Registration No.______________ Date: (For Office Use)
Under Section 43 of Electricity Act – 2003 hereinafter called ‘Act’ and MERC (Electricity supply code and
other conditions of supply) Regulation 2005, herein after called ‘Regulations’.
Note: Intending consumers are requested to see that this form is fully, clearly and legibly filled and signed
with date before sending to the company. Please strike out words or clauses which are not applicable.
I/We hereby submit application for:- Single Phase/Three Phase-L.T/H.T Supply
New Connection (Permanent) Additional Load Reduction of Load
Change in Contract Demand Change of Name (Alongwith XYZ or W form) Shifting
New connection (Temporary) from date__________ to date ___________
and request to supply energy to the premises owned/occupied by me/us and situated within the area of MSEDCL.
I/We further request you to supply me/us with the necessary meter. I/We agree to give you such security that may be
required as per rules, whenever called upon to do so. I/We shall abide by the rules & regulations prescribed by MERC
& the Electricity Act 2003 and amendments therein from time to time.
Surname
Occupation/
Designation
Address at which Supply is required
(Please provide complete details)
Plot/Flat No/survey No
House No/Building Name
Lane /Street
Landmark/.
Bank
Account No.(optional)
Bank Name /
Branch (optional)
2.1 Purpose
2.2 Details of the Apparatus No. of Points Wattage of each point Voltage Total Wattage
a) Bulbs
b) CFLs
c) Tube lights
d) Fans
e) Geysers
f) Ovens / Microwave
g) Air Conditioners/
Chillers
h) Refrigerator
i) Television
j) Plug - 5 AMP
- 15 AMP
- 30 AMP
k) Lift
l) Water Pump
m) Motors/ Machine**
n) Others*
2.3 The wiring/ installation, carried out, is certified by the following Licensed Electrical Contractor
Existing Load/Contract Demand: ___________ KVA/KW/ HP
Additional/ Reduction Load/ Contract Demand: ___________ KVA/KW/ HP
Total Load/ Contract Demand: _____________ KVA/KW/ HP
3. The wiring, carried out, is certified by the following Licensed Electrical Contractor
Name
Address
Rubber Stamp
Tel. No.
E-mail
License No. Valid up to
4.0 List of document/NOC/clearances attached .(Please bring originals for verification)
Date:
Place:
Acknowledgement
Name of Consumer:
Address:
* Load in KW feed with one decimal Load in HP feed with two decimal
eg. feed 1.5 KW as follows, e.g. feed 15 HP as follows,
0 0 0 0 1 5 0 0 1 5 0 0
** Feed Duty code ‘49’ instead of the Duty code given in the above table, if the consumer has been exempted from electricity duty.
For Office Use (to be submitted to IT for Billing after release of connection)
|-------------------------------66-73----------------------------| |--------------------75-80-----------------------|
31 | 32 |------------------------33-38---------------------|---------------------------------------39-48--------------------------------------------|-------------------------49-54---------------------|----55-56-----|
|---------------------69-74--------------------|------------------75-80--------------------------|
Meter ID (17-18) MP: Meter Phase codes(31) Amp: Amperage (32) MO: Meter Owner(29)
Residential 90 Single Phase—1 Upto 2.5 Amp – 1 MSEDCL – 0
Commercial 80 Three Phase 3 wire –3 5 Amp – 2 Consumer – 1
Industrial 60 Three Phase 4 wire – 4 10 Amp – 3 CT meter –2
Agriculture 70 20 Amp –5 Static Meter -6, Static electronic--7