WHEREAS, the ITB and PBD for the subject procurement indicated that
the deadline for submission of bids is on 04 December 2020 at twelve o’clock
in the afternoon (12:00 P.M.);
WHEREAS, on the said date, the ERC BAC did not receive any submission
of bids from any prospective bidder;
WHEREAS, on 06 December 2020, the ITB and the PBD for the
Second (2nd) Bidding under Lot No. 2020-53 for the subject procurement
were posted at the websites of the PhilGEPS and the ERC, as well as in the latter’s
conspicuous place reserved for the purpose;
WHEREAS, the ITB and PBD for the subject procurement indicated that
the deadline for submission of bids is on 28 December 2020 at nine o’clock
in the morning (09:00 A.M.);
WHEREAS, on the said date, the BAC through its Secretariat received one
(1) sealed envelope from Sunertech Corporation at thirty minutes past
eight in the morning (8:30 A.M.), which is within the deadline for
submission of bids;
WHEREAS, based on the financial component of its bid, the bid amount
submitted by Sunertech Corporation is Four Million One Hundred Twenty
One Thousand Three Hundred Twenty Pesos (PhP4,121,320.00),
inclusive of all government taxes, and other fees and charges;
WHEREAS, after due evaluation, the ERC BAC found that Sunertech
Corporation’s bid in the aforesaid amount is within the ABC. Consequently, the
ERC BAC directed the Technical Working Group (TWG) to assist in further
evaluating the bid submitted by Sunertech Corporation, being the Single
Calculated Bid (SCB);
WHEREAS, on the same date, the ERC BAC reviewed and evaluated the
said report and bid documents submitted by Sunertech Corporation and
concurred with the TWG’s evaluation, making Sunertech Corporation’s bid the
Single Calculated and Responsive Bid (LCRB);
RESOLVED at the ERC Main Office, Pasig City, this 29th day of December
2020.
SHARON O. MONTAÑER
BAC Vice Chairperson
Dr. August
(TOOK NO PART) Anthony N. Balute
MARINA A. CRUZ-BUGAYONG AUGUST ANTHONY N. BALUTE
BAC Member BAC Member
(TOOK NO PART)
JOSE ROMULO L. CASTRO†
BAC Member
29 December 2020
Approved/Disapproved on: ____________
Reason: GPRA-IRR, §41.a. Prima facie collusion
GPRA-IRR, §41.b. Failure to follow prescribed bidding procedures
GPRA-IRR, §41.c. Contract award will not benefit ERC
§41.c. (i) project no longer physically and economically feasible
§41.c. (ii) project no longer necessary
§41.c. (iii) project fund has been withheld or reduce
Page 4 of 4