You are on page 1of 83

Internal Technical Document

VIETNAMESE STANDARD 6809-2001

RULES FOR THE CLASSIFICATION AND CONSTRUCTION OF


SINGLE POINT MOORINGS.

1. Scope of the application.

1.1. This standard regulates the required requests to the technical supervision
and the classification to the single point moorings (SPM) without having
accommodated persons, in the design, fabrication and repairing, recovering that
are used for tightening the ships, oil transport ships and other floating means
(hereafter called as ships) operating in the sea territory of Vietnam.
1.2. Technical supervisions and the classification of SPM are implemented by
the register of Vietnam (hereafter called as register).
1.3. For SPM design having new functions on floating, structure, arrangement of
the ship tightening, machine, equipments and fixed living arrangement etc…that
have not been mentioned in this standard will be considered by the register in a
separate manner in specific cases.
1.4. For parts that are not mentioned sufficiently in this standard or other
standards of Vietnam relating to, they maybe applied with practices and rules of
the foreign nations if they are accepted by the Register.
1.5. SPM are designed or fabricated according to other standards will be
classified by the register, if they have the safety level equal to the requirements
of this standard. In such cases, it is necessary to inform the register immediately
right in the period of the initial design that will lay a foundation for the design
acceptance.
1.6. For SPM that is a part of oil transport ship, it is not necessary to make a
separate classification according to this standard, then they will be classified
according to requirements for the mooring systems of TCVN 6474:1999.

Construction Dept. - Internal translation only (TCVN 6809-2001) 1


Internal Technical Document

2. Quoted standards
TCVN 6474: 1999: Rule for the classification and technical supervision of oil
transport ships.
TCVN 5309: 1991: TCVN 5319: 1991: Rule for the classification and
fabrication of off shore oil drilling systems.
3. Definitions and interpretations.
3.1. Anchor leg.
Anchor leg is a part used to connect the SPM body with the bottom of the sea, it
is also a main part to keep the system in location of SPM.
3.2. Buoyancy Element.
Buoyancy element is a element used to support the weight of anchored
equipment and devices or vertical pipes, it is designed in order to resist the
differential of the inner pressure and outer pressure from the underground part.
3.3. Cargo.
Cargo is any kind of the liquid that is transported from PLM (pipe line end
manifold) to ship that is anchored and tightened such as coarse oils, oil products,
combustion products, burning gases, bitumen and asphalts, and heavy fuels.
3.4. Hawsers.
Hawsers are chains and ropes for connecting the SPM structure to the ships.
3.5. Hose and transmission pipes.
Hose and transmission pipes are used to transport the cargos from the supply
place to receiving place that have capacity of transporting relatively and
resisting against the large deforming. Normally, the transmission pipelines is
formed from sections of the pipe and they are assembled to each other by
flanges and it may be a long pipe.
3.6. Floating hoses and pipes.

Construction Dept. - Internal translation only (TCVN 6809-2001) 2


Internal Technical Document

Floating pipes and hoses are used to transport the commodities from SPM to the
ships. When an end of the hose/pipe is not connected to the ship, another end
will be still connected to SPM and floating on the sea surface.
3.7. Underbuoy hoses and pipes.
Underbuoy hoses and pipes are and hoses and pipes of the transmission from
SPM to PLEM (pipe line and manifold) to transport the commodities.
3.8. Main bearing.
Main bearing is used to resist against the tightening loadings, chains, tights and
securing that train is under tightened can be rotate around the wind directions in
surrounding the tightening structure.
3.9. Product swivel.
Product swivel is a structure that secure the cargo or products can pass but not
being leaked in a large scale at the designed pressure when the main structure
rotates freely to the fixed structure.
3.10. Flexible riser hoses.
Flexible riser hoses are pipes and hoses used to transport the cargo from the
supply place to receiving place with or without the transportation capacity in a
considerable scale and being under a large deforming. Flexible riser hoses are
normally a continuous long pipe and hoses, it is used in deep water areas and
being fabricated in a suitable manner in a totally-underground conditions.
3.11. SPM – Single Point Mooring.
SPM – Single Point Mooring is a system that allows the ships to rotate
according to the wind directions when the ships are tightened to it. Fixed
structure or floating buoys of SPM are anchored to sea bottom by a frigid
structure system or swivels or being anchored in many directions. For example:
The system of this type is mooring buoys CALM (Catenary Anchored Leg
Mooring), SALM anchor mooring (Single Anchor leg Mooring) and tower
moorings.

Construction Dept. - Internal translation only (TCVN 6809-2001) 3


Internal Technical Document

3.12. SPM – Fixed Single Point Mooring


Tower mooring and SPM – Single Point Mooring have a system of gravity
basement (fixed or pinned) which are considered as a fixed SPM – Single Point
Mooring.
3.13. Floating SPM – Single Point Mooring.
CALM anchor moorings is an example of floating anchor mooring.
3.14. Swing circle.
Swing circle is an area for tightening the ships to SPM– Single Point Mooring
surrounding the tightening places.
3.15. PLEM Valve group (Pipe line end manifold).
PLEM Valve group (Pipe line end manifold) is a group of valves and parts or
equipments having equivalent functions used to connect the production systems
to the pipelines transporting the cargos to or from the banks and offshore,
system of releasing the cargo or to another system.
3.16. Maneuvering area.
Maneuvering area is an area for the ships to operate when arriving to the
destination ports and leaving SPM– Single Point Mooring.
4. Classifications
4.1. Awarding the classifications.
SPM– Single Point Moorings after being designed, fabricated and inspected that
are totally suitable with this standard will be awarded with the classification by
the register and it will be recorded into book of registering the sea works.
4.2. Classification symbols of SPM– Single Point Mooring.
4.2.1. Basic classification symbols of SPM– Single Point Mooring are as
follows:
* VRSPM *_VRSPM, or (*)VRSPM
Where:
VRSPM is a symbol of SPM classified by the register.

Construction Dept. - Internal translation only (TCVN 6809-2001) 4


Internal Technical Document

* is a symbol of SPM– Single Point Mooring that is designed, and new


fabrication under the supervision of the register.
*_ is a symbol of SPM– Single Point Mooring that is designed, and new
fabrication under the supervision of other classification organizations which are
agreed, authorized and accepted by the register.
(*) is a symbol of SPM– Single Point Mooring that is designed, and new
fabrication under the supervision of other classification organizations which are
not agreed, not authorized and not accepted by the register.
4.2.2. Additional symbols.
Basic classification symbols of SPM may be added the following symbols:
4.2.2.1. Symbols and types of SPM– Single Point Mooring.
Symbols of types of SPM– Single Point Mooring are notes on the types and
models of SPM– Single Point Mooring.
Example: SPM– Single Point Mooring of type CALM.
4.2.2.2. Symbols on area are notes of the geographical locations where installed
by SPM.
Example: Dragon drilling system.
4.2.2.3. Symbols on limits on operation are notes on norms of the limited design
equipments.
Example: Limits on sea status and allowable wind speed for ships being
tightened to SPM.
4.2.2.4. Symbols on the data of SPM such as longitudes, coordinates of the
locations of the tightening, total length and amount of occupied waters of the
ships under the calculation when implementing the design for tightening, depth
of the water areas, maximum tension force on ropes and types of the transported
goods.
4.2.3. Registration.

Construction Dept. - Internal translation only (TCVN 6809-2001) 5


Internal Technical Document

All items: SPM– Single Point Mooring class symbols, additional symbols,
SPM– Single Point Mooring names, main sizes and dimensions and the
equipments will be included in the marine works registration books after SPM–
Single Point Mooring has been awarded by the official classification by the
register.
4.3. Maintaining SPM– Single Point Mooring.
4.3.1. Circle inspection.
SPM– Single Point Mooring has been awarded the classification by the register,
and the register will be inspected by the register staffs in a periodical manner or
unusually inspected in order to re-confirm the awarded classifications.
4.3.2. Inspecting when making changes or recovery.
In case if SPM– Single Point Mooring or the equipments are changed or
recovering that influence the inspection content as regulated in item 4.1, then
SPM or that equipment must be checked by the register staffs according to the
content regulated by the register in each specific case.
4.4. Writing request for the inspection.
14.4.1. First inspection.
The classification and the registration will be implemented by the register after
receiving the writing request of owner of SPM– Single Point Mooring or the
fabrication plants.
14.4.2. Circle inspection.
Inspection of the circle for recovering the classification or certifying the
classification again will be implemented by the register after in receipt of the
writing request of SPM– Single Point Mooring, persons in charge of SPM–
Single Point Mooring or representative of SPM– Single Point Mooring.
14.5. Certificates.
14.5.1. Certificates of SPM classification and temporary SPM– Single Point
Mooring Certificates.

Construction Dept. - Internal translation only (TCVN 6809-2001) 6


Internal Technical Document

14.5.1.1. If SPM– Single Point mooring after being inspected by the register
meet all requirements of this standard it will be awarded with the certificate of
SPM– Single Point Mooring by the register and it will be registered into marine
works book of the register according to the regulation in the item 4.1. In time of
pending the register makes the consideration to the request to award the
certificate of official SPM– Single Point Mooring, the register will award the
SPM– Single Point Mooring with the interim certificate of SPM– Single Point
Mooring.
14.5.1.2. The register will expand the certificate of official SPM– Single Point
Mooring right after the register staffs implement the yearly inspection and
certifying that SPM– Single Point Mooring meets all regulations of this
standard.
14.5.2. validity of SPM– Single Point Mooring classification certificate and
temporary SPM– Single Point Mooring temporary classification certificates.
14.5.2.1. Certificate of the classification will be in a validity in a term of 5 years
since date of completing the inspection of the classification or periodical
inspection. The classification certificate will be expanded in a maximum period
of 5 months since date of completing the periodical inspection. If the inspection
results meets all requirements (the expansion carries meaning in places for
issuing the temporary certificate of the classification). This expanded
classification certificate will become null and void after SPM– Single Point
Mooring receives the official SPM– Single Point Mooring certificate.
14.5.2.2. Temporary classification certificate will be valid in a maximum period
of 5 months since date of issuing that certificate.
Official classification certificate and temporary classification certificate will
become null and void when SPM– Single Point Mooring classification is
suspended or cancelled.
14.5.3. Archiving, re-issuing and returning the certificates.

Construction Dept. - Internal translation only (TCVN 6809-2001) 7


Internal Technical Document

14.5.3.1. SPM– Single Point Mooring owner or person who is in charge of


SPM– Single Point Mooring will be responsible for archiving the classification
certificates or temporary classification certificates which must be submitted to
the register if having a request.
14.5.3.2. SPM– Single Point Mooring owner or person who is in charge of
SPM– Single Point Mooring will be responsible for requesting the register to
immediately issuing the classification certificate and temporary classification
certificates if it is torn, lost, damaged or content of the classification certificates
are changed and modified.
14.5.3.3. SPM– Single Point Mooring owner or person who is in charge of
SPM– Single Point Mooring will be responsible for immediately returning the
register with temporary classification certificates after SPM– Single Point
Mooring has been issued with an official classification certificates or when that
temporary certificates expires according to regulations in 4.5.2 and must return
the previous certificates after the classification certificates have been re-issued
or being renewed according to article 14.5.3.2 as above-mentioned, excepting
cases when that certificates are lost.
14.5.3.4. SPM– Single Point Mooring owner or person who is in charge of
SPM– Single Point Mooring will be responsible for immediately returning the
classification certificates or temporary classification certificates to the register
when SPM– Single Point Mooring’s classification has been withdrawn
according to regulations in item 14.7.1.
14.5.3.5. SPM– Single Point Mooring owner or person who is in charge of
SPM– Single Point Mooring will be responsible for immediately returning the
classification certificates or temporary classification certificates to the register
when SPM– Single Point Mooring’s classification that were lost but have been
looked for and found out, after the certificates have been re-issued according to
article 14.5.3.2 as above mentioned.

Construction Dept. - Internal translation only (TCVN 6809-2001) 8


Internal Technical Document

4.6. Inspection documents.


4.6.1 Issuing the inspection documents.
The register will issue the inspection documents to SPM– Single Point Mooring
after the inspection has been completed in accordance with the requirement of
this standard.
14.6.2. Archiving the inspection documents.
14.6.2.1. All inspection documents issued by the register to SPM– Single Point
Mooring must be archived and stored on spot. These documents must be
submitted to the register for consideration when having a request.
4.7. Withdrawing the classifications and canceling the registration.
4.7.1. Grounds for withdrawing the classifications or canceling the registration.
14.7.1.1. The register will withdraw the classification or canceling the
registration and notifying the withdrawal of the classification or canceling the
registration of SPM– Single Point Mooring to SPM– Single Point Mooring
owner when:
(1) Being requested by SPM– Single Point Mooring owner.
(2) Register staffs certify that SPM– Single Point Mooring is no longer to
continue to be used because SPM– Single Point Mooring is dissolved or sank
etc….
(3) The register staff reports that SPM– Single Point Mooring is no longer
suitable with the requirements of the standard through the inspection results as
regulated in article 4.3.1 and the register accepts that report.
(4) SPM– Single Point Mooring is not included in the inspection according to
regulation in item 14.3.
(5) SPM– Single Point Mooring owner does not pay the inspection fees.
14.7.2. Store of the register.
In case of (4) or (5) of article 14.7.1.1 as above mentioned, the register may
withdraw the SPM– Single Point Mooring classification in a certain time.

Construction Dept. - Internal translation only (TCVN 6809-2001) 9


Internal Technical Document

14.8. Re-classifying or re-registering.


14.8.1. Re-classification or re-registration.
SPM– Single Point Mooring owner may make application for re-classification of
SPM– Single Point Mooring whose classification has been withdrawn, the
classification of this SPM– Single Point Mooring will be decided by the register
after inspecting the present technical status and making consideration to
characters of SPM– Single Point Mooring at time when SPM– Single Point
Mooring’s classification is withdrawn.
14.8.2. Re-registration.
After being re-classified, if owner of the SPM– Single Point Mooring makes a
request, SPM– Single Point Mooring may be re-registered into marine works
registration book of the register.
15. Technical supervision
15.1. Technical design documents submitted for approval.
15.1.1. Drawing
Before making a new fabrication, recovering or re-equipping, the SPM– Single
Point Mooring owner or its representatives must submit the register to approve
the technical design documents with the quantity being regulated as follows:
- Common arrangement.
- Arranging the water tight chambers, including locations, types and
arrangement of water sealing lids and weather sealing ones.
- Cover iron sheet structure drawings, sides, partitions, boards, floors,
reinforcement parts and connections and joints.
- Parts of water sealing doors, water sealing lids.
- Welding procedures and welding technical parameters and specifications.
- Anti-corrosion system.
- Types, location and quantity of fixed chocking materials if any.
- Arranging the dried suction system, measuring depth and ventilation of air.

Construction Dept. - Internal translation only (TCVN 6809-2001) 10


Internal Technical Document

- Dangerous areas.
- Diagram of arranging wires of power system.
- Arranging fire fighting equipments and devices.
- Arranging the anchoring and moorings.
- Group of the parts of the mooring and anchoring, including the foot of anchors,
accessories, tightened chains and character line of the tension and curve level of
wires, tightening chains.
- Basement of tightening part and groups, industrial equipment and devices
etc….that have clearly specified the binding to the cover.
- Anchor system that have clearly specified the size of anchor, capacity of
resisting the adhesives, dimension of the piles etc…
- PLEM (pipe line end manifold) and valve group.
- Main bearing of SPM– Single Point Mooring.
- Product swivel includes the transmission structure, rotation part parts of
electrical swivel.
- Pipe and hose systems having list of the materials.
- Data of the design of the equipment, pipes and hoses and parts relating to the
pressure and minimum/maximum temperature.
- Accessory pipes and hoses system, attached to the list of the materials.
- Floating hoses and pipes and underbuoy pipes and hoses/flexible riser hoses
and pipes.
- Measurement system and control system.
- Marine equipments.
- Method and test location of Non-destruction location (NDT).
- Signs for inspecting the sinking parts of SPM– Single Point Mooring under
waters in place for the parts.

Construction Dept. - Internal translation only (TCVN 6809-2001) 11


Internal Technical Document

- Plan for testing and checking the parts of chiefly bearing loadings or parts
under the pressures such as product swivels, power connection swivels,
bearings.
- Testing procedures.
15.1.2. Map of the operation areas.
In order to prove that the marine consideration has been implemented when
determining the location of installing the anchored buoy, it is necessary to
submit a map of anchoring areas as regulated in item 8.1, in which it is
necessary to specify the location of the anchor buoy, possibility of the risk of
marine and the marine equipments that have been equipped and will be equipped
with, terrain of the marine bottom, maneuvering area and swing circle.
15.1.3. Reporting the condition of the working areas.
In order to secure the conditions in location of the anchoring buoys that it has
been considered carefully and being included in the design standard, it is
necessary to submit the report on the following issues and problems for the
approval according to the requirement of 8.1:
a. The environmental conditions on the winds, waves, current and flow,
fluctuation of water levels, tides, visions, temperature.
b. Water depth in location of the placing the anchoring buoys and maneuvering
areas, conditions of the floor soils and dangerous levels of the water level.
15.1.4. Testing the model.
If making test of the model so as to determine the loading of the design and to
prove that the designed loading that has been selected is suitable with the result
of testing the models, then it is necessary to report immediately to the register, in
which it is b\necessary to specify the designed loading, calculations, description
of the equipments and testing procedures together with the brief information on
testing results. The designer must make a discussion with the register on the

Construction Dept. - Internal translation only (TCVN 6809-2001) 12


Internal Technical Document

issues and problems in concern to the model testing, procedures, method and
data analysis so as to secure the model testing will be suitable.
15.1.5. Calculations.
The following calculation sheets must be submitted:
a. Structure calculation sheets according to item 8.3.
b. Stability calculation sheets according to item 8.3.
c. Anchoring and mooring calculation sheets according to item 8.4.
d. Hose and pipe system calculation sheets according to item 9.1 and 9.2.
e. Calculation sheets of parts under the pressure and parts under the loading
according to part 9.
f. Static and moving calculation sheets of product swivel according to 9.1.4.1.
15.1.6. Additional drawings.
When implementing the classification according to other regulations and rules, it
may be necessary to submit other additional reports to the register.
15.1.7. Submittals.
SPM– Single Point Mooring or the design agency must submit 3 sets of the
technical documents to the register for approval, in which one set will be stored
ion the central register, one set will be forwarded to the construction supervision
register section and one set will be sent to the design agency. However, number
of the technical design documents that are approved can be increased according
to the actual request of the customers and requirements of construction
supervision of the register.
15.1.8. Data book and maintenance.
For each SPM– Single Point Mooring, it is necessary to submit one set of the
document to the register in which it is necessary to record the operation
instructions and manuals and that of the maintenance of SPM– Single Point
Mooring, information on the anchoring areas and parts of SPM– Single Point
Mooring.

Construction Dept. - Internal translation only (TCVN 6809-2001) 13


Internal Technical Document

15.1.8.1. Content of data and maintenance book.


Data and maintenance book includes the following information.
a. Map of the operation as mentioned in article 15.1.2.
b. Technical features of the designed ships used to be tightened to SPM– Single
Point Mooring, including the water occupation amount, length of the
underground and direction of the sinking and distance from nose of the ship to
valve group.
c. Design environmental standard with different sizes of the ships, including
winds, waves, current flows and tides in the exploitation conditions.
d. Standard for transporting the goods including various types of the goods,
working pressure, temperature, maximum speed, minimum time for closing
valve, including valve group on the ships.
e. Drawing for arranging SPM– Single Point Mooring parts and other necessary
parts for the exploitation process or maintenance including entry parts of that
part group.
f. Describing the marine equipments and safety characters.
g. Procedure of tightening the ships to SPM– Single Point Mooring and
disassembling ships from SPM– Single Point Mooring.
h. Procedure of disassembling floating hoses and pipes from PLEM pipe line
end manifold and valve group and connecting the floating pipes and hoses to
PLEM pipe line end manifold and valve group placed on the ship.
i. Schedule of the maintenance and procedure of the maintenance of SPM–
Single Point Mooring, including the detail list of the inspection of the inspection
phase in the periodical inspection. Procedures of adjusting the tension of the
anchoring foot, disassembling and re-connecting the transmission pipes and
hoses, inspecting the flexible hoses and riser pipes, adjusting the floating
chambers and replacing the tight cushions of goods swivels, if they are applied
they must be included in data and maintenance book.

Construction Dept. - Internal translation only (TCVN 6809-2001) 14


Internal Technical Document

j. Testing the pressure of goods transport system.


Data and maintenance book submitted to the register for approval must not only
have enough all contents as above mentioned, but it also secure that these
content are suitable and meet all requirements to the design data and other limits
as specified in SPM– Single Point Mooring classification. The register will be
not responsible for operation of SPM– Single Point Mooring.
15.2. Testing in the time of fabrication.
15.2.1. Testing chambers and partition.
15.2.1.1. General regulations.
After finishing the assemble of lids, water sealing gates and sections of pipes
piercing the partition, including the joints and connections of the pipe, it is
necessary to implement the water tight testing in chambers and partitions
according to requirements mentioned in table 15.2.1 The assess inspection will
be suitable with test of NDT (Non-destruction Test) can be accepted as a method
of testing replacing the test with big injectors for certain areas.
15.2.1.2. Testing the chambers.
Procedure of testing the chambers must be submitted to the register for approval.
Table 5.2.1 shows the widely-used testing methods.
It is necessary to only test gases or making a combination of gas testing as
mentioned in table 5.2.1 according to the approved procedure, if the register
staffs do not make any additional requirements. When conducting the tests with
gases in all welding seams in surrounding areas, joints of the assemble and
sections of the connection pipes piercing the partition that must be inspected
according to the approved testing procedures with solvent of index of the
leakage in relative before painting. Pressure differential of the gas test in normal
status is 0.14 kG/cm2. It is necessary to equip with the prevention tools and
means that are beyond the pressure of the chamber when conducting the tests.
Conducting the test of leakage by watching and observing the gas pressure

Construction Dept. - Internal translation only (TCVN 6809-2001) 15


Internal Technical Document

reduction that can not be replaced by hydraulic methods or gas testing


method/soaps.
When conducting the chamber testing, it is necessary to have the witness of the
register staffs. Register staffs may make request to implement the additional
tests or making tests according to other methods, if it is necessary.
Table 5.2.1. Requirement of tight sealed
tests for first time in chambers and partition.
Item Test method
Chamber Testing gas or hydraulic
Water sealed partition, floor and sea Testing gas or hydraulic
Dry holds, chambers Testing gas or hydraulic
Chain tunnel Filled up with waters full

Table 5.2.1 Requirement to first tight test and partition (finishing)


Item Test method
Pipes for tightening rope Testing with big injector
Device for tightening water Testing with big injector
Oil container Testing air or hydraulic
Chamber for tight water Testing air or hydraulic
Annotate: “Testing with big injector” in this table and 5.2.1.4 are testing of outer
marginal with water currents from pipes.
5.2.1.3. Hydraulic testing
Design and chamber configuration are not normal and the structure is designed
to resist against the hydraulic loading from outside area must be tested with the
hydraulic method, excepting for other testing methods that are regulated.
Hydraulic testing may be implemented before or after lowering the buoys on
water. If the welding connections and connection sections pierce the partition
and after the inspection they meet all requirements of the standard, it may be
permitted to make painting before the hydraulic test.
5.2.1.4. Testing with big injector

Construction Dept. - Internal translation only (TCVN 6809-2001) 16


Internal Technical Document

Testing with big injector is conducted simultaneously with the inspection in both
ends of the connection and joints and testing pressure will be not less than 2.1
kG/cm2.
5.2.2. Testing the durability of the chamber.
Marine pipeline systems here after called as pipeline includes the whole
pipelines, vertical pipelines, valves, dampers, accessory equipments, safety
devices, anti-corrosion systems and other systems in concern. This standard will
be a technical standard to be compulsory to be applied to phases: technical
supervision and pipeline classification.
5.2. 3. Testing the mooring system.
Technical supervisions and classifications of marine pipelines will be conducted
by Vietnamese Register hereafter called as register. It is permitted to apply
requirements in the rule and other equivalent technical standards if they are
accepted by the register pipeline classification.
Conditions for classifying the pipelines. All pipelines are fabricated and
technically supervised in accordance with all requirements of this standard or
other equivalent requirements and then they will be granted with the certificates.
This will be still maintained when the inspection results prove that they are still
in accordance with the requirements of this regulation with 8.4.3.
Classification of the pipeline SPM is made on basis of requirements on the
design, (fabrication and the materials), possibility of the construction and
maintaining the pipelines as specified in this standard. Owner of the pipelines
must be responsible for supplying the instructions and guidance as well as
adopting limits of the exploitation so as to secure that it will not beyond the
design conditions used in the classification. All instructions and guide and limits
must be recorded in the exploitation book. Owner of the pipelines must update
SPM sufficiently all data in accordance with the requirements of this standard.
All troubles, deforms and damages influencing condition of the classifications
must be immediately informed to the register applied objects. This standard is
applied to the following objects, welded steel pipelines, welded steel vertical
pipes chambers of shooting and receiving billets.

Construction Dept. - Internal translation only (TCVN 6809-2001) 17


Internal Technical Document

Piles and anchor of the piles or basement of the gravity used for anchor system
of SPM must be tested with NDT according to requirements of the
acknowledged standards.
Supervision to the fabrication and anchor testing according to the acknowledged
standards.
5.2.4. Goods transport system.
After installing the whole goods transport system including the transmission
pipes/flexible risers, clutches, valve for testing the hydraulic with the designed
pressure according to requirements of items 5.2.6 and table 5.2.4.
Table 5.2.4: Requirement to supervision and testing during the fabrication
Item A B C D
Buoy structure, floating structure and x x X
other structures
Piles and anchor x x x
Goods clutch/products x x x
Hydraulic clutch x x x
Electrical clutch X
Clutch transmission structure X
SPM support main bearing X X X
Riser flexible, pipes underground lifebuoy X X X
Floating pipes X x X
Joint of the expansion pipes X
Anchor chain X
Ropes and chains X
Connection flanges, spared parts and X
standard valve
Measurement devices/electrical checker X
Marine equipments X
Annotate:
A – With the presence of the register staff in the supply place to check the
materials whether they are in compliance with the design/technical features and
records, consideration of welding parameters, procedure of the welding, NDT

Construction Dept. - Internal translation only (TCVN 6809-2001) 18


Internal Technical Document

test technical characters, skill and qualification of the welding workers and NDT
testing workers.
B- With the presence of the register staff in the supply place in important phases
of the production such as assemble, adjustment and NDT testing.
C- With the presence of the register staff in the supply place to witness and
record the testing results.
D- Permitting to make the inspection and testing at the workshop in the absence
of the register staff. These items can be accepted on basis that the sellers or the
producer present enough documents proving that these components are designed
and fabricated in pilot and meeting all acknowledged standards.
Additional testing requirements are pointed out in parts of this rule.
5.2.5. Control system and safety.
All control equipment and safety ones must be inspected and certified the
rationality with the use purposes, refer to table 5.2.4.
5.2.6. Transmission pipes/riser flexible.
Relating to test of transmission pipes/riser flexible, please refer to item 9.1.3 of
this standard.
5.2.7. Testing the pressure of the floating tanks.
Floating tanks that are compressed are equal to outside pressure and being tested
with a pressure equal to 1.5 times of the maximum working pressure.
5.3. Inspecting SPM under the exploitation.
5.3.1. Annual inspection.
The yearly inspections must be implemented in a duration of 3 months before or
after the regulated date of the annual inspection date in the inspection phase of
classification or periodical inspections before.
5.3.2. Periodical inspection.
a. Term of the inspection.
Valves control equipments and accessories safety equipments protection
coating, layers cathode protection system. In this standard, when mentioning
pipeline, it means a mentioning to application to one or the whole objects as
specified, this standard is not only limited to be applied to the above-said objects

Construction Dept. - Internal translation only (TCVN 6809-2001) 19


Internal Technical Document

but it also adds other objects in an appropriate manner according to the


requirements of the competent authorities or owner of the pipelines.
b. Start of the periodical inspection.
Pipelines being designed or fabricated in accordance with other regulations or
standards that differ from requirements of this standard will be considered to be
classified, that is according to the equivalency among the design and fabrication
standards. In those cases, it is necessary to inform immediately the Register in
initial phase to lay a foundation for the classification. For pipelines who
materials are not made of steels and soft vertical pipes made of the steels will be
considered separately.
c. Periodical inspection before deadline.
Periodical inspection can be implemented before deadline but it must be not
earlier than 12 months, excepting having the advance agreements with the
register.
d. Finishing the periodical inspection.
Class of the pipelines symbols of the class, symbols of basic classes for the
pipeline has been classified by the Register in which means that the pipeline
meets all requirements in this standard of the register, means the pipeline is
fabricated under the supervision of Register.

5.3.3. Continuous inspection.

a. It means the pipeline SPM is fabricated under the supervision of other


classification organization that is authorized by the Register and/or accepts. The
pipeline is fabricated not under the supervision of other classification
organization that is authorized by the Register and/or accepts. Note on the class
basing on the specific conditions, pipelines being classified by the Register will
be added with some information on the class.
b. Note in the type: means notes for function of the pipeline, for example
chemical transport pipelines oil transport pipelines, gas transport pipelines.
Water pressing pipelines oil transport vertical pipelines. Note in areas means
notes to supplying information on geographical location and territory where the
pipeline are installed.

Construction Dept. - Internal translation only (TCVN 6809-2001) 20


Internal Technical Document

c. Note on the service limit: means notes to supplying information on the


pipeline being classified with main exploitation limits. Maximum pressure under
exploitation maximum design temperature, notes of the description. These are
additional notes that provide detail description of the pipeline against the notes
on class that are included in the pipeline register book. Example: diameter of the
pipeline, flow and water static pressure etc. Inspection in new fabrication.
3.4. Suspending the operation and recovering the operation.
a. Pile foundations of machines having moving loads SPM must be designed
according to SPM requirements of standard on designing machine’s foundations
having moving loading. Pile foundations of houses and built works in places
where are instable of geology in places where may appear sliding, and in SPM
special conditions and circumstances. They should be designed in a
consideration to additional requirements to the construction and use of the
houses and buildings and works in the above-mentioned areas.
b. Choice of foundation structures SPM for example the pile foundations (for
example 6 months or more) or natural plane, which are reinforced by compact
ramming, chemistry or with thermal as well as various types piles and type of
pile foundations for example piles driven according to groups, according to long
lines. Long piles must derive from the specific conditions of the construction
site, which are characterized by the documents of technical survey and on basis
of the results of the comparison of the real situations on economy and
techniques of the possible solutions SPM of the solutions on foundation design.
c. According to the requirements of technical principles and saving SPM the
fundamental construction materials. Pile foundations should be designed on
basis of results of investigating the construction site’s geology and hydro
meteorological conditions of the construction site as per requirements of item of
this standard.
d. According to data SPM on climate conditions of the construction site as well
as according to the characteristics of houses and building that are designed and
according to the experiences in construction SPM of the locality.
5.3.5. Inspection the unfinished items.

Construction Dept. - Internal translation only (TCVN 6809-2001) 21


Internal Technical Document

Not permitting to design the pile foundations if without a rational foundations on


the construction geology or when lacking the geological ground to SPM owner
and the register.
5.3.6. Accidents and repairing.
In case when SPM falls in a n accident and damaging the structure, machine
systems, equipments and anchoring systems or transmission pipes and riser
flexible and causing an influence or may impact on the classification of SPM,
then owner of SPM or its representative must request the Register to inspect and
supervise the technical aspects of SPM. Al repairing so that SPM can continue
keep the classification must be inspected and certified by the register that meet
all requirement of the rule.
5.3.7. Recovering.
Inspecting the classification to existing pipelines SPM the construction site so as
to choose an appropriate structure of the foundations, type of piles and to
determine dimensions of piles SPM. In the construction drawings of the pile
foundations, it is necessary to specify the type of piles, its number and
parameters of piles, sections, profiles. Length of piles, loading resistance and
allowable loadings of the piles these parameters are not necessary to be made
further accurate by testing the piles.
5.3.8. Welding and replacing the materials.
a. Normal steels and steels having high durability.
In soils during the construction process. Testing the piles, tubular piles or pile
foundations for example.
b. Special materials.
Pile group, which are implemented during the construction process or after the
construction, it is necessary to follow up the standards on construction and
(acceptance 7 of the plane and foundation).
c. Replacing and repairing.
Repairing and replacement so as to keep the pipelines must be implemented
according to the requirements of this standard. In cases when according to the
acceptance and put the finished works into operation, in order to determine the
quality of the pile foundation and the rationality.

Construction Dept. - Internal translation only (TCVN 6809-2001) 22


Internal Technical Document

5.3.9. Inspecting on stones or equivalent ones.


Underground parts of SPM and other accessory parts must be inspected in a
duration of time not beyond 5 years and it must be suitable with periodical
inspection schedules.
Periodical inspection the foundation to design as well as to determine the
corresponding SPM of the geographical conditions in construction site to the
documents gained in the design. Solutions of the pile foundation, it is necessary
to estimate the actual measurement of the deforming of plane and foundation
according to special benchmarks pre-made in the following cases SPM.
5.3.10. Content of yearly inspection.
When using new structures for houses and works or for pile foundations,
granting certificates, granting SPM certificates of the classification. Studied
sufficiently in the mass construction SPM. When having a special tasks, in
design when having individual requirements on measuring the deforming in
order to study the working of plane, foundation, structure of the houses and
building or of the technological equipments. Choice of the objects to SPM
measure the deforming must be approved by the bid deliverer. According to the
additional requirements of standard years.
5.3.10.1. Lids for protecting mouth of chambers and other holes.
a. Mouths of chambers, holes for persons and shelter doors.
b. Wall of the chamber mouth including the connection with boards and areas.
c. Yearly certificate of granting certificates of the classification. Program and
results of the measurement during the construction must be written in the
documents 3.10. If design and being transported to the acceptance agency and
user of that house or works. Pile foundations used in the conditions of the
corrosion environment must be designed. Granting the temporary certificates of
the classification. Protecting the anti-corrosion construction structures, regarding
the woody structures of pile foundations, it should be given an attention to
requirements on protection from being ruined and damaged as well as defects
caused by intersects.
d. In this standard, it is necessary to survey the following types of the piles SPM.

Construction Dept. - Internal translation only (TCVN 6809-2001) 23


Internal Technical Document

e. Piles made 6 months from the issuing date. What should be noted during the
inspection.
5.3.10.2. Other areas.
a. Reinforcement concretes and woody materials, being placed on soils with
hammers, vibration machines.
b. And pressing vibration machines, withdrawing the classification.
c. Tubular piles made of the reinforcement concretes, boring piles made SPM
inspecting the classification when making a new fabrication.
d. Concretes redone in soils article reinforcement concrete piles under lowering
drill.
e. That are made of pre-fabricated reinforcement concretes structures being
lowered into pre-drilled holes.
f. Piles tightened to the body made of steels or reinforcement concretes.
g. According to characteristics of soils under the pile tips, piles will be divided
into support piles and suspended piles. Piles of various types and tubular piles,
when they transmit the loading through pile tips.
h. On soils actually they are not pressed and sprinkled, they are supporting piles,
friction forces in sides of the support piles will be not included in the calculation
of the force.
i. Dried suction pump system.
j. Load resistance of piles according to the plane soils when being suffered from
pressing load.
k. All types of piles and tubular piles are lowered into soil areas that are capable
of pressing and displaying the goods level.
l. And sprinkle that belong to suspended piles SPM, Suspending piles transmit
the load on ground via side areas and via pile tips. Real soils can not be pressed
and sprinkled that are various types of soils and sands, rough soil pieces.
m. Gravels, macadam, grits mixed with other substances such as sands and clays
having the solid viscosity.
5.3.11. Content of periodical inspection.
Including the covering soils having the water sufficiency SPM. Including the
soils, type of soil, expanded soils and salted soils. Piles driven as reinforcement

Construction Dept. - Internal translation only (TCVN 6809-2001) 24


Internal Technical Document

concrete and tubular piles are divided according to way of placing the
reinforcement. Piles and pile tubular having the lengthwise part that are not
stretch to horizontal reinforcement.
5.3.11. Structure.
a. Having lengthwise part SPM or having the lengthwise steel strip that are
pulled in stretch before. Steel and steels of high strength is months, with
horizontal reinforcement and without the horizontal reinforcement, at the same
time only the pile of cross section. According to the shape of horizontal section,
square piles, rectangular piles, square piles having round holes that are empty
diameter up to including the tubular piles having a diameter of more than to the
shape of lengthwise section.
Piles of cylinder shape and piles. Having oblique surface according to the
characters of the structure of the pile body, intact pile and connected pile.
Including the separated section according to the structure of the pile tips, sharp
nose-piles, flat-nose piles, piles having expanded or not expanded bottom,
empty piles having tight or opened tips, and piles having expanded bottom by
blaster. Driven piles having expanded bottom by blaster are fabricated by
driving the round piles with empty inner part. In the nose part, there is empty
steel nose and closed tips. After mixing the concrete mixtures into inner part of
the piles, implementing the blaster in tip section to make the deformed foot of
the piles in the project of the pile foundation.
b. Regulations on annual inspection when using the closed and opened piles
according to blaster it is necessary to specify the observation.
c. Strict manner to requirement of the construction blaster which it is necessary
to SPM determine the allowed distance
d. Houses or works to places of blaster changes of the driven piles. Used as
reinforcement concretes according to the structure. Method of lowering the
piles. Piles pillars part in ground of the piles will be used as house piles. It is not
allowed to use as piles, pillars for reinforcement piles that are stretched in
advance. With the lengthwise reinforcement that are steels as well as pre-
stretched piles cathode having the horizontal part to any type of the piles. Piles

Construction Dept. - Internal translation only (TCVN 6809-2001) 25


Internal Technical Document

being lowered in pre-drilled holes, at the same time diameter of the boring
should be not more than the minimum side of the cross section.
e. Diameter of the piles regarding the dept of the bored holes. Less than that of
the lowering the piles requirement according to the calculation. Pre-drilled holes
are allowed to use when there is a need. Flanges, bolts and joint bolts. Through
the piles via clays having solid viscosity and semi-solid. With the lengthwise
reinforcement that are steels as well as pre-stretched piles cathode. Cases when
SPM according to the result of driving piles, construction experience and
determining that.
f. Place piles T, through layers and that soils if without advanced drilling. Piles
when being driven use the water erosion method then the erosion must be not
implemented in the last meters when placing the piles, regarding piles should be
further driven to reach the designed level. Water erosion is permitted to be done
mainly when driving the piles through soil and sand layers having a large
thickness.
g. Driving piles made of woody materials are divided into the following types.
Intact piles made of a woody tree piles connected in length SPM, piles bundled
include some intact piles or joined ones. According to the fabrication method,
are divided into the following types. Boring piles are fabricated by pre-driven
methods, steel piles are sealed.
h. With pipe’s tips which is left in soil or being sealed with concretes gradually
drawing out.
5.3.11.2. Parts of anchoring system.
a. The piles that depend on number of concretes poured in to holes. Boring piles
of vibration and punching, that are formed in pre-drilled holes or closed holes by
pouring these holes. Classification of the pipeline without the supervision and
inspection of the register. Documents and drawing with solid concrete mixtures.
Compact ramming with by vibration ram machines having the tubular shape
with sharp head and being installed into machine of lowering piles with
vibration method. Piles bored in punched pipes are fabricated by method of
pressing drill of this standard. Generating pyramid-holes or conical ones and

Construction Dept. - Internal translation only (TCVN 6809-2001) 26


Internal Technical Document

then pouring the concrete mixture into the holes. Bored piles having the
expansion, or not having expansion of bottom.
b. Which are fabricated in clays not having sufficient waters (20 years old), not
necessary to support the hole walls, and in soil inundated with water and in
sands.
c. Technical features, data and drawing, it is necessary to retain the hole’s wall
with clay solutions, or by chocked pipes which then will be pulled up and only
in special cases when having SPM rational foundations.
Bored piles having expanded bottom by blaster are fabricated by drilling holes
and then holes are expanded by blaster. Pouring the concrete mixture into the
holes. Pre-fabricated piles and placed into the drilled holes, according to the
construction methods that are divided as follows.
5.3.11.3. Goods transmission pipes and riser flexible.
a. Goods transmission pipes.
Drawings and data for the approval, drawings and main data for the approval.
Piles pillars fabricated in the pre-drilled holes by placing in these holes with the
pre-fabricated, components having the cylinder shape or similar ones, having the
condensed section with the side or diameters of or more. Them using the cement
mortar or sands to pour into the apertures width of in mid drilled holes and these
components. Pre-fabricated piles placed into the drilled holes and having the
expanded bottom.
By blaster that is different from that of the drilled piles having the blaster item d
of article. After pouring the concrete mixture and expanding the bottom by
blaster in the drilled holes.
b. Riser flexible.
Reinforcement concrete piles have been placed before SPM being fabricated in
factory:
1. Reinforcement piles and concrete piles, tubular piles and pile made concretes
should be designed with the heavy concretes.
2. Less than designed grade that are J regulated by regulations etc situation of
the sea bottom. Standard of the state applied to piles and tubular piles.

Construction Dept. - Internal translation only (TCVN 6809-2001) 27


Internal Technical Document

3. Grade of the concrete and durability and force resistance (spreader bar)
driven piles and tubular piles must be taken that.
4. For the bored piles tightened piles cathode other types of the driving piles.
Advanced striping and stretching.
5.3.11.4. Safety equipments.
Safety equipments relating to SPM classification must be inspected and tested
according to requirement of the register on basis of regulations pointed in item 5
of this standard.
5.3.11.5. Clutch and goods transport equipments.
When not having the state standards, they should use the concretes. Having
grade not less than grade, if in case of having the stretch, it should be not less
than grade. For short bored piles length is less than meters it is allowed to use
the heavy concretes. Whose design grade is not less than. Foundation of the
reinforcement concrete piles should be designed with heavy concretes.
Design according to the strength of the force resistance, that is not less than for
bridges. Irrigation works and large-size pillars of outdoor power transmission
lines, installing and connection with grade.
5.3.11.6. Electrical equipments.
On spot pouring with grade. For house and works, excepting cases mentioned in
point. Installing and connection with grade on spot pouring with grade.
Concretes are used chocked in the reinforcement concrete piles in the nodes of
the pile foundations as well as used for chocking in the heads of piles to the
foundations. Drawings and additional documents that are need to be submitted.
Pre-fabricated ones, that should be in accordance with the requirements of the
design standard applied to the concrete structures and reinforcement concretes,
used for the concretes poured in joints and connections when designing the
water resource projects and bridges.
6. Materials.
6.1. General regulations.
This standard is used for SPM and being manufactured of the production
materials and being tested according to requirement of TCVN 5317-91. If using

Construction Dept. - Internal translation only (TCVN 6809-2001) 28


Internal Technical Document

other materials, then respective dimensions of all parts and details and SPM
components made of that materials will be inspected separately by the register.
6.2. Structure.
Calculation sheets and data design SPM grade of the concretes for choking the
pre-fabricated components of the pile foundation must be more than level of
digit with the design grade of the concrete belong to the connected components
maximum local pressure, SPM evaporation point to the gas transport pipeline
TCVN 5317-91. Designed grade of water-proof concretes for the piles driven
with the reinforcement concretes.
Having the square sections round holes in the middle area SPM round and
tubular piles reinforcement concretes.
6.3. Mooring systems.
Materials used for mooring, foot of anchoring and other accessories must meet
all recognized standards.
If using the synthetic materials, characters of the materials must be submitted to
the register for consideration.
6.4. Good transport system or product.
It is necessary to follow the requirements and standards the state applied to the
above-mentioned types of the piles. For the bored piles tightened piles and other
piles, without the state’s standards as well as for the pile foundations. Designed
grade of the water-proof concretes. Regulated according to the documents of the
standards of design. House and works in which use of the pile foundations.
When not having these requirements in the standard documents, then design
grade of the concrete of water proof should be regulated on basis of the
temperature conditions and climates of the construction site.
Geological conditions where use the pile foundation, which are similar to the
abovementioned requirements in the state standards. For the piles having the
square sections, round and tubular piles. Connections of the reinforcement piles
are connected and that of the tubular piles must be secured. Having the equal
durability of the joined connection and that of the pile body when being pressed
along with the axial and cross force as well as bent torque. Refer to 9.1.3.4

Construction Dept. - Internal translation only (TCVN 6809-2001) 29


Internal Technical Document

foundations having the working piles under a small load and being force of the
pull.
7. Welding and fabrication
Welding body of SPM or buoy structures of the mooring system must meet all
requirement in this chapter. For parts that have not been mentioned sufficiently
in this chapter may be applied with TCVN 5318:91. When implementing the
welding, it is necessary to mark as a fixed one in outer side of SPM cover or
body of the buoy and areas of the partition. In all cases, the welding materials
and procedure of the welding must be secured so that that meet all recognized
standards.
7.1.2. Drawings and technical features.
The approved drawings must specify the level of the welding with the main
structures, Process of the welding, type of metals, upgrading the pipeline.
Characteristics of the co-axial of the connected components. Foundations are
connected and joined with the reinforcement concretes, and that of the pile
groups. Preventing from the troubles. Urgent closing it is allowed to use the
intact components as we as that being connected partially.
7.1.3. Skill of the welding workers and supervision.
This depends on loading capacity of the transport means and machines of cranes
and hoists. Woody piles must be fabricated with woody like the piddle leaves
wood used for the piles must be chipped the covers. Protecting and positioning
the vertical pipes. Removed the eyes of wood and branches in 7.3.9 physical flat
of the wood body must be kept and meet all requirements of the register.
7.1.4. Welding procedure.
a. General regulation.
Sizes and cross sections and length of piles or bundle must be taken according to
the calculated results. Capacity of using the woody piles having the body of
more than is only permitted.
When having the agreement of the pile fabrication enterprise. Connection and
joint according to the length in wood piles and bundle piles.
b. It is necessary to use the symmetric connection that are coated with steel
saddles or steel pipes. Connections and joint in the piles must be arranged.

Construction Dept. - Internal translation only (TCVN 6809-2001) 30


Internal Technical Document

c. In co-axial and not be less than of this standard. Protection coating layer in
outer side of the pipeline. Requirement to the survey. Volume and parts of the
survey for the (2/3 designed objects on the pile foundations must be regulated by
a program).
7.2. Preparation for welding.
7.2.1. Preparing the edges and mounting.
That is elaborated by a survey agency, basing on the technical tasks in time of
conducting the survey, according to requirement of the bid deliverer design
agency and chair person of the design. That are in accordance with the
requirements of the survey standards of the construction works, of the standards
of the state and of the existing standard documents relating to the survey work.
Protection coating layer in inner side of the pipeline. In order to research the
house floor’s soils and that of the works, as well as according to requirements of
part of this standard. Driven piles having expanded bottom by blaster are
fabricated by driving the round piles. With empty inner part. In the nose part,
there is empty steel nose and closed tips, after mixing the concrete mixtures into
inner part of the piles. Implementing the blaster in tip section to make the
deformed foot of the piles. In the project of the pile foundation, when using the
closed and opened piles, expanding the bottom by blaster. Loading coating layer
it is necessary to specify the observation in a strict manner to requirement of the
construction and drilling, blaster. In which, it is necessary to determine the
allowed distance. From the houses or works to places of blaster. Changes of the
driven piles used as reinforcement concretes according to the structure and
method of lowering the piles are as follows.
7.2.2. Position.
All steel pipes at are fabricated must be in accordance with the approved
technical standards to the pipeline. For pipelines transporting sour gases, steel
must be chosen so that it will eradicate possibility of appearing the cracks or
oxygen caused by gas included in the transported gases. It is necessary to install
the anti-corrosion systems and all its details must be submitted for approval.
7.2.3. Cleaning.

Construction Dept. - Internal translation only (TCVN 6809-2001) 31


Internal Technical Document

All chambers and rooms and receiving the billets will be designed according to
the technical standards of the state or international regulations relating to tanks
under the pressure that are accepted. Designed loads general regulations. All
types of the exploitation of the pipelines must be surveyed according to the
conditions of suffering the actual loadings such as floating pushing force,
gravity, loading impacted by the environment and under the impact of winds,
waves and currents, seism and earthquakes (if any), loading resistance capacity
of the sea bottom, temperature, marine creatures and other conditions. Various
types of the allowed exploitation, maximum inner pressure , temperature of the
transported substances, speed of the current in the pipelines, standard of the
maximum environment must be included in the exploitation book.
7.2.4. Tack welding.
Normally environmental standards as specified in the design must bases on a
cycle of repeating of years. In places where have data on the environment with
high reliability, the register may accept a year-repeating cycle. When using
wave theories that are accepted to determine local wave speed for smooth and
round bars, values of the coefficients for calculating the wave loading impacted
on the vertical pipes may be taken as follows. These coefficients have the values
of change when making the calculation in areas that are near to the sea bottom
or near to the system’s parts.
7.2.5. Welding having temporary cushions in both ends of the welding (Run on
and Run off tabs).
When making the calculation of the pipelines, values of the coefficients are
dependent on conditions of the flows and currents, loading of the flow currents.
7.2.6. Stud welding.
When the flowed current impacts simultaneously with waves, it is necessary to
consider the influence of the flowed currents to calculate the loadings. Speed of
the flowed current will be plus with vector with speed of wave parts. Total
vector will be used to calculate the total loading of waves and flowed current. If
there are not sufficient the detail data, we may make a supposition of the
allocation of speed of the flowed currents according to a depth of rule. Loading
caused by twisting tracks, it is necessary to consider the possibility of the

Construction Dept. - Internal translation only (TCVN 6809-2001) 32


Internal Technical Document

oscillation of the structure parts caused by twisting tracks, this is applied for
winds with vertical pipes on water surface and for waves, and flowed currents
for the vertical pipes and pipelines underground the water.
7.27. Geometry creation
Design and chamber configuration are not normal and the structure is designed
to resist against the hydraulic loading from outside area 205 OC and 425 OC. It
must be tested with the hydraulic method, excepting for other testing methods
that are regulated 650OC. Hydraulic testing may be implemented before or after
lowering the buoys on water. If the welding connections and connection sections
pierce 29OC the partition and after the inspection they meet all requirements of
the standard, it may be permitted to make painting before the hydraulic test
testing with big injector testing with big injector is conducted simultaneously
with the inspection in both ends of the connection and joints and testing pressure
will be not less than.
Testing the durability of the chamber. Marine pipeline systems here after called
as pipeline includes the whole pipelines 650 OC, vertical pipelines, valves,
dampers 3%, accessory equipments, safety devices, anti-corrosion systems and
other systems in concern. This standard will be a technical standard to be
compulsory to be applied to phases: technical supervision and pipeline 229 OC
classification. Testing the mooring system, technical supervisions and
classifications of marine pipelines will be conducted by Vietnamese Register
hereafter called as register. It is permitted to apply requirements in the rule and
other equivalent technical standards if they are accepted by the register pipeline
classification.
% level of the deform = 65 x length of sheet/outer radius
7.3. Fabrication welding.
7.3.1. Environment.
It is necessary to adopt measures and precautions so as to secure that welding is
implemented in conditions not being in the humidity, winds and low
temperature.
7.3.2. Sequence of welding.

Construction Dept. - Internal translation only (TCVN 6809-2001) 33


Internal Technical Document

Conditions for classifying the pipelines. All pipelines are fabricated and
technically supervised in accordance with all requirements of this standard or
other equivalent requirements and then they will be granted with the certificates.
This will be still maintained when the inspection results prove that they are still
in accordance with the requirements of this regulation with classification of the
pipeline is made on basis of requirements on the design.
7.3.3. Preliminary heating
Fabrication and the materials, possibility of the construction and maintaining the
pipelines as specified in this standard. Owner of the pipelines must be
responsible for supplying the instructions and guidance as well as adopting
limits of the exploitation so as to secure that it will not beyond the design
conditions used in the classification. All instructions and guide and limits must
be recorded in the 16OC exploitation book. Owner of the pipelines must update
SPM sufficiently all data in accordance with the requirements of this standard.
All troubles, deforms and damages influencing condition of the classifications
must be immediately informed to the register applied objects. This standard is
applied to the following objects, welded steel pipelines, welded steel vertical
pipes chambers of shooting and receiving billets. Piles and anchor of the piles or
basement of the gravity used for anchor system of SPM must be tested with
according to requirements of the acknowledged standards.
7.3.4. Low hydro soldering stick.
a. Welding normal steels and steels having high durability.
Low hydro soldering stick should be used to making the welding with steels
having high durability and they can be also used for normal steel structures
having high rigidness. When using low hydro soldering stick, it is necessary to
adopt rational precautions securing the solderign sticks, soldering chemicals and
gases will be always clean and dried.
b. Welding rigid steels and metals.
Supervision to the fabrication and anchor testing according to the acknowledged
standards. Goods transport system after installing the whole goods transport
system including the transmission pipes and flexible risers, clutches, valve for
testing the hydraulic with the designed pressure according to requirements of

Construction Dept. - Internal translation only (TCVN 6809-2001) 34


Internal Technical Document

items and table requirement to supervision and testing during the fabrication.
With the presence of the register staff in the supply place to check the materials
whether they are in compliance with the design/technical features and records,
consideration of welding parameters, procedure of the welding, test technical
characters, skill and qualification of the welding workers and testing workers.
With the presence of the register staff in the supply place in important phases of
the production such as assemble, adjustment and testing. With the presence of
the register staff in the supply place to witness and record the testing results.
Permitting to make the inspection and testing at the workshop in the absence of
the register staff.
7.3.5. Back gouging
]These items can be accepted on basis that the sellers or the producer present
enough documents proving that these components are designed and fabricated in
pilot and meeting all acknowledged standards. Additional testing requirements
are pointed out in parts of this rule. Control system and safety. All control
equipment and safety ones must be inspected and certified the rationality with
the use purposes, refer to table. Transmission pipes and riser flexible. Relating
to test of transmission pipes and riser flexible, please refer to item of this
standard.
7.3.6. Using hammer
Testing the pressure of the floating tanks. Floating tanks that are compressed are
equal to outside pressure and being tested with a pressure equal to times of the
maximum working pressure. Inspecting under the exploitation annual
inspection. The yearly inspections must be implemented in a duration of 3
months before or after the regulated date of the annual inspection date in the
inspection phase of classification or periodical inspections before.
7.3.7. Expanding and sprinkling with flames
Periodical inspection term of the inspection. Valves control equipments and
accessories safety equipments protection coating, layers cathode protection
system. In this standard, when mentioning pipeline, it means a mentioning to
application to one or the whole objects as specified, this standard is not only
limited to be applied to the above-said objects but it also adds other objects in an

Construction Dept. - Internal translation only (TCVN 6809-2001) 35


Internal Technical Document

appropriate manner according to the requirements of the competent authorities


or owner of the pipelines. Start of the periodical inspection. Pipelines being
designed or fabricated in accordance with other regulations or standards that
differ from requirements of this standard will be considered to be classified, that
is according to the equivalency among the design and fabrication standards.
7.3.8. Surface and quality of the welding joints.
a. Surface of the welding joint.
In those cases, it is necessary to inform immediately the Register in initial phase
to lay a foundation for the classification. For pipelines who materials are not
made of steels and soft vertical pipes made of the steels will be considered
separately. Periodical inspection before deadline, periodical inspection can be
implemented before deadline but it must be not earlier than 12 months,
excepting having the advance agreements with the register.
b. Finishing the periodical inspection.
Class of the pipelines symbols of the class, symbols of basic classes for the
pipeline has been classified by the Register in which means that the pipeline
meets all requirements in this standard of the register, means the pipeline is
fabricated under the supervision of Register articles 7.1.3. and 7.1.4 and 7.1.9.

7.3.9. Inspecting the welding points

Continuous inspection it means the pipeline is fabricated under the supervision


of other classification organization that is authorized by the Register and/or
accepts. The pipeline is fabricated not under the supervision of other
classification organization that is authorized by the Register and/or accepts.
Note on the class basing on the specific conditions, pipelines being classified by
the register will be added with some information on the class. Note in the type
means notes for function of the pipeline, for example chemical transport
pipelines oil transport pipelines, gas transport pipelines. Water pressing
pipelines oil transport vertical pipelines. Note in areas means notes to supplying
information on geographical location and territory where the pipeline are
installed. Note on the service limit means notes to supplying information on the
pipeline being classified with main exploitation limits. Maximum pressure under

Construction Dept. - Internal translation only (TCVN 6809-2001) 36


Internal Technical Document

exploitation maximum design temperature, notes of the description. These are


additional notes that provide detail description of the pipeline against the notes
on class that are included in the pipeline register book. Example: diameter of the
pipeline, flow and water static pressure etc. Inspection in new fabrication.
Suspending the operation and recovering the operation. Pile foundations (415-
690 N/mm2) of machines having moving loads must be designed according to
requirements of standard on designing machine’s foundations having moving
loading. Pile foundations of houses and built works in places where are instable
of geology in places where may appear sliding, and in special conditions and
circumstances. They should be designed in a consideration to additional
requirements to the construction and use of the houses and buildings and works
in the above-mentioned areas. Choice of foundation structures for example the
pile foundations for example months or more or natural plane, which are
reinforced by compact ramming, chemistry or with thermal as well as various
types piles and type of pile foundations for example piles driven according to
groups, according to long lines. Long piles must derive from the specific
conditions of the construction site, which are characterized by the documents of
technical survey and on basis of the results of the comparison of the real
situations on economy and techniques of the possible solutions of the solutions
on foundation design.
7.3.10. Repairing the welding points.
According to the requirements of technical principles and saving the
fundamental construction materials. Pile foundations should be designed on
basis of results of investigating the construction site’s geology and hydro
meteorological conditions of the construction site as per requirements of item of
this standard. According to data on climate conditions of the construction site as
well as according to the characteristics of houses and building that are designed
and according to the experiences in construction of the locality. Inspection the
unfinished items. Not permitting to design the pile foundations if without a
rational foundations on the construction geology or when lacking the geological
ground to owner and the register accidents and repairing. In case when falls in a
n accident and damaging the structure, machine systems, equipments and

Construction Dept. - Internal translation only (TCVN 6809-2001) 37


Internal Technical Document

anchoring systems or transmission pipes and riser flexible and causing an


influence or may impact on the classification of then owner of or its
representative must request the Register to inspect and supervise the technical
aspects. All repairing so that SPM can continue keep the classification must be
inspected and certified by the register that meet all requirement of the rule.
Inspecting the classification to existing pipelines the construction site so as to
choose an appropriate structure of the foundations.
7.4. Welding in facing edges.
7.4.1. Mannual welding with using covered electrodes.
Type of piles and to determine dimensions of piles. In the construction drawings
of the pile foundations, it is necessary to specify the type of piles, its number
and parameters of piles, sections, profiles. Length of piles, loading resistance
and allowable loadings of the piles these parameters are not necessary to be
made further accurate by testing the piles. Welding and replacing the materials.
Normal steels and steels having high durability. In soils during the construction
process. Testing the piles, tubular piles or pile foundations for example. Pile
group, which are implemented during the construction process or after the
construction, it is necessary to follow up the standards on construction and
acceptance of the plane and foundation. Replacing and repairing repairing and
replacement so as to keep the pipelines must be implemented according to the
requirements of this standard. In cases when according to the acceptance and
put the finished works into operation, in order to determine the quality of the
pile foundation and the rationality. Inspecting on stones or equivalent ones.
Underground parts of SPM and other accessory parts must be inspected in a
duration of time not beyond years and it must be suitable with periodical
inspection schedules.
7.4.2. Submerged-arc welding
Submerged-arc welding with periodical inspection the foundation to design as
well as to determine the corresponding of the geographical conditions 16 mm in
construction site to the documents gained in the design. Solutions of the pile
foundation 16 mm, it is necessary to estimate the actual measurement of the
deforming of plane and foundation according to special benchmarks pre-made in

Construction Dept. - Internal translation only (TCVN 6809-2001) 38


Internal Technical Document

the following cases. Content of yearly inspection when using new structures for
houses and works or for pile foundations, granting certificates, granting
certificates of the classification. Studied sufficiently in the mass construction.
When having a special tasks, in design when having individual requirements on
measuring the deforming in order to study the working of plane article 7.3.5
foundation, structure of the houses and building or of the technological
equipments. Choice of the objects to measure the deforming must be approved
by the bid deliverer. According to the additional requirements of standard years.
7.4.3. Gas metal – arc and flux cored –arc welding.
Lids for protecting mouth of chambers and other holes. Mouths of chambers,
holes for persons and shelter doors. Wall of the chamber mouth including the
connection with boards and areas yearly certificate of granting certificates of the
classification 7.4.1 program and results of the measurement during the
construction must be written in the documents.
If design and being transported to the acceptance agency and user of that house
or works. Pile foundations used in the conditions of the corrosion 6.5 mm
environment must be designed.
7.4.4. Electroslag and electrogas welding.
Using methods of electroslag and electrogas welding granting the temporary
certificates of the classification. Protecting the anti-corrosion construction
structures, regarding the woody structures of pile foundations.
7.4.5. Special welding methods.
It should be given an attention to requirements on protection from being ruined
and damaged in 7.4.1 and 7.4.4 as well as defects caused by intersects. In this
standard, it is necessary to survey the following types of the piles. Piles made 6
months from the issuing date. What should be noted during the inspection.
Reinforcement concretes and woody materials, being placed on soils with
hammers, vibration machines. And pressing vibration machines, withdrawing
the classification. Tubular piles made of the reinforcement concretes, boring
piles made inspecting the classification when making a new fabrication.
Concretes redone in soils article reinforcement concrete piles under lowering
drill.

Construction Dept. - Internal translation only (TCVN 6809-2001) 39


Internal Technical Document

7.5. Replacement.
That are made of pre-fabricated reinforcement concretes structures being
lowered into pre-drilled holes. Piles tightened to the body made of steels or
reinforcement concretes.
7.6. Tubular welding.
According to characteristics of soils under the pile tips, piles will be divided into
support piles and suspended piles. Piles of various types and tubular piles, when
they transmit the loading through pile tips.
7.7. Welding procedure.
On soils actually they are not pressed and sprinkled, they are supporting piles,
friction forces in sides of the support piles will be not included in the calculation
of the force TCVN 5316-91..
Dried suction pump system load resistance of piles according to the plane soils
when being suffered from pressing load.
7.8. Welding design.
7.8.1. Welding points.
7.8.1.1. General regulaitons.
a. Drawings and technical features.
All types of piles and tubular piles are lowered into soil areas that are capable of
pressing and displaying the goods level.
b. Allowable tolerances due to workmanship.
And sprinkle that belong to suspended piles, suspending piles transmit the load
on ground via side areas and via pile tips. Real soils can not be pressed and
sprinkled that are various types of soils and sands, rough soil pieces. Gravels,
macadam, grits mixed with other substances such as sands and clays having the
solid viscosity. Content of periodical inspection including the covering soils
having the water sufficiency. Including the soils, type of soil, expanded soils and
salted soils. Piles driven as reinforcement concrete and tubular piles are divided
according to way of placing the reinforcement.
c. Special attention
Piles and pile tubular having the lengthwise part that are not stretch to horizontal
reinforcement. Having lengthwise part SPM or having the lengthwise steel strip

Construction Dept. - Internal translation only (TCVN 6809-2001) 40


Internal Technical Document

that are pulled in stretch before. Steel and steels of high strength is months, with
horizontal reinforcement and without the horizontal reinforcement, at the same
time only the pile of cross section. According to the shape of horizontal section,
square piles, rectangular piles.
7.8.1.2. T-shaped welding point.
a. Size of the welding points.
T-shaped welding point, in general, is conducted continuously or being
interrupted in both ends as requirements in table 7.8.1. Width of the welding
foot f (refer to figure 7.8.1) is determined according to following formulas:
f = tpt C p/w + 2.00
fmr = 0.3 tpt or 4.5 mm. If applying article 7.8.5 then fmnt = 4.0 mm.
Where:
w is actual length of welding point, taken as mm.
p is welding step which is distance from central line of interrupted welding
point, taken as mm.
p/w = 1.0 for continuous welding points.
tpt is length of thinner parts, taken as mm.
C is welding coefficient as specified in table 7.8.1.
Square piles having round holes that are empty diameter up to including the
tubular piles having a diameter of more than to the shape of lengthwise section.
Piles of cylinder shape and piles or 0.7 tpt + 2.00 mm.
Having oblique surface according to the characters of the structure of the pile
body, intact pile and connected pile 0.5 mm.
Including the separated section according to the 0.70 structure of the pile tips,
sharp nose-piles, flat-nose piles tpt is less than 6.5 mm, then refer to 7.8.1.2 of
item f.
b. Length and arranging the welding point.
If the welding point is interrupted it is necessary to implement according to table
7.8.1, then length of each welding point will be not less than 75 mm for tpt and
bigger than 7.0 mm, but not less than 65 mm for tpt thinner. Length of the non-
welded sections must be not less than 32 tpt.
c. Piles having expanded or not expanded bottom.

Construction Dept. - Internal translation only (TCVN 6809-2001) 41


Internal Technical Document

Empty piles having tight or opened tips, and piles having expanded bottom by
blaster. Driven piles having expanded bottom by blaster are fabricated by
driving the round piles with empty inner part. In the nose part, there is empty
steel nose and closed tips. After mixing the concrete mixtures into inner part of
the piles, implementing the blaster in tip section.
d. Welding the lengthwise girders and sheet iron sheets.
Make the deformed foot of the piles in the project of the pile foundation.
Regulations on annual inspection when using the closed and opened piles
according to blaster it is necessary to specify the observation. Strict manner to
requirement of the construction blaster which it is necessary to SPM determine
the allowed distance.
e. Houses or works to places of blaster changes of the driven piles.
Used as reinforcement concretes according to the structure. Method of lowering
the piles. Piles pillars part in ground of the piles will be used as house piles it is
not allowed to use as piles.
f. Thin sheets.
In a comparison with the iron sheets having a thickness of 6.5 mm or less, then
requirement in article 7.8.1.2 in item (a) as above mentioned may be changed as
follows:
F = tpt C p/w = 2.00 (mm)
Fmin = 3.5 mm
Pillars for reinforcement piles that are stretched in advance 6.5 mm with the
lengthwise reinforcement that are steels as well as pre-stretched piles cathode
having the horizontal part to any type of the piles.
7.8.1.3 T-shaped end joint.
T-shaped end joint piles being lowered in pre-drilled holes, at the same time
diameter of the boring should be not more than the minimum side of the cross
section table 7.8.1 for diameter of the piles regarding the dept of the bored holes.
Less than that of the lowering the piles requirement according to the calculation.
Pre-drilled holes are allowed to use when there is a need. Flanges, bolts and joint
bolts. Through the piles via clays having solid viscosity and semi-solid. With the
lengthwise reinforcement that are steels as well as pre-stretched piles cathode.

Construction Dept. - Internal translation only (TCVN 6809-2001) 42


Internal Technical Document

Cases when according to the result of driving piles, construction experience and
determining that.
7.8.1.4. End of the nippers not mounted with code
Place piles through layers and that soils if without advanced drilling. Piles when
being driven use the water erosion method then the erosion must be not
implemented in the last meters 1/10 when placing the piles, regarding piles
should be further driven to reach the designed level. Water erosion is permitted
to be done mainly when driving the piles through soil and sand layers having a
large thickness.
7.8.1.5. Reducing the dimension of welding point.
Reducing the dimension of welding point can be accepted by the register
according to articles 7.8.1.45 in item a or 7.8.1.5 in item b if meeting
requirements as pointed out in 7.8.1.2, excepting lengthwise girders having a
thickness of more than 25 mm.
a. Inspecting the aperture.
Driving piles made of woody materials are divided into the following types
Intact piles made of 1mm woody tree piles connected in length, piles bundled
include some intact piles or joined ones 0.5 mm.
b. Level of contact of the welding points.
According to the fabrication method, are divided into the following types boring
piles are fabricated 1mm by pre-driven methods, steel piles are sealed 1.5 mm.
With pipe’s tips which is left in soil or being sealed with concretes gradually
drawing out 1,5 mm.
7.8.1.6. Lapped joints.
Size of the lapped joints at depend on number of concretes poured in to holes
boring piles of vibration and punching 25 mm.
Overlapped end connections.
Overlapped end connections of that are formed in pre-drilled holes or closed
holes by pouring these holes. Classification of the pipeline without the
supervision and inspection of the register. Documents and drawing with solid
concrete mixtures. Compact ramming with by vibration ram machines having
the tubular shape with sharp head and being installed into machine of lowering

Construction Dept. - Internal translation only (TCVN 6809-2001) 43


Internal Technical Document

piles with vibration method. Piles bored in punched pipes are fabricated by
method of pressing drill of this standard.
Overlapped seams.
Generating pyramid-holes or conical ones and then pouring the concrete mixture
into the holes table 7.8.1 for bored piles having the expansion, or not having
expansion of bottom, which are fabricated in clays not having sufficient waters
12.5 mm, not necessary to support the hole walls, and in soil inundated with
water and in sands according to table 7.8.1 for water tight partition.

Construction Dept. - Internal translation only (TCVN 6809-2001) 44


Internal Technical Document

Table 7.8.1 – Coefficient of C welding


No. Content Coefficient of Welding Note
welding C process
I Circumstance welding
A Water tight sealing
1 Main partition with board, 0.42 DC
bottom and double bottom
2 All other water sealing
A Water sealing partition 0.59 C One way-
Tpt = 12.5 mm 0.12 other
directions
b All other welding points 0.35 DC
B Non-water sealing welding
points
1 Floor and boards 0.29 DC
2 Partition of deep chamber 0.20
3 Water sealing partition for article 0.15
B2
II Bottom horizontal bars
1 With cover-iron cast 0.20 DC
2 With bottom –iron cast 0.20 DC
3 With main back of bottom 0.30
4 With side iron cast 0.35
5 Opened horizontal bars
a With middle back of the bottom 0.15
b With side sheets 0.30
III Lengthwise bottom back
1 Middle back 0.25
IV Strong side, back of the board,
and strong horizontal girders
1 With sheet iron sheets
a In chambers 0.20
b Other places 0.15
2 With surface iron sheets
a Area of surface sheets 0.12
<=64.5cm3
B Area of surface sheets >64.5cm3 0.15
3 End connection
a Not having connection code 0.12
(refer to note 1)
b Having connection code 0.15

Construction Dept. - Internal translation only (TCVN 6809-2001) 45


Internal Technical Document

V Horizontal side and nippers


1 With cover iron cast 0.55
2 With other iron casts 0.40
3 Mounting the ends
a Not having the connection code 0.25 DC
(refer to note 1)
t Having the connection codes 0.35 DC
Vi Lid of the holes
1 Oil sealing point 0.40 DC
2 Water sealing point
a Outer area 0.40 C
b Inner area 0.15
3 Nipper and strong nippers with 0.12
sheets and surface sheets (refer
to annotate 2)
4 Nipper and strong nippers with
side iron casts and other nippers
a Not having connection codes 0.45 DC
(refer to annotate 1)
t Having connection code 0.35 DC
VII Wall enclosing the hole mouth
and air ventilation
1 With boards
a In hole angle 0.45 DC
b Other places 0.25 DC
2 Vertical nippers
a With board iron cast 0.20 DC
b Wall enclosing the hole mouth 0.15 DC
VII Machine basement
I
1 Main and subsidiary equipments 0.40 DC
Notes:
1. Size of the welding point is determined according to welded detail thickness.
2. Nippers not being attached with codes and strong nippers of lid of the holes
must be continuously welded with iron cast of the lid of holes and their surface
iron casts.
3. C – continuous welding; DC: continuous welding in both directions.
7.8.1.7. Hole welding or trench welding.

Construction Dept. - Internal translation only (TCVN 6809-2001) 46


Internal Technical Document

Technical features, data and drawing, it is necessary to retain the hole’s wall
with clay solutions, or by chocked pipes which then will be pulled up and only
in special cases when having rational foundations. Bored piles 305 mm having
expanded bottom by blaster are fabricated by drilling holes.
7.8.2. Angle welding or T-shaped ones in totally one part.
Then holes are expanded by blaster. Pouring the concrete mixture into the holes.
Pre-fabricated piles and placed into the drilled holes, according to the T-shaped
construction methods that are divided as follows. Goods transmission pipes and
riser flexible. Goods transmission pipes. Drawings and data for the approval,
drawings and main data for the approval.
7.8.3.Other welding methods.
Piles pillars fabricated in the pre-drilled holes by placing in these holes with the
pre-fabricated, components having the cylinder shape or similar ones, having the
condensed section with the side or diameters of or more. Them using the cement
mortar or sands to pour into the apertures width of in mid drilled holes and these
components. Pre-fabricated piles placed into the drilled holes and having the
expanded bottom.
8. Design of the mooring system
8.1. Working area and environmental conditions.
8.1.1. General regulations.
All regulations included in this part are aimed to prepare and determine the
methods of determining the location and position of SPM, environmental
conditions influencing the SPM operation and it is necessary to make a
consideration when preparing the design standards, and condition of soils in the
sea bottom that influences the SPM mooring.
8.1.2. Position of the moorings.
By blaster that is different from that of the drilled piles having the blaster item d
of article. After pouring the concrete mixture and expanding the bottom by
blaster in the drilled holes. Reinforcement concrete piles have been placed
before SPM being fabricated in factory. Reinforcement piles and concrete piles,
tubular piles and pile made concretes should be designed with the heavy
concretes. Less than designed grade that are regulated by regulations etc

Construction Dept. - Internal translation only (TCVN 6809-2001) 47


Internal Technical Document

situation of the sea bottom. Standard of the state applied to piles and tubular
piles. Grade of the concrete and durability and force resistance spreader bar
driven piles and tubular piles must be taken that. For the bored piles tightened
piles cathode (PLEM) other types of the driving piles. Advanced striping and
stretching. Safety equipments relating to SPM classification must be inspected
and tested according to requirement of the register on basis of regulations
pointed in item 5 of this standard. Clutch and goods transport equipments.
When not having the state standards, they should use the concretes. Having
grade not less than grade, if in case of having the stretch, it should be not less
than grade. For short bored piles length is less than meters it is allowed to use
the heavy concretes. Whose design grade is not less than. Foundation of the
reinforcement concrete piles should be designed with heavy concretes. Design
according to the strength of the force resistance, that is not less than for bridges.
Irrigation works and large-size pillars of outdoor power transmission lines,
installing and connection with grade.
8.1.2.2. Map of the sea bottom.
On spot pouring with grade. For house and works, excepting cases mentioned in
point. Installing and connection with grade on spot pouring with grade or less
and concretes are used chocked in the reinforcement concrete piles 15 m in the
nodes of the pile foundations as well as used for chocking in the heads of piles
to the foundations. Drawings and additional documents that are 1.5 m need to be
submitted. Pre-fabricated ones, that should be in accordance with the
requirements of the design standard applied to the concrete structures and
reinforcement concretes, used for the concretes poured in joints and connections
when designing the water resource projects and bridges (Sonar) or this standard
is used for (Wire drag) and being manufactured of the production materials and
being tested according to requirement.
If using other materials, then respective dimensions of all parts and details and
components made of that materials will be inspected separately by the register.
Calculation sheets and data design grade of the concretes for choking the pre-
fabricated components of the pile foundation must be more than level of digit
with the design grade of the concrete belong to the connected components

Construction Dept. - Internal translation only (TCVN 6809-2001) 48


Internal Technical Document

maximum local pressure, SPM evaporation point to the gas transport pipeline.
Designed grade of water-proof concretes for the piles driven with the
reinforcement concretes.
8.1.2.3. Maneuvering area.
Maneuvering area having the square sections round holes in the middle area
SPM round and tubular piles reinforcement concretes. Mooring systems
materials used for mooring, foot of anchoring SPM and other accessories must
meet all recognized standards. If using the synthetic materials, characters of the
materials must be submitted to the register for consideration. Good transport
system or product SPM.
It is necessary to follow the requirements and standards the state applied to the
above-mentioned types of the piles SPM. For the bored piles tightened piles and
other piles, without the state’s standards as well as for the pile foundations.
Designed grade of the water-proof concretes. Regulated according to the
documents of the standards of design. House and works in which use of the pile
foundations. When not having these requirements in the standard documents,
then design grade of the concrete of water proof should be regulated on basis of
the temperature conditions and climates of the construction site. Geological
conditions where use the pile foundation, which are similar to the
abovementioned requirements in the state standards.
For the piles having the square sections, round and tubular piles. Connections of
the reinforcement piles are connected and that of the tubular piles must be
secured. Having the equal durability of the joined connection and that of the pile
body when being pressed along with the axial and cross force as well as bent
torque SPM.
8.1.2.4. Rotation circle
Refer to foundations having the working piles 3.14 under a small load and being
force of the pull. Welding and fabrication, welding body of SPM or buoy
structures of the mooring system must meet all requirement in this chapter. For
parts that have not been mentioned sufficiently in this chapter may be applied
with. When implementing the welding, it is necessary to mark as a fixed one in
outer side of SPM cover or body of the buoy and areas of the partition. In all

Construction Dept. - Internal translation only (TCVN 6809-2001) 49


Internal Technical Document

cases, the welding materials and procedure of the welding must be secured so
that that meet all recognized standards 30 m.
8.1.2.5. Water depth.
Drawings and technical features. The approved drawings must specify the level
of the welding with the main structures, SPM process of the welding, type of
metals, upgrading the pipeline.
Characteristics of the co-axial of the connected components. Foundations are
connected and joined with the reinforcement concretes, and that of the pile
groups. Preventing from the troubles. Urgent closing it is allowed to use the
intact components as we as that being connected partially.
Skill of the welding workers and supervision. This depends on loading capacity
of the transport means and machines of cranes and hoists. Woody piles must be
fabricated with woody like the piddle leaves.
The designer must make a demonstration to the register when determining the
depth of water and have calculated the following influences:
a. Dimension of ships and other relating characters.
b. Height of waves, circle of waves, direction of waves against the ship.
c. Winds and tides.
d. Vertical instability, horizontality, lengthwise and distance between the bottom
of ship and bottom of sea.
e. Unification level of the floor or concaves and protrudes on seas bottom.
f. Accurate standard level of data of surveying the water depth.
8.1.3. Data on the floor soils.
8.1.3.1. Wood used for the piles must be chipped the covers. Protecting and
positioning the vertical pipes. Removed the eyes of wood and branches in
physical flat of the wood body must be kept and meet all requirements of the
register welding procedure general regulation. Sizes and cross sections and
length of piles or bundle must be taken according to the calculated results.
8.1.3.2. Condition of compressing soils under sea bottom.
Capacity of using the woody piles having the body of more than is only
permitted. When having the agreement of the pile fabrication enterprise.

Construction Dept. - Internal translation only (TCVN 6809-2001) 50


Internal Technical Document

Connection and joint according to the length in wood piles and bundle piles. It is
necessary to use the symmetric connection that are coated with steel saddles or
steel pipes. Connections and joint in the piles must be arranged.
In co-axial and not be less than of this standard. Protection coating layer in outer
side of the pipeline. Requirement to the survey. Volume and parts of the survey
for the designed objects on the pile foundations must be regulated by a program.
Preparing the edges and mounting that is elaborated by a survey agency, basing
on the technical tasks in time of conducting the survey, according to requirement
of the bid deliverer design agency and chair person of the design. That are in
accordance with the requirements of the survey standards of the construction
works.
8.1.4. Environmental condition and data used in design.
When designing the SPM it is necessary to consider the following
environmental conditions as follows:
a. Working conditions.
Working conditions of SPM is determined as the standards of the state and of
the existing standard documents relating to the survey work. Protection coating
layer in inner side of the pipeline. In order to research the house floor’s soils and
that of the works, as well as according to requirements of part of this standard.
Driven piles having expanded bottom by blaster are fabricated by driving the
round piles. With empty inner part. In the nose part, there is empty steel nose
and closed tips, after mixing the concrete mixtures into inner part of the piles.
b. Storm condition.
Implementing the blaster in tip SPM section to make the deformed foot of the
piles. In the project of the pile foundation, when using the closed and opened
piles 100 years, expanding the bottom by blaster. Loading coating layer it is
necessary to specify SPM the observation SPM in a strict manner to requirement
of the construction and drilling, blaster. In which, it is necessary to determine
the allowed distance. From the houses or works to places of blaster. Changes of
the driven piles used as reinforcement concretes according to the structure and
method of lowering the piles are as follows.
8.1.4.2. Waves.

Construction Dept. - Internal translation only (TCVN 6809-2001) 51


Internal Technical Document

a. All steel pipes at are fabricated must be in accordance with the approved
technical standards 8.1.4.1 to the pipeline. For pipelines transporting sour gases,
steel must be chosen so that it will eradicate possibility of appearing (h1/3
average of 1/3 the cracks) or oxygen caused by gas included in the transported
gases. It is necessary to install the anti-corrosion systems and all its details must
be submitted for approval.
b. Designed storm waves.
All chambers and rooms and receiving the billets will be designed according to
the technical 8.1.4.1standards of the state SPM or international regulations
relating to tanks under the pressure that are accepted 100 years. Designed loads
general regulations. All types of the exploitation of the pipelines must be
surveyed according to the conditions of suffering the actual loadings such as
floating pushing force, gravity, loading impacted by the environment and under
the impact of winds, waves and currents, seism and earthquakes if any, loading
resistance capacity of the sea bottom, temperature, marine creatures and other
conditions. Various types of the allowed exploitation, maximum inner pressure ,
temperature of the transported substances, speed of the current in the pipelines,
standard of the maximum environment must be included in the exploitation
book.
c. Statistic of waves.
Normally environmental standards as specified in the design must bases on a
cycle of repeating of years. In places where have data on the environment with
high reliability, the register may accept a year-repeating cycle. When using
wave theories that are accepted to determine local wave speed for smooth and
round bars, values of the coefficients for calculating the wave loading.
Impacted on the vertical pipes may be taken as follows, these coefficients have
the values of change SPM when making the calculation in areas that are near to
the sea bottom or near to the system’s parts. Welding having temporary cushions
in both ends of the welding run on and run off tabs. When making the
calculation of the pipelines, values of the coefficients are dependent on
conditions of the flows and currents, loading of the flow currents. When the
flowed current impacts simultaneously with waves, it is necessary to consider

Construction Dept. - Internal translation only (TCVN 6809-2001) 52


Internal Technical Document

the influence of the flowed currents to calculate the loadings. Speed of the
flowed current will be plus with vector with speed of wave parts. Total vector
will be used to calculate the total loading of waves and flowed current. If there
are not sufficient the detail data, we may make a supposition of the allocation of
speed of the flowed currents according to a depth of rule.
Loading caused by twisting tracks, it is necessary to consider the possibility of
the oscillation of the structure parts caused by twisting tracks, this is applied for
winds with vertical pipes.
8.1.4.3. Winds.
a. Wind in the working conditions.
Water surface and for waves, and flowed currents for the vertical pipes in item
8.1.4.1 and pipelines underground the water height of 10 m conditions for
classifying the pipelines. All pipelines are fabricated and technically supervised
in accordance with all requirements of this standard.
b. Storm winds.
Other equivalent requirements and then they will be granted with the certificates
SPM in 8.1.4.1. This will be still maintained when the inspection results prove
that they are still in 100 years. In accordance with the requirements of this
regulation with 10 m classification of the pipeline SPM is made on basis of
requirements on the design, fabrication and the materials, possibility of the
construction.
c. Statistic of winds.
Maintaining the pipelines as specified in this standard. Owner of the pipelines
must be responsible for supplying the instructions and guidance as well as
adopting limits of the exploitation so as to secure that it will not beyond the
design conditions used in the classification. All instructions and guide and limits
must be recorded in the exploitation book. Owner of the pipelines must update
sufficiently all data in accordance with the requirements of this standard.
All troubles, deforms and damages influencing condition of the classifications
must be immediately informed to the register applied objects. This standard is
applied to the following objects, welded steel pipelines, welded steel vertical
pipes chambers of shooting and receiving billets. Piles and anchor of the piles or

Construction Dept. - Internal translation only (TCVN 6809-2001) 53


Internal Technical Document

basement of the gravity used for anchor system of SPM must be tested with
according to requirements of the acknowledged standards. Supervision to the
fabrication and anchor testing according to the acknowledged standards.
After installing the whole goods transport system including the transmission
pipes and flexible risers, clutches, valve for testing the hydraulic with the
designed pressure according to requirements of items and table. Requirement to
supervision and testing during the fabrication. With the presence of the register
staff in the supply place to check the materials whether they are in compliance
with the design/technical features and records, consideration of welding
parameters, procedure of the welding, test technical characters, skill and
qualification of the welding workers and testing workers. With the presence of
the register staff in the supply place in important phases of the production such
as assemble, adjustment and testing.
With the presence of the register staff in the supply place to witness and record
the testing results. Permitting to make the inspection and testing at the workshop
in the absence of the register staff. These items can be accepted on basis that the
sellers or the producer present enough documents proving that these components
are designed and fabricated in pilot and meeting all acknowledged standards.
8.1.4.4. Flow and currents.
a. Flow and current in working condition:
Additional testing requirements are pointed out in parts of this rule control
system and safety 8.1.4.1. All control equipment and safety ones must be
inspected and certified the rationality with the use purposes, refer to table.
Transmission pipes and riser flexible. Relating to test of transmission pipes/riser
flexible, please refer to item of this standard SPM. Testing the pressure of the
floating tanks. Floating tanks that are compressed are equal to outside pressure
and being tested with a pressure equal to times of the maximum working
pressure.
b. Flow and currents in storm.
Inspecting under the exploitation the yearly 8.1.4.1. Inspections must be
implemented in a duration of months before or after the regulated date of the
annual inspection date in the inspection phase of classification or periodical

Construction Dept. - Internal translation only (TCVN 6809-2001) 54


Internal Technical Document

inspections before. Valves control equipments and accessories safety


equipments protection coating, layers cathode protection system.
8.1.4.5. Seiche.
In this standard, when mentioning pipeline, it means a mentioning to application
to one or the whole objects as specified, this standard is not only limited to be
applied to the above-said objects but it also adds other objects in an appropriate
manner according to the requirements of the competent authorities or owner of
the pipelines. Start of the periodical inspection. Pipelines being designed or
fabricated in accordance with other regulations or standards that differ from
requirements of this standard will be considered to be classified, that is
according to the equivalency among the design and fabrication standards. In
those cases, it is necessary to inform immediately the Register in initial phase to
lay a foundation for the classification. For pipelines who materials are not made
of steels and soft vertical pipes made of the steels will be considered separately.
8.1.4.6. Tide data.
Periodical inspection can be implemented before deadline but it must be not
earlier than months, excepting having the advance agreements with the register.
Finishing the periodical inspection class of the pipelines symbols of the class,
symbols of basic classes for the pipeline has been classified by the register in
which means that the pipeline meets all requirements in this standard of the
register, means the pipeline is fabricated under the supervision of register. It
means the pipeline is fabricated under the supervision of other classification
organization that is authorized by the register and accepts. The pipeline is
fabricated not under the supervision of other classification organization that is
authorized by the Register and/or accepts.
Note on the class basing on the specific conditions, pipelines being classified by
the Register will be added with some information on the class. Note in the type
means notes for function of the pipeline.
For example chemical transport pipelines oil transport pipelines, gas transport
pipelines. Water pressing pipelines oil transport vertical pipelines. Note in areas
means notes to supplying information on geographical location and territory

Construction Dept. - Internal translation only (TCVN 6809-2001) 55


Internal Technical Document

where the pipeline are installed. Note on the service limit means notes to
supplying information (maximum).
8.1.4.7. Data on temperature:
Data on temperature in working area must be submitted for approval.
8.2. Designed loading.
On the pipeline being classified with main exploitation limits. Maximum
pressure under exploitation maximum design temperature, notes of the
description these are additional notes that provide 8.1.4. Detail description of the
pipeline against the notes on class that are included in the pipeline register book.
Example diameter of the pipeline, flow and water static pressure inspection in
new fabrication.
Static loading and floating force.
Environmental loadings.
Tightening loading.
Fatigue loadings.
8.2.2. 3.4. Static loading and floating force.
Static loading and floating force suspending the operation and recovering the
operation. Pile foundations of machines having moving loads SPM.
It must be designed according to SPM requirements of standard on designing
machine’s foundations having moving loading.
8.2.3. Environmental loadings.
It is necessary to include the design of the environmental loading due to the
following factors:
Wave
Winds
Flow and currents
Tide and raised water due to storms.
Marine creatures attached to.
Temperature of the atmosphere and sea water.
Pile foundations of houses and built works in places where are instable of
geology in places where may appear sliding, and in special conditions and

Construction Dept. - Internal translation only (TCVN 6809-2001) 56


Internal Technical Document

circumstances etc….they should be designed in a consideration to additional


requirements.
8.2.3.1. Wave loadings.
The construction and use of the houses SPM and buildings and works in the
above-mentioned areas. Choice of foundation structures for example the pile
foundations for example 6 months or more Morison.
Natural plane, which are reinforced by compact ramming, chemistry or with
thermal as well as various types piles and type of pile foundations for example
piles driven according 3 groups, according to long lines (wave frequency). Long
piles must derive from the specific conditions of the construction site, which are
characterized by the documents (steady drift) of technical survey and on basis of
the results of the comparison of the real situations etc…
8.2.3.2. Wind loading
Techniques of the possible solutions SPM of the solutions on foundation design.
According to the requirements of technical principles and saving SPM the
fundamental construction materials. Pile foundations should be designed on
basis of results of investigating the construction site’s geology and hydro
meteorological conditions of the construction site as per requirements of item of
this standard. According to data on climate conditions of the construction site as
well as according to the characteristics of houses and building that are designed.
And according to the experiences in construction SPM of the locality inspection
the unfinished items. Not permitting to design the pile foundations if without a
rational foundations on the construction geology or when lacking the geological
ground to owner and the register.
In case when SPM falls in a n accident and damaging the structure, machine
systems, equipments and anchoring systems or transmission pipes and Pw riser
flexible and causing an influence and being according to the following formula:
Pw = 0.0623 x Cs x Ch x V2w (kG/m2)
Where:
Vw is wind velocity, m/s.
Cs is shaping coefficient (not secondary one)
Ch is height coefficient (not secondary one)

Construction Dept. - Internal translation only (TCVN 6809-2001) 57


Internal Technical Document

Ch is influence of profil and velocity of winds vw according to height, being


calculated according to formula:
Ct = (V2Vch)2
In which: V2 is wind speed at height of z on water route that is calculated as
follows:
V2 = Vcn x (Z/Zch)2 as m/s.
V2 is taken as reference wind speed Vch when height of z is less than reference
height zgh.
Vch is taken as wind speed at reference height zch = 10 m, as m/s.
Β = 0.10, normally used with wind on average of 1 minute, other values are
suitable with operation area that is necessary to make a calculation.
Air loading in relative manner on air collecting area:
Fw = px x Aw
Where:
Aw is geometry of collection face of winds on standard face in perpendicular to
wind direction, taken as m2.
It may impact on the classification then owner its representative must request the
Register to inspect and supervise the technical aspects. All repairing so that table
8.2.1. It can continue keep the classification must be inspected and certified by
the (corresponding to value β = 0.10) as shown in table 8.2.2. register that meet
all requirement of the rule 16.5 m.
Table 8.2.1- C shaping coefficient, for wind collection surface
Cylinder pipe 0.5 – 1.0
Buoy body on water route 1
Super-area 1
Separate structures (cranes, 1.5
horizontal beams, angle)
Board-under areas (smooth) 1
Board-under areas (beams and wind 1.3
collection face)
Girder and brackets structure (each 1.25
side)*
(*) 30% of total geometry of the reflection of area for both front areas and

Construction Dept. - Internal translation only (TCVN 6809-2001) 58


Internal Technical Document

rear areas
Table 8.2.2. Coefficient of C height (used for β = 0.10)
Height on water route Ch / 1 minute
M Feet
0.0-15.3 0-50 1.0
15.3-30.5 50-100 1.19
30.5-46.0 100-150 1.31
46.-61.00 150-200 1.40
61.0-76.0 200-250 1.47
76.0-91.5 250-300 1.53
91.5-106.5 300-350 1.59
8.2.3.3. Flow current loading.
Inspecting the classification to existing pipelines SPM the construction site so as
to choose an appropriate structure of the foundations, type of piles and to
determine dimensions of piles. In the construction drawings of the pile
foundations, it is necessary to specify the type of piles, its number and
parameters of piles, sections, profiles. Length of piles, loading resistance and
allowable loadings of the piles these parameters.
They are not necessary to be made further accurate by testing the piles. In soils
during the construction process. Testing the piles, tubular piles or pile
foundations for example. Pile group, which are implemented during the
construction process or after the construction, it is necessary to follow up the
standards on construction and acceptance of the plane and foundation in item
8.1.4.1.
Repairing and replacement Fc so as to keep the pipelines must be implemented
SPM, anchor chain, riser flexible etc…. will be calculated as stop force
according to the following instructions:
Fc = ½ p xCo x A x U2 x Uc (T)
Where:
P is water density equal to 1.025 T/m3.
CD is stop coefficient (not secondary)
Uc is flow and current speed, m/s

Construction Dept. - Internal translation only (TCVN 6809-2001) 59


Internal Technical Document

Ac is area under the impact of flow, m2.


8.2.4. Tightening loading
According to according to the requirements of this standard SPM (chains for
tight or rigid connection structure such as beams, horizontal bars). In cases when
according to the acceptance and put the finished works into operation, in order
to determine the quality of the pile foundation and the rationality. Underground
parts of SPM and other accessory parts must be inspected in a duration of time
not beyond 5 years and it must be suitable with periodical inspection schedules.
Periodical inspection the foundation to design as well as to determine the
corresponding SPM of the geographical conditions in construction site to the
documents gained in the design. Solutions of the pile foundation, it is necessary
to estimate the actual measurement of the deforming of plane and foundation
8.1.4.2 according to special benchmarks pre-made in the following cases.
8.2.4.1 Working tightening load
When using new structures for houses and works or for pile foundations,
granting certificates, granting SPM certificates of the classification. Studied
sufficiently in the mass construction 8.1. When having a special tasks, in design
when having individual requirements on measuring the deforming in order to
study the working of plane, foundation, structure of the houses and building or
of the technological equipments SPM.
a. Ship tightening loading to SPM in working regime.
Choice of the objects to SPM measure the deforming must be approved by the
bid deliverer. According to the additional requirements of standard years. Lids
for protecting mouth of chambers and other holes. Wall of the chamber mouth
including the connection with boards and areas. Yearly certificate of granting
certificates of the classification. Program and results of the measurement during
the construction must be written in the documents 8.1.4.1, if design and being
transported to the acceptance agency and user of that house or works. Pile
foundations used in the conditions of the corrosion environment must be
designed 8.1. Granting the temporary certificates of the classification.
Protecting the anti-corrosion construction structures, regarding the woody
structures of pile foundations, it should be given an attention to requirements on

Construction Dept. - Internal translation only (TCVN 6809-2001) 60


Internal Technical Document

protection from being ruined and damaged as well as defects caused by


intersects. In this standard, it is necessary to survey the following types of the
piles. Piles made months from the issuing date. What should be noted during the
inspection. Reinforcement concretes and woody materials, being placed on soils
with hammers, vibration machines. And pressing vibration machines,
withdrawing the classification. Tubular piles made of the reinforcement
concretes, boring piles made inspecting the classification when making a new
fabrication.
b. Mooring foot loading in working regime.
Concretes redone in soils article reinforcement concrete piles under lowering
drill. That are made of pre-fabricated reinforcement concretes structures being
lowered into pre-drilled holes. Piles tightened to the body made of steels or
reinforcement concretes. According to characteristics of soils under the pile tips,
piles will be divided into support piles and suspended piles. Piles of various
types and tubular piles, when they transmit the loading through pile tips. On
soils actually they are not pressed and sprinkled, they are supporting piles,
friction forces in sides of the support piles will be not included in the calculation
of the force. Load resistance of piles according to the plane soils when being
suffered from pressing load. All types of piles and tubular piles are lowered into
soil areas that are capable of pressing and displaying the goods level.
8.2.4.2. Designed storm loading.
And sprinkle that belong to 8.1.4.1 that must be determined as suspended piles
SPM, Suspending piles transmit the load on ground via side areas and via pile
tips. Real soils can not be pressed and sprinkled that are various types of soils
and sands, rough soil pieces.
8.2.5. Fatigue loading.
With the tower mooring system it is necessary to implement the fatigue analysis
for the structure according to standards that have been acknowledged by the
register.
8.3. Structure and stability.
8.3.1. General regulation.
Generally, one SPM has a structure of floating or fixed.

Construction Dept. - Internal translation only (TCVN 6809-2001) 61


Internal Technical Document

8.3.1.1. Floating SPM structure.


Gravels SPM macadam, grits mixed with other substances such as sands and
clays having the solid viscosity. Including the covering soils having the water
sufficiency SPM. Including the soils, type of soil, expanded soils and salted
soils. Piles driven as reinforcement concrete and tubular piles are divided
according to way of placing the reinforcement.
8.3.1.2 Fixed SPM structure.
Piles and pile tubular having the lengthwise part SALM that are not stretch to
horizontal reinforcement. Having lengthwise part SALM or having the
lengthwise steel strip that are pulled in stretch before. Steel and steels of high
strength is months, with SPM horizontal reinforcement and without the
horizontal reinforcement, at the same time only the pile of cross section.
According to the shape of horizontal section, square piles, rectangular piles,
square piles having round holes that are empty diameter up to including the
tubular piles having a diameter.
8.3.2. Norm of the general design.
8.3.2.1. Durability of the structure.
Piles of cylinder shape and piles. Having oblique surface according to the
characters of the structure of the pile body, intact pile and connected pile in 8.2.
Including the separated section according to the structure of the pile tips, sharp
nose-piles, flat-nose piles, piles having expanded or not expanded bottom,
empty piles having tight or opened tips, and piles having expanded bottom by
blaster. Driven piles having expanded bottom by blaster are fabricated by
driving the round piles with empty inner part. In the nose part, there is empty
steel nose and closed tips. After mixing the concrete mixtures into inner part of
the piles, caused by 8.2 implementing the blaster in tip section to make the
deformed foot of the piles in the project 8.3.3 and 8.3.4.
8.3.2.2. Pile foundation.
With SPM will be anchored into piles, it must be designed according to
requirements of the acknowledged standard.
8.3.2.3. Anti-corrosion.

Construction Dept. - Internal translation only (TCVN 6809-2001) 62


Internal Technical Document

Regulations on annual inspection when using the closed and opened piles
according to blaster it is necessary to specify the observation. Strict manner to
requirement of the construction blaster which it is necessary to SPM determine
the allowed distance. Houses or works to places of blaster changes of the driven
piles 8.3.4.8; 8.3.4.9 and 8.3.4.10. Used as reinforcement concretes according to
the structure 10% method of lowering the piles. Piles pillars part in ground of
the piles 10% will be used as house piles. It is not allowed to use as piles, pillars
for reinforcement piles that are stretched in advance. With the lengthwise
reinforcement that are steels as well as pre-stretched piles cathode having the
horizontal part to any type of the piles. Piles being lowered in pre-drilled holes,
at the same time diameter of the boring should be not more than the minimum
side of the cross section. Diameter of the piles regarding the dept of the bored
holes. Less than that of the lowering the piles requirement according to the
calculation.
Pre-drilled holes are allowed to use when there is a need 8.3.3 and 8.3.4 or
flanges, bolts and joint bolts according to design method that is different from
that of 8.3.4.7, then it is necessary to use the following articles:
a. Through the piles via clays having solid viscosity and semi-solid. With the
lengthwise reinforcement that are steels as well as pre-stretched piles cathode.
Cases when according to the result of driving piles, construction experience and
determining that.
b. Place piles through layers and that soils if without advanced drilling. Piles
when being driven use the water erosion method then the erosion must be not
implemented in the last meters when placing the piles, regarding piles should be
further driven to reach the designed level. Water erosion is permitted to be done
mainly when driving the piles through soil and sand layers having a large
thickness.
8.3.3. Stress.
8.3.3.1. Calculating the structure.
Driving piles made of woody materials are divided into the following types.
Intact piles made of a woody tree piles connected in length SPM, piles bundled
include some intact piles or joined ones. According to the fabrication method,

Construction Dept. - Internal translation only (TCVN 6809-2001) 63


Internal Technical Document

are divided into the following types. Boring piles are fabricated by pre-driven
methods, steel piles are sealed. With pipe’s tips which is left in soil or being
sealed with concretes gradually drawing out.
a. The piles that depend on number of concretes poured in to holes. Boring piles
of vibration and punching, that are formed in pre-drilled holes or closed holes by
pouring these holes.
b. Classification of the pipeline without the supervision and inspection of the
register. Documents and drawing with solid concrete mixtures.
c. Compact ramming with by vibration ram machines having the tubular shape
with sharp head.
8.3.3.2. Flexing stress.
a. Being installed into machine of lowering piles with vibration method. Piles
bored in punched pipes are fabricated by method of pressing drill of this
standard. Generating pyramid-holes or conical ones and then pouring the
concrete mixture into the holes. Bored piles having the expansion, or not having
expansion of bottom.
b. Loading is placed in symmetrical manner.
When considering the flexing stress, it is necessary to calculate the plasticity
deforming when determining the impact of the loading along with the axial that
is placed in a symmetrical manner and bending torque caused by itself that is
plus with bending torque calculated for other loadings.
8.3.3.3. Stress caused by losing the stability.
Possibility of losing the stability of the structure’s parts and components must be
considered according to 8.3.4.3. With structures SPM fixed one, losing the
stability of the tubular structure must be also calculated.
8.3.3.4. Cut stress.
When calculating the cut stress in partitions and walls of strong structures, side
sheets and partitions, it is only necessary to calculate the area influence of the
wall sheets. Height of the whole structure can be regarded as wall sheets.
8.3.4. Allowable stress.
8.3.4.1. General regulations.

Construction Dept. - Internal translation only (TCVN 6809-2001) 64


Internal Technical Document

Parts and components of the structure SPM must be calculated in the conditions
of the loading as below mentioned and total stress of their must be also
determined in these conditions.
With each and every condition of the considered loading, the following stresses
must be determined and must not beyond the allowed stress as mentioned in
article 8.2.4.2.
a. Stress formed by general impact of gravity, environmental loading and
tightening loading in the working condition as mentioned in article 8.1.4.1.
b. Stress formed by general impact of gravity, , environmental loading and
tightening loading in the storm condition as mentioned in article 8.1.4.1.
8.3.4.2. Stress in the parts.
Each parts of the stress and total stress, if it is necessary to make the calculation,
it must not beyond the F allowable stress that is calculated according to the
following formula:
F = Fγ/FS
Fγ = melting limit of the materials.
FS is safety coefficient
With design working loading as defined in article 8.3.4.1 of item a.
FS = 1.67 for stress along with the axial or bending stress.
FS = 2.50 for cutting stress.
With storm loading of design as defined in article 8.1.4.1 of item b.
FS = 1.25 for stress along with the axial and bending stress.
FS = 1.88 for cutting stress.
8.3.4.3. Stable calculation.
When considering the stability of a part of structure caused by compressing
stress or cutting stress or by both of them, then stresses of the compression and
cutting stress must be not more than the allowable stress respectively F, it is
calculated according to the following formula:

F= Fcr/FS
Fct - critical stress causing instability due to press and cutting respective to
structural form, boundary condition, load type, material...

Construction Dept. - Internal translation only (TCVN 6809-2001) 65


Internal Technical Document

FS – Safety factor
FS = 1,67 for designed working load as definition at 8.3.4.2
FS = 1.25 for designed storm load as definition at 8.3.4.2

8.3.4.4 Items affected by integrated impact of longitudinal and bending


force

a) For items affected by integrated impact of longitudinal and bending force,


design stress has to meet the following demands:
If fa/Fa  0.15, then (fa/Fa) + (fb/Fb)  1.0
If fa/Fa  0.15, then fa/Fa + [ Cmfb/(1 – fa/F’e)Fb]  1.0
And additional condition at ends of each item:
1.67 (fa/Fy) + (fb/Fb)  1.0 for designed working stress as definition at 8.3.4.2
1.25 (fa/Fy) + (fb/Fb)  1.0 for designed storm stress as definition at 8.3.4.2
b) If items are affected by longitudinal tensile force and blending strain, design
stress has to meet the following demands:
fa + fb  Fy/1.67 for designed working stress as definition at 8.3.4.2
fa + fb  Fy/1.25 for designed storm stress as definition at 8.3.4.2
In every case, compressive stress due to blending f b that is calculated separately
must not excess Fb, in which:
fa – additional stress due to compression and longitudinal pulling force
fb - compressive or design tensile stress due to blending
Fa - admissible longitudinal compressive stress is the smallest value in the
following:
- yield stress over safety factor, for longitudinal stress mentioned in 8.3.4.2
- generally unsteady stress over safety factor mentioned in 8.3.4.5 item a
- locally unsteady stress over safety factor for longitudinal stress mentioned
in 8.3.4.5 item b.
Fb – limit compressive stress due to blending, determined by taking smaller
value in yield stress or locally unsteady stress over safety factor mentioned in
8.3.4.2
F’e = 5.15E/(Kl/r)2
F’e = *** stress which may increase 1/3 for total stress mentioned in 8.3.4.2
E = elastic module
l = raising-over length of the column

Construction Dept. - Internal translation only (TCVN 6809-2001) 66


Internal Technical Document

K = effective length factor with consideration to boundary condition at two ends


of the length. In case there is horizontal transposition at ends of column, the
factor K is not smaller than 1.0
r – radius of inertia
Cm – this factor is defined as follow:
- for compressed items of frame with node transposition Cm = 0.95
- for compressed stress of the frame with halving node and without
horizontal load in blending plane
Cm = 0.6 – 0.4 (M1/M2)
But it is not smaller than 0.4, in which M 1/M2 is the ratio of smallest moment
and largest moment at nodes of items without tie rod in blending plane being
considered. The ratio M1/M2 is positive only when the blended item is curved
and it is negative when that item is sagged down.
- For compressed items of the frame which has halving cushion, does not change
its position in the loaded plane and has horizontal load among cushions, the C m
value can be defined by suitable calculation. However, the following values can
be used instead of calculated ones.
For the items with halving node:
Cm = 0.95
For the item without halving node
Cm = 1.0
8.3.4.5. The stress due to column’s instability
a) General instability: For compressed items which are generally instable, the
limit stress is calculated according to the following formula:

Fcr = Fy – (Fy2/42E)(Kl/r)2 with Kl/r < (22E/Fy)1/2


Fcr = 2E/(Kl/r)2 with Kl/r  (22E/Fy)1/2
Fcr – generally instable stress
Fy – as defined in 8.3.4.2
E, K, l, r - as defined in 8.3.4.2 item b
The safety factor for general instability is determined as follow:
With stress of gravity and as 8.3.4.2

FS = 1.67 [ 1 + 0.15 Kl/r/(22E/Fy)1/2] with Kl/r < (22E/Fy)1/2


FS = 1.92 with Kl/r  (22E/Fy)1/2

Construction Dept. - Internal translation only (TCVN 6809-2001) 67


Internal Technical Document

With the total load as mentioned in 8.3.4.2

FS = 1.25 [ 1 + 0.15 Kl/r/(22E/Fy)1/2] with Kl/r < (22E/Fy)1/2


FS = 1.44 with Kl/r  (22E/Fy)1/2

b) Local instability
For the items which is affected by longitudinal tensile stress or blending tensile
stress, the local instability must be considered with suitable method, adding to
the general instability mentioned in 8.3.4.5a
If there is no longitudinal splint or circumferential splint on the pillar’s cover, it
is necessary to calculate local instability, when the diameter of the pillar’s cover
is:
D/t > E/9 Fy
D_ Average diameter of pillar’s cover
T – the thickness of pillar’s cover
E and Fy as defined in 8.3.4.5a

8.3.4.6. Respective stress criteria for plate structure

For plate structure, we select basing on the respective stress criteria and
calculate according to the load mentioned in 8.1.4.1; the safety factor will be
considered seperately.

8.3.4.7. Structure design

The cover and framework of raised structure should be designed in accordance


with demand in 8.3.3 and 8.3.4. Besides, the plate’s size, reinforced splint and
tie rod have to meet additional requirement in 8.3.4.8, 8.3.4.9 and 8.3.4.10. The
cover and the framework of SPM can be designed basing on the systematic
analysis with consideration to static and dynamic pressure of marine
environment and the pressure of the liquid in container and compartment.
8.3.4.8 Plate
a) Cover plate and water jacket. The thickness of steel cover is calculated
according to the formula:
t = (sk(qh)1/2/254) + 2.5 mm
but it is not greater than 6.5 mm or s/150 + 2.5mm, the greater value is taken.
t = thickness, measured in mm

Construction Dept. - Internal translation only (TCVN 6809-2001) 68


Internal Technical Document

s = space, measured in mm
k = (3.075 - 2.077) ( + 0.272) if (1   2)
k = 1 if ( > 2)
 = the ratio of the plate’s edges (length/width)
q = 24/Y, measured in kG/mm2
Y = yield limit (kG/mm2) or 72% of tensile endurance, select the smallest value
h = the maximum height (m) from the low edge of the plate to the highest wave
top for the most inconvenient calculation or h = 1.0m, select the greater value
b) Containers’ plates
If the space inside is container, the height from the design pressure column h in
the formula mentioned in a should be considered from the lowest edge of the
plate to the point at 2/3 way from the container’s top to the top of spill pipe or
1.0m, select the greatest value. If the density of the liquid is over 1.05, the height
of pressure column in this item should be raised to 1.05 times.
8.3.4.9 The splint and tie rod

The anti-blending of each edge splint or tie rod with edge is not smaller than:
SM = fchsl2 (cm3_
In which:
f = 7.8
c = 0.9 for splint with end halving with deck or floor at end node or halving at
one end and another end raises over longitudinal ridge
c = 1.0 for splint with two ends raising over longitudinal ridge
h = vertical height (m) from the center of the length l to the same height when
defining height of the pressure column h as that of plate (see article 8.3.4.8 item
a).
s = space among splints, measured in m
l = length among cushions, measured in m. If every position uses (connecting
plate) connected with steel cover, deck or edge and connecting plate meets the
demand mentioned in the table 8.3.4 and has cross-cut angle approximately 45 0,
the length l which can be calculated up to the end point of connecting plate is
equal to 25% of the connecting plate’s length.
The table 8.3.4. The thickness of connecting plate and the size of their flanged
edges, measured in mm
The length of The thickness* The width of

Construction Dept. - Internal translation only (TCVN 6809-2001) 69


Internal Technical Document

big edge Without flanged Without flanged flanged edges


edge edge
150 6.5
7.0
7.0
7.5
9.0

* the thickness of connecting plate is increased respectively in case the length of


the weld is smaller than 2/3 the ma’s thickness.
8.3.4.10. Longitudinal edge and supporting structure
a) the endurance requirement.
Each longitudinal edge and supporting structure supporting the frame, beam and
splint must have anti-blending module which is not smaller than :
SM = fchsl2 (cm3)
f = 7.47
c = 1.5
h – the vertical height (m) measuring from the central point of S in case of
longitudinal edge or from the central point of l in case of supporting structure to
the same height h as plate (see 8.3.4.8a)
s – the total of half length (m) toward each direction of longitudinal edge or the
supporting structure of the splints or supported beams.
l – the length (m) among cushions. If connecting plate is used for steel cover,
deck or edge and connecting plate meets the demand mentioned in the table
8.3.1 and has cross-cut angle approximately 450, the length l which can be
calculated up to the end of connecting plate is equal to 25% of the connecting
plate’s length.
If the press-proof tie rods are used to connect longitudinal edge or supporting
structure at each side of the container and are placed at the space that does not
excess the height of longitudinal edge or supporting structure four times, the

Construction Dept. - Internal translation only (TCVN 6809-2001) 70


Internal Technical Document

anti-blending module of longitudinal edge and supporting structure may be


equal to half of above result.
b) The size ratio
The height of longitudinal edge and supporting structure is not smaller than
theirs length 0.125 times in case of no reinforced splint and 0.0933 times in case
of reinforced splint. The thickness of longitudinal edge and supporting structure
must not be smaller than 1% of the height plus 3mm, but it should not be greater
than 11 mm. In general, their height should not smaller than that of the pierced
hole 2.5 times.
c) Anti-torsion connecting plate
Anti-torsion connecting plates of longitudinal edge and supporting structure is
placed far from each other 3 m at changeable sections. If the width of the cover
plate is over 200 mm, a anti-torsion connecting plates should be used to support
it.
8.3.5. Stability.
SPM main part is divided into waterproof compartment by baffle plates. A
waterproof access hole should be designed to go to all main closed holes that
can be flooded.
8.3.5.1. Absolute stability
Buoy’s body must ensure stability in following cases:
a) On static water, the buoy is not fastened to anchor’s base
b) During installation
c) In the working condition with all anchors’s base connected to the buoy
and extensively pulled under binding load.
d) On pulling, in case of pulling buoys
Designer has to check the following criteria:
1) The value of slanting centre height must be positive enough to ensure
primary stability on slack water, when the buoys are not fastened to
anchors’ base.
2) The reserve stability is enough to resist to titling moment caused by
environment, working load on pulling, installation or exploitation. The
water level at each balance status must be under the first water coming
point.
3) The compartments must be designed in such way to ensure that the stem
or SPM buoy are not upturned or sunk due to the towing force of anchor’s

Construction Dept. - Internal translation only (TCVN 6809-2001) 71


Internal Technical Document

bases in tense water and the tensile force of pipe/vertical hose under the
buoy in design storm condition.
8.3.5.2 . Problem stability
The designer must ensure that the buoys have enough force of floating when one
compartment is pierced. In that case, the water way must under the first water
coming way in problem stability condition.
8.36. Fixed mooring buoy structure
Fixed mooring buoy structure must be designed in the form of spatial frame,
with consideration to gravity, functional load, environmental load and fastened
load in working condition and extreme condition. For SPM in the form of
SALM, the calculation has to meet the demands in 8.3.3 and 8.3.4. The
connection of ship with fixed mooring buoy which is different from the
requirement in 8.4.5 should be fully designed. The fixed mooring buoy designed
must be able to meet the working and storm condition as mentioned in 8.1.4.1.
Buoy forming structure has to meet the requirement of 8.3.3 and 8.3.4, and
tower anchor structure which is designed as fix one with gravity base of pipe
elements must meet recognized standard.
8.3.7. Structural additional requirement.
It is necessary to design a suitable system to avoid damage to goods
transportation system caused by clashing with service ship.
8.3.8 Floating container for pipe/ vertical hose.
Floating container is used to support the pipe and vertical hose of SPM system.
The average pellicle stress at testing pressure is smaller than 90% of minimum
yield limit during hydraulic test and smaller than 80% during compression air
test. The combined stress of average pellicle stress and blending stress at
designed working pressure should be limited to 50% of maximum endurance or
minimum yield limit, select the smaller value. When the outside pressure is not
balance with inside one, the value of this pressure must be tested with regard to
critical stability.
8.4 The fastening node and anchor
8.4.1. General regulation.
The fastening nodes and anchors of SPM must be designed in order to not
damage the pipe under the buoy or vertical hoses when the anchor string is
broken in design working condition mentioned in 8.1.4.1.
8.4.2. Anchoring position
The anchors must have enough adhesive force. For the anchor system with drag
anchor, the adhesive force of each one should be defined by using the

Construction Dept. - Internal translation only (TCVN 6809-2001) 72


Internal Technical Document

characteristics of soil sample taken from the seabed. The type of anchor must be
suitable with the base conditions and maximum design anchoring load.
The anchor’s design safety factor of adhesive force is not smaller than 2.0 in
working condition with ship fastened to SPM and 1.5 in storm working
condition (with no ship fastened). If the safety factor of the anchor’s base is
smaller, it is necessary to make additional calculation for the case in which one
string is broken as mentioned in 8.4.3, and in this case the anchor’s safety factor
of adhesive force should not be smaller than 1.6
For the SPM system using anchor, the anchor’s foundation has to be designed as
recognized standards. The report of driving pile or filling pile is submitted for
approval for each. The method of pile installation and the device to install pile
must be mentioned in driving pile report.
For anchor system using gravity base, it should calculate the anti-sliding ability,
pulling out and upturn of the base. It should consider the environmental force,
gravity and fastening load. In design, the affect of gravity base’s washing out
should be taken into consideration.
When using anchor system with drag anchor, each anchoring string must be
tested with 80% of greatest design load in 30 minutes with the witness of
supervisor. The previous calculation and actual data have to be submitted to help
to select anchoring system and number of anchoring position (see 8.1.3.2)
8.4.3. Anchor’s base
The anchor’s base items must be designed with anti-breaking safety factor as
follow:
- design storm condition without ship connected
The string is unbroken 2.5
- design storm condition with ship connected
The string is unbroken 3.0

The safety factor which is smaller than 2.5 regarding to the minimum breaking
endurance of the anchor’s base parts is allowed in exploitation condition. If the
connection string of anchor system is broken, the safety factor is equal to 2.0
regarding to minimum breaking endurance.
The anchor structure of fixed SPM system must be selected according to 8.36.
8.4.4. Anchor and chain
The anchors and chains must be designed as recognized standard
8.4.5. Fastening the ship to SPM

Construction Dept. - Internal translation only (TCVN 6809-2001) 73


Internal Technical Document

The string and chains for connecting must be designed with consideration to the
anti-broken safety factor of the weakest string. The endurance of the rope or
string, connecting chain has to meet the requirement of recognized standards.
The breaking endurance of the rope or string, connecting chain is determined by
testing. The breaking endurance of the rope or string, connecting chain is the
smallest value in wet or dry condition.
With one roller, FS = 1.67
With many rollers, FS = 2.50
When the ship is fastened to SPM by string or chain through more than two
rollers, the gravity of rope, chain is calculated as if it is connected through two
rollers.
The rope, chain must be manufactured in accordance with recognized standards.
If the hard structure is used to connect ship with SPM, this structure has to meet
the requirement of recognized standards
8.4. Structural parts
If there is no other requirement, structural parts and mechanical parts
(connecting chain, manipulator...) which are used to transfer fastening load is
designed with the greater value in two following loads:
a) 2.50 times the maximum design anchor’s base (or change) load in storm
condition.
b) 3.0 times the maximum design anchor’s base (or change) load in working
condition.
9. The equipment and system
9.1. Goods or product transferring system.
9.1.1. General regulation
The requirements in this part are applied for goods or product transferring
system and other attached parts of SPM. The goods or product transferring
system consists of many parts from the mechanism connecting with pipes at
seabed to the seabed to the first coupling flange on ship. The valve cluster
(PLEM) if any must meet the requirements in this part.
9.1.1.1. The applied condition to connect pipe line.
The following conditions are used for connecting valve cluster (PLEM) or
connecting underground pipe with pipe/ vertical hose under buoy.
a) Must be anchored to seabed to resist against wave load, current flow and
force caused by SPM and hose.

Construction Dept. - Internal translation only (TCVN 6809-2001) 74


Internal Technical Document

b) Must have disconnecting device to separate SPM with seabed pipe line.
9.1.2. Material
The material for goods or product transferring system has to meet the
requirement mentioned in 6.4
9.1.3. Pipe/hose
9.1.3.1. General regulation
The length of pipe/hose, regulation of floating property, the split pipe between
pipes/hoses, outside clip (if required) and connecting angle with pipe’s end and
with SPM should be defined basing on following calculations:
a) The maximum transferring of SPM structure in working condition with
connected ship and without connected ship.
b) The changing of system’s parts.
c) The external force on pipe/hose system
d) The specific weight of products in pipe/hose system including other
planned products and sea water.
9.1.3.2. Pipe/hose under buoy
This system should be designed to avoid the friction of pipe/hose with SPM
stem or buoy, anchor’s base and other pipe/hose (if any). The system which is
designed to prevent contacting abrasion with seabed in storm should be
considered separately. On design, it is necessary to carry out test of contacting
level. It is necessary to reinforce the pipe/hose in the most blending affected
zone. The installation or dismounting process (if any) and maintenance should
be submitted to Register Organization approval.
9.1.3.3 Surface pipe
Lifting device should be installed at the end of surface pipe. A special pipe
should be equipped at the pipe end near the ship to regulate the blending level of
pipe at the side of the ship. For the pipe end connected to ship, there should be a
closed flange to prevent sea water from entering. It should consider equipping
swivel joint, special reinforced pipe or both of them at the joint of surface pipe
with the parts of SPM system. The split joint with cut-off valve should be placed
on each surface pipe to protecting against pressure surge and longitudinal
overload and minimized pollution degree in case the pressure is over allowed
level or oil overflow from tanker
9.1.3.4. Manufacturing.

Construction Dept. - Internal translation only (TCVN 6809-2001) 75


Internal Technical Document

All pipes must be manufactured in accordance with recognized standards and


under supervision of Register Organization. The sample pipe also has to be
approved according to the recognized standards.
Any differ from the standard requirements will be considered in each case and it
should have full explanation for such differ.
Material for bolt and joint ring and their design as well have to meet the design
standards and to be suitable for the using purpose.
For vertical hoses, if they are used, they have to meet the standards.
9.1.3.5. Design pressure of the system.
Design pressure of the system is the greater value in two followings:
a) Disconnecting pressure column at the valve cluster on ship at zero
current, plus the weight of liquid contained in the SPM’s pipe.
b) The pressure column caused by pressure surge when closing the valve.
9.1.3.6. Testing
Each pipe part must be tested hydraulically and vacuum tested to define whether
they meet the standard or not and under the supervision of register personnel. In
every case, if the design pressure of the system is not over 15.8 kG/cm 2, it
should carry out the hydraulic test at the pressure lower than design. If the hoses
are used, they must be tested with recognized standards.
9.1.4. Goods or product joint with relating system and devices.
9.1.4.1. Goods or product joint
a) Design
Goods or product joint has to made of steel and be connected by flange or weld.
The details of fix pipe joint with swivel pipe of SPM should be submitted for
approval. These details include fix and swivel part, the plate thickness, closed
flange and ball bearing design, and weld.
In designing joints, it should be taken into consideration of the most
disadvantageous load that will be used and at least, the following forces will be
considered:
1) Starting rotated moment for each joint at maximum design
pressure.
2) The joint weight and its structural parts.
3) Dynamic load caused by the movement of ship
4) Pipe load
5) Fastening force

Construction Dept. - Internal translation only (TCVN 6809-2001) 76


Internal Technical Document

6) Pressure load
7) Thermal load
The pressure affected parts of the joint should be designed in accordance with
common standards. The structural parts of the joint and operating machine must
be suitable with 8.3 of this standard or with other structural design common
standards.
c) Testing
Testing should be made at manufacturing place in accordance with testing
process approved by supervisor. This process has to find out the acceptable
leaking standard and at least the testing regulation as follow:
1) The hydraulic pressure is at least equal to 1.5 times of design pressure; the
testing time is at least 2 hours.
2) The hydraulic pressure as design for 2 rotating revolutions toward each
direction at the speed of approximately 10 minutes per revolution.
3) The hydraulic pressure as design for 4 rotating revolutions: the first is
clockwise and the last is counterclockwise. Each rotating time is 30 0 at the
speed of approximately 30 seconds per 300 and 30 seconds for breaking
between two rotating times. Starting rotated moment and rotated moment
should be recorded with the swivel angle of 30 0. If the liquid joint rotates
together with fastening one, the testing should be carried out as combined
system.
9.1.4.2. System to detect leakage, leakage recovery and pressure
adjustment.
All pipes of system for leakage recovery and pressure adjustment have to be
made of steel or similar and be designed in accordance with the common
standard.
Isolated closed buffer, anti-overpressure or pressure balance will be used
between the lowest close buffer and joint in order to allow the air or liquid pass
through.
9.1.4.3. Supporting bearing
a) Fastened bearing
The bearing is affected by slope load, fastening chain in working condition, the
swivel structural load and fastening load are designed with safety factor not less
than 2 to prevent bearing surface from yielding.

Construction Dept. - Internal translation only (TCVN 6809-2001) 77


Internal Technical Document

The bolt used to assembling the bearing must be designed in accordance with
recognized standard. For the bolt suffering from great stretch, the corrosive
cracking must be considered.
c) Pivot bearing
For pivot bearing not affected by slope and fastening chain load, it has to be
designed in accordance with common standard.
9.1.4.4 Corrosion resistance
The surface of swivel joint must be covered with suitable corrosion resistant
material. The items made of corrosion resistant material do not need the
cover. On designing the joint, it must take into consideration the corrosion of
goods or products caused by CO2, O2 or H1.
9.1.5 Goods or product transporting pipe system.
9.1.5.1 Pipe line
The pipe line system to transport goods or products on SPM must be made of
steel and connected by flange or weld. The pipe system is jointed with SPM
and anchor to resist to additional forces caused by inside pressure and the
flow within the system and the load caused by pipe/hose system. It must have
space for elastic pipe. The pipes are tested at workshop after manufactured
with the minimum pressure equal to 1.5 times of design pressure with the
presence of supervisor.
The pipe line system to transport goods or products on SPM must meet the
recognized standard.
9.1.5.2. Valves
The cut-off valve is placed on SPM for each goods transporting pipe. This
valve is made of steel and can be operated by hand and tested according to
recognized standard. Unstandadized valve is one that is not certificated
according to accepted standards. The use of unstandadized valve is
considered separately. The drawings of this valve show clearly structure
details and material, norm pressure and design calculation as well or the
results of bursting and exploding test have to be submitted for approval.
9.1.5.3. Flange and spare parts.
Flange and spare parts have to be designed and tested according to
recognized standard. Unstandadized flange and spare parts is not certificated
according to accepted standards. The use of unstandadized flange and spare

Construction Dept. - Internal translation only (TCVN 6809-2001) 78


Internal Technical Document

parts is considered separately. The structural, material and calculation or


testing drawings of them have to be submitted for approval.
9.1.5.4. Elastic joint
The maximum working pressure of elastic joint must not be greater than a
third of static hydraulic bursting pressure. For nonferrous elastic joint, cross
sectional drawing of the joint which represents clearly the structure of the
joint including connecting spare part and bill of material has to be submitted
for approval. For ferrous elastic one, cross sectional drawing of the joint and
bill of material has to be submitted. The calculations proving the accordance
of design elastic joint with recognized standard and using purpose also have
to be submitted for consideration.
9.1.5.5. Valve cluster (PLEM)
The requirements of 9.1.5.1, 9.1.5.2 and 9.1.5.3 are also applied to pipe line,
valve, flange and spare parts of valve cluster (PLEM).
9.1.5.6 Corrosion resistance
The surface of pipe system for transporting goods and products, of vavle and
spare parts must be covered with corrosion resistant material. The items
made of corrosion resistant material do not need the cover. On designing the
joint, it must take into consideration the corrosion of goods or products
caused by CO2, O2 or H1.
9.2.The system and supporting devices.
9.2.1. General regulation
The supporting systems such as hydraulic, compression air, oil, measuring
and testing installed on SPM have to meet the recognized standard, except
the items mentioned in this part.
9.2.2. Dry suction pump
The SPMs have to be equipped with devices to pump residual water and dry
the containers and empty compartment. Manual pump is used in drying
system instead of fix dry suction pump.
9.2.3. Measuring the depth of container.
The manual depth measuring equipments should be equipped for containers
and empty compartment.
9.2.4. Air ventilation system for container.

Construction Dept. - Internal translation only (TCVN 6809-2001) 79


Internal Technical Document

All containers are filled and dry suctioned by fix pump system and for empty
compartment though which the pressure pipe system passes, it’s necessary to
locate a air pipes.
The structure of the container or empty compartment must contain holes to
make air and steam from every corner of the container and empty
compartment move freely to the air pipe. For each container or empty
compartment, at least one air pipe is located at its highest position. This air
pipe must be designed so that it can push air by itself in normal condition.
The air hole on open compartment must be ended with downward bent pipe.
It requires suitable fix devices to close the air pipe.
The internal diameter of the air pipe is not smaller than 51 mm, except for
special approved case. If the containers are filled with liquid by pump, the
smallest section of air hole is 125% the effective area of container filling
pipe. Beside that, the pump flow and pressure column should be selected in
accordance to air hole’s size.
The air pipe must be in open air and rise above deck at least 760 mm,
excepting that this height is obstacle to SPM. If the lower pipe is used, it
must be ensured that all devices are closed and other factors are suitable for
this kind of air pipe.
9.2.5. Auxiliary devices.
The mechanical auxiliary devices such as winch, fast connecting –
dismounting aid devices have to be designed according to recognized
standard.
9.3. Danger zone and electric equipments.
9.3.1 General regulation:
The electric equipments on SPM have to meet the requirements of TCVN
5316 – 91 standard regarding to electric equipments and additional
requirements in this part.
9.3.2. Danger zone
9.3.2.1 Definition
Danger zones: danger zone is the area that is constantly or periodically
explosive. Danger zones are divided into zone 0, 1 and 2 and defined as
follow:
Zone 0: where the compound of vapor and explosive air appears constantly
or in long period.

Construction Dept. - Internal translation only (TCVN 6809-2001) 80


Internal Technical Document

Zone 1: where the compound of vapor and explosive air is likely to appear in
normal exploiting condition.
Zone 2: where the compound of vapor and explosive air is impossible to
appear or only exist in short period.
The close space is space that is limited by decks and wattles with or without
door, window, or similar holes.
9.3.2.2. Zoning
The zone within 3 m surrounding goods or products compartment in open
zone is considered as zone 2
If goods or products compartment is placed in close space, this space is
considered as zone 1
The internal of container, compartment of hydrocarbon containing pipe is
considered as zone 0.
9.3.3. Electric cable and type of electric equipments used in danger zone.
9.3.3.1. Electric equipment.
The following electric equipment and cable are used in danger zone:
a) Zone 0: Only naturally safe certified electric equipments and cables are
used in zone 0.
b) Zone 1: electric equipments and cables used in zone 1 must be:
1) Naturally safe certified electric circuits or equipments and cables.
2) Certified spark preventative electric equipments
3) Certified safety enhancing electric equipments: for safety
enhancing motor, it should consider overload prevention.
4) Pressurized close-type electric equipments (Pressurizing system has
to meet the recognized industrial standard)
5) Cables are fixed within metal cover or in metal pipe with explosion
protecting close part. Except: flexible cable, if necessary it can be
installed in parallel but it must ensure to be heavy load part.
c) Zone 2: electric equipments ad cables used in zone 2 are ones used in
zone 1 and following equipments but it should be ensured that the
working temperature is not over 3150C and the bush, contact or ignition
devices are accepted to use in zone 1:
1) Close squirrel-cage motor
2) Fix lightening devices avoiding mechanical damage.
3) Transformer, solenoid or common covered impedance coin.

Construction Dept. - Internal translation only (TCVN 6809-2001) 81


Internal Technical Document

4) Cable with damp-proof and mechanical damage preventing cover


9.3.3.3. Electric cable installation
The electric cable must be placed as far from air accumulated area as possible.
Do not place the cable ends in danger zone, except for naturally safe electric
circuit. If it is necessary to connect electric cable in danger zone ( as connecting
flexible with inflexible cable), the joint must be placed in approved terminal bos.
9.3.4. Electric joint.
If it is necessary to use joint in danger zone, the electric joint must be certified
basing on the suitable independent test in lab to use in this zone as 9.3.2 items of
standard.
Norm current of electric joint must be suitable enough to bear full load current
of the supply source.

9.4. Safety regulation

9.4.1. Shipping equipment

9.4.1.1. Pilot light

Pilot light must be equipped as demand of administrative authorities. IF SPM is


beyond the country of administrative authorities or administrative authorities
have no demand, at least pilot light must be equipped.
There is a white light with vision angle of 3600, visibility of 5 sea miles,
atmosphere transmission of 0.95, flashing 6 times per minute and light from the
sunset to the sunrise as local time. The position of float pipe is marked by flash
light.

9.4.1.2. Mist signal.

The equipment of mist signal by sound will be considered in specific cases.

9.4.1.3. Radar radiation

The equipment of radar radiation will be considered in specific cases.

9.4.2. Fire fighting equipment.

Construction Dept. - Internal translation only (TCVN 6809-2001) 82


Internal Technical Document

SPM is equipped with at least one handy fire-extinguisher B-II type. Where is
likely to be burnt due to electric, the handy fire-extinguisher C-II type. It is
possible to equip one integrated fire-extinguisher for both oil and electric
burning. Fire-extinguisher B-II type may contain 9.5 litre of foam, 6.7kg CO 2 or
4.5 kg dry chemical substances. Fire-extinguisher C-II type may contain 6.7kg
CO2 or 4.5 kg dry chemical substances.

9.4.3. Identification

Name and code for each SPM must meet the requirement of register
organisation. Name and code must be fixed on structure and written in marine
work registering book. The SPM dry side must be inerasable written at least at
two position of SPM.

Construction Dept. - Internal translation only (TCVN 6809-2001) 83

You might also like