C A S E S T U D Y : D E LTA P, I N C .

“Wärtsilä has the design and engineering capabilities worldwide


and can provide best practices solutions.”

Delta P, Inc. a Philippine-based power provider signed a Challenge


zz Relocating a planned power plant
15-year Power Supply Agreement (PSA) with the Palawan
with used engines and auxiliaries
Electric Cooperative (PALECO). The agreement meant that as an EPC contract with total
Delta P needed to build a power plant with an output of at responsibility
least 26.65MW to the main Palawan Grid. Wärtsilä provided an
Solution
EPC solution (engineering, procurement and construction) for zz Inspection and overhauls of existing
a relocation project. gensets and auxiliaries
   “Our best option, as it were, was to build a plant with re- zz Engineering and Supply of Balance
of Plant equipment
located engines. We could not get a better company to do this zz EPC installation and commissioning
than Wärtsilä, who originally manufactured them,” says Mark for four Wärtsilä 18V32 engines
Ferrer, Project Manager at Gigawatt Power Inc. including civil works

Benefit
The power demand on the island of – Our unsolicited proposal was zz A single vendor for the overhauls,
Palawan, Philippines is ever increas- accepted thru a so called Swiss Chal- installation and commissioning of
ing. The Power distribution company lenge, and we had to look for an EPC the plant
(PALECO) at Palawan requested offers contractor for this relocation project, zz Cost savings when compared to an
from power producers to provide ad- says Mr Ferrer. entirely new power plant
ditional power. zz Reliability of power
zz Guaranteed output
Wärtsilä was awarded
total responsibility
Wärtsilä provided a solution to build
a 30MW power plant based on
relocated equipment consisting of
four Wärtsilä 18V32 generating sets
including auxiliaries. The relocation
project was offered on an EPC basis,
meeting contractual obligations such
as a guaranteed completion date and
performance guarantees. Delta P, Inc. was established in 1997 as the Paragua Power Company and was acquired by
– Wärtsilä and Delta P Inc have Wärtsilä in 2003. In 2007 Delta P was acquired by a joint venture between Gigawatt Power, Inc.
and Vivant Energy Corporation (a subsidiary of Vivant Corporation). Gigawatt Power, based in
been working hand in hand for dec-
the Philippines, owns and operates both conventional and renewable power plants through its
ades, and most of our previous major subsidiaries.
repairs and maintenance activities
have been handled by the company. stability, reliability and flexibility to the project activities were of vital impor-
We chose Wärtsilä for the reloca- grid was built in only 15 months and tance in this project.
tion EPC-project because we would was completed in April 2017. It is worth mentioning that during
get a single vendor to carry out the Mr Ferrer says that the project the whole project execution phase no
overhauls, the whole installation, and went well and according to plan. lost time incidents (LTI) were record-
commissioning, which gives us cost – Wärtsilä has the template for the ed. For this exemplary safety culture
savings compared to an entirely new design of a power plant for any site Delta P presented a safety award to
plant, says Mr Ferrer. requirements. The good cooperation Wärtsilä’s team, says Mr Ferrer.
Wärtsilä’s wide-ranging delivery and dedication of both Wärtsilä and According to Mr Ferrer, the com-
comprised engineering, EPC instal- the Delta P project management team missioning of the plant is still ongoing
lation – including civil works and helped this project become a suc- to reach full capacity. Safety inspec-
commissioning of the power plant – cess. tions and re-adjustments to grid set-
and inspection, overhaul and upgrade Wärtsilä as a team performed well, tings are being made.
of four Wärtsilä 18V32 engines and but there is no such thing as a 100% – Since the engines are not new
auxiliaries, including parts supply. In perfect project. and this is a relocation project, we
addition, each generating set went – The unexpected long heavy rainy were prepared for possible technical
through a performance test to ensure season and the cyclones during the challenges. Wärtsilä has, however,
that the performance guarantees stip- construction phase were, however, demonstrated excellent flexibility and
ulated in the contract were achieved. the biggest challenges we faced. we are still relying on their support
Furthermore, the heating systems The work even had to be stopped a for engineering and technical mainte-
were converted from steam to electric few times completely. Another chal- nance and spare parts.
on the auxiliaries. lenge was the coordination of logistic The relocation project was suc-
– Having Wärtsilä take on the activities versus the installation phase cessfully completed within the agreed
EPC for the whole project resulted since the construction site has limited time frame. Thanks to this, the
in savings regarding cost, time and space for equipment storage. All chal- customer can achieve his set targets
communications. It also meant that lenges were overcome with proper with their customer, the Power Grid
we could focus on our core business, planning, scheduling, coordination Company.
says Ferrer. and timely action from both Wärtsilä – With all the results from this
and Delta P, says Mr Ferrer. project at hand, I would recommend
Construction work and other plant owners with similar needs
cyclones Successful EPC project to contract Wärtsilä for this type of
Palawan has three independent pow- Despite this being the first EPC relo- project, because Wärtsilä has the
08.2017 / Bock´s Office

er producers of which Delta P is one, cation project for Wärtsilä Services, design and engineering capabilities
and the company owns and operates the result was a success in many worldwide and can provide best prac-
an existing 16MW diesel-fired power ways. Proper planning, effective com- tices solutions, concludes Mr Mark
plant in Puerto Princesa, Palawan. munication and close monitoring and Ferrer.
The new power plant that will add control of the project progress and