING SILO
Doc. No. : HST-R-PY-001-R00

RADIUS/ POSITION
NO ELEVATION DIMENSION INSIDE / ITEM SHAPE QUANTITY SIGN REMARKS
DEGREE
(M) OUTSIDE

450
IPL-10, embedded for
20 EL. + 38,845 7,650 Inside Slab EL.+39.070 (TOC), 5 By: PT.HK

450
Posisi kolom
EL. + 38,845

Detail In Column

D22 @100
Perubahan besi vertical
luar dan dalam EL.+39,300
21 EL. + 39,300 8,450 Out / In 112.5° 528 By: PT. HK
D32@100 menjadi
D22@100 D32 @100

EL.+39,400 D16 @100


Perubahan besi
horizontal luar dan
22 EL. + 39,300 8,450 Out / In 0° - 360° 111 By: PT. HK
dalam D19@100
menjadi D16@100 EL.+39,300 D19 @100

150 150

IPL - 4
150

150
23 EL. + 40,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 40,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

150 150

IPL - 4
150

150

24 EL. + 42,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 42,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"


PT.TING TAI KONSTRUKSI INDONESIA
EMBEDMENT LIST OF SLIPFORM WORK
Project : PROJECT EPC TUBAN JETTY UPGRADE AND ITS ANCILLARY PRODUCTION & TRANSPORTASION FACILITIES PROJECT
Page : 7/21
Building : BLENDING SILO
Doc. No. : HST-R-PY-001-R00

RADIUS/ POSITION
NO ELEVATION DIMENSION INSIDE / ITEM SHAPE QUANTITY SIGN REMARKS
DEGREE
(M) OUTSIDE

Opening 415x415 (See EL. + 43,350


Drawing TPJC-TQ1-DW-
C3-391-3S02-001
25 EL. + 42,360 8,450 Out / In 113,6°
TPJC-TQ1-DW-C6-391- EL. + 42,785 1 By: PT.HK
3S02-004) : Install Add
Rebar For Opening EL. + 42,360

Opening 415x415 (See


Drawing TPJC-TQ1-DW-
C3-391-3S02-001
26 EL. + 42,860 8,450 Out / In 113,6° 1 By: PT. Ting Tai
TPJC-TQ1-DW-C6-391-
3S02-004) : Install frame
opening

150 150

IPL - 4

150

150
27 EL. + 44,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 44,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

(6pcs)

IPL-10 & IPL-16,


embedded for Slab (6pcs)
28 EL. + 44,795 7,650 Inside Column 12 By: PT. HK
EL.+45.920 (TOC),
EL. + 45,245
Posisi Kolom
EL. + 44,795
PT.TING TAI KONSTRUKSI INDONESIA
EMBEDMENT LIST OF SLIPFORM WORK
Project : PROJECT EPC TUBAN JETTY UPGRADE AND ITS ANCILLARY PRODUCTION & TRANSPORTASION FACILITIES PROJECT
Page : 8/21
Building : BLENDING SILO
Doc. No. : HST-R-PY-001-R00

RADIUS/ POSITION
NO ELEVATION DIMENSION INSIDE / ITEM SHAPE QUANTITY SIGN REMARKS
DEGREE
(M) OUTSIDE

200

300
IPL - 5
(Embedded Support
29 EL. + 45,500 8,450 Outside 137,9° & 158,4° Platform EL.+47.000 EL. + 45,500 2 By: PT.HK
TOS)
200 x 300 x 16
137,9° & 158,4°

450
IPL-10, embedded for
30 EL. + 45,395 7,650 Inside 267° Slab EL.+45.920 (TOC), 1 By: PT.HK

450
Posisi dinding
EL. + 45,395

267°

450
IPL-10, embedded for
31 EL. + 45,395 7,650 Inside 267° Slab EL.+45.920 (TOC), 5 By: PT.HK
450

Posisi Kolom
EL. + 45,395

Detail in Column

EL. + 49,175

Opening 900x2100 (See


Drawing TPJC-TQ1-DW-
C3-391-3S02-001
32 EL. + 46,000 8,450 Out / In 150° 1 By: PT. HK
TPJC-TQ1-DW-C6-391-
3S02-004) : Install Add EL. + 46,925
Rebar For Opening
EL. + 46,000
PT.TING TAI KONSTRUKSI INDONESIA
EMBEDMENT LIST OF SLIPFORM WORK
Project : PROJECT EPC TUBAN JETTY UPGRADE AND ITS ANCILLARY PRODUCTION & TRANSPORTASION FACILITIES PROJECT
Page : 9/21
Building : BLENDING SILO
Doc. No. : HST-R-PY-001-R00

RADIUS/ POSITION
NO ELEVATION DIMENSION INSIDE / ITEM SHAPE QUANTITY SIGN REMARKS
DEGREE
(M) OUTSIDE

EL. + 48,575

Opening 800x1500 (See


Drawing TPJC-TQ1-DW-
15°, 75°, 195°, C3-391-3S02-001
33 EL. + 46,000 8,450 Out / In 5 By: PT. HK
255°, 315° TPJC-TQ1-DW-C6-391-
3S02-004) : Install Add EL. + 46,925
Rebar For Opening
EL. + 46,000

150 150

IPL - 4

150

150
34 EL. + 46,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 46,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

500
700

IPL - 16
(Embedded For Floor EL. + 46,450
35 EL. + 46,450 7,650 Inside Column 6 By: PT.HK
EL.+47.000 TOS)
500 x 700 x 16

Detail In Column

450
450

IPL - 10
36 EL. + 46,625 7,650 Inside Column
(Embedded For Floor EL. + 46,625 6 By: PT.HK
EL.+47.000 TOS)
450 x 450 x 16
Detail In Column
PT.TING TAI KONSTRUKSI INDONESIA
EMBEDMENT LIST OF SLIPFORM WORK
Project : PROJECT EPC TUBAN JETTY UPGRADE AND ITS ANCILLARY PRODUCTION & TRANSPORTASION FACILITIES PROJECT
Page : 10/21
Building : BLENDING SILO
Doc. No. : HST-R-PY-001-R00

RADIUS/ POSITION
NO ELEVATION DIMENSION INSIDE / ITEM SHAPE QUANTITY SIGN REMARKS
DEGREE
(M) OUTSIDE

450

450
IPL - 10
0°; 38°; 82°;
37 EL. + 46,625 7,650 Inside 120°; 158°; 202°;
(Embedded For Floor EL. + 46,625 10 By: PT.HK
EL.+47.000 TOS)
240°; 278°; 322°
450 x 450 x 16
0°; 38°; 82°; 120°;
158°; 202°; 240°;
278°; 322°

450

450
IPL - 10
(Embedded Platform EL. + 46,625
38 EL. + 46,625 8,450 Outside 137,9° & 158,4° 2 By: PT.HK
EL.+47.000 TOS)
450 x 450 x 16

137,9° & 158,4°

Opening 900x2100 (See


Drawing TPJC-TQ1-DW-
C3-391-3S02-001
39 EL. + 47,000 8,450 Out / In 150° 1 By: PT. Ting Tai
TPJC-TQ1-DW-C6-391-
3S02-004) : Install frame
opening

Opening 800x1500 (See


Drawing TPJC-TQ1-DW-
15°, 75°, 195°, C3-391-3S02-001
40 EL. + 47,000 8,450 Out / In 5 By: PT. Ting Tai
255°, 315° TPJC-TQ1-DW-C6-391-
3S02-004) : Install frame
opening

15°, 75°, 195°, 255°, 315°


PT.TING TAI KONSTRUKSI INDONESIA
EMBEDMENT LIST OF SLIPFORM WORK
Project : PROJECT EPC TUBAN JETTY UPGRADE AND ITS ANCILLARY PRODUCTION & TRANSPORTASION FACILITIES PROJECT
Page : 11/21
Building : BLENDING SILO
Doc. No. : HST-R-PY-001-R00

RADIUS/ POSITION
NO ELEVATION DIMENSION INSIDE / ITEM SHAPE QUANTITY SIGN REMARKS
DEGREE
(M) OUTSIDE

150 150

IPL - 4

150

150
41 EL. + 48,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 48,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

Install Dyneset untuk


90°, 180°; 270° & pasang Siku Tahanan
42 EL. + 48,900 8,450 Outside wall 8 By: PT. Ting Tai
360° Butress

200
300

IPL - 5
(Embedded Support
43 EL. + 49,275 8,450 Outside 144,4° & 153,6° Platform EL.+50.775 EL. + 49,275 2 By: PT.HK
TOS)
200 x 300 x 16
144,4° & 153,6°
PT.TING TAI KONSTRUKSI INDONESIA
EMBEDMENT LIST OF SLIPFORM WORK
Project : PROJECT EPC TUBAN JETTY UPGRADE AND ITS ANCILLARY PRODUCTION & TRANSPORTASION FACILITIES PROJECT
Page : 12/21
Building : BLENDING SILO
Doc. No. : HST-R-PY-001-R00

RADIUS/ POSITION
NO ELEVATION DIMENSION INSIDE / ITEM SHAPE QUANTITY SIGN REMARKS
DEGREE
(M) OUTSIDE

Wall Change
(Perubahan Tebal
Dinding dari 800mm ke
44 EL. + 49,500 7,650 Inside wall 0° ~ 360 ° 450mm Pasang Insert 81 By: PT. Ting Tai
Form)
(See Drawing TPJC-TQ1-
DW-C6-391-3S02-004)

D19 @100
Perubahan besi vertical
luar dan dalam
45 EL. + 50,300 8,450 Out / In 0° - 360° EL.+50,300 528 By: PT. HK
D22@100 menjadi
D19@100 D22 @100

150 150

IPL - 4
150

150
46 EL. + 50,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 50,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

EL.+50,400 D13 @100


Perubahan besi
horizontal luar dan
47 EL. + 50,300 8,450 Out / In 0° - 360° 120 By: PT. HK
dalam D16@100
menjadi D13@100 EL.+50,300 D16 @100
PT.TING TAI KONSTRUKSI INDONESIA
EMBEDMENT LIST OF SLIPFORM WORK
Project : PROJECT EPC TUBAN JETTY UPGRADE AND ITS ANCILLARY PRODUCTION & TRANSPORTASION FACILITIES PROJECT
Page : 13/21
Building : BLENDING SILO
Doc. No. : HST-R-PY-001-R00

RADIUS/ POSITION
NO ELEVATION DIMENSION INSIDE / ITEM SHAPE QUANTITY SIGN REMARKS
DEGREE
(M) OUTSIDE

Start dinding Butress


(Bongkar baut waller
90°, 180°; 270° &
48 EL. + 50,300 8,450 Outside wall butress / turun bekisting 4 By: PT. Ting Tai
360°
Butress)

450

450
IPL - 10
(Embedded Platform EL. + 50,400
49 EL. + 50,400 8,450 Outside 144,4° & 153,6° 2 By: PT.HK
EL.+50.775 TOS)
450 x 450 x 16

144,4° & 153,6°

EL. + 52,449

Pasang rangka Opening


900x900 OF & Opening
50 EL. + 50,474 8,450 Outside 150° 1
1100x1100 Install Add
Rebar For Opening EL. + 51,399
EL. + 50,474
PT.TING TAI KONSTRUKSI INDONESIA
EMBEDMENT LIST OF SLIPFORM WORK
Project : PROJECT EPC TUBAN JETTY UPGRADE AND ITS ANCILLARY PRODUCTION & TRANSPORTASION FACILITIES PROJECT
Page : 14/21
Building : BLENDING SILO
Doc. No. : HST-R-PY-001-R00

RADIUS/ POSITION
NO ELEVATION DIMENSION INSIDE / ITEM SHAPE QUANTITY SIGN REMARKS
DEGREE
(M) OUTSIDE

Pasang rangka Opening


900x900 OF & Opening
51 EL. + 51,374 8,450 Out / In 150° 1 By: PT. Ting Tai & PT. HK
1100x1100 IF, Pasang
frame IPL-18 IF

150 150

IPL - 4

150

150
52 EL. + 52,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 52,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

150 150

IPL - 4
150

150
53 EL. + 54,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 54,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

Perubahan besi vertical


D16 @100
luar dan dalam EL.+56,300
54 EL. + 56,300 8,450 Out / In 0° - 360° 1 By: PT. HK
D19@100 menjadi
D16@100 D19 @100
PT.TING TAI KONSTRUKSI INDONESIA
EMBEDMENT LIST OF SLIPFORM WORK
Project : PROJECT EPC TUBAN JETTY UPGRADE AND ITS ANCILLARY PRODUCTION & TRANSPORTASION FACILITIES PROJECT
Page : 15/21
Building : BLENDING SILO
Doc. No. : HST-R-PY-001-R00

RADIUS/ POSITION
NO ELEVATION DIMENSION INSIDE / ITEM SHAPE QUANTITY SIGN REMARKS
DEGREE
(M) OUTSIDE

150 150

IPL - 4

150

150
55 EL. + 56,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 56,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

150 150

IPL - 4

150

150
56 EL. + 58,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 58,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

150 150

IPL - 4
150

150
57 EL. + 60,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 60,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

D13 @100
Perubahan besi vertical
luar dan dalam EL.+62,300
58 EL. + 62,300 8,450 Out / In 0° - 360° 528 By: PT. HK
D16@100 menjadi
D13@100 D16 @100

EL.+62,400 D13 @100


Perubahan besi
horizontal luar dan
59 EL. + 62,300 8,450 Out / In 0° - 360° 172 By: PT. HK
dalam D13@100
menjadi D13@100 EL.+62,300 D13 @100
PT.TING TAI KONSTRUKSI INDONESIA
EMBEDMENT LIST OF SLIPFORM WORK
Project : PROJECT EPC TUBAN JETTY UPGRADE AND ITS ANCILLARY PRODUCTION & TRANSPORTASION FACILITIES PROJECT
Page : 16/21
Building : BLENDING SILO
Doc. No. : HST-R-PY-001-R00

RADIUS/ POSITION
NO ELEVATION DIMENSION INSIDE / ITEM SHAPE QUANTITY SIGN REMARKS
DEGREE
(M) OUTSIDE

150 150

IPL - 4

150

150
60 EL. + 62,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 62,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

150 150

IPL - 4

150

150
61 EL. + 64,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 64,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

150 150

IPL - 4
150

150
62 EL. + 66,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 66,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

150 150

IPL - 4
150

150

63 EL. + 68,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 68,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"


PT.TING TAI KONSTRUKSI INDONESIA
EMBEDMENT LIST OF SLIPFORM WORK
Project : PROJECT EPC TUBAN JETTY UPGRADE AND ITS ANCILLARY PRODUCTION & TRANSPORTASION FACILITIES PROJECT
Page : 17/21
Building : BLENDING SILO
Doc. No. : HST-R-PY-001-R00

RADIUS/ POSITION
NO ELEVATION DIMENSION INSIDE / ITEM SHAPE QUANTITY SIGN REMARKS
DEGREE
(M) OUTSIDE

150 150

IPL - 4

150

150
64 EL. + 70,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 70,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

150 150

IPL - 4

150

150
65 EL. + 72,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 72,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

150 150

IPL - 4
150

150
66 EL. + 74,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 74,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

150 150

IPL - 4
150

150

67 EL. + 76,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 76,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"


PT.TING TAI KONSTRUKSI INDONESIA
EMBEDMENT LIST OF SLIPFORM WORK
Project : PROJECT EPC TUBAN JETTY UPGRADE AND ITS ANCILLARY PRODUCTION & TRANSPORTASION FACILITIES PROJECT
Page : 18/21
Building : BLENDING SILO
Doc. No. : HST-R-PY-001-R00

RADIUS/ POSITION
NO ELEVATION DIMENSION INSIDE / ITEM SHAPE QUANTITY SIGN REMARKS
DEGREE
(M) OUTSIDE

400 400

500

500
IPL - 17
(Embedded For Support EL. + 76,550 EL. + 76,550
68 EL. + 76,550 8,450 Outside 15° & 345° 2 By: PT.HK
TC)
400 x 500 x 16

15° 345°

150 150

IPL - 4

150

150
69 EL. + 78,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 78,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

150 150

IPL - 4
150

150
70 EL. + 80,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 80,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

150 150

IPL - 4
150

150

71 EL. + 82,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 82,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"


PT.TING TAI KONSTRUKSI INDONESIA
EMBEDMENT LIST OF SLIPFORM WORK
Project : PROJECT EPC TUBAN JETTY UPGRADE AND ITS ANCILLARY PRODUCTION & TRANSPORTASION FACILITIES PROJECT
Page : 19/21
Building : BLENDING SILO
Doc. No. : HST-R-PY-001-R00

RADIUS/ POSITION
NO ELEVATION DIMENSION INSIDE / ITEM SHAPE QUANTITY SIGN REMARKS
DEGREE
(M) OUTSIDE

150 150

IPL - 4

150

150
72 EL. + 84,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 84,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

150 150

IPL - 4

150

150
73 EL. + 86,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 86,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

150 150

IPL - 4
150

150
74 EL. + 88,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 88,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

150 150

IPL - 4
150

150

75 EL. + 90,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 90,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"


PT.TING TAI KONSTRUKSI INDONESIA
EMBEDMENT LIST OF SLIPFORM WORK
Project : PROJECT EPC TUBAN JETTY UPGRADE AND ITS ANCILLARY PRODUCTION & TRANSPORTASION FACILITIES PROJECT
Page : 20/21
Building : BLENDING SILO
Doc. No. : HST-R-PY-001-R00

RADIUS/ POSITION
NO ELEVATION DIMENSION INSIDE / ITEM SHAPE QUANTITY SIGN REMARKS
DEGREE
(M) OUTSIDE

150 150

IPL - 4

150

150
76 EL. + 92,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 92,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

150 150

IPL - 4

150

150
77 EL. + 94,225 8,450 Outside 125° & 159° ( Support For Stair ) 2 By: PT.HK
150 x 150 x 9
EL. + 94,225
2498 2498

90°0'0" 125°0'0" 142°0'0" 159°0'0" 180°0'0"

Pasang embedded IPL-8


Roof beam tipe Rolled
78 EL. + 95,050 8,450 Inner wall 10 By: PT. HK
Drawing No. TPJC-TQ1- EL.+95,350
DW-C7-391-3S02-011

EL.+95,050

Pasang embedded IPL-8


Roof beam tipe Pined
79 EL. + 95,150 8,450 Inner wall EL.+95,450 10 By: PT. HK
Drawing No. TPJC-TQ1-
DW-C7-391-3S02-011
EL.+95,150
PT.TING TAI KONSTRUKSI INDONESIA
EMBEDMENT LIST OF SLIPFORM WORK
Project : PROJECT EPC TUBAN JETTY UPGRADE AND ITS ANCILLARY PRODUCTION & TRANSPORTASION FACILITIES PROJECT
Page : 21/21
Building : BLENDING SILO
Doc. No. : HST-R-PY-001-R00

RADIUS/ POSITION
NO ELEVATION DIMENSION INSIDE / ITEM SHAPE QUANTITY SIGN REMARKS
DEGREE
(M) OUTSIDE

Pasang block-out roof


beam tipe Rolled
80 EL. + 95,350 8,450 Inner wall 10 By: PT. Ting Tai
Drawing No. TPJC-TQ1- EL.+95,350
DW-C7-391-3S02-011

Pasang block-out roof


beam tipe Pined Drawing
81 EL. + 95,450 8,450 Inner wall EL.+95,450 10 By: PT. Ting Tai
No. TPJC-TQ1-DW-C7-
391-3S02-011

EL.+95,750
Top pengecoran wall
Blnding Silo Drawing
82 EL. + 96,750 8,450 Wall silo 1 By: PT. HK
No. TPJC-TQ1-DW-C7-
391-3S02-011

PT. HUTAMA KARYA (HK) PT.TING TAI KONSTRUKSI INDONESIA

Engineering Site manager QC / Planning Construction

PT-E&C-013-035-R0
6/5/2008