Professional Documents
Culture Documents
INE 425
Lec 10
1
The Line Balancing Problem
2
Definition
• The line balancing problem is to arrange the individual
processing & assembly tasks at the workstations so that the
total time required at each workstation is approximately the
same.
• If the work elements can be grouped so that all the station
times are exactly equal, we have perfect balance on the line &
we can expect the production to flow smoothly.
• In most practical situations it is very difficult to achieve
perfect balance. When the workstations times are unequal,
the slowest station determines the overall production rate of
the line.
3
Minimum Rational Work Element
In order to spread the job to be done on the line
among its stations, the job must be divided into its
component tasks.
• The minimum rational work elements are the
smallest practical indivisible tasks into which the job
can be divided. These work elements cannot be
subdivided further.
4
Minimum Rational Work Element
For example,
• The drilling of a hole would normally be considered
as a minimum rational work element.
5
Minimum Rational Work Element
6
Example
A new small electrical appliance is to be assembled on a
production flow line. The total job of assembling the product has
been divided into minimum rational work elements.
8
Total work content Twc
9
Workstation Process Time
• A workstation is a location along the flow line
where work is performed, either manually or
by some automatic device.
• The work performed at the station consists of
one or more of the individual work elements
& the time required is the sum of the times
of the work elements done at the station.
10
Workstation Process Time
11
Cycle Time Tc
12
Cycle Time Tc
13
Cycle Time Tc
14
Cycle Time Tc
15
Cycle Time Tc
Finally, since the station times are comprised of
element times,
16
Precedence Constraints
These are also referred to as “technological sequencing
requirements”. The order in which the work elements can be
accomplished is limited at least to some extent.
17
Precedence Diagram
• This is a graphical representation of the sequence of work
elements as defined by the precedence constraints.
• It is customary to use nodes to symbolize the work elements,
with arrows connecting the nodes to indicate the order in
which the elements must be performed.
• Elements that must be done first appear as nodes at the left
of the diagram.
• Then the sequence of processing and/or assembly progresses
to the right.
• The element times are recorded above each node for
convenience.
18
Precedence Diagram
19
Balance Delay.
20
Balance Delay.
21
Balance Delay.
22
Balance Delay.
23
minimum number of workstations
1
24
Methods of Line Balancing
1. Largest Candidate Rule (LCR).
25
1. Largest Candidate Rule (LCR)
Procedure:
26
Example
A new small electrical appliance is to be assembled on a
production flow line. The total job of assembling the product has
been divided into minimum rational work elements.
28
Solution by Largest Candidate Rule: example
29
Solution by Largest Candidate Rule
30
Solution by Largest Candidate Rule
• Step 2. To assign elements to the first
workstation:
• start at the top of the list and work done,
• selecting the first feasible element for placement
at the station.
• A feasible element is one that satisfies the
precedence requirements and does not cause the
sum of the Tej value at station to exceed the cycle
time Tc.
Step 3. Repeat step 2.
31
Solution by Largest Candidate Rule
32
Solution by Largest Candidate Rule
33
Kilbridge and Wester's Method (KWM).
Steps involved in solving line balancing problem by
kilbridge and westers method is as follows:
34
Example
• Solve the pervious example using Kilbridge and
Wester's Method .
The cycle time is 1 min. Apply the Kilbridge and Westers procedure for
above task and determine the balance delay o f the line.
Example
1. Construct the precedence diagram.
2. I f cycle time is 10 min., what is the number of stations
required?
3. Compute the balance delay o f the line by using
largest candidate method.
Solution
Precedence Diagram:
Column
1 2 3 4 5 6
Diagram
Solution
• From the above station assignment in the line it is
observed that station 2 and 3 are exceeding the cycle time
of I min. Hence it is considered as two stations of each.
but
Ranked Positional Weight method (RPW)
• RPW takes into account both elemental time and elemental
position weights of the task. It combines the strategies of largest
candidate rule and Kilbridge and Westers method.
Procedure for solving the line balancing problem by RPW method
1. Draw the network diagram as per the precedence relationship.
2. Calculate the RPW for each element by summing the elements
that follow the arrow chain of the precedence diagram
(succeeding elements).
3. List and group the elements in the order of their RPW.
4. Group the activities into the station considering the positional
weights, elemental time and position.
5. Find the idle time of each station.
6. Calculate the balance delay and efficiency of the line.
Example
• Solve the pervious example using Kilbridge and
Wester's Method .
41
precedence Matrix
Ranked Positional Weight method (RPW)
List the elements in the order of
their RPW Group the activities into the
station considering the positional
weights, elemental time and
position
Thank you