Professional Documents
Culture Documents
Jetting Method
&
Method Statement
Client: SEC
CONTENT
1. PURPOSE ................................................................................................................... 4
2. SCOPE ......................................................................................................................... 4
3.7. The Basic Rules and Recommendation for blowing cable in HDPE Duct ........... 7-8
3.8. Field planning and Route Survey .............................................................................. 9
3.9. Testing the duct prior to cable installation ............................................................. 9
3.10. Blowing in high temperatures ................................................................................... 10
3.11. Construction Considerations ..................................................................................... 10
3.12. Safety Note and Precautions ...................................................................................... 10-12
3.12.1 General Precautions
3.12.2 Optical Power Sources and Light Emitting Diodes (LED)
3.12.3 Invisible Radiation
3.13. General Precautions – when installing F.O. cable ................................................. 12
Appendix 1 Typical cable closure arrangement in handhole
Appendix 2 Method of Statement for Duct Integrity Test
Page 2 of 23
Client: SEC
Page 3 of 23
Client: SEC
1. PURPOSE
The purpose of this procedure is to ensure that the laying and testing of FOC and FOC
Splicing & Testing works shall be done in accordance with the contract specifications
related codes & standards and required quality standards shall be met.
2. SCOPE
This procedure is valid only for the laying and testing of FOC related to the
communication system of NEW SULAY S/S-8234 with 132kV NETWORK RIYADH Once
formally approved by Employer/Engineer, this work procedure shall be the reference
document for FOC laying along the electric cable and in stations, related quality control
inspection frequencies and acceptance criteria.
3.1.1 Cable Blowing by Jetting method will be used to install the Fiber Optic
Cable inside the 25mm HDPE conduit.
3.1.2 Referenced Specifications and Method Statement
Please see attached Appendix 2 - Method Statement for FOC Duct
Integrity Test (DIT) WTX-FOC-012.
The cable laying shall be started after the cable conduit has been tested
successfully between two points of cable termination. This to be done at
the same time of cable installation.
3.2 Methods for Fibre Optic cable installation into HDPE Ducts
The two most common methods used for installation of Fibre Optic (F.O.) cable into
HDPE Telecom duct are :
Page 4 of 23
Client: SEC
Blowing of cable is different from cable pulling in several ways. During cable pulling,
the cable is kept taut and only pull force is applied. It travels in a straight line until a
bend or a curve changes its path. The cable ultimately rubs on each of the bends or
curves, creating friction. As more pulling force is added to counteract the friction,
additional stress is added to the cable. It is a time consuming process and requires a
larger cabling team.
With the blowing method, typical maximum distances of up to 3.0 Kms can be
achieved. within 2Hrs of time. The blower and a mid-assist attachment will provide a
longer, single run distances compared to a pulling application, blowing cable is faster,
puts the cable under less stress and requires less man power. On the negative side the
blowing equipment is more expensive and the HDPE duct needs to be air tight.
This is an advanced method based on the concept of a consistent high pressure air flow,
equally distributed along the entire cable throughout the duct.
AIR INLET
CHAMBER OPEN END
AIR
COMRESSOR
MOVEMENT
O.F.CABLE
DUCT
MECHANICAL
PUSHER
The cable is mechanically fed into the Superjet Machine which will push the cable
inside the cable duct. The additional pushing force from the compressor air at the air
chamber attached to the cable jet machine will improve the cable flow . It also
minimizes the internal temperature for blowing because the air passes to the air chamber
via a cooling device before the entry. This process will minimize the friction between
the cable and the cable duct . A blowing machine (typical manufacturer Superjet) in
combination with an appropriate compressor, cooling device and a power pack is
essential for optimal blowing. For an effective cable blowing at an average speed of
50 -60 meter/min and the compressor should have the following parameters:
Page 5 of 23
Client: SEC
A typical joint box and joint closure arrangement is shown in appendix 1. Nomenclature
varies from client to client and quite often the joint box is called a hand hole.
3.6.3 Spare Coil requirements : As per SEC standard & SOW/PTS required
for this project. 15m spare in each end manhole for splice and termination (Para.
5.3.B & 5.3.C).
3.7 The Basic Rules and Recommendations for Blowing Cable in HDPE Duct
Use a proper compressor (minimum 12 bar). Never underestimate the
compressor parameters.
Ideally the internal diameter (I.D) of the duct should be 2 times the outside diameter
(O.D) of the cable. For appropriate duct size please refer the following table:
Before starting the cable blowing, be sure that duct is free of any obstacles or
damage. Also to confirm the maximum withstanding pressure of the cable
duct. Use a proper mandrel equipped with a transmitting device. This method
will quickly locate the damaged areas if any, which must be repaired
immediately.
Proper cable blowing lubricant (Poly Water) will be used during the cable
blowing in order to reduce friction and to cool the duct. This is a typical
lubricant used in the industry for the cable blowing.
When cable blowing is carried in high temperatures, protect cable from direct
sunlight where possible. High temperature drastically reduces blowable
lengths. A crush test is mandatory to determine the safe pushing force before
the cable buckles, typically in temperatures greater than 40oC the safe speed
Page 7 of 23
Client: SEC
is maximum 40m per minute. The use of water sprayed over the cable drum
also gives a good cooling effect.
a) longitudinal corrugation
b) transverse corrugation
c) dry lubricated coating
d) standard HDPE duct (requiring lubricant)
The blowing method is far less sensitive to bends and curves along the route
compared to the pulling technique. When using state-of-the-art HDPE duct
and good quality blowing machines (typically Cablejet), it is possible to
safely install F.O. cable around 300 to 900 bends without any additional
lubricant.
Before beginning the cable blowing, survey the route to determine the best
locations, for access points for blowing machines and compressors. This can save
considerable materials and labour.
Always blow downhill where ever possible. Up-hill slopes located at the
beginning of the route reduce the blowable length.
The blowing technique can be used in almost any situation and reduces costs
relative to the pulling method in many cases, blowing exerts less stress on the
cable. This lowered stress combined with fewer splices to the F.O. cable
increases overall network quality.
The average blowable distance with one machine ranges between 1200 and
2400 meters depending on the above mentioned parameters. Longer distances
can be achieved by utilising several blowing machines in tandem positioned in
access points along the route. Another technique for achieving extra long cable
installation distances is to access the cable at manholes and pull out the cable
using figure of 8 and then continue installation from this point along the route.
Fleeting the cable in "figure 8" form can be made more efficient by using one
of the proprietary machines now available in the market.
Page 8 of 23
Client: SEC
Detailed planning of the installation work involved must be carried out prior to
commencement of the work. With the aid of previous project work and documentation
the following must be considered during field planning.
The survey team must carefully investigate the cable route in order to become familiar
with obstructions, etc. which will be present along the route.
The two cable ends at each joint position on the entire cable route must have an overlap
of a minimum of 10m. Take care that after each cut the cable ends are carefully sealed
against atmospheric factors.
Prior to cable blowing, each section of cable duct shall be checked by blowing through a
special caliper (Piston/Probe) with incorporated sensor to allow localization of the probe
along the route, in case the probe gets stuck due to sharp bends, duct blockage,
deformation or shrinkage.
Any duct damages or deformations detected during this caliper probe run (mandrel test)
shall be repaired by excavation and replacement of the damaged duct section.
On satisfactory completion of the test run, the FO Cable shall be blown into the HDPE
duct.
Page 9 of 23
Client: SEC
When ambient air temperatures are 48-50O C the air blowing compressor outlet
temperature becomes about 65O C (The outgoing air temperature for the compressor is
always 15-20O higher than the inlet, even with air cooler). At these temperatures the
HDPE duct begins to loose its properties, becoming soft and sticky. This means the
friction between the cable and duct increases, lowering the blowing efficiency
considerably. The cable sheath also loses it's rigidity which could result in bending or
kinking.
In countries where these temperatures are experienced, the network or project owner,
has to consider installation at night time when it is cooler, or choose the season for
installation carefully to achieve longer cabling lengths.
Ideally the new duct route shall be completely available to enable blowing operation to
be done at one time. This may not always be achievable, due to route construction
delays and lack of building access. In these cases the cable may be installed by hand or
by winch. There is no limit on the length of cable installed, installation by hand or by
winch is equally as safe providing a competent installer is used.
If buildings are delayed, the cable can be blown in to a manhole / hand hole / joint box
left adjacent to the site for the building. A cable coil can be left in the manhole for
extension into the building at a later date. Alternatively, if the transmission
specification allows, the extra length of cable can be jointed or spliced in.
Communication between the different work station must be tested and safety
signals / messages such as STOP and RUN are to be perfect understood by the
operators.
Page 10 of 23
Client: SEC
Whilst installing a cable, operators must be sure to advise the down stream
operators from the instant that the duct is pressurized.
Do not pass or stand in front of the outlet of the duct when it is under pressure.
Before the progressive opening of the compressor valve, ensure that the valve of
the Superject is closed, that all connectors are in place and locked and that all
hoses are free of bends, twists and abnormal torsion.
Many optical fiber systems utilize lasers as optical power sources, which produce
invisible radiation. When working normally they are designed to operate as closed
systems and all of this radiation is contained within closed optical fiber paths.
Some optical fiber systems use light emitting diodes (LED) as power sources.
These LEDs are different to LEDs used as indicators on equipment and are to be
treated in the same way as laser products.
During jointing operations use only the microscope on the Fusion Splicer. In
order to avoid possible exposure, before commencing work on a fiber end it should
be checked with an optical power meter to confirm that the power source has been
switched off.
Handle optical fiber carefully as broken fibers can be very sharp and pieces of
waste fiber should be disposed of in a suitable container.
Page 11 of 23
Client: SEC
3.12.4 When test the duct with a caliper a safety basket must be fitted over the
duct at the receiving end. Always stand away at the far end when the
blowing process is in operation.
Smaller size, greater flexibility and limited weight allow cable span-lengths of up to
several kilometers to be installed in one work operation.
The immunity from electrical disturbances allows optical fiber cable to be installed in
the vicinity of electrical power cables without requirements for any special arrangement
to equalize different potentials and protections against disturbances.
Most of the standard tools, equipment and installation methods used for conventional
copper cables may be used directly for optical fiber cables in many cases.
However, some special precautions must be taken in order to minimize tensile and
bending stresses during installation, as well as after final placement of the cable.
Loads exceeding the cables manufacturing specifications can result in fiber breakage.
Fibers may fail immediately or they may fail later during the service life. External signs
of damage will not necessarily be evident in either case. Thus the tensile load rating of
an optical cable must not be exceeded in any phase of application.
A detailed planning record for the actual installation shall be drawn up when the whole
route is physically inspected and should be carried out shortly before starting the work.
Using an already installed duct system is always the most cost effective method and
should be used when it is possible and convenient.
It means in many cases that the shortest cable route does not give the most economical
solution if a more costly installation method must be used, such as trenching by
machine, ploughing, blasting or breaking the ground by other means.
4. FOC SPLICING
4.1 General Requirement
4.1.1 Cable modality and the splicing reserve length shall be check prior to
FOC splicing. FOC splicing tools, material and environment shall keep
cleanliness. For fiber optic cable connection only electric-arc fusion
splicing is acceptable. Only for test purposes, mechanical splicing is
allowed.
4.1.2 A dustproof and waterproof tent shall be provided at FOC joint point. In
order to ensure that the splicing device is in normal work condition, a
neatly plastic cloth shall be used at drying ground or a worktable shall
be used at damp ground.
4.1.3 Steadily power or generator shall be used for power supply.
4.1.4 The splicing of cables shall be produced by use of fully automatic
splicing devices applying fusion splicing technology.
4.1.5 Fiber splicing shall be operated continually and avoid cable affected
with damp to ensure the connecting quality.
4.1.6 The FOC network shall be terminated at each location at an ODF, which
shall be either wall mounted or standalone. Hook up and splicing shall
be done as per fiber allocation diagram.
4.1.7 Fiber connection parts shall avoid fiber stress.
4.1.8 All spare and standby fibers terminated at the optical distribution frame
shall be connected through patch cords.
Page 13 of 23
Client: SEC
4.2.8 Splicing
To make a good splice, the optical fiber is observed with the image
processing system equipped in the splicing device. If the measured
cleave angle is greater than its set threshold or fiber chipping is
detected, the buzzer will sound and an error message warns the
operator. If no error message is displayed, the chip, lip and incline
of fiber end-face shall be visual inspection. If observed, remove
Page 14 of 23
Client: SEC
Page 15 of 23
Client: SEC
Page 16 of 23
Client: SEC
Page 18 of 23
Client: SEC
Specification: HDPE -PE 100 25mm -32mm reducer coupler SDR 11 (PN 16)
Page 19 of 23
Client: SEC
through our it's length. The internal surface of the will be free from burrs &
sharp edges.
Colour: Self
PVC Coating: Grey PVC Also available in LFHS. UV resistant
Specification:
Labelling in Manholes, Joint Box, Splitter Box, etc. using stainless steel, however cable
tagging in Manholes & buildings shall be provided in Lead Tag as per SEC SOW/PTS
requirements for cable tagging (Para. 5.7).
HH& MH
All the Handhole / Manhole labelling needs to be done in the format:
Material: Stainless Steel, Black Engraved, Label Size: 180mm x 100mm
Text below:
SEC- IT & DT Fiber Optic Cable Systems
MANHOLE/HANDHOLE NO. :
CONTRACT NO. :
LINK DESTINATION/CIRCUIT :
CABLE TYPE/NO. OF CORES :
CABLE MANUFACTURER :
INST. YEAR/CONTRACTOR :
Splice Joint
All the Handhole / Manhole that contains Joint Box labelling needs to be done in the
format:
Material: Stainless Steel, Black Engraved, Label Size: 180mm x 100mm
Text below:
SEC- IT & DT Fiber Optic Cable Systems
MANHOLE/HANDHOLE NO. :
CONTRACT NO. :
JOINT BOX NO. :
LINK DESTINATION/CIRCUI T :
CABLE TYPE/NO. OF CORES :
CABLE MANUFACTURER :
INST. YEAR/CONTRACTOR :
Page 21 of 23
Client: SEC
FSTP-FTM
All the FSTP / Splitter Box / FTM labelling needs to be done in the format:
Material: Plastic, Black background with white letters, Label Size: 60mm x 120mm
Text below:
SEC- IT & DT Fiber Optic Cable Systems
CONTRACT NO.:
LINK DESTINATION/CIRCUIT:
CABLE TYPE/NO. OF CORES:
CABLE LENGTH (IN KM):
CABLE MANUFACTURER:
INSTALLATION YEAR/CONTRACTOR:
Cable loop
All the Direction & Loop inside Manhole / Handhole and Telecom rooms labelling
needs to be done in the format:
Material: Stainless Steel, Black Engraved, Label Size: 120mm x 60mm
Text below:
SEC- IT & DT Fiber Optic Cable Systems
CONTRACT NO. :
DIRECTION TO/FROM :
CABLE MANUFACTURER :
INST. YEAR/CONTRACTOR :
Page 22 of 23
Client: SEC
Direction
Page 23 of 23