Professional Documents
Culture Documents
INCORRECT
INCORRECT
INCORRECT
Your answer is incorrect. The correct answer is “standard cost card” (option
3).
The standards that require peak efficiency and do not allow any work
interruptions are known as:
o normal standards
o practical standards
o ideal standards
o budgeted standards
INCORRECT
Your answer is incorrect. The correct answer is “ideal standards” (option 3).
The Three Star Company produces a product known as product X. The company
uses a standard costing system and provides you the following information:
o Direct materials required to produce one unit of product X: 6 pounds
o Standard cost of direct materials: $10 per pound
o Normal wastage while producing one unit of product X: 0.5 pounds
Based on the above information, what is the standard direct materials cost per
unit of product X?
o $60
o $65
o $50
o $55
INCORRECT
INCORRECT
INCORRECT
During the month of January, Ali BaBa purchased 25,000 ponds of materials at a
cost of $128,750 and used 10,250 ponds of materials to produce 2,500 units of
product K. The direct materials price variance for January was:
o $3,750 favorable
o $3,750 unfavorable
o $3,700 favorable
o $3,700 unfavorable
INCORRECT
Your answer is incorrect. The correct answer is “$3,750 unfavorable”
(option 2).
Computations:
Direct materials price variance = (Actual quantity purchased × Actual rate)
– (Actual quantity purchased × Standard rate)
= $128,750 – (25,000 pounds × $5)
= $128,750 – $125,000
= $3,750 Unfavorable
Or direct materials price variance can be computed as follows:
Direct materials price variance = Actual quantity × (Actual rate – Standard rate)
= 25,000 ponds × ($5.15* – $5.00)
= 25,000 ponds × $0.15
= $3,750 Unfavorable
*Actual rate of direct materials: $128,750/25,000 ponds = $5.15
The Crescent Manufacturing company established the following direct materials
cost standards for one unit of product X:
During the month of June, the company purchased 40,000 pounds of direct
materials at a cost of $199,200 and produced 5,000 units of product X using
19,750 pounds of direct materials. The direct materials quantity variance for June
was:
o 800 favorable
o 800 unfavorable
o 1,250 unfavorable
o 1,250 favorable
INCORRECT
INCORRECT
INCORRECT
CORRECT
INCORRECT
CORRECT
INCORRECT
INCORRECT
INCORRECT
Your answer is incorrect. The correct answer is “4,000 hours” (option 2).
Computations:
Direct labor rate variance = (AH × AR) – (AH × SR)
-$450* = $39,550 – (AH × $10)
-$450 – $39,550 = -$10AH
-$40,000 = -$10AH
AH = $40,000/$10
AH = 4,000 hours
AH = Actual hours
AR = Actual rate
SR = Standard rate
*The negative sign (-) indicates a favorable variance because a favorable
variance means less production cost than expected.
During the month of January, the standard cost of actual hours worked amounted
to $25,000, the standard direct labor rate was $10 per hour and the direct labor
efficiency variance amounted to $1,000 favorable. The standard hours allowed
for actual production were:
o 2,500 hours
o 2,400 hours
o 10,000 hours
o 2,600 hours
CORRECT
INCORRECT
Your answer is incorrect. The correct answer is “$20 per hour” (option 2).
Computations:
Direct labor efficiency variance = (AH × SR) – (SH × SR)
$2,000 = $42,000 – (2,000 × SR)
$2,000 – $42,000 = -2,000SR
-$40,000 = -2,000SR
SR = $40,000/2,000
SR = $20 per hour
AH = Actual hours
SR = Standard rate
SH = Standard hours
You are provided the following information for December 2017:
o Actual direct labor hours used: 3,000
o Standard direct labor hours allowed: 2,950
o Actual variable manufacturing overhead rate: $12.20/direct labor hour
o Standard variable manufacturing overhead rate: $12.30/direct labor hour
Based on the above information, the variable manufacturing overhead rate
variance is:
o 295 favorable
o 295 unfavorable
o $300 unfavorable
o $300 favorable
INCORRECT
Your answer is incorrect. The correct answer is “$300 favorable” (option 4).
Computations:
Variable manufacturing overhead rate variance = (Actual hours × Actual rate)
– (Actual hours × Standard rate)
= (3,000 hours × $12.2) – (3,000 hours × $12.3)
= $36,600 – $36,900
= $300 favorable
Or we can compute the above variance by using factored formula as follows:
Variable manufacturing overhead rate variance = Actual hours × (Actual rate –
Standard rate)
= 3,000 hours × ($12.2 – $12.3)
= 3,000 hours × $0.1
= $300 favorable
Variable manufacturing overhead rate variance is also known as:
o variable manufacturing overhead efficiency variance
o variable manufacturing overhead spending variance
o variable manufacturing overhead usage variance
o none of the above
INCORRECT
INCORRECT
Variance analysis
1. A variance is the difference between a planned, budgeted or standard
cost and the actual cost incurred. The same comparisons may be
made for revenues.
1.
1. True
2. False
2. The process by which the total difference between standard and actual
results is analysed is known as variance analysis.
1.
1. False
2. True
3. Variances can be divided into:
1.
1. Variable cost variances
2. Sales variances
3. Fixed production overhead variances
4. All of the above
4. A cost variance is the difference between an actual cost and a
standard cost.
o When actual cost is higher than standard cost, the cost variance
is adverse (A) or unfavourable (U).
o When actual cost is less than standard cost, the cost variance is
favourable (F).
1. The above is correct
2. The above is incorrect
5. Variances are calculated, relating to:
1.
1. Direct materials, direct labour
2. Variable production overhead and fixed production overhead
3. Both A&B
4. None
6. In a cost accounting system, cost variances are adjustments to the
profit in an accounting period.
o Favourable variances increase the reported profit.
o Adverse variances reduce the reported profit.
1. True
2. False
7. The method of calculating cost variances is similar for all variable
production cost items (direct materials, direct labour and variable
production overhead), while a different method of calculating cost
variances is required for fixed production overhead.
1.
1. The above statement is incorrect
2. The above statement is correct
8. Variances might be reported in a statement for the accounting period
that reconciles the budgeted profit with the actual profit for the period.
This statement is known as:
1.
1. Statement of evaluation
2. Statement of Reconciliation
3. Operating statement
4. None
9. The direct materials total cost variance can be analysed into:
1.
1. Price variance and usage variance
2. Wage variance and usage variance
3. Efficiency variance and price variance
4. Usage variance and rate variance
10. If there are two or more direct materials, a price/usage variance
is calculated separately for each material.
1.
1. False
2. True
11. What are the possible causes of favourable materials price
variances?
1.
1. Different suppliers were used and these charged a lower price
(favourable price variance) than the usual supplier.
2. Materials were purchased in sufficient quantities to obtain a bulk
purchase discount (a quantity discount), resulting in a favourable
price variance.
3. Materials were bought that were of lower quality than standard
and so cheaper than expected.
4. All of the above
12. What are the possible causes of adverse materials price
variances?
1.
1. Different suppliers were used and these charged a higher price
(adverse price variance) than the usual supplier.
2. Suppliers increased their prices by more than expected. (Higher
prices might be caused by an unexpected increase in the rate of
inflation.)
3. There was a severe shortage of the materials, so that prices in the
market were much higher than expected.
4. Materials were bought that were better quality than standard and
more expensive than expected.
5. All of the above
13. What are the possible causes of favourable materials usage
variances?
1.
1. Wastage rates were lower than expected.
2. Improvements in production methods resulted in more efficient
usage of materials (favourable usage variance).
3. Both A&B
4. None
14. Possible causes of adverse materials usage variances include:
1.
1. Wastage rates were higher than expected.
2. Poor materials handling resulted in a large amount of breakages
(adverse usage variance). Breakages mean that a quantity of
materials input to the production process are wasted.
3. Materials used were of cheaper quality than standard, with the
result that more materials had to be thrown away as waste.
4. All of the above
15. The direct labour total cost variance can be analysed into:
1.
1. Rate variance and efficiency variance
2. Price variance and efficiency variance
3. Wage variance and usage variance
4. None
16. The direct labour rate variance is calculated for the actual
number of hours ______ for.
1.
1. Worked
2. Paid
3. Both A&B
4. None
17. If there are two or more different types or grades of labour, each
paid a different standard rate per hour, a rate variance is calculated
separately for each labour grade.
1.
1. The above is true
2. The above is false
18. The direct labour efficiency variance is calculated for the hours
_______ on the units produced.
1.
1. Used/worked
2. Paid
3. Both A&B
4. None
19. Idle time occurs when the direct labour employees are being
paid but have no work to do. A feature of idle time is that it is recorded,
and the hours ‘lost’ due to idle time are measured. Idle time variance is
part of the efficiency variance.
1.
1. The above statement is incorrect
2. The above statement is correct
20. Calculating the idle time variance will affect the calculation of
the direct labour efficiency variance. If idle time occurs but is not
recorded the idle time variance is part of the direct labour efficiency
variance.
1.
1. True
2. False
21. Possible causes of favourable labour rate variances include:
1.
1. Using direct labour employees who were relatively inexperienced
and new to the job (favourable rate variance, because these
employees would be paid less than ‘normal’).
2. Actual pay increase turning out to be less than expected.
3. Both A&B
4. None
Target costing
An estimated price, which is expected to be paid by customers for
particular market offering is classified as
A. target price
B. target cost
C. outsource price
D. off shore price
Answer
MCQ: An estimated cost per unit in long run, which enables the company to
achieve it's per unit target, operating income is classified as
A. target operating income per unit
B. target cost per unit
C. total current full cost
D. total cost per unit
Answer
MCQ: The target price is subtracted from per unit target operating income
to calculate
A. total current full cost
B. total cost per unit
C. target operating income per unit
D. target cost per unit
Answer
MCQ: An income, which a company aims to earn by selling each unit of
market offering is classified as
A. target operating income per unit
B. target cost per unit
C. total current full cost
D. total cost per unit
Answer
MCQ: The process which leads to disassembling and analysis of
competitors, operating activities to become acquainted with competitors'
technologies is called
A. outsource engineering
B. reverse engineering
C. target engineering
D. off shore engineering
Answer The fixed cost is divided by break-even revenues to calculate
A. cost margin
B. fixed margin
C. revenue margin
D. contribution margin
Answer
MCQ: If break-even number of units are 120 units and the fixed cost is $62000, then the
contribution margin per unit will be
A. $74,400
B. $7,440,000
C. $516.67
D. $51,667
Answer
MCQ: If the break-even number of units are 200 units and the fixed cost is $80000, then the
contribution margin per unit will be
A. $400
B. $600
C. $800
D. $1,000
Answer
MCQ: At the break-even point, an operating income must be equal to
A. $3,000
B. $2,000
C. $1,000
D. zero
Answer
MCQ: If the contribution margin per unit is $700 per unit and the break-even per unit
is $40, then the fixed cost would be
A. $35,000
B. $28,000
C. $17,500
D. $82,000
when the fixed cost is divided into contribution margin per unit, it gives
A. fixed output
B. variable output
C. breakeven number of units
D. total number of units
Answer
MCQ: If the contribution margin percentage is 30%, the selling price is
$5000, then the contribution margin per unit will be
A. $900
B. $1,200
C. $1,500
D. $1,600
Answer
MCQ: If the revenue is $15000, the total variable cost is $5000 and the fixed
cost $2000 then the operating income will be
A. $4,000
B. $8,000
C. $5,000
D. $3,000
Answer
MCQ: If the fixed cost is $30000, the contribution margin percentage is
40%, an actual variable quantity is 70, the actual and budgeted overhead
cost of allocation is $8650 and $3500 respectively, then the variable ove
the breakeven revenue will be
A. $120,000
B. $75,000
C. $12,000
D. $175,000
Answer
MCQ: If the budgeted sales in unit is 50 and the breakeven sales in unit is
12, then the margin of safety in units will be
A. 62
B. 38
C. 48
D. 58
AnswerPDF Download
MCQ: A measure which evaluates overall tradeoff and effect among non-
financial performance measure is
A. non-financial measures
B. financial measures
C. effective measure
D. lump sum measure
Answer
MCQ: In overhead cost variance analysis, the variable overhead does not
include
A. favorable volume variance
B. profit volume variance
C. cost volume variance
D. production volume variance
Answer
MCQ: The measure which provides the feedback on manager's
performance, considering individual aspects only is classified as
A. effectively measure
B. lump sum measure
C. non-financial measures
D. financial measures
Answer
MCQ: In overhead cost variance analysis, the fixed overhead does not
include
A. efficiency variance
B. unfavorable variance
C. production volume variance
D. favorable variance
Answer
MCQ: If an actual variable quantity is 70, the actual and budgeted overhead
cost of allocation is $8650 and $3500 respectively, then the variable
overhead spending variance will be
A. $660,500
B. $560,500
C. $460,500
D. $360,500
E.