Professional Documents
Culture Documents
Bidding Document
for
CONSTRUCTION OF ADIT TUNNELS III, V and VI
Contract No: NCB: CSHEP-CW-NCB-02-2078/79
1
“GoN” word indicates all public entities according to Public Procurement Act, 2063
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
Table of Contents
Invitation for Bids .................................................................................................................. 1
Part I: BIDDING PROCEDURES ....................................................................................................... 3
Section I: Instructions to Bidders ......................................................................................... 6
Section II: Bid Data Sheet .................................................................................................. 33
Section III: Evaluation and Qualification Criteria .................................................................. 36
Section IV: Bidding Forms ................................................................................................. 44
Signature of Bidder ............................................................................................................. 65
Section V - Eligible Countries ............................................................................................ 69
Part II : BIDDING PROCEDURES ................................................................................................... 70
Section VI: Works Requirements ....................................................................................... 72
Part III:CONDITIONS OF CONTRACT AND CONTRACT FORMS ..................................................... 101
Section VIII:General Conditions of Contract ..................................................................... 104
Section IX: Special Conditions of Contract ......................................................................... 132
Section X: Contract Forms ................................................................................................ 137
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
1. The Nepal Electricity Authority (NEA) has allocated funds from Government of Nepal
(GoN) towards the cost of Chainpur Seti (210MW) Hydroelectric Project (CSHEP) and
intends to apply part of the funds to cover eligible payments under the Contract for
Construction of Adit Tunnels, Contract Identification No: CSHEP-CW-NCB-02-2078/79.
Bidding is open to all eligible as per Section V of bidding document.
2. Chainpur Seti Hydroelectric Project invites sealed bids or electronic bids from eligible
bidders for the construction of Construction of Adit Tunnels III, V & VI under National
Competitive Bidding – Single Stage Two Envelope Bidding procedures.
Only eligible bidders with the following key qualifications should participate in this bidding:
Minimum Average Annual Construction Turnover of the best 3 years within the
last 10 years: 330.90 Million NRs (In words: Three Thirty Hundred Million
and Nine Hundred Thousand Rupees Only).
Minimum Work experience of similar size and nature: At least one project of
Successful Completion of tunnel with minimum length of 360 m and cross-section
of 13.00 sq. m not less than Minimum Average Annual Construction Turnover
of the best 3 years within the last 10 years: 330.90 Million NRs (In words:
Three Thirty Hundred Million and Nine Hundred Thousand Rupees Only).
3. Under the Single Stage, Two Envelope Procedure, Bidders are required to submit
simultaneously two separate sealed envelopes, one containing (i) the Technical Bid
and the other (ii) the Price Bid, both in turn enclosed in one sealed envelope as per the
provision of ITB 21 of the Bidding Document.
4. Eligible Bidders may obtain further information and inspect the Bidding Documents at the
office of Nepal Electricity Authority, Durbarmarg, Kathmandu, Nepal and
chainpurseti@nea.org.np or may visit PPMO e-GP system www.bolpatra.gov.np/egp.
5. A complete set of Bidding Documents may be downloaded for E-submission from
PPMO’s website: www.bolpatra.gov.np/egp. Bidders submitting their bid electronically,
should deposit the cost of bidding document as non-refundable fee of NRs.20,000.00 (
In Words: Twenty Thousand Rupees Only) in the Project’s Rajaswa (revenue)
account as specified below and scanned copy (pdf format) of the Bank deposit voucher
shall be uploaded by the bidder at the time of electronic submission of the bids.
Information to deposit the cost of bidding document in Bank:
Name of the Bank: Jyoti Bikash Bank Limited
Name of Office: NEA, Chainpur Seti Hydroelectric Project
Office Account no.: 00700100089507000001
Rajaswa (revenue) Shirshak no. : 1.285
6. Pre-bid meeting shall be held at Chainpur Seti Hydroelectric Project, Third floor,
Nepal Electricity Authority, Durbarmarg, Kathmandu on 2079/03/29 (13th July,2022)
at 14:00 Hours.
1
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
2
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
3
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
Table of Clauses
A. General ............................................................................................................................ 6
1. Scope of Bid .............................................................................................................................. 6
2. Source of Funds ........................................................................................................................ 6
3. Fraud and Corruption ............................................................................................................... 6
4.Eligible Bidders........................................................................................................................... 9
5. Eligible Materials, Equipment and Services ............................................................................ 11
B. Contents of Bidding Documents ...................................................................................... 11
6. Sections of Bidding Document ................................................................................................ 11
7. Clarification of Bidding Document, Site Visit, Pre-Bid Meeting .............................................. 12
8. Amendment of Bidding Document........................................................................................ 12
9. Cost of Bidding ........................................................................................................................ 13
10. Language of Bid .................................................................................................................... 13
11. Documents Comprising the Bid ............................................................................................ 13
12. Letter of Bid and Schedules .................................................................................................. 14
13. Alternative Bids.................................................................................................................... 14
14. Bid Prices and Discounts ...................................................................................................... 14
15. Currency of Bid and Payment ............................................................................................. 15
16. Documents Comprising the Technical Proposal.................................................................... 15
17. Documents Establishing the Qualifications of the Bidder ................................................... 15
18. Period of Validity of Bids ...................................................................................................... 16
19. Bid Security .......................................................................................................................... 16
20. Format and Signing of Bid .................................................................................................... 17
D. Submission and Opening of Bids...................................................................................... 18
21. Sealing and Marking of Bids .................................................................................................. 18
22. Deadline for Submission of Bids ........................................................................................... 21
23. Late Bids ............................................................................................................................... 21
24. Withdrawal, and Modification of Bids .................................................................................. 21
25. Bid Opening.......................................................................................................................... 22
E. Evaluation and Comparison of Bids .................................................................................. 24
26. Confidentiality ...................................................................................................................... 24
27. Clarification of Bids .............................................................................................................. 24
28. Deviations, Reservations, and Omissions ............................................................................ 25
29. Examination of Technical Bid ............................................................................................... 25
4
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
5
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
A. General
1. Scope of Bid 1.1 In connection with the Invitation for Bids indicated in the Bid Data
Sheet (BDS), the Employer, as indicated in the BDS, issues this Bidding
Document for the procurement of Works as specified in Section VI
(Works Requirements). The name, identification, and number of
lots (contracts) of the National Competitive Bidding (NCB) are
provided in the BDS.
1.2 Throughout this Bidding Document:
(a)the term “in writing” means communicated in written form and
delivered against receipt;
(b) except where the context requires otherwise, words
indicating the singular also include the plural and words
indicating the plural also include the singular; and
(c) “day” means calendar day.
2. Source of Funds 2.1 GoN Funded: In accordance with its annual program and budget,
approved by the GoN, the implementing agency indicated in the
BDS plans to apply a portion of the allocated budget to eligible
payments under the contract(s) for which this Bidding Document is
issued.
Or
Public Entities' own Resource Funded: In accordance with its annual
program and budget, approved by the public entity, the implementing
agency indicated in the BDS plans to apply a portion of the
allocated budget to eligible payments under the contract(s) for which
this Bidding Document is issued.
3. Fraud and 3.1 Procuring Entities as well as Bidders, suppliers and contractors and
Corruption their sub-contractors shall adhere to the highest standard of ethics
during the procurement and execution of such contracts. In
pursuance of this:;
(a) the Employer adopts, for the purposes of this provision, the
terms as defined below:
(i) “corrupt practice” means the offering, giving, rec
eiving, or soliciting, directly or indirectly, anything of value to
influence improperly the actions of another party;
6
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
7
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
3.2 The Bidder shall not carry out or cause to carry out the
following acts with an intention to influence the implementation
of the procurement process or the procurement agreement :
8
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
4.2 A Bidder, and all parties constituting the Bidder, shall have the
nationality of an eligible country, in accordance with Section V
(Eligible Countries). A Bidder shall be deemed to have the nationality
of a country if the Bidder is a citizen or is constituted, or incorporated,
and operates in conformity with the provisions of the laws of that
country. This criterion shall also apply to the determination of the
nationality of proposed sub-contractors or suppliers for any part of
the Contract including related services.
4.3 A Bidder shall not have a conflict of interest. A Bidder found to have a
conflict of interest shall be disqualified. A Bidder may be considered to
be in a conflict of interest with one or more parties in this bidding
process, if any of, including but not limited to, the following apply:
(a) they have controlling shareholders in common; or
(b) they receive or have received any direct or indirect subsidy from
any of them; or
(c) they have the same legal representative for purposes of this bid; or
(d) they have a relationship with each other, directly or through
common third parties, that puts them in a position to have access
to material information about or improperly influence the Bid
of another Bidder, or influence the decisions of the Employer
regarding this bidding process; or
(e) a Bidder participates in more than one bid in this bidding process
either individually or as a partner in a joint venture. This will result
in the disqualification of all Bids in which it is involved. However,
9
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
10
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
4.9 Maximum number of bidding process that a Bidder, and all parties
constituting the Bidder can participate shall be as specified in BDS.
The bidders shall be considered ineligible if number of participation in
bidding process exceeds the number as specified.
5. Eligible Materials, 5.1 The materials, equipment and services to be supplied under the
Equipment and Contract shall have their origin in any source countries as defined
Services in accordance with Section V (Eligible Countries) and all
expenditures under the Contract will be limited to such materials,
equipment, and services. At the Employer’s request, Bidders may
be required to provide evidence of the origin of materials, equipment
and services.
5.2 For purposes of ITB 5.1 above, “origin” means the place where the
materials and equipment are mined, grown, produced or
manufactured, and from which the services are provided.
Materials and equipment are produced when, through
manufacturing, processing, or substantial or major assembling of
components, a commercially recognized product results that differs
substantially in its basic characteristics or in purpose or utility from
its components.
11
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
7.3 The Bidder and any of its personnel or agents will be granted
permission by the Employer to enter upon its premises and lands
for the purpose of such visit, but only upon the express condition
that the Bidder, its personnel, and agents will release and indemnify
the Employer and its personnel and agents from and against all liability
in respect thereof, and will be responsible for death or personal injury,
loss of or damage to property, and any other loss, damage, costs, and
expenses incurred as a result of the inspection.
7.6 Minutes of the pre-bid meeting, including the text of the questions
raised, without identifying the source, and the responses given,
together with any responses prepared after the meeting, will be
transmitted promptly to all Bidders who have acquired the Bidding
Document in accordance with ITB 6.3. Any modification to the
Bidding Document that may become necessary as a result of the pre-
bid meeting shall be made by the Employer exclusively through the
issue of an addendum pursuant to ITB 8 and not through the minutes
of the pre-bid meeting.
8. Amendment of 8.1 At any time prior to the deadline for submission of bids, the
Bidding Document Employer may amend the Bidding Document by issuing agenda.
12
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
8.2 Any addendum issued shall be part of the Bidding Document and
shall be communicated in writing to all who have obtained the Bidding
Document from the Employer in accordance with ITB 6.3.
C. Preparation of Bids
9. Cost of Bidding 9.1 The Bidder shall bear all costs associated with the preparation and
submission of its Bid, and the Employer shall in no case be responsible
or liable for those costs, regardless of the conduct or outcome of the
bidding process.
10. Language of Bid 10.1 The Bid, as well as all correspondence and documents relating to the
bid exchanged by the Bidder and the Employer, shall be written in
the language specified in the BDS. Supporting documents and
printed literature that are part of the Bid may be in another language
provided they are accompanied by an accurate translation of the
relevant passages in the language specified in the BDS, in which
case, for purposes of interpretation of the Bid, such translation shall
govern.
11. Documents 11.1 The Bid shall comprise two envelopes submitted simultaneously,
Comprising the Bid one called the Technical Bid containing the documents listed in ITB
11.2 and the other the Price Bid containing the documents listed in
ITB 11.3, both envelopes enclosed together in an outer single
envelope.
13
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
12. Letter of Bid and 12.1 The Letters of Technical Bid and Price Bid, Schedules, and all
Schedules documents listed under ITB 11, shall be prepared using the relevant
forms in Section IV (Bidding Forms) and in Section VII (Bill of
Quantities). The forms must be completed without any alterations to
the text, and no substitutes shall be accepted. All blank spaces shall
be filled in with the information requested.
13. Alternative Bids 13.1 Unless otherwise specified in the BDS, alternative bids shall not be
considered.
13.3 When specified in the BDS pursuant to ITB 13.1, and subject to ITB
13.4 below, Bidders wishing to offer technical alternatives to the
requirements of the Bidding Document must first price the Employer’s
design as described in the Bidding Document and shall further
provide all information necessary for a complete evaluation of the
alternative by the Employer, including drawings, design calculations,
technical specifications, breakdown of prices, and proposed
construction methodology and other relevant details. Only the
technical alternatives, if any, of the lowest evaluated Bidder
conforming to the basic technical requirements shall be
considered by the Employer.
14. Bid Prices and 14.1 The prices and discounts quoted by the Bidder in the Letter of
Discounts Price Bid and in the Schedules shall conform to the requirements
specified below.
14
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
14.2 The Bidder shall submit a bid for the whole of the works
described in ITB 1.1 by filling in prices for all items of the Works,
as identified in Section VII (Bill of Quantities). In case of Unit Rate
Contracts, the Bidder shall fill in rates and prices for all items of the
Works described in the Bill of Quantities. Items against which no rate
or price is entered by the Bidder will not be paid for by the Employer
when executed and shall be deemed covered by the rates for other
items and prices in the Bill of Quantities.
14.3 The price to be quoted in the Letter of Price Bid shall be the total price
of the Bid, excluding any discounts offered. Absence of the total price
in the Letter of Price Bid or the Bid Price in the Bill of Quantities shall
result in rejection of the Bid.
14.4 The Bidder shall quote any discounts and the methodology for their
application in the Letter of Price Bid, in accordance with ITB 12.1.
14.5 If so indicated in ITB 1.1, bids are invited for individual Contracts or for
any combination of Contracts (packages). Bidders wishing to offer any
price reduction for the award of more than one Contract shall
specify in their bid the price reductions applicable to each package, or
alternatively, to individual Contracts within the package. Price
reductions or discounts shall be submitted in accordance with ITB
14.4, provided the Bids for all Contracts are submitted and opened
at the same time.
14.7 All duties, taxes, and other levies payable by the Contractor under the
Contract, or for any other cause, as of the date 30 days prior to the
deadline for submission of bids, shall be included in the rates and
prices and the total bid price submitted by the Bidder.
15. Currency of Bid 15.1 The currency of the bid and payment shall be in Nepalese
and Payment Rupees.
16. Documents 16.1 The Bidder shall furnish a Technical Proposal including a
Comprising the statement of work methods, equipment, personnel, schedule and
Technical Proposal
any other information as stipulated in Section IV (Bidding Forms),
in sufficient detail to demonstrate the adequacy of the Bidders’
proposal to meet the work requirements and the completion time.
15
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
Qualifications of the the Bidder shall provide the information requested in the
Bidder corresponding information sheets included in Section IV (Bidding
Forms).
18. Period of Validity 18.1 Bids shall remain valid for the period specified in the BDS after the
of Bids bid submission deadline date prescribed by the Employer. A bid valid
for a shorter period shall be rejected by the Employer as
nonresponsive.
19. Bid Security 19.1 The Bidder shall furnish as part of its bid, in original form, a bid
security as specified in the BDS. In case of e-submission of bid, the
Bidder shall upload scanned copy of Bid security letter at the time of
electronic submission of the bid. The Bidder accepts that the scanned
copy of the Bid security shall, for all purposes, be equal to the original. The
details of original Bid Security and the scanned copy submitted with e-bid
should be the same otherwise the bid shall be non-responsive.
19.2 The bid security shall be, at the Bidder’s option, in any of the following
forms:
(a) an unconditional bank guarantee from Commercial Bank or
Financial Institution eligible to issue Bank Guarantee as per
prevailing Law or;
(b) a cash deposit voucher in the Employer's Account as
specified in BDS.
In the case of a bank guarantee, the bid security shall be submitted
either using the Bid Security Form included in Section IV (Bidding
Forms) or in another Form acceptable to the employer. The form must
include the complete name of the Bidder. The bid security shall be valid for
minimum thirty (30) days beyond the original validity period of the bid, or
beyond any period of extension if requested under ITB 18.2.
19.3 The bid security issued by any foreign Bank outside Nepal must be
counter guaranteed by Commercial Bank or Financial Institution
eligible to issue Bank Guarantee as per prevailing Law in Nepal.
16
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
acceptable Bid Security letter is not uploaded with the electronic Bid
then Bid shall be rejected.
19.5 The bid security of unsuccessful Bidders shall be returned within three
days, once the successful Bidder’s furnishing of the required
performance security and signing of the Contract Agreement
pursuant to ITB 40.1 and 41.1
19.7 The Bid Security of a Joint Venture shall be in the name of the
Joint Venture that submits the bid. If the Joint Venture has not been
legally constituted at the time of bidding, the Bid Security shall be in
the names of all future partners as named in the letter of intent
mentioned in ITB 4.1.
20. Format and 20.1 The Bidder shall prepare one original set of the Technical Bid and
17
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
Signing of Bid one original of the Price Bid comprising the Bid as described in ITB
11 and clearly mark it “ORIGINAL – TECHNICAL BID” and
“ORIGINAL – PRICE BID.” Alternative bids, if permitted in
accordance with ITB 13, shall be clearly marked “ALTERNATIVE”.
In addition, the Bidder shall submit copies of the bid in the number
specified in the BDS, and clearly mark each of them “COPY.” In
the event of any discrepancy between the original and the copies,
the original shall prevail.
In case of e-submission of bid, the Bidder shall submit his bid
electronically in PDF or web forms files as specified in ITB Clause
21.1(b).
20.2 The original and all copies of the bid shall be typed or written in
indelible ink and shall be signed by a person duly authorized to sign
on behalf of the Bidder. This authorization shall consist of a written
confirmation as specified in the BDS and shall be attached to the
bid. The name and position held by each person signing the
authorization must be typed or printed below the signature. All
pages of the bid, except for un amended printed literature, shall be
signed or initialed by the person signing the bid.
21. Sealing and 21.1 Unless otherwise specified in BDS, Bidders shall submit their bids
Marking of Bids by electronic or by mail/by hand/by courier. Procedures for
submission, sealing and marking are as follows:
(a) Bidders submitting bids by mail, by hand or by courier
shall enclose the original of the Technical Bid, and the original
of the Price Bid and each copy of the Technical Bid and Price
Bid, including alternative bids, if permitted in accordance with
ITB 13, in separate sealed envelopes, duly marking the
envelopes as “ORIGINAL TECHNICAL BID”, “ORIGINAL –
PRICE BID”, “ALTERNATIVE” and “COPY No. – TECHNICAL
BID” and “COPY NO. PRICE BID” These envelopes containing
the original and the copies shall then be enclosed in one single
envelope.
(b) Bidders submitting Bids electronically shall follow the electronic
bid submission procedure specified in this clause.
i. The bidder is required to register in the e-GP system
https://www.bolpatra.gov.np/egp following the
procedure specified in e-GP guideline.
ii. Interested bidders may either purchase the bidding
document from the Employer's office as specified in
the Invitation for Bid (IFB) or bidders may download
the IFB and bidding document from e-GP system.
iii. The registered bidders need to maintain their profile
18
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
19
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
viii. After providing all the details and documents, two separate bid
response documents i.e technical bids and price bids will be
generated from the system. Bidders are advised to download
and verify the response documents prior to bid submission.
ix. For verifying the authentic user, the system will send one time
password (OTP) in the registered e-mail address of the bidder.
System will validate the OTP and allow bidder to submit their
bid.
x. Electronically submitted bids can be modified and/or withdrawn
through system. The bidder may modify their bids multiple times
online within bid submission date and time specified in e-GP
system. Once a Bid is withdrawn, bidder won’t be able to submit
another bid response for the same bid.
xi. The Bidder / Bid shall meet the following requirements and
conditions for e-submission of bids;
aa) The e-submitted bids must be readable through PDF
reader.
bb) The facility for submission of bid electronically through e-
submission is to promote transparency, non-discrimination,
equality of access, and open competition in the bidding
process. The Bidders are fully responsible to use the e-
submission facility properly in e-GP system as per specified
procedures and in no case the Employer shall be held liable
for Bidder's inability to use this facility.
cc) When a bidder submits electronic bid through the PPMO e-
GP portal, it is assumed that the bidder has prepared the
bid by studying and examining the complete set of the
Bidding documents including specifications, drawings and
conditions of contract.
21.2. The inner and outer envelopes shall:
(aa) bear the name and address of the Bidder;
(bb) be addressed to the Employer as provided in BDS 22.1;
(cc) bear the specific identification of this bidding process
indicated in BDS 1.1; and
21.3 The outer envelope and the inner envelope containing Technical
Proposal shall bear a warning not to open before the time and date for the
20
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
22. Deadline for 22.1 Bids must be received by the Employer at the address and no later
Submission of Bids than the date and time indicated in the BDS.
In case of e-submission, the standard time for e-submission is Nepal
Standard Time as set out in the server. The e-procurement system
will accept the e-submission of bid from the date of publishing of
notice and will automatically not allow the e-submission of bid after
the deadline for submission of bid.
22.2 The Employer may, at its discretion, extend the deadline for the
submission of bids by amending the Bidding Document in
accordance with ITB 8, in which case all rights and obligations of the
Employer and Bidders previously subject to the deadline shall
thereafter be subject to the deadline as extended.
23. Late Bids 23.1 The Employer shall not consider any bid that arrives after the
deadline for submission of bids, in accordance with ITB 22. Any bid
received by the Employer after the deadline for submission of bids
shall be declared late, rejected, and returned unopened to the Bidder.
24. Withdrawal, and 24.1 A Bidder may withdraw, or modify its bid- Technical or Price -
Modification of Bids after it has been submitted either in hard copy or by e-submission.
Once a Bid is withdrawn, bidder shall not be able to submit another
bid for this bidding process. Procedures for withdrawal or
modification of submitted bids are as follows:
(i) Bids submitted in Hard Copy
GoN Funded:
a) Bidders may withdraw or modify its bids by sending a written
notice in a sealed envelope, duly signed by an authorized
representative, and shall include a copy of the authorization in
accordance with ITB 20.2. The corresponding modification of
the bid must accompany the respective written notice. All
notices must be:
(aa)prepared and submitted in accordance with ITB 20 and ITB
21,and in addition, the respective envelopes shall be
clearly marked “WITHDRAWAL”, “MODIFICATION;” and
(bb) received by the Employer twenty four hour prior to the
deadline prescribed for submission of bids, in accordance
with ITB 22.
ii) E-submitted bids.
a) Bidder may submit modification or withdrawal prior to the
deadline prescribed for submission of bids through e-GP
system by using the forms and instructions provided by the
system.
24.2 Bids requested to be withdrawn in accordance with ITB 24.1 shall
not be opened. In case of hard copy submission, the Bid will be
21
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
25. Bid Opening 25.1 The Employer shall open the Technical Bids in public at the address,
on the date and time specified in the BDS in the presence of Bidders`
designated representatives who choose to attend. The Price Bids
will remain unopened and will be held in custody of the Employer
until the specified time of their opening. If the Technical Bid and
Price Bid are submitted together in one envelope, the Employer
shall reject the entire Bid.
25.2 The Employer shall download the e-submitted Technical Bid. The
e-GP system allows the Employer to download the e-submitted
technical bid only after bid opening date and time after login
simultaneously by at least two members of the Bid Opening
Committee.
22
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
opened and read out with the corresponding bid. No Technical Bid
and/or Price Bid modification shall be permitted unless the
corresponding modification notice contains a valid authorization to
request the modification and is read out and recorded at bid opening.
Only the Technical Bid, both Original as well as Modification, are to be
opened, read out, and recorded at the opening. Price Bids, both
Original and Modification, will remain unopened in accordance with
ITB 25.1.
25.5 All other envelopes holding the Technical Bid shall be opened
one at a time, reading out: the name of the Bidder; whether there
is a modification; the presence of a bid security and any other details
as the Employer may consider appropriate.
Only Technical Bids read out and recorded at bid opening shall be
considered for evaluation.
No bid shall be rejected at opening of Technical Bids except for late
bids, in accordance with ITB 23.1.
25.6The Employer shall prepare a record of the opening of Technical Bids
that shall include, as a minimum: the name of the Bidder and whether
there is a withdrawal, or modification; and the presence or absence
of a bid security. The Bidders’ representatives who are present shall
be requested to sign the record. The omission of a Bidder’s signature
on the record shall not invalidate the contents and effect of the record.
25.7 At the end of the evaluation of the Technical Bids, the Employer will
invite bidders who have submitted substantially responsive
Technical Bids and who have been determined as being qualified
for award to attend the opening of the Price Bids. The date, time,
and location of the opening of Price Bids will be advised in writing
by the Employer. Bidders shall be given at least 7 days notice for
the opening of Price Bids.
25.8 The Employer will notify Bidders in writing who have been rejected
on the grounds of their Technical Bids being substantially
nonresponsive to the requirements of the Bidding Document and
return their Price Bids unopened.
25.9 The Employer shall conduct the opening of Price Bids of all Bidders
who submitted substantially responsive Technical Bids, in the
presence of Bidders` representatives who choose to attend at the
address, on the date, and time specified by the Employer. The
Bidder’s representatives who are present shall be requested to sign
a register evidencing their attendance.
25.10 All envelopes containing Price Bids shall be opened one at a time
and the following read out and recorded:
(a) the name of the Bidder;
(b) whether there is a modification;
23
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
(c) the Bid Prices, including any discounts and alternative offers;
and
(d) any other details as the Employer may consider appropriate.
Only Price Bids, discounts, modifications, and alternative offers
read out and recorded during the opening of Price Bids shall be
considered for evaluation. No Bid shall be rejected at the opening
of Price Bids.
25.11 The Employer shall prepare a record of the opening of Price Bids
that shall include, as a minimum, the name of the Bidder, the Bid
Price (per lot if applicable), any discounts, modifications and
alternative offers. The Bidders’ representatives who are present
shall be requested to sign the record. The omission of a Bidder’s
signature on the record shall not invalidate the contents and effect
of the record.
26.3 Notwithstanding ITB 26.2, from the time of bid opening to the time of
Contract award, if any Bidder wishes to contact the Employer on
any matter related to the bidding process, it may do so in writing.
27. Clarification of 27.1 To assist in the examination, evaluation, and comparison of the
Bids Technical and Price Bids, the Employer may, at its discretion, ask
any Bidder for a clarification of its Bid. Any clarification submitted
by a Bidder that is not in response to a request by the Employer shall
not be considered. The Employer’s request for clarification and the
response shall be in writing. No change in the substance of the
Technical Bid or prices in the Price Bid shall be sought, offered, or
permitted, except to confirm the correction of arithmetic errors
discovered by the Employer in the evaluation of the Price Bids, in
accordance with ITB 33. In case of e-submission of bid, upon
notification from the employer, the bidder shall also submit the original
of documents comprising the Technical and Price Bid as per ITB 11.2
and ITB 11.3 for verification of submitted documents for acceptance of
the e-submitted bid.
27.2 If a Bidder does not provide clarifications of its Bid by the date and
time set in the Employer’s request for clarification, its Bid may be
rejected.
24
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
28. Deviations, 28.1 During the evaluation of bids, the following definitions apply:
Reservations, and
Omissions (a) “Deviation” is a departure from the requirements specified in the
Bidding Document;
(b) “Reservation” is the setting of limiting conditions or withholding
from complete acceptance of the requirements specified in the
Bidding Document; and
(c) “Omission” is the failure to submit part or all of the information or
documentation required in the Bidding Document.
29. Examination of 29.1The Employer shall examine the Technical Bid to confirm that all
Technical Bid documents and technical documentation requested in ITB 11.2
have been provided, and to determine the completeness of each
document submitted.
29.2 The Employer shall confirm that the following documents and
information have been provided in the Technical Bid. If any of
these documents or information is missing, the offer shall be
rejected.
(a) Letter of Technical Bid;
(b) written confirmation of authorization to commit the Bidder;
(c) Bid Security; and
(d) Technical Proposal in accordance with ITB 16
30.3 The Employer shall examine the technical aspects of the Bid
submitted in accordance with ITB 16, Technical Proposal, in
particular, to confirm that all requirements of Section VI (Works
Requirements) have been met without any material deviation,
reservation or omission.
25
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
30.5 In case of e-submission bids, the Employer evaluates the bid on the
basis of the information in the electronically submitted bid files. If the
Bidder cannot substantiate or provide evidence to establish the
information provided in e-submitted bid through documents/
clarifications as per ITB Clause 27.1, the bid shall not be
considered for further evaluation.
30.6 In Case, a corruption case is being filed to Court against the Natural
Person or Board of Director of the firm/institution /company or any
partner of JV, such Natural Person or Board of Director of the
firm/institution /company or any partner of JV such bidder’s bid shall
be excluded from the evaluation, if public entity receives instruction
from Government of Nepal.
30.7Except in case of e-submission, the Financial Bid of the bidder, which
is evaluated as substantially non-responsive in technical bid, shall be
returned to the respective bidders.
31.Nonconformities 31.1 Provided that a bid is substantially responsive, the Employer may
Errors, and waive any non-conformities in the bid that do not constitute a
Omissions material deviation, reservation, or omission.
32 Qualification of the 32.1 The Employer shall determine to its satisfaction during the
Bidder evaluation of Technical Bids whether Biddersmeet the qualifying
criteria specified in Section III (Evaluation and Qualification
Criteria).
26
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
33. Correction of 33.1 During the evaluation of Price Bids, the Employer shall correct
Arithmetical Errors arithmetical errors on the following basis:
(a) only for unit price Contracts, if there is a discrepancy between
the unit price and the total price that is obtained by multiplying the
unit price and quantity, the unit price shall prevail and the total
price shall be corrected, unless in the opinion of the Employer
there is an obvious misplacement of the decimal point in the unit
price, in which case the total price as quoted shall govern and
the unit price shall be corrected;
(b) if there is an error in a total corresponding to the addition or
subtraction of subtotals, the subtotals shall prevail and the total
shall be corrected;
(c) If there is a discrepancy between the bid price in the Summary
of Bill of Quantities and the bid amount in item (c) of the Letter
of Price Bid, the bid price in the Summary of Bill of Quantities
will prevail and the bid amount in item (c) of the Letter of Price
Bid will be corrected.
(d) if there is a discrepancy between words and figures, the
amount in words shall prevail, unless the amount expressed in
words is related to an arithmetic error, in which case the
amount in figures shall prevail subject to (a), (b) and (c) above.
33.2 If the Bidder that submitted the lowest evaluated bid does not
accept the correction of errors, its bid shall be disqualified and its bid
security shall be forfeited.
34 Subcontractors 34.1 In case of Prequalification, the Bidder’s Bid shall name the same
subcontractor as submitted in the prequalification application and
approved by the Employer.
In case of Post-qualification, the Employer may permit
subcontracting for certain specialized works as indicated in Section
III When subcontracting is permitted by the Employer, the sub-
contractor shall meet the qualifications criteria as indicated in
section III.
Sub-contractors’ qualification and experience will not be considered
for evaluation of the Bidder. The Bidder on its own (without taking
into account the qualification and experience of the sub-contractor)
should meet the qualification criteria.
Bidders may propose subcontracting up to the percentage of total
value of contracts or the volume of works as specified in the BDS.
27
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
35. Evaluation of 35.1 The Employer shall use the criteria and methodologies listed in this
Price Bids Clause. No other evaluation criteria or methodologies shall be
permitted.
35.2 To evaluate a Price Bid, the Employer shall consider the following:
(a) the bid price, excluding Value Added Tax , Provisional Sums, and
the provision, if any, for contingencies in the Summary Bill of
Quantities, for Unit Rate Contracts, or Schedule of Prices for lump
sum Contracts, but including Day work items, where priced
competitively;
(b) price adjustment for correction of arithmetic errors in
accordance with ITB 33.1;
(c) price adjustment due to discounts offered in accordance with
ITB 14.4;
(d) adjustment for nonconformities in accordance with ITB 31.3;
(e) application of all the evaluation factors indicated in Section III
(Evaluation and Qualification Criteria);
35.5 if the bid for an Unit Rate Contract, which results in the lowest
Evaluated Bid Price is seriously unbalanced or front loaded or
extremely low in the opinion of the Employer, the Employer may
require the Bidder to produce detailed price analysis for any or all
items of the Bill of Quantities, to demonstrate the internal consistency
of those prices with the construction methods and schedule
proposed. After evaluation of the price analysis, taking into
consideration the schedule of estimated Contract payments, the
Employer may require that the amount of the performance security be
increased at the expense of the Bidder as mentioned in BDS to
protect the Employer against financial loss in the event of default of
the successful Bidder under the Contract or may consider the bid
as non-responsive.
28
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
35.6 In case of e-submission bids, the Employer evaluates the bid on the
basis of the information in the electronically submitted bid files. If the
Bidder cannot substantiate or provide evidence to establish the
information provided in e-submitted bid through documents/
clarifications as per ITB Clause 27.1, the bid shall not be
considered for further evaluation.
35.7 In Case, a corruption case is being filed to Court against the Natural
Person or Board of Director of the firm/institution /company or any
partner of JV, such Natural Person or Board of Director of the
firm/institution /company or any partner of JV such bidder’s bid shall
be excluded from the evaluation, if public entity receives instruction
from Government of Nepal.
36. Comparison of 36.1 The Employer shall compare all substantially responsive bids in
Bids accordance with ITB 35.2 to determine the lowest evaluated bid.
37. Employer’s Right 37.1 The Employer reserves the right to accept or reject any bid, and to
to Accept Any Bid, annul the bidding process and reject all Bids at any time prior to
and to Reject Any or contract award, without thereby incurring any liability to Bidders.
All Bids In case of annulment, all Bids submitted and specifically, bid securities,
shall be promptly returned to the Bidders.
F. Award of Contract
38. Award Criteria 38.1 The Employer shall award the Contract to the Bidder whose offer
has been determined to be the lowest evaluated bid and is
substantially responsive to the Bidding Document, provided further
that the Bidder is determined to be qualified to perform the Contract
satisfactorily.
39. Letter of Intent to 39.1 The Employer shall notify the concerned Bidder whose bid has been
Award the selected in accordance with ITB 38.1 within seven days of the
Contract/Notification selection of the bid, in writing that the Employer has intention to accept
of Award its bid and the information regarding the name, address and amount
of selected bidder shall be given to all other bidders who submitted
the bid.
39.3 In Case, a corruption case is being filed to Court against the Natural
Person or Board of Director of the firm/institution /company or any
partner of JV, such Natural Person or Board of Director of the
firm/institution /company or any partner of JV such bidder’s bid shall
be excluded from the evaluation, if public entity receives instruction
from Government of Nepal.
40. Performance 40.1 Within Fifteen (15) days of the receipt of Letter of Acceptance from
29
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
Security and Line of the Employer, the successful Bidder shall furnish the performance
Credit security in accordance with the Conditions of Contract, subject to ITB
35.5, as specified below from Commercial Bank or Financial Institution
eligible to issue Bank Guarantee as per prevailing Law in Nepal using
Sample Form for the Performance Security included in Section X
(Contract Forms), or another form acceptable to the Employer. The
performance security issued by any foreign Bank outside Nepal must be
counter guaranteed by Commercial Bank or Financial Institution eligible to
issue Bank Guarantee as per prevailing Law in Nepal.
i) If bid price of the bidder selected for acceptance is up to 15 (fifteen)
percent below the approved cost estimate, the performance security
amount shall be 5 (five) percent of the bid price.
ii) For the bid price of the bidder selected for acceptance is more than 15
(fifteen) percent below of the cost estimate, the performance security
amount shall be determined as follows:
41 Signing of 41.1 The Employer and the successful Bidder shall sign the Contract
Contract Agreement within the period as stated ITB 40.1.
41.2 At the same time, the Employer shall affix a public notice on the result
of the award on its notice board and make arrangement for causing
such notice to be affixed on the notice board also of the District
Coordination Committee, District Administration Office,
Provincial Treasury and Controller Office and District Treasury
and Controller Office. The Employer may make arrangements to
post the notice into its website, if it has; and if it does not have, into
the website of the Public Procurement Monitoring Office, identifying
the bid and lot numbers and the following information: (i) the result
of evaluation of bid; (ii) date of publication of notice inviting bids; (iii)
name of newspaper; (iv) reference number of notice; (v) item of
procurement; (vi) name and address of bidder making contract and
(viii) contract price
30
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
41.3 Within thirty (30) days from the date of issuance of notification
pursuant to ITB 39.1 unsuccessful bidders may request in writing to
the Employer for a debriefing seeking explanations on the
grounds on which their bids were not selected. The Employer shall
promptly respond in writing to any unsuccessful Bidder who,
requests for debriefing.
41.4 If the bidder whose bid has been accepted fails to sign the contract as
stated ITB 40.1, the Public Procurement Monitoring Office shall
blacklist the bidder on recommendation of the Public Entity.
42. Complaint and 42.1 If a Bidder is dissatisfied with the Procurement proceedings or
Review thedecision made by the Employer in opening of the price bid or the
intention to award the Contract, it may file an application to the
Chief of the Public Entity or Public Procurement Monitoring Office or
office established as per Clause 145(a) of the Public Procurement
Regulation within Seven (7) days of providing the notice under ITB
25.8 and ITB 39.1 by the Public Entity, for review of the proceedings
stating the factual and legal grounds.
42.2 Late application filed after the deadline pursuant to ITB 42.1 shall
not be processed.
42.3 The chief of Public Entity shall, within five (5) days after
receiving the application, give its decision with reasons, in
writing pursuant to ITB 42.1:
(a) whether to suspend the procurement proceeding and indicate the
procedure to be adopted for further proceedings; or
(b) to reject the application.
The decision of the chief of Public Entity shall be final for the Bid
amount up to the value as stated in 42.4.
42.4 If the Bidder is not satisfied with the decision of the Public Entity in
accordance with ITB 42.3, is not given within five (5) days of receipt
of application pursuant to ITB 42.1, it can, within seven (7) days
of receipt of such decision, file an application to the Review
Committee of the GoN, stating the reason of its disagreement on
the decision of the chief of Public Entity and furnishing the relevant
documents, provided that its Bid amount ,equal or more than Rupees
Twenty Million (NRs. 20,000,000). The application may be sent by
hand, by post, by courier, or by electronic media at the risk of the
Bidder itself.
42.5 Late application filed after the deadline pursuant to ITB 42.4 shall
not be processed.
42.6 Within three (3) days of the receipt of application from the Bidder,
pursuant to ITB 42.4, the Review Committee shall notify the
concerning Public Entity to furnish its procurement proceedings,
pursuant to ITB 42.3.
42.7 Within three (3) days of receipt of the notification pursuant to ITB
31
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
42.6, the Public Entity shall furnish the copy of the related
documents to the Review Committee.
42.8 The Review Committee, after inquiring from the Bidder and the
Public Entity, if needed, shall give its decision within one (1) month
of the receipt of the application filed by the Bidder, pursuant to ITB
42.4.
42.9 The Bidder, filing application pursuant to ITB 42.4, shall have to
furnish a cash amount or Bank guarantee from Commercial
Bank or Financial Institution eligible to issue Bank Guarantee
as per prevailing Law equivalent to one percent (1%) of its quoted
Bid amount with the validity period of at least ninety (90) days from
the date of the filing of application pursuant to ITB 42.4.
42.10 If the claim made by the Bidder pursuant to ITB 42.4 is justified, the
Review Committee shall have to return the security deposit to the
applicant, pursuant to ITB 42.9, within seven (7) days of such
decision made.
32
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
A. General
ITB 1.1 The number of the Invitation for Bids is: 1 (One)
ITB 1.1 The number and identification of lots (contracts) comprising this bidding process is: 1
(One)
Identification : CSHEP-CW-NCB-02-2078/79
ITB 2.1 The name of the Project is Chainpur Seti Hydroelectric Project (210 MW)
The implementing agency is Nepal Electricity Authority
GoN Funded or DP Funded: GoN Funded
B. Bidding Document
For clarification purposes only, the Employer’s address is:
ITB 7.1
Attention: The Project Chief
Address: Chainpur Seti Hydroelectric Project,
Nepal Electricity Authority,
Durbarmarg , Kathmandu
Telephone: : 01-4153243
Electronic mail address: chainpurseti@nea.org.np
A Pre-Bid meeting “shall” held Pre-Bid Meeting will
ITB 7.4
Take place at the following date, time and place:
Date:2079/03/29 (13th July,2022 )
33
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
Time:14:00 hours
Place: Chainpur Seti Hydroelectric Project, Nepal Electricity Authority,
Nepal Electricity Authority, Engineering Services Directorate
ITB 7.5 Time for request: Requests for clarification should be received by the Employer no later
than 10 days prior to the deadline for submission of bids.
C. Preparation of Bids
ITB 11.2 (h) The Bidder shall submit with its Technical Bid the following additional documents: Site
Visit is not compulsory. Site visit should be organized by bidders. Bidder has to
manage Site Visit at their own cost.
ITB 11.3 (b) In accordance with ITB 12 and ITB 14, the following schedules shall be submitted with
the bid, including the priced Bill of Quantities for Unit Rate Contracts and Schedule of
Prices for lump sum contracts.
(a) Letter of Price Bid;
(b) Detailed Work Schedule
11.3 (d) The Bidder shall submit with its Price Bid the following additional documents:
Not Applicable
ITB 13.2 Alternative times for completion “shall not be” permitted.
ITB 13.4 Alternative technical solutions shall be permitted for the following parts of the Works:
Not Permitted.
ITB 14.6 The prices quoted by the Bidder “shall not be “subject to adjustment during the
performance of the Contract.
ITB 18.1 The bid validity period shall be: One Hundred Twenty (120) days.
ITB 19.1 The Bidder shall furnish a bid security, from Commercial Bank or Financial Institution
eligible to issue Bank Guarantee as per prevailing Law with a minimum of 8.80 Million(
In Words: Eight Million Eight Hundred Thousand Rupees Only), which shall be
valid for 30 days beyond the validity period of the bid.
Office Name: Nepal Electricity Authority (Chainpur Seti Hydroelectric Project)
ITB 19.2 (b)
Bank Name: Jyoti Bikas Bank Limited, Ason Branch
Bank Address: Ason Branch, Kathmandu
Account Number: 00700100089507000001
ITB 20.1 In addition to the original of the bid, the number of copy/ies is/are: Not Applicable
34
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
ITB 20.2 The written confirmation of authorization to sign on behalf of the Bidder shall
indicate:
(a) The name and description of the documentation required to demonstrate the
authority of the signatory to sign the Bid such as a Power of Attorney; and
(b) In the case of Bids submitted by an existing or intended JV, an undertaking
signed by all parties (i) stating that all parties shall be jointly and
severally liable, and (ii) nominating a Representative who shall have the
authority to conduct all business for and on behalf of any and all the parties
of the JV during the bidding process and, in the event the JV is awarded
the Contract, during contract execution.
ITB 35.5 The amount of the performance security be increased by Eight (8) percent of the
quoted bid price.
ITB 40.1 Letter of Commitment for Bank’s Undertaking for Line of Credit shall be of NRs.
75,000,000.00 (In Words: Seven Million Five Hundred Thousand Rupees Only)
ITB 41.4 The bidder whose bid has been accepted fails to sign the contract 40% of the
public procurement monitoring office shall blacklist the bidder on
recommendation of Public Entity.
35
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
1. Evaluation
In addition to the criteria listed in ITB 35.2 (a) - (e) the following criteria shall apply:
Note:
Use the evaluation criteria listed below as appropriate and required for the project.
An alternative Completion Time, if permitted under ITB 13.2, will be evaluated as follows:
Not Applicable
Alternative technical solutions, if permitted under ITB 13.4, will be evaluated as follows:
Not Applicable
“Pursuant to ITB 31.3, the cost of all quantifiable nonmaterial nonconformities shall be
evaluated, but excluding omission of prices in the BoQ.The Employer will make its own
assessment of the cost of any nonmaterial nonconformities and omissions for the purpose of
ensuring fair comparison of bids.”
36
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
2. Qualification
2.1 Eligibility
2.1.1 Nationality
Letter of
Nationality in must meet must meet must meet not
Technical Bid
accordance with requirement requirement requirement applicable
Forms
ITB sub-clause 4.2
ELI –1; ELI
–2
with
attachments
2.1.2 Conflict of Interest
Not having been must meet must meet must meet not Letter of
declared ineligible requirement requirement requirement applicable Technical Bid
by government
/DP, as described
in ITB Sub-Clause
4.4.
Bidder required to must meet existing or must meet not Forms ELI - 1,
meet conditions of requirement intended JV requirement applicable ELI - 2, with
ITB Sub-Clause must meet attachments
4.5. requirement
2.1.5 UN Eligibility
Not having been must meet existing or must meet not Letter of
declared ineligible requirement intended JV requirement applicable Technical Bid
based on a United must meet
Nations resolution requirement
or Employer's
country law, as
described in ITB
37
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
Sub-Clause 4.8
VAT and PAN must meet not must meet not Document
Registration requirement applicable requirement applicable attachment
certificate (only
for domestic
bidders)
38
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
All pending must meet not must meet not Form LIT - 1
litigation shall be requirement applicable requirement by applicable
treated as by itself or itself or as
resolved against as partner partner to past
the Bidder and to past or or existing JV
so shall in total existing JV
not represent
more than Fifty
percent (50 %)
percent of the
Bidder's net
worth.
Submission of audited must meet not must meet not Form FIN - 1
balance sheets and requirement applicable requirement applicabl with
income statements, for e attachments
the last Three years to
demonstrate the
current soundness of
the Bidder's financial
position. As a
minimum, a Bidder's
net worth calculated as
the difference between
total assets and total
liabilities should be
positive.
Note:
(1) The financial information provided by a Bidder should be reviewed in its entirety to allow a truly
informed judgment, and the pass-fail decision on the financial position of the Bidder should be
39
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
given on this basis. Balance sheet of the past three to five years period which shall be decided
according to the nature of the work.
2.3.2 Average Annual Construction Turnover
Minimum average annual must must meet must meet must meet Form
construction turnover of meet requiremen at least 25 40 % FIN -2
NRs 330.90 Million NRs requirem t %
of the
(In words: Three Thirty ent
of the requirement
Hundred Million and
requirement
Nine Hundred
Thousand Rupees
Only) calculated as total
certified payments
received for construction
contracts in progress or
completed, within best
three years out of last ten
fiscal years.
Only the net amount shall be calculated after deducting the amount for VAT and such amount shall be
adjusted to present value by applying wholesale price index of Nepal Rastra Bank.
2.4 Experience
40
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
41
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
2.5 Personnel
The Bidder must demonstrate that it has the personnel for the key positions that meet the
following requirements:
2 Master in Geology/
Geologist/
2. Geotechnical or 5 3
Geotechnical
Equivalent
2 Diploma in Survey or
3. Surveyor 3 2
Equivalent or more
1 License holder/
8. Blaster 2 1
Experience Certificate
1 License holder/
9. Driller 2 1
Experience Certificate
42
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
2.6 Equipment
The Bidder must demonstrate that it has the key equipment listed hereafter:
3. Ventilation Fan 3
8. Total Station 2
9. Tripper /Truck 3
10. Excavator 2
11. Backhoe 2
12. Loader 2
43
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
This Section contains the forms which are to be completed by the Bidder and submitted as
part of its Bid.
44
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
The Bidder must accomplish the Letter of Bid in its letterhead clearly showing the
Bidder’s complete name and address.
Date: .........................................................
To:…………………………………………………………………………………………………….....
(a) We have examined and have no reservations to the Bidding Documents, including Addenda
issued in accordance with Instructions to Bidders (ITB) Clause 8.
(b) We offer to execute in conformity with the Bidding Documents the following Works:
(c) Our Bid consisting of the Technical Bid and the Price Bid shall be valid for a period of [insert
validity period as specified in ITB 18.1 of the BDS] days from the date fixed for the bid
submission deadline in accordance with the Bidding Documents, and it shall remain binding
upon us and may be accepted at any time before the expiration of that period.
(d) Our firm, including any subcontractors or suppliers for any part of the Contract, have nationalities
from eligible countries in accordance with ITB 4.2and meet the requirements of ITB 3.4,& 3.5
(e) We are not participating, as a Bidder or as a subcontractor, in more than one Bid in this
bidding process in accordance with ITB 4.3(e), other than alternative offers submitted in
accordance with ITB 13.
(f) Our firm, its affiliates or subsidiaries, including any Subcontractors or Suppliers for any part
of the contract, has not been declared ineligible by DP, under the Employer’s country laws or
official regulations or by an act of compliance with a decision of the United Nations Security
Council;
(g) We are not a government owned entity/We are a government owned entity but meet
the requirements of ITB 4.5;1
(h) We declare that, we including any subcontractors or suppliers for any part of the contract
do not have any conflict of interest in accordance with ITB 4.3 and we have not been punished
for an offense relating to the concerned profession or business.
(i) We declare that we are solely responsible for the authenticity of the documents submitted
by us. The document and information submitted by us are true and correct. If any
document/information given is found to be concealed at a later date, we shall accept any
legal actions by the Employer.
(j) We agree to permit the Employer/DP or its representative to inspect our accounts and records
and other documents relating to the bid submission and to have them audited by auditors
appointed by the Employer.
45
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
(k) If our Bid is accepted, we commit to mobilizing key equipment and personnel in accordance
with the requirements set forth in Section III (Evaluation and Qualification Criteria) and our
technical proposal, or as otherwise agreed with the Employer.
(l) We are committed to submit the Letter of Commitment for Bank’s Undertaking for Line of Credit
of ……………..Millions at the time of contract agreement, if the bid is awarded to us.
Name: .................................................................................................
Signed …………………………………………………………...
Date …………………………………………………………....
46
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
The Bidder must accomplish the Letter of Bid in its letterhead clearly showing the
Bidder’s complete name and address.
Date: .........................................................
To:…………………………………………………………………………………………………….....
(a) We have examined and have no reservations to the Bidding Documents, including Addenda
issued in accordance with Instructions to Bidders (ITB) Clause 8;
(b) We offer to execute in conformity with the Bidding Documents the following Works:
(c) The total price of our Bid, excluding any discounts offered in item (d) below is:
NRs……………………………….. or when left blank is the Bid Price indicated in the Bill of
Quantities.
(d) The discounts offered and the methodology for their application for subject contract [single
contract] are:……………………………………………..
(e) Our bid shall be valid for a period of 120 days after the deadline for the bid submission
deadline in accordance with the Bidding Documents, and it shall remain binding upon us and
may be accepted at any time before the expiration of that period;
(f) If our bid is accepted, we commit to obtain a performance security in accordance with the
Bidding Document;
(g) We have paid, or will pay the following commissions, gratuities, or fees with respect to the
bidding process or execution of the Contract:2
Name of Recipient Address Reason Amount
(h) We understand that this bid, together with your written acceptance thereof included in your
notification of award, shall constitute a binding contract between us, until a formal contract
is prepared and executed;
(i) We understand that you are not bound to accept the lowest evaluated bid or any other
2
If none has been paid or is to be paid, indicate “None”.
47
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
(j) We declare that we are solely responsible for the authenticity of the documents
submitted by us.
(k) We agree to permit the Employer/DP or its representative to inspect our accounts and
records and other documents relating to the bid submission and to have them audited by
auditors appointed by the Employer.
Name: ..............................................................................................
Signed …………………………………………………………...
Date …………………………………………………………....
48
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
Employer's
Base Bidder's
Source Proposed
Index Value Proposed
Code of Weighting
Description and Weighting
Index* Range
Date (coefficient)**
(coefficient)
1 2 3 4 5 6
Non -
Adjustable (A)
Labor (b)
Materials (c)
Equipment
usage (d)
Total
*Normally following source of index shall apply. Public Entity shall choose applicable Index for
each item.
(a) Labor: "National Salary and Wage Rate Index"- "Construction Labor" of Nepal Rastra Bank
or rate fixed by District Rate Fixation Committee
(b) Material:"National Wholesale Price Index" - Construction Materials" of Nepal Rastra Bank
(c) Equipment usage: "National Wholesale Price Index" - Machinery and Equipment" of Nepal
Rastra Bank or "Fuel" Price fixed by Nepal Oil Corporation.
** Bidders proposed weightings should be within the range specified by the Employer in column
-5
49
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
** Base Price and source normally to be specified by Employer (or alternatively informed to be
proposed by bidder) in column 4 and 5.
Note:
The base prices of the construction materials shall be taken as of 30 days before the deadline for submission
of the Bid as quoted by the Bidder and verified by the Employer. For the purpose of calculation of price
adjustment, the Ex-factory price of the same source shall be taken into consideration.
50
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
Bid Security
Bank Guarantee
Bank’s Name, and Address of Issuing Branch or Office
(On Letter head of the Commercial bank or any Financial Institution eligible to issue Bank
Guarantee as per prevailing Law)
Beneficiary: .............................. name and address of Employer ………………………………
Date: ……………………………………………Bid Security No.: ..............................................
We have been informed that. …………. [insert name of the Bidder] (hereinafter called “the
Bidder”)intends to submit its bid (hereinafter called “the Bid”) to you for the execution of
…………...name of Contract . …………… under Invitation for Bids No. ……………… (“the
IFB”).
Furthermore, we understand that, according to your conditions, bids must be supported by a bid
guarantee.
At the request of the Bidder, we…………………. . name of Bank ……………….. hereby
irrevocably undertake to pay you any sum or sums not exceeding in total an amount of . .
………...amount in figures ………………………. (. …………..amount in words ……………….)
upon receipt by us of your first demand in writing accompanied by a written statement stating that
the Bidder is in breach of its obligation(s) under the bid conditions, because the Bidder:
(a) has withdrawn or modifies its Bid:
i) during the period of bid validity specified by the Bidder on the Letter of Technical and
PriceBid, in case of electronic submission
(ii) from the period twenty-four hours prior to bid submission deadline up to the period of bid
validity specified by the Bidder on the Letter of Technical Bid and Price Bid, in case of hard
copy submission; or
(b) does not accept the correction of errors in accordance with the Instructions to Bidders
(hereinafter “the ITB”); or
(c) changes the prices or substance of the bid while providing information pursuant to clause 27.1
of ITB; or
(d) having been notified of the acceptance of its Bid by the Employer during the period of bid
validity, (i) fails or refuses to execute the Contract Agreement, or (ii) fails or refuses to
furnish the performance security, in accordance with the ITB.
(e) is involved in fraud and corruption in accordance with the ITB
This guarantee will remain in force up to and including the date ………number…………days
after the deadline for submission of Bids as such deadline is stated in the instructions to Bidders
or as it may be extended by the Employer, notice of which extension(s) to the Bank is hereby
waived. Any demand in respect of this guarantee should reach the Bank not letter than the above
date.
This Bank guarantee shall not be withdrawn or released merely upon return of the original
guarantee by the Bidder unless notified by you for the release of the guarantee.
This guarantee is subject to the Uniform Rules for Demand Guarantees, ICC Publication No. 758.
. . .Bank’s seal and authorized signature(s) . . .
Note:
The bid security of ………..……………. has been counter guaranteed by the Bank ……..………..…… on
…………... .................................................……..………. (Applicable for Bid Security of Foreign Banks).
51
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
Personnel
Equipment
Site Organization
Method Statement
Mobilization Schedule
Construction Schedule
Others
52
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
Personnel
Form PER - 1: Proposed Personnel
Bidders should provide the names of suitably qualified personnel to meet the specified
requirements for each of the positions listed in Section III (Evaluation and Qualification Criteria).
The data on their experience should be supplied using the Form below for each candidate.
Academic Experience
Total Work
Qualification in Similar
No. Name Position* Experience
Works
[Years]
[years]
1.
2.
3.
4.
5.
53
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
The Bidder shall provide all the information requested below. Fields with asterisk (*) shall be
used for evaluation.
Position*
Personal Information Name Date of Birth
Professional qualifications
Present employment Name of employer
Address of employer
Telephone Contact (manager/personnel officer)
Fax E-mail
Job title Years with present employer
Summarize professional experience over the last twenty years in reverse chronological order.
Indicate particular technical and managerial experience relevant to the project.
Note:
In case of e-submission the Resume of Proposed Personnel shall be submitted on notification by the
Employer as per ITB 27.
54
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
Equipment
The Bidder shall provide adequate information to demonstrate clearly that it has the capability to
meet the requirements for the key equipment listed in Section III (Evaluation and Qualification
Criteria). A separate Form shall be prepared for each item of equipment listed, or for alternative
equipment proposed by the Bidder. The Bidder shall provide all the information requested below,
to the extent possible. Fields with asterisk (*) shall be used for evaluation.
(i) For the equipment under Bidder's ownership
Type of Equipment*
The following information shall be provided only for equipment not owned by the Bidder.
55
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
Address of owner
Fax email
the project
The Bidder shall be solely responsible for the data provided. However, this shall not
limit the right of Employer to verify the authenticity of submitted information.
Note:
In case of e-submission the “Agreements” shall be submitted on notification by the Employer as per ITB 27.1
56
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
Site Organization
Method Statement
Mobilization Schedule
Construction Schedule
Others
57
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
Bidder’s Qualification
To establish its qualifications to perform the contract in accordance with Section III (Evaluation
and Qualification Criteria) the Bidder shall provide the information requested in the corresponding
Information Sheets included hereunder.
Bidder's Information
constitution
mail address)
1. In case of single entity, articles of incorporation or constitution of the legal entity named
above, in accordance with ITB 4.1 and 4.2.
2. Authorization to represent the firm or JV named in above, in accordance with ITB 20.2.
3. In case of JV, letter of intent to form JV or JV agreement, in accordance with ITB 4.1.
4. In case of a government-owned entity, any additional documents not covered under 1 above
required to comply with ITB 4.5.
58
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
JV Partner's or
JV Partner's or
JV Partner's or
constitution
JV Partner's or
59
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
* Mention “On going” if the bid has not been awarded yet and “Awarded” if the bid has been awarded to
the bidder. Status of bidding process only the ongoing and awarded has to be mentioned.
** Insert date of issuance of taking over certificate if the awarded bid has been substantially completed
and taking over certificate has been issued.
60
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
Pending Litigation
No pending litigation in accordance with Criteria 2.2 of Section III (Evaluation and
Qualification Criteria)
Pending litigation in accordance with Criteria 2.2 of Section III (Evaluation and Qualification
Criteria)
Value of Pending
Value of Pending Claim as a
Year Matter in Dispute
Claim in NRS Percentage on Net
Worth
61
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
Total Assets
Total Liabilities
Net Worth
Current Assets
Current Liabilities
Total Revenues
o Attached are copies of financial statements (balance sheets including all related notes, and
income statements) for the last three or above years, as indicated above, complying with the
following conditions.
o All such documents reflect the financial situation of the Bidder or partner to a JV, and not sister
or parent companies.
o Historic financial statements must be audited by a certified auditor.
o Historic financial statements must be complete, including all notes to the financial statements.
o Historic financial statements must correspond to accounting periods already completed and
audited (no statements for partial periods shall be requested or accepted).
Note:
In case of e-submission the attachments should not be uploaded but shall be submitted on
notification by the Employer as per ITB 27.1
62
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
The information supplied should be the Annual Turnover of the Bidder or each member of a
JV in terms of the amounts billed to clients for each year for work in progress or completed to
NRs at the end of the period reported.
63
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
A = Average Annual Turnover of best three years out of last ten fiscal years.
B = Annual Value of the existing commitments and works (ongoing) to be completed, calculated
from FIN-4.
A, in B, in Bid Capacity,
SN Name of Bidder Pan No.
Million Million in Million
Signature of Bidder
64
Procurement of Works- Single Stage Two Envelope Procedure | 65
Signature of Bidder
# The Outstanding Works means Contract Price (excluding Vat) minus Work Evaluated by Employer till the reference date. Bidder shall have to
submit the relevant documentary evidence to substantiate the facts/figures.
(e) ( a )
Note 1: “B” shall be calculated as : B ( f ) x12 , If (f) is less than 12, then value of (f) shall be taken as 12.
Note 2: If Initial or Revised Contract Date is run out with respect to Date of Invitation of Bid, the Estimated Time in Month to Complete the outstanding
works shall be taken equal to 12 months.
65
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
66
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
Description of the similarity in accordance with Criteria 2.4.2 (a) of Section III
Note :
The Employer should insert here contract
size, complexity, methods, technology, or
other characteristics as described in Section
VI (Work Requirements) against which the
bidder demonstrates similarity in the box on
the right-hand-side.
67
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
Role in Contract
Contractor Management Subcontractor
Contractor
Employer's Name
Address
Telephone/Fax
Number
E-mail
Description of the similarity in accordance with Criteria 2.4.2 (a) of Section III
Note :
The Employer should insert here production
rate(s) for the key activity (activities) subject
contract against which the bidder
demonstrates in the box on the right-hand-
side production rates achieved by him on
previous contracts.
68
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
[This section contains the list of eligible countries. Select one option, either GoN Funded or
DP Funded.]
69
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
70
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
Table of Clauses
Scope of Work............................................................................................................................ 73
Specifications ............................................................................................................................. 74
Drawings ................................................................................................................................... 75
Supplementary Information......................................................................................................... 76
Section VI: Bill of Quantities ........................................................................................................ 78
Notes for Unit Rate Contracts: ...............................................................................................78
Preamble of Bill of Quantities .................................................................................................80
A. General .............................................................................................................................80
B. Day work Schedule ...........................................................................................................81
Provisional Sums ...................................................................................................................82
Bill of Quantities ......................................................................................................................... 83
71
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
This Section contains the Specification, the Drawings, and supplementary information
that describe the Works to be procured.
72
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
Scope of Work
1. Work under this section consists of furnishing of all labour, material, equipments and
appliances necessary or required to complete the construction of adit tunnels (adit III, adit V
and adit VI) of Chainpur seti (210 MW) Hydroelectic project.
a) Excavation of Adit Tunnels (Adit III at Rumaligad Adit V at Basti Gaun and Adit VI at left
bank of Sitalikhola) as according to the mention shape and size of adit tunnels at drawing.
b) Dewatering and Care of water during construction for all adit tunnels.
73
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
Specifications
Note : Separate Volume of Specification is attached for Online Document and
Separate volume – II Specification is available in case of detail specification of
work mentioned.
VOLUME – II SPECIFICATIONS
74
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
Drawings
This section has been separately included in Volume II of the Bid Document.
75
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
Supplementary Information
Chainpur Seti Hydroelectric Project (CSHEP) is located in Saipal and Talkot Rural Municipality
of Bajhang District, Sudurpaschim Province of Nepal. NEA has identified the project and has also
acquired the study license to conduct the feasibility study. CSHEP is a Peaking Run-of-the-river
(PRoR) type project in the Seti River.
The project lies between 81° 16’ 00” E to 81° 20’ 15” E and 29° 36’ 20” N to 29° 44’ 40” N. The
major structures including diversion dam, settling basin, water conveyance tunnel lies in Saipal
and Talkot Rural Municipality. The powerhouse is located at at the Basti village of Talkot Rural
Municipality at an elevation of 1370 masl. Both the headworks and powerhouse locations are on
the right bank of the Seti River.The gross head of the project is 496 m and calculated net head
is 474.49 m. The design discharge of 50.68 m3/sec at 36.5% exceedance of flow is derived from
hydrological studies and project optimization studies. The Seti River is a part of the Karnali River
Basin System. The size of the entire catchment of the Seti River at the intake is about 1390.40
km2 and lies completely within Bajhang District. One of the major tributaries of the Seti River,
before it reaches the proposed intake site of CSHEP, is the Ghatganga River. Mean annual
rainfall in the catchment is 1561.27 mm. The average monthly flow at the headworks site is 63.65
m3/s. The 100-year return period flood is 1018.00 m3/s at the intake site and the design flood of
1000-year return period at the intake site is 1659 m3/s and PMF at headworks is 3935 m3/s.
The project headworks area is about 962 km from Kathmandu. Project area can be accessed by
travelling 114 km from Kathmandu to Mugling via Prithvi highway (H02), 42.8 km from Mugling
to Narayangad via Madan Ashrit highway (H05), 506 km from Narayangad to Attariya via
Mahendra highway (H01), 147 km from Attariya to Khodpe via Mahakali Highway (H14) and 103
km from Khodpe to Chainpur via Khodpe- Bajhang road (F49). The proposed Headworks site is
accessible within 51 Km form Chainpur which is under construction by Government of Nepal
(GoN), Department of Road (DoR) as Seti Highway.
The diversion dam has been designed with a diurnal pond of approximate 0.735 Mm 3 between
Full Reservoir Level (FRL) at El. 1874 masl and Minimum Operating Level (MOL) at El. 1862
masl with considering the live storage is sufficient to serve full peaking during 4 hours in the
afternoon and 2 hours in the morning. Dam platform level is at 1880 masl.
The diversion structure will consist of a structure with gates to regulate flood flow. The structure
consists of a radial gate and a flap gate for sediment/ bed load flushing. Gravel trap has been
provided to collect gravel and coarse sand after the intake consisting of three vertical gates.
Underground settling basin of three chambers has been proposed with each basin having
dimensions of 130 m x 15 m x 20.4 m (Lx B x H). The 20.4 m height of the settling basin is of
settling zone. The connecting tunnel will be a single chambered D shape Tunnel at the inlet, later
then it will be divided into three connecting tunnels to the settling basin. The total length of HRT
from the Settling Basin to the Surge Tank is 12,468 m. The finished diameter of D shaped
concrete lined HRT is 5.4 m and shotcrete lined is 5.9 m.
The pressure shaft is designed to carry the design discharge, from the surge tank to the turbine
via vertical and horizontal shaft to the semi-powerhouse. Pressure shaft having 3.5 m diameter
76
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
of length 1581.5 m is provided which bifurcates to a semi-surface powerhouse. After the branch,
the length of three number of 2.0 m internal diameter is 140.44 m long steel penstock pipe
conveys the flow to the powerhouse. The total length of pipe from surge tank to the powerhouse
is 1744.20 m.
The powerhouse size is 73 m x 18m x 32.2 m (L x B x H). It contains three units of vertical axis
pelton turbine each of 70 MW rated output. The center line level of the turbine is at 1374 masl.
The flow from the turbines will be released back to the Seti River through (5.5 m X 5.5 m)
rectangular tailrace culvert of 70 m long.
The installed capacity of the project is 210 MW. Estimated duration of the project is 5 years
excluding the construction of the access road, camp facilities. Total saleable energy is estimated
to be 1158.02 GWh consisting of dry season energy of 219.50 GWh (6 hrs peaking) and dry off
peaking season energy of 136.91 GWh and wet season energy is 801.62 GWh. The dry season
energy comes to be 30.78% of the total energy generated. The generated power is planned to
evacuate through 220 kV double circuit transmission line of length 500 m to proposed Bajhang
hub substation at Basti Village. The construction period of the project is 5 years.
The estimated total project cost of the project is NRs.42,631,879,425.66 including IDC of NRs.
6,085,993,445.74 for Private scenario. The financial analysis for the PROR plant with energy
price at posted rate, i.e. NPR 4.80/kWh for wet season energy and NPR 8.40/kWh for dry off
peaking season energy and NPR 10.55/kWh for dry peaking season energy considering annual
price escalation on electricity at the rate of 3% for 8 years. For Private scenario, with interest rate
of 10 %, NPV is NRs. 16,717.0 million, B/C ratio is 1.53 at 9 % discount rate and IRR is 13.17%.
For NEA scenario, with interest of 5% and with the NEA Scenario, results in an NPV of NRs.
19,363.0 million, B/C ratio of 1.63 at 9% discount rate and IRR of 14.11%.Chainpur Seti
Hydroelectric Project (CSHEP) is found to be technically feasible and financially viable.
77
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
In order to attain these objectives, Works should be itemized in the Bill of Quantities in sufficient
detail to distinguish between the different classes of Works, or between Works of the same nature
carried out in different locations or in other circumstances which may give rise to different
considerations of cost. Consistent with these requirements, the layout and content of the Bill of
Quantities should be as simple and brief as possible.
Content
The Bill of Quantities should be divided generally into the following sections:
(a) Preamble;
(b) Work Items (grouped into parts);
(c) Day works Schedule;
d) Provisional Sums; and
(d) Summary.
Preamble
The Preamble should indicate the inclusiveness of the unit prices, and should state the methods
of measurement which have been adopted in the preparation of the Bill of Quantities and which
are to be used for the measurement of any part of the works.
Work Items
The items in the Bill of Quantities should be grouped into sections to distinguish between those
parts of the Works which by nature, location, access, timing, or any other special characteristics
may give rise to different methods of construction, or phasing of the Works, or considerations of
cost. General items common to all parts of the works may be grouped as a separate section in
the Bill of Quantities.
In lump sum contracts, delete “Bill of Quantities” and replace with “Schedule of Activities” throughout this section.
3
78
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
(a) A list of the various classes of labor, materials, and Constructional Plant for which basic day
work rates or prices are to be inserted by the Bidder, together with a statement of the
conditions under which the Contractor will be paid for work executed on a day work basis.
(b) Nominal quantities for each item of Day work, to be priced by each Bidder at Day work rates
as bid. The rate to be entered by the Bidder against each basic Day work item should include
the Contractor’s profit, overheads, supervision, and other charges.
Provisional Sums
Provisional Sums included and so designated in the Bill of Quantities shall be expended in
whole or in part at the direction and discretion of the Project Manager in accordance with the
Conditions of Contract.
Summary
The Summary should contain a tabulation of the separate parts of the Bill of Quantities carried
forward, with provisional sums for Day work, for physical (quantity) contingencies, and for price
contingencies (upward price adjustment) where applicable.
79
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
A. General
1. The Bill of Quantities shall be read in conjunction with the Instructions to Bidders, General and
Special Conditions of Contract, Technical Specifications, and Drawings.
2. The quantities given in the Bill of Quantities are estimated and provisional, and are given
to provide a common basis for bidding. The basis of payment will be the actual quantities
of work ordered and carried out, as measured by the Contractor and verified by the Project
Manager and valued at the rates and prices bid in the priced Bill of Quantities, where
applicable, and otherwise at such rates and prices as the Project Manager may fix within the
terms of the Contract.
3. For any item for which measurement is based on records made before or during construction
the records shall be prepared and agreed between the Engineer and the Contractor. Should the
Contractor carry out such work without the prior agreement of the Engineer, the Engineer may
request the Contractor to carry out investigations to confirm the extent of the work and the
quantity of work certified for payment shall be solely at the Engineer's discretion. The cost of any
such investigation shall be borne by the Contractor.
4. The rates and prices bid in the priced Bill of Quantities shall, except as otherwise provided
under the Contract, include all construction equipment, labor, supervision, materials, erection,
maintenance, insurance, profit, taxes, and duties, together with all general risks, liabilities, and
obligations set out or implied in the Contract.
5. A rate or price shall be entered against each item in the priced Bill of Quantities, whether
quantities are stated or not. The cost of items against which the Contractor has failed to enter
a rate or price shall be deemed to be covered by other rates and prices entered in the Bill of
Quantities.
6. The whole cost of complying with the provisions of the Contract shall be included in the Items
provided in the priced Bill of Quantities, and where no Items are provided, the cost shall be
deemed to be distributed among the rates and prices entered for the related Items of Work.
7. General directions and descriptions of work and materials are not necessarily repeated nor
summarized in the Bill of Quantities. References to the relevant sections of the Contract
documentation shall be made before entering prices against each item in the priced Bill of
Quantities. The Specification Clause references where given in the item description of the Bills
of Quantities are for the convenience of bidders and generally refer to the principal relevant-
specification clause but do not necessarily represent the whole of the specification requirements
for the work required within the item. The presence of a Specification clause reference shall not
in any way reduce the Bidders obligation to complete work in accordance with all the
requirements of the Specification.
8. Provisional Sums included and so designated in the Bill of Quantities shall be expended in
whole or in part at the direction and discretion of the Project Manager in accordance with the
Conditions of Contract.
9. The method of measurement of completed work for payment shall be in accordance with the
Specifications.
80
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
81
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210MW)
Engineering Services Directorate Bidding Document
Provisional Sums
A general provision for physical contingencies (quantity overruns) may be made by including a
provisional sum in the Summary Bill of Quantities. Similarly, a contingency allowance for possible
price increases should be provided as a provisional sum in the Summary Bill of Quantities. The
inclusion of such provisional sums often facilitates budgetary approval by avoiding the need to
request periodic supplementary approvals as the future need arises. Where such provisional sums
or contingency allowances are used, the SCC should state the manner in which they will be used,
and under whose authority (usually the Project Manager’s).
The estimated cost of specialized work to be carried out, or of special goods to be supplied, by
other contractors should be indicated in the relevant part of the Bill of Quantities as a particular
provisional sum with an appropriate brief description. A separate procurement procedure is
normally carried out by the Employer to select such specialized contractors. To provide an element
of competition among the Bidders in respect of any facilities, amenities, attendance, etc., to be
provided by the successful Bidder as prime Contractor for the use and convenience of the
specialist contractors, each related provisional sum should be followed by an item in the Bill of
Quantities inviting the Bidder to quote a sum for such amenities, facilities, attendance, etc.
82
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
Bill of Quantities
83
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bill of Quantities
Rate (NRs.)
Item Description of Works Unit Quantity Amount Remarks
No. In Figure In Words (NRs.)
Construction of Adit Tunnels (Adit III , Adit V and Adit VI) at the Headrace Tunnel
A Provisional Sum
A.1 Provisional sum for required unforeseen works as
assigned by Project Manager (rate of such items will P.S. 1.00 500000.00 Five Lakhs 500000.00
be based on Day Works schedule submitted during
bidding).
Sub-Total A
B General Items
84
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bill of Quantities
B.6 Establish, maintain and operate laboratory at the site Refer to Item H. Tests
with equipment furnishing required for testing
specified quality of the materials as per specification
or testing of the material as per instruction by site
Engineer as specified in specification.
85
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bills of Quantities
Description of Works Unit Quantity Rate (NRs.) Amount Remarks
Item (NRs.)
No. In Figure In Words
Total B
C Construction of Adit Tunnel III at Rumaligad (451.00m long Adit III along Main Access Tunnel Headrace Tunnel at Elevation 1817.80m)
C.1.1 Dewatering and Care of water during construction for Job 1.00
all adits.
86
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bill of Quantities
Rate (NRs.)
Item Description of Works Unit Quantity Amount Remarks
No. In Figure In Words (NRs.)
C.1.5 Providing, fabricating and fixing T Anchor bar 12mm
diameter including cost of all materials, machinery,
labour, cleaning and flushing the holes, grouting with m 53.41
cement slurry, etc. complete as per drawing and
specification or instructed by Engineer.
87
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bills of Quantities
Rate (NRs.)
Item Description of Works Unit Quantity Amount Remarks
No. (NRs.)
In Figure In Words
88
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bill of Quantities
Rate (NRs.)
Item Description of Works Unit Quantity Amount Remarks
No. (NRs.)
In Figure In Words
C.1.15 Providing, fabricating and fixing Forepole 25 mm dia m 1848.00
@ 6 m long spacing 30 cm at crown including cost of
all materials, machinery, labour, cleaning and flushing
the holes, grouting with cement slurry, etc. complete
as per drawing and specification or instructed by
Engineer.
Sub Total C
D Construction of Adit Tunnel V at Basti (290m long Adit 5 along Main Access Tunnel Headrace Tunnel at Elevation 1396.60m)
D.1 Adit Tunnel V
89
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bills of Quantities
Rate (NRs.)
Item Description of Works Unit Quantity Amount Remarks
No. (NRs.)
In Figure In Words
D.1.2 Preparation of site before excavation of tunnel which m2 415.38
includes removing the bushes, taking out the roots,
making the undulated surface in level etc. as per
specification or instructed by Engineer.
D.1.3 Overburden soil excavation after cleaning the site etc. m³ 849.71
as per specification or instructed by Engineer.
90
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bill of Quantities
Rate (NRs.)
Item Description of Works Unit Quantity Amount Remarks
No. (NRs.)
In Figure In Words
D.1.7 Underground Rock Excavation in rock class IV and V
by supply, handling, storing of the explosive in safe
way for tunneling method (full face excavation) for
adit tunnel including excavation for support in rock,
shoring, strutting, ventilation, lighting, supply of
construction power, drainage, dewatering, wherever
Rm 290.00
needed and all ancillary operations such as removing
and hauling the excavated material up to specified
disposal area including cost of all materials,
machinery, labour, etc. all complete as per instruction
and specification or instructed by Engineer.
91
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bills of Quantities
Rate (NRs.)
Item Description of Works Unit Quantity Amount Remarks
No. (NRs.)
In Figure In Words
D.1.11 Providing 50 mm thick Fibre reinforced shotcrete
including all required materials, equipment and
manpower for application etc. complete as per m2 1,461.82
drawing and specification or instructed by Engineer.
92
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bill of Quantities
Rate (NRs.)
Item Description of Works Unit Quantity Amount Remarks
No. (NRs.)
In Figure In Words
D.1.16 Providing, fabricating and fixing Drainage Pipe
HDPE (50 mm dia) including cost of all materials,
machinery, labour, cleaning and flushing the holes, m 244.00
etc. complete as per drawing and specification or
instructed by Engineer.
93
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bills of Quantities
Rate (NRs.)
Item Description of Works Unit Quantity Amount Remarks
No. (NRs.)
In Figure In Words
D.1.20 Providing, mixing and laying Plain Cement
Concrete(P.C.C.) conforming to I.S. code with stone
aggregate 20 mm and down gauge ( R.C.C. ) works
including compaction, curing and making access for
conveyance of concrete in M25 (1:1:2) cement, sand m3 15.13
and aggregate etc.at front face of inlet portal all
complete as per drawing or instructed by Engineer.
Sub Total D
E Construction of Adit Tunnel VI at Left Bank of Sitalikhola (230m long Adit VI along Main Access Tunnel Headrace Tunnel at Elevation
1396.60m)
E.1 Adit Tunnel VI
E.1.1 Dewatering and Care of water during construction for Job 1.00
all adit tunnels
E.1.2 Preparation of site before excavation of tunnel which
includes removing the bushes, taking out the roots, m2 535.00
making the undulated surface in level etc. as per
specification or instructed by Engineer.
94
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bill of Quantities
Rate (NRs.)
Item Description of Works Unit Quantity Amount Remarks
No. In Figure In Words (NRs.)
E.1.3 Overburden soil excavation after cleaning the site etc. m³ 1700.16
as per specification or instructed by Engineer.
95
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bills of Quantities
Rate (NRs.)
Item Description of Works Unit Quantity Amount Remarks
No. In Figure In Words (NRs.)
96
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bill of Quantities
E.1.14 Providing, fabricating and fixing Rib I beam ISMB tonne 45.58
150 @ 1.2 m c/c at portal upto 10 m length etc.
complete as per drawing and specification or
instructed by Engineer.
97
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bills of Quantities
Sub Total E
G Dayworks
98
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bill of Quantities
Rate (NRs.)
Item Description of Works Unit Quantity Amount Remarks
No. (NRs.)
In Figure In Words
G.7 Tipper (10 T) with fuel, operator all complete. Hr. 250.00
G.8 Loader (1-1.5m3 capacity) with fuel, operator all Hr. 250.00
complete.
G.9 Excavator (2m3 capacity) with fuel, operator all Hr. 250.00
complete.
H Tests
99
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bills of Quantities
Rate (NRs.)
Item Description of Works Unit Quantity Amount Remarks
No. (NRs.)
In Figure In Words
H.2.2 Block Shear Test
Set 2.00
H.2.3 Core Drilling works, as necessary
Set 100.00
VAT@13%
Grand Total(A+B+C+D+E+F+G+H)
In Words :
100
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
101
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
Table of Clauses
A. General ....................................................................................................................... 105
1. Definitions ....................................................................................................................... 105
2. Interpretation ................................................................................................................... 107
3. Language and Law.......................................................................................................... 107
4. Contract Agreement ........................................................................................................ 107
5. Assignment ..................................................................................................................... 108
6. Care and Supply of Documents....................................................................................... 108
7. Confidential Details ......................................................................................................... 108
8. Compliance with Laws .................................................................................................... 109
9. Joint and Several Liability................................................................................................ 109
10. Project Manager's Decisions ......................................................................................... 109
11. Delegation ..................................................................................................................... 109
12. Communications ........................................................................................................... 109
13. Subcontracting .............................................................................................................. 109
14. Other Contractors.......................................................................................................... 109
15 Personnel and Equipment .............................................................................................. 109
16. Employer’s and Contractor's Risk .................................................................................. 110
17. Employer’s Risks.......................................................................................................... 110
18. Contractor’s Risks ........................................................................................................ 110
19. Insurance .................................................................................................................... 110
20. Site Investigation Reports ............................................................................................ 111
21. Contractor to Construct the Works ................................................................................ 111
22. The Works to Be Completed within intended Completion Date..................................... 111
23. Design by contractor and Approval by the Project Manager .......................................... 111
24. Safety, Security and Protection of the Environment ....................................................... 111
25. Discoveries .................................................................................................................. 112
26. Possession of the Site.................................................................................................. 112
27. Access to the Site ........................................................................................................ 112
28. Instructions, Inspections and Audits ............................................................................. 112
29. Dispute Settlement ....................................................................................................... 113
30. Procedures for Disputes ............................................................................................... 113
B. Staff and Labor .................................................................................................................... 113
31. Forced Labor................................................................................................................. 113
32. Child Labor.................................................................................................................... 113
33.Non-discrimination and Equal Opportunity ..................................................................... 113
B. Time Control ............................................................................................................... 113
34. Program ....................................................................................................................... 113
35. Extension of the Intended Completion Date .................................................................. 114
36. Acceleration ................................................................................................................. 114
37. Delays Ordered by the Project Manager ...................................................................... 114
38. Management Meetings ................................................................................................. 115
39. Early Warning .............................................................................................................. 115
C. Quality Control .................................................................................................................... 115
40.Identifying Defects.......................................................................................................... 115
41. Tests115
42. Correction of Defects .................................................................................................... 115
43.Uncorrected Defects ...................................................................................................... 115
D. Cost Control ........................................................................................................................ 115
44. Contract Price .............................................................................................................. 115
45. Changes in the Contract Price ...................................................................................... 116
102
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
103
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
104
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
105
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
beyond a Party's control; which such Party could not reasonably have
provided against before entering into the Contract; which, having arisen,
such Party could not reasonably have avoided or overcome; and, which
is not substantially attributable to the other Party.
(t) The Initial Contract Price is the Contract Price listed in the Employer’s
Letter of Acceptance.
(u) In writing or written means hand written, type written, printed or
electronically made, and resulting in permanent record.
(v) The Intended Completion Date is the date on which it is intended
that the Contractor shall complete the Works. The Intended
Completion Date is specified in the SCC. The Intended Completion
Date may be revised only by the Project Manager by issuing an extension
of time or an acceleration order.
(w) Letter of Acceptance means the formal acceptance by the
Employer of the Bid and denotes the formation of the contract at the date
of acceptance.
(x) Materials are all supplies, including consumables, used by the
Contractor for incorporation in the Works.
(y) Party means the Employer or the Contractor, as the context requires.
(z) SCC means Special Conditions of Contract
(aa) Plant is any integral part of the Works that shall have a mechanical,
electrical, chemical, or biological function.
(bb) The Project Manager is the person named in the SCC (or any other
competent person appointed by the Employer and notified to the
Contractor, to act in replacement of the Project Manager) who is
responsible for supervising the execution of the Works and administering
the Contract.
(cc) Retention Money means the aggregate of all monies retained by the
Employer pursuant to GCC 54.1.
(dd) Schedules means the document(s) entitled schedules, completed by
the Contractor and submitted with the Letter of Bids, as included in the
Contract. Such document may include the Bill of Quantities, data, lists, and
schedules of rates and/or prices.
(ee) The Site is the area defined as such in the SCC
(ff) Site Investigation Reports are those that were included in the
bidding documents and are factual and interpretative reports about the
surface and subsurface conditions at the Site.
(gg) Specification means the Specification of the Works included in
the Contract and any modification or addition made or approved by the
Project Manager.
(hh) The Start Date is given in the SCC. It is the latest date when the
Contractor shall commence execution of the Works. It does not
necessarily coincide with any of the Site Possession Dates.
(ii) A Subcontractor is a person or corporate body who has a Contract
with the Contractor to carry out a part of the work in the Contract, which
includes work on the Site.
(jj) Temporary Works are works designed, constructed, installed, and
removed by the Contractor that are needed for construction or installation
106
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
of the Works.
(kk) A Variation is an instruction given by the Project Manager which
varies the Works
(ll) The Works are what the Contract requires the Contractor to construct,
install, and turn over to the Employer, as defined in the SCC.
2. Interpretation
2.1 In interpreting these GCC, singular also means plural, male also means
female or neuter, and the other way around. Headings have no
significance. Words have their normal meaning under the language of
the Contract unless specifically defined. The Project Manager shall
provide instructions clarifying queries about these GCC.
2.2 If sectional completion is specified in the SCC, references in the
GCC to the Works, the Completion Date, and the Intended Completion
Date apply to any Section of the Works (other than references to the
Completion Date and Intended Completion Date for the whole of the
Works).
2.3 The documents forming the Contract shall be interpreted in the following
order of priority:
(a) Contract Agreement,
(b) Letter of Acceptance,
(c) Letters of Technical Bid and Price Bid,
(d) Special Conditions of Contract,
(e) General Conditions of Contract,
(f) Specifications,
(g) Drawings,
(h) Bill of Quantities (or Schedules of Prices for lump sum contracts),
and
(i) Any other document listed in the SCC as forming part of the
Contract.
3. Language and
3.1 The language of the Contract and the law governing the Contract are
Law stated in the SCC.
1.2. Throughout the execution of the Contract, the Contractor shall comply
with the import of goods and services prohibitions in the Employer’s
country when
(a) by an act of compliance with a decision of the United Nations
Security Council taken under Chapter VII of the Charter of the
United Nations, the Borrower’s Country prohibits any import of
goods from, or any payments to, a particular country, person, or
entity. Where the borrower’s country prohibits payments to a
particular firm or for particular goods by such an act of compliance,
that firm may be excluded.
4. Contract
4.1 The Parties shall enter into a Contract Agreement within 15 days after
Agreement the Contractor receives the Letter of Acceptance, unless the Special
Conditions establish otherwise. The Contract Agreement shall be
107
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
6.2 Each of the Contractor’s Documents shall be in the custody and care
of the Contractor, unless and until taken over by the Employer. Unless
otherwise stated in the Contract, the Contractor shall supply to the
Engineer six copies of each of the Contractor’s Documents.
6.3 The Contractor shall keep, on the Site, a copy of the Contract,
publications named in the Specification, the Contractor’s Documents
(if any), the Drawings and Variations and other communications given
under the Contract. The Employer’s Personnel shall have the right of
access to all these documents at all reasonable times.
6.4 If a Party becomes aware of an error or defect in a document which
was prepared for use in executing the Works, the Party shall promptly
give notice to the other Party of such error or defect.
7. Confidential
7.1 The Contractor’s and the Employer’s Personnel shall disclose all such
Details confidential and other information as may be reasonably required in
order to verify the Contractor’s compliance with the Contract and allow
its proper implementation.
7.2 Each of them shall treat the details of the Contract as private and
confidential, except to the extent necessary to carry out their respective
obligations under the Contract or to comply with applicable Laws. Each
of them shall not publish or disclose any particulars of the Works
prepared by the other Party without the previous agreement of the
other Party. However, the Contractor shall be permitted to disclose
any publicly available information, or information otherwise required to
establish his qualifications to compete for other projects.
108
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
8. Compliance with
8.1 The Contractor shall, in performing the Contract, comply with
Laws applicable Laws.
9. Joint and
9.1 If the Contractor is a joint venture of two or more entities, all such
Several Liability entities shall be jointly and severally liable to the Employer for the
fulfillment of the provisions of the Contract, and shall designate one of
such persons to act as a leader with authority to bind the joint venture.
The contractor shall not handover the responsibility of the
contract to any one member or some members of Joint Venture
or any other parties, not involved in the contract. The composition
or the constitution of the joint venture shall not be altered without the
prior consent of the Employer.
10. Project
10.1 Except where otherwise specifically stated, the Project Manager shall
Manager's decide contractual matters between the Employer and the Contractor in
Decisions the role representing the Employer.
11. Delegation
11.1 The Project Manager may delegate any of his duties and responsibilities
to other people after notifying the Contractor, and may cancel any
delegation after notifying the Contractor.
12.
12.1 Communications between parties that are referred to in the Conditions
Communications shall be effective only when in writing. A notice shall be effective only
when it is delivered.
13. Subcontracting
13.1 For GoN Funded:
A list of approved Subcontractors including its value/works is included as
Article 2 (k) of contract Agreement. Approval by the Employer for any of
the Subcontractors shall not relieve the Contractor from any of its
obligations, duties, or responsibilities under the contract.
14. Other
14.1 The Contractor shall cooperate and share the Site with other
Contractors contractors, public authorities, utilities, and the Employer between the
dates given in the Schedule of Other Contractors, as referred to in the
SCC. The Contractor shall also provide facilities and services for them
as described in the Schedule. The Employer may modify the Schedule
of Other Contractors, and shall notify the Contractor of any such
modification
15 Personnel and
15.1 The Contractor shall employ the key personnel and use the
Equipment
equipment identified in its Bid to carry out the Works, or other
personnel and equipment approved by the Project Manager. The Project
Manager shall approve any proposed replacement of key personnel and
equipment only if their relevant qualifications or characteristics are
substantially equal to or better than those proposed in the Bid.
15.2 If the Project Manager asks the Contractor to remove a person who is a
member of the Contractor’s staff or work force, stating the reasons, the
Contractor shall ensure that the person leaves the Site within seven
days and has no further connection with the work in the Contract.
15.3 If the Employer, Project Manager, or Contractor determines, that any
employee of the Contractor be determined to have engaged in corrupt,
109
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
110
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
before the Start Date. All such insurance shall provide for
compensation to be payable in the proportions of Nepalese Rupees
required to rectify the loss or damage incurred.
19.3 If the Contractor does not provide any of the policies and
certificates required, the Employer may affect the insurance which
the Contractor should have provided and recover the premiums the
Employer has paid from payments otherwise due to the Contractor or,
if no payment is due, the payment of the premiums shall be a debt due.
19.4 Alterations to the terms of insurance shall not be made without the
approval of the Project Manager.
19.5 Both parties shall comply with any conditions of the insurance policies.
20. Site
20.1 The Contractor, in preparing the Bid, shall rely on any Site
Investigation Investigation Reports referred to in the SCC, supplemented by any
Reports information available to the Contractor.
21. Contractor to
21.1 The Contractor shall construct and install the Works in accordance with
Construct the the Specifications and Drawings.
Works
111
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
c. Take all reasonable steps to protect the environment on and off the
site and to avoid damage or nuisance to persons
or to property of the public or others resulting from pollution, noise or
other causes arising as a consequence of his methods of
operation.
d. Ensure that any cut or fill slopes are planted in grass or other plant
cover as soon as possible to protect them from erosion.
e. Any spoil or material removed from drains shall be disposed of to
designated stable tipping areas as directed by the Project
Manager.
f. Shall not use fuel wood as a means of heating during the
processing or preparation of any materials forming part of the works.
g. The Project Manager shall have the power to disallow any
working practice or activity of the Contractor or direct that such
practices or activities be modified should the Project Manager
consider, on the advice of the relevant Government Departments,
that the practices or activities will be harmful to wildlife.
h. Provide on the Site such lifesaving apparatus as may be
appropriate and an adequate and easily accessible first aid outfit
or such outfits as may be required by any government ordinance,
factory act, etc., subsequently published and amended from time
to time.
25. Discoveries
25.1 Anything of historical or other interest or of significant value
unexpectedly discovered on the Site shall be the property of the
employer. The Contractor shall notify the Project Manager of such
discoveries and carry out the Project Manager’s instructions for dealing
with them.
26. Possession of
26.1 The Employer shall give possession of all parts of the Site to the
the Site Contractor. If possession of a part is not given by the date stated in the
SCC, the Employer shall be deemed to have delayed the start of the
relevant activities, and this shall be a Compensation Event.
27. Access to the
27.1 The Contractor shall allow the Project Manager and any person
Site authorized by the Project Manager access to the Site and to any place
where work in connection with the Contract is being carried out or is
intended to be carried out.
28. Instructions,
28.1 The Contractor shall carry out all instructions of the Project Manager
Inspections and which comply with the applicable laws where the Site is located.
Audits
28.2 The Contractor shall keep, and shall make all reasonable efforts to
cause its Subcontractors and sub consultants to keep accurate and
systematic accounts and records in respect of the Works in such form
and details as will clearly identify relevant time changes and costs.
28.3 The Contractor shall permit the GoN/DP and/or persons appointed by
the GoN/DP to inspect the Site and/or the accounts and records of the
Contractor and its sub-contractors relating to the performance of the
Contract, and to have such accounts and records audited by auditors
appointed by the GoN/DP if required by the GoN/DP. The Contractor’s
attention is drawn to Sub-Clause 73.2 which provides, inter alia, that
112
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
33.Non-
33.1 The Contractor shall not make employment decisions on the basis of
discrimination and personal characteristics unrelated to inherent job requirements. The
Equal Opportunity Contractor shall base the employment relationship on the principle of
equal opportunity and fair treatment, and shall not discriminate with
respect to aspects of the employment relationship, including
recruitment and hiring, compensation (including wages and benefits),
working conditions and terms of employment, access to training,
promotion, termination of employment or retirement, and discipline. In
countries where national law provides for non-discrimination in
employment, the Contractor shall comply with national law. When
national laws are silent on nondiscrimination in employment, the
Contractor shall meet this Sub clause's requirements. Special
measures of protection or assistance to remedy past discrimination or
selection for a particular job based on the inherent requirements of
the job shall not be deemed discrimination.
B. Time Control
34. Program
34.1 Within the time stated in the SCC, after the date of the Letter of
Acceptance, the Contractor shall submit to the Project Manager for
approval a Program showing the general methods, arrangements, order,
113
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
and timing for all the activities in the Works. In the case of a lump sum
contract, the activities in the Program shall be consistent with those in
the Activity Schedule.
34.2 An update of the Program shall be a program showing the actual
progress achieved on each activity and the effect of the progress
achieved on the timing of the remaining work, including any changes to
the sequence of the activities.
34.3 The Contractor shall submit to the Project Manager for approval an
updated Program at intervals no longer than the period stated in the
SCC. If the Contractor does not submit an updated Program within
this period, the Project Manager may withhold the amount stated in the
SCC from the next payment certificate and continue to withhold this
amount until the next payment after the date on which the overdue
Program has been submitted. In the case of a lump sum contract, the
Contractor shall Provide an updated Activity Schedule within 15 days of
being instructed to by the Project Manager.
34.4 The Project Manager’s approval of the Program shall not alter the
Contractor’s obligations. The Contractor may revise the Program and
submit it to the Project Manager again at any time. A revised Program
shall show the effect of Variations and Compensation Events.
35. Extension of
35.1 The Project Manager shall extend the Intended Completion Date if a
the Intended Compensation Event occurs or a Variation is issued which makes it
Completion Date impossible for Completion to be achieved by the Intended
Completion Date without the Contractor taking steps to accelerate
the remaining work, which would cause the Contractor to incur
additional cost.
35.2 The Project Manager shall decide whether and by how much to
extend the Intended Completion Date within 21 days of the Contractor
asking the Project Manager for a decision upon the effect of a
Compensation Event or Variation and submitting full supporting
information at least 21 days prior to the intended completion date. If the
Contractor has failed to give early warning of a delay or has failed to
cooperate in dealing with a delay, the delay by this failure shall not be
considered in assessing the new Intended Completion Date. Along with
full supporting information the contractor shall also submit Performance
Security, Advanced Payment Guarantee and insurance Policy with
extended validity as well as revised work schedule.
36. Acceleration
36.1 When the Employer wants the Contractor to finish before the
Intended Completion Date, the Project Manager shall obtain priced
proposals for achieving the necessary acceleration from the Contractor.
If the Employer accepts these proposals, the Intended Completion
Date shall be adjusted accordingly and confirmed by both the
Employer and the Contractor.
36.2 If the Contractor’s priced proposals for acceleration are accepted by the
Employer, they are incorporated in the Contract Price and treated as a
Variation.
37. Delays
37.1 The Project Manager may instruct the Contractor to delay the start or
Ordered by the progress of any activity within the Works.
Project Manager
114
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
38. Management
38.1 Either the Project Manager or the Contractor may require the other to
Meetings attend a management meeting. The business of a management
meeting shall be to review the plans for remaining work and to deal with
matters raised in accordance with the early warning procedure.
38.2 The Project Manager shall record the business of management
meetings and provide copies of the record to those attending the
meeting and to the Employer. The responsibility of the parties for
actions to be taken shall be decided by the Project Manager either at
the management meeting or after the management meeting and
stated in writing to all who attended the meeting.
39. Early Warning
39.1 The Contractor shall warn the Project Manager at the earliest
opportunity of specific likely future events or circumstances that may
adversely affect the quality of the work, increase the Contract Price, or
delay the execution of the Works. The Project Manager may require the
Contractor to provide an estimate of the expected effect of the future
event or circumstance on the Contract Price and Completion Date.
The estimate shall be provided by the Contractor as soon as
reasonably possible.
39.2 The Contractor shall cooperate with the Project Manager in making
and considering proposals for how the effect of such an event or
circumstance can be avoided or reduced by anyone involved in the
work and in carrying out any resulting instruction of the Project Manager.
C. Quality Control
40.Identifying
40.1 The Project Manager shall check the Contractor’s work and notify the
Defects Contractor of any Defects that are found. Such checking shall not
affect the Contractor’s responsibilities. The Project Manager may
instruct the Contractor to search for a Defect and to uncover and test
any work that the Project Manager considers may have a Defect.
41. Tests
41.1 If the Project Manager instructs the Contractor to carry out a test not
specified in the Specification to check whether any work has a Defect and
the test shows that it does, the Contractor shall pay for the test and any
samples. If there is no Defect, the test shall be a Compensation Event.
42. Correction of
42.1 The Project Manager shall give notice to the Contractor of any Defects
Defects before the end of the Defects Liability Period, which begins at
Completion, and is defined in the SCC. The Defects Liability Period
shall be extended for as long as Defects remain to be corrected.
42.2 Every time notice of a Defect is given, the Contractor shall correct
the notified Defect within the length of time specified by the Project
Manager’s notice.
43.Uncorrected
43.1 If the Contractor has not corrected a Defect within the time specified
Defects in the Project Manager’s notice, the Project Manager shall assess the
cost of having the Defect corrected, and the Contractor shall pay this
amount.
D. Cost Control
44. Contract Price
44.1 In the case of a Unit Rate contract, the Bill of Quantities shall
contain priced items for the Works to be performed by the Contractor.
The Bill of Quantities is used to calculate the Contract Price. The
115
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
Contractor will be paid for the quantity of the work accomplished at the
rate in the Bill of Quantities for each item.
44.2 In the case of a lump sum contract, the Activity Schedule shall contain
the priced activities for the Works to be performed by the Contractor. The
Activity Schedule is used to monitor and control the performance of
activities on which basis the Contractor will be paid. If payment for
Materials on Site shall be made separately, the Contractor shall show
delivery of Materials to the Site separately on the Activity Schedule.
45. Changes in the
45.1 In the case of an Unit Rate contract:
Contract Price
(a) If the final quantity of the work done differs from the quantity in the
Bill of Quantities for the particular item by more than 25 percent,
provided the change exceeds 2 percent of the Initial Contract Price,
the Project Manager shall adjust the rate to allow for the change.
(b) The Project Manager shall not adjust rates from changes in
quantities if thereby the Initial Contract Price is exceeded by more
than 10 percent, except with the prior approval of the Employer.
(c) If requested by the Project Manager, the Contractor shall provide
the Project Manager with a detailed cost breakdown of any rate in
the Bill of Quantities.
45.2 In the case of a lump sum contract, the Activity Schedule shall be
amended by the Contractor to accommodate changes of Program or
method of working made at the Contractor’s own discretion. Prices in the
Activity Schedule shall not be altered when the Contractor makes such
changes to the Activity Schedule.
46. Variations
46.1 All Variations shall be included in updated Programs, and, in the case
of a lump sum contract, also in the Activity Schedule, produced by the
Contractor.
46.2 The Contractor shall provide the Project Manager with a quotation for
carrying out the Variation when requested to do so by the Project
Manager. The Project Manager shall assess the quotation, which
shall be given within seven (7) days of the request or within any
longer period stated by the Project Manager and before the Variation
is ordered.
46.3 If the Contractor’s quotation is unreasonable, the Project Manager
may order the Variation and make a change to the Contract Price,
which shall be based on the Project Manager’s own forecast of the
effects of the Variation on the Contractor’s costs.
46.4 If the Project Manager decides that the urgency of varying the work
would prevent a quotation being given and considered without
delaying the work, no quotation shall be given and the Variation shall
be treated as a Compensation Event.
46.5 The Contractor shall not be entitled to additional payment for costs that
could have been avoided by giving early warning.
46.6 In the case of an Unit Rate contract, if the work in the Variation
corresponds to an item description in the Bill of Quantities and if, in the
opinion of the Project Manager, the quantity of work above the limit
stated in GCC 45.1 or the timing of its execution do not cause the cost
per unit of quantity to change, the rate in the Bill of Quantities shall be
116
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
used to calculate the value of the Variation. If the cost per unit of quantity
changes, or if the nature or timing of the work in the Variation does not
correspond with items in the Bill of Quantities, the quotation by the
Contractor shall be in the form of new rates for the relevant items of work.
47. Cash Flow
47.1 When the Program, or, in the case of a lump sum contract, the Activity
Forecasts Schedule, is updated, the Contractor shall provide the Project
Manager with an updated cash flow forecast.
48. Payment
48.1 The Contractor shall submit to the Project Manager monthly statements
Certificates of the estimated value of the work executed less the cumulative amount
certified previously.
48.2 The Project Manager shall check the Contractor’s monthly statement
and certify the amount to be paid to the Contractor within 30 days of
submission by contractor.
48.3 The value of work executed shall be determined by the Project Manager.
48.4 The value of work executed shall comprise:
(a) In the case of an Unit Rate contract, the value of the quantities
of work in the Bill of Quantities that have been completed; or
(b) In the case of a lump sum contract, the value of work executed
shall comprise the value of completed activities in the Activity
Schedule.
48.5 The value of work executed shall include the valuation of Variations
and Compensation Events.
48.6 The Project Manager may exclude any item certified in a previous
certificate or reduce the proportion of any item previously certified in
any certificate in the light of later information.
49. Payments
49.1 Payments shall be adjusted for deductions for advance payments and
retention. The Employer shall pay the Contractor the amounts certified
by the Project Manager within 30 days of the date of each certificate. If
the Employer makes a late payment, the Contractor shall be paid
interest as indicated in the SCC on the late payment in the next
payment. Interest shall be calculated from the date by which the payment
should have been made up to the date when the late payment is made.
49.3 Items of the Works for which no rate or price has been entered in BOQ
shall not be paid for by the Employer and shall be deemed covered by
other rates and prices in the Contract.
50. Compensation
50.1 The following shall be Compensation Events:
Events
(a) The Employer does not give access to a part of the Site by the Site
Possession Date pursuant to GCC 26.1.
117
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
118
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
4 For complex Works involving several types of construction work with different inputs, a family of
Formulae will be necessary. The various items of Day work may also require different formulae, depending
on the nature and source of the inputs
5 Insert a figure for factor A only where there is a part of the Contractors’ expenditures which will not be
subject to fluctuation in cost or to compensate for the unreliability of some indices. A should normally be
0.15. The sum of A, b, c, d, etc., should be one.
119
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
120
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
in accordance with GCC 70.1, half the total amount retained shall be
repaid to the Contractor and half when the Contractor has submitted
the evidence of submission of tax return to the concerned Internal
Revenue Office. The Contractor may substitute retention money with
an “on demand” bank guarantee having validity at least one month more
than the end of defect liability period if:
(a) at least eighty (80) percent of the whole works have been completed,
(b) progress of the works is satisfactory in accordance with the Contract
as per approved work schedule
(c) it can be assured that the works can be completed at the intended
completion date
55. Liquidated
55.1 The Contractor shall pay liquidated damages to the Employer at the rate
Damages
per day stated in the SCC for each day that the Completion Date is later
than the Intended Completion Date. The total amount of liquidated
damages shall not exceed the amount defined in the SCC. The
Employer may deduct liquidated damages from payments due to the
Contractor. Payment of liquidated damages shall not affect the
Contractor’s liabilities.
55.2 If the Intended Completion Date is extended after liquidated damages
have been paid, the Project Manager shall correct any overpayment of
liquidated damages by the Contractor by adjusting the next payment
certificate. The Contractor shall be paid interest on the overpayment,
calculated from the date of payment to the date of repayment, at the
rates specified in GCC.49
56. Bonus
56.1 The Contractor shall be paid a Bonus calculated at the rate per
calendar day stated in the SCC for each day (less any days for
which the Contractor is paid for acceleration) that the Completion is
earlier than the Intended Completion Date. The Project Manager shall
certify that the Works are complete, although they may not be due to be
complete.
57. Advance
57.1 The Employer shall make advance payment to the Contractor of the
Payment
amounts stated in the SCC in two equal installments by the date
stated in the SCC, against provision by the Contractor of an
unconditional bank guarantee from Commercial Bank or Financial
Institution eligible to issue Bank Guarantee as per prevailing Law in
Nepal.in a form acceptable to the Employer in amounts equal to the
advance payment. The guarantee shall remain effective until the
advance payment has been repaid, but the amount of the guarantee
shall be progressively reduced by the amounts repaid by the Contractor.
Interest shall not be charged on the advance payment.
57.2 The Contractor is to use the advance payment only to pay for
Equipment, Plant, Materials, and mobilization expenses required
specifically for execution of the Contract. The Contractor shall
121
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
58. Securities
58.1 The Performance Security, including any additional security required
as per ITB 35.5 and ITB 40.1, shall be provided to the Employer no
later than the date specified in the Letter of Acceptance and shall be
issued in an amount specified in the SCC, by a Commercial Bank
or Financial Institution eligible to issue Bank Guarantee as per
prevailing Law in Nepal acceptable to the Employer, and denominated
in Nepalese Rupees. The Performance Security shall be valid until a
date 30 days from the date of issue of the Defect Liability Certificate in
the case of a bank guarantee.
Any additional performance security required as per ITB 35.5 shall be
valid until a date 30 days from the date of issue of the certificate of
Completion in the case of a bank guarantee.
Any additional performance security required as per ITB 40.1 shall be
valid until a date 30 days from the date of issue of the certificate of DLP
in the case of a bank guarantee.
58.2 The performance security issued by any foreign Bank outside
Nepal must be counter guaranteed by Commercial Bank or Financial
Institution eligible to issue Bank Guarantee as per prevailing Law in
Nepal.
59. Dayworks
59.1 If applicable, the Dayworks rates in the Contractor’s Bid shall be used
for small additional amounts of work only when the Project Manager
has given written instructions in advance for additional work to be paid
for in that way.
59.2 All work to be paid for as Dayworks shall be recorded by the
Contractor on forms approved by the Project Manager. Each
completed form shall be verified and signed by the Project
Manager within two days of the work being done.
59.3 The Contractor shall be paid for Dayworks subject to obtaining signed
Dayworks forms.
60. Cost of
60.1 Loss or damage to the Works or Materials to be incorporated in the
Repairs Works between the Start Date and the end of the Defects Correction
periods shall be remedied by the Contractor at the Contractor’s cost
if the loss or damage arises from the Contractor’s acts or omissions.
F. Force Majeure
61. Definition of
61.1 In this Clause, “Force Majeure” means an exceptional event or
Force Majeure
circumstance,
122
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
61.2 Force Majeure may include, but is not limited to, exceptional events
or circumstances of the kind listed below, so long as conditions (a) to
(d) above are satisfied:
(a) war, hostilities (whether war be declared or not), invasion, act of
foreign enemies;
(b) rebellion, terrorism, sabotage by persons other than the
Contractor’s Personnel, revolution, insurrection, military or
usurped power, or civil war;
(c) riot, commotion, disorder, strike or lockout by persons other than
the Contractor’s Personnel;
(d) munitions of war, explosive materials, ionizing radiation or
contamination by radio-activity, except as may be attributable to
the Contractor’s use of such munitions, explosives, radiation or
radio-activity; and
(e) natural catastrophes such as earthquake, hurricane, typhoon or
volcanic activity.
62. Notice of Force
62.1 If a Party is or will be prevented from performing its substantial
Majeure
obligations under the Contract by Force Majeure, then it shall give
notice to the other Party of the event or circumstances constituting the
Force Majeure and shall specify the obligations, the performance of
which is or will be prevented. The notice shall be given within 14 days
after the Party became aware, or should have become aware, of the
relevant event or circumstance constituting Force Majeure.
62.2 The Party shall, having given notice, be excused performance of its
obligations for so long as such Force Majeure prevents it from
performing them.
123
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
63.2 A Party shall give notice to the other Party when it ceases to be
affected by the Force Majeure.
64. Consequences
64.1 If the Contractor is prevented from performing its substantial
of Force Majeure
obligations under the Contract by Force Majeure of which notice has
been given under GCC 62, and suffers delay and/or incurs Cost by
reason of such Force Majeure, the Contractor shall be entitled subject
to GCC 30 to
(a) an extension of time for any such delay, if completion is or will
be delayed, under GCC35 ; and
(b) if the event or circumstance is of the kind described in sub-
paragraphs (a) to (d) of GCC 61.2 and, in the case of
subparagraphs (b) to (d), occurs in the Country, payment of any
such Cost, including the costs of rectifying or replacing the
Works and/or Goods damaged or destructed by Force Majeure,
to the extent they are not indemnified through the insurance
policy referred to in GCC 19.
64.2 After receiving this notice, the Project Manager shall proceed in
accordance with GCC 10 to agree or determine these matters.
65. Force Majeure
65.1 If any Subcontractor is entitled under any contract or agreement
Affecting
relating to the Works to relief from force majeure on terms additional
Subcontractor
to or broader than those specified in this Clause, such additional or
broader force majeure events or circumstances shall not excuse the
Contractor’s nonperformance or entitle him to relief under this Clause.
66. Optional
66.1 If the execution of substantially all the Works in progress is prevented
Termination,
for a continuous period of 90 days by reason of Force Majeure of
Payment and
which notice has been given under GCC 62, or for multiple periods
Release
which total more than 150 days due to the same notified Force
Majeure, then either Party may give to the other Party a notice of
termination of the Contract. In this event, the termination shall take
effect 7 days after the notice is given, and the Contractor shall proceed
in accordance with GCC 72.5.
66.2 Upon such termination, the Project Manager shall determine the value
of the work done and issue a Payment Certificate, which shall include
(a) the amounts payable for any work carried out for which a price
is stated in the Contract;
(b) the Cost of Plant and Materials ordered for the Works which
have been delivered to the Contractor, or of which the
Contractor is liable to accept delivery: this Plant and Materials
shall become the property of (and be at the risk of) the Employer
when paid for by the Employer, and the Contractor shall place
the same at the Employer’s disposal;
124
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
125
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
(b) reject the application, giving reasons and specifying the work
required to be done by the Contractor to enable the Taking-Over
Certificate to be issued. The Contractor shall then complete this
work before issuing a further notice under this Sub-Clause.
69.3 If the Engineer fails either to issue the Taking-Over Certificate or
to reject the Contractor’s application within the period of 30 days,
and if the Works or Section (as the case may be) are substantially
completed in accordance with the Contract, the Taking-Over
Certificate shall be deemed to have been issued on the last day of
that period.
70. Final Account
70.1 The Contractor shall supply the Project Manager with a detailed account
of the total amount that the Contractor considers payable under the
Contract before the end of the Defects Liability Period. The Project
Manager shall issue a Defects Liability Certificate and certify any final
payment that is due to the Contractor within 60 days of receiving the
Contractor’s account if it is correct and complete. If it is not, the
Project Manager shall issue within 60 days a schedule that states
the scope of the corrections or additions that are necessary. If the
Final Account is still unsatisfactory after it has been resubmitted, the
Project Manager shall decide on the amount payable to the Contractor
and issue a payment certificate.
71. Operating and
71.1 If “as built” Drawings and/or operating and maintenance manuals are
Maintenance required, the Contractor shall supply them by the dates stated in the
Manuals SCC.
71.2 If the Contractor does not supply the Drawings and/or manuals by the
dates stated in the SCC pursuant to GCC 71.1, or they do not receive
the Project Manager’s approval, the Project Manager shall withhold the
amount stated in the SCC from payments due to the Contractor.
72. Termination
72.1 The Employer may terminate the Contract at any time if the
contractor;
a. does not commence the work as per the Contract,
b. abandons the work without completing,
c. fails to achieve progress as per the Contract.
72.2 The Employer or the Contractor may terminate the Contract if the
other party causes a fundamental breach of the Contract.
72.3 Fundamental breaches of Contract shall include, but shall not be limited
to, the following :
(a) The Contractor uses the advance payment for matters other than the
contractual obligations,
(b) the Contractor stops work for 30 days when no stoppage of work is shown
on the current Program and the stoppage has not been authorized by
the Project Manager;
(c) the Project Manager instructs the Contractor to delay the progress of the
Works, and the instruction is not withdrawn within 30 days;
(d) the Employer or the Contractor is made bankrupt or goes into
liquidation other than for a reconstruction or amalgamation.
(e) a payment certified by the Project Manager is not paid by the Employer
126
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
127
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
128
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
79.3 For purposes of GCC 79.2, “origin” means the place where the
materials and equipment are mined, grown, produced, or
manufactured, and from which the services are provided. Materials
and equipment are produced when, through manufacturing,
processing, or substantial or major assembling of components, a
commercially recognized product results that differs substantially in its
basic characteristics or in purpose or utility from its components.
80. Project
80.1 The Project Manager’s duties and authorities are restricted to the
Manager’s Duties extent as stated in the SCC.
and Authorities
129
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
130
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
not Personally bound or liable for the act or obligations of the Employer under
Liable the Contract or answerable for any default or omission in the
observance or performance of any of act, matter or thing which
are herein contained.
87. Approval of
87.1 No explosives of any kind shall be used by the Contractor without the
Use of Explosives prior consent of the Employer in writing and the Contractor shall
provide, store and handle these and all other items of every kind
whatsoever required for blasting operations, all at his own expense in a
manner approved in writing by the Employer.
88 Compliance 88.1 The Contractor shall comply with all relevant ordinances, instructions
with and regulations which the Government, or other person or persons
Regulations for having due authority, may issue from time to time regarding the
Explosives handling, transportation, storage and use of explosives.
89. Permission for
89.1 The Contractor shall at all times maintain full liaison with and
Blasting inform well in advance, and obtain such permission as is required
from all Government authorities, public bodies and private parties
whatsoever concerned or affected, or likely to be concerned or affected
by blasting operation.
90. Records of
90.1 Before the beginning of the Defects Liability Period, the Contractor shall
Explosives account to the satisfaction of the Project Manager for all explosives
brought on to the Site during the execution of the Contract and
the Contractor shall remove all unused explosives from the Site on
completion of works when ordered by the Project Manager.
91.Traffic
91.1 The Contractor shall include the necessary safety procedures regarding
Diversion and pedestrian traffic diversion that is needed in execution of the works.
The Contractor shall include in his costing of works, any temporary
works or diversion that are needed during the construction period. All
traffic diversion should be designed for the safety of both the motoring
public and the men at work. It shall ensure the uninterrupted flow of
traffic and minimum inconvenience to the public during the period
concerned. As such, adequate warning signs, flagmen and other
relevant safety precautionary measures shall be provided to warn
motorists and pedestrians well ahead of the intended diversion as
directed by the Project Manager. All traffic devices used shall be
designed in accordance with the instruction of Project Manager.
131
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
The following Special Conditions of Contract shall supplement the GCC. Whenever there is a conflict,
the provisions herein shall prevail over those in the GCC
132
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
GCC 1.1 (v) The Intended Completion Date for the whole of the Works shall be 500 (Five
Hundred) Days from the date of Contract.
The Project Manager is project chief of the Chainpur Seti Hydroelectric Project
GCC 1.1(bb)
& 10.1
The Project Manager and Engineer are synonyms.
GCC 1.1 (ee) The Site is located at 16 km North from Chainpur (District Headquarter) of
Bajhang District of Far Western Province
GCC 1.1 (hh) The Start Date shall be 21(Twenty One) days from date of signing of
Contract.
GCC 1.1 (ll) The Works consist of Construction of adit tunnel including Excavation of
tunnel, Fiber Shotcrete ,wiremesh Shotcrete ,Ribs work, etc.
GCC 2.3(i) The following documents also form part of the Contract: Day Work
Schedule, Memorandum of Understanding (MoU).
GCC 11.1 The Project Manager may delegate any of his duties and responsibilities.
GCC 14.1 Schedule of other contractors: For Adit VI, Construction shall start after the
track opening of Access road of Contract ID: CSHEP-CW-NCB-02-078/79.
133
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
GCC 19.1 The minimum insurance amounts and deductibles shall be:
1. The minimum cover for loss of or damage to the Works, Plant and
Materials is: 110% of the Contract Amount.
2. The maximum deductible for insurance of the Works and of Plant and
Materials is: 5,00,000.00 (Five Lakhs).
3. The minimum cover for loss or damage to Equipment is: Full
Replacement Value.
4. The maximum deductible for insurance of Equipment is 10% of
Claimed amount.
5. The minimum for insurance of other property is: 2,000,000(Twenty
Lakhs) with unlimited number of occurrences
6. The maximum deductible for insurance of other property is:
1,00,000.00 (One Lakh).
7. The minimum cover for personal injury or death insurance
i. for the Contractor’s employees is that specified in the Labor act of
Nepal and
ii. for other people is :1,000,000.00(Ten Lakhs) with an unlimited
number of occurrences.
GCC 23.1 The following shall be designed by the Contractor : Not Applicable
GCC 26.1 The Site Possession Date(s) shall be: within Fourteen(14) Days of the signing
of the Agreement
GCC 30.1 The place of arbitration shall be: NEPCA, Kathmandu, Nepal
C. Time Control
GCC 34.1 The Contractor shall submit for approval a Program for the Works within
Thirty (30) days from the date of the Letter of Acceptance.
D. Quality Control
GCC 42.1 The Defects Liability Period is 365 days.
E. Cost Control
GCC 49.1 Interest rate is the minimum rate of any commercial (Class A) bank
approved by Nepal Rastra Bank of Nepal. The minimum rate of interest
is 7.00%.
GCC 53.1 The Contract is subject to price adjustment, and the following information
regarding coefficients does apply.
The coefficients and indices for adjustment of prices in Nepalese Rupees shall
be as specified in the Table of Adjustment Data submitted by bidder together
with the Letter of Price Bid which is approved by the Project manager.
134
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
GCC 53.6 Base Price of Construction Materials applicable for price adjustment shall be
as per the Table of Adjustment Data submitted by Bidder together with the Letter
of Price Bid which is approved by the Project manager.
GCC 53.7 The Price Adjustment amount shall be limited to a maximum of:
For GoN Funded: 25 % (Twenty Five) percentage of the initial Contract
Amount
GCC 55.1 The liquidated damages for the whole of the Works are 0.05 Percent of the
final Contract Price per day. The maximum amount of liquidated damages for
the whole of the Works is 10 Percent of the final Contract Price.
GCC 57.1 The Advance Payments shall be: Ten percent (10%) of the Accepted
Contract Amount (excluding Provisional Sum and VAT) and shall be paid in
two equal installments and to the Contractor.
The first installment of 5% of the accepted Contract Amount shall be made
to the Contractor within 30 days of submission of an acceptable bank
guarantee for the advance payment.
The second installment of the remaining 5% shall be made after the
Contractor completes full mobilization at Site and has submitted insurance
policies after the submission of an acceptable bank guarantee for the advance
payment.
GCC 57.3 Deductions from Payment Certificates will commence in the first certificate in
which the value of works executed exceeds 20% of the Contract Price.
Deduction will be at the rate of 30% of the respective Monthly Interim Payment
Certificate until such time as the advance payment has been repaid; provided
that the advance payment shall be completely repaid prior to the end of 80
% of the approved contract price.
GCC 58.1 i) If bid price of the bidder selected for acceptance is up to 15 (fifteen) percent
below the approved cost estimate, the performance security amount shall be 5
(five) percent of the bid price.
ii) For the bid price of the bidder selected for acceptance is more than 15 (fifteen)
percent below of the cost estimate, the performance security amount shall be
determined as follows:
Performance Security Amount = [(0.85 x Cost Estimate –Bid Price) x 0.5] +
5% of Bid Price.
The Bid Price and Cost Estimate shall be inclusive of Value Added Tax. The
Standard form(s) of Performance Security acceptable to the employer shall be an
Unconditional Bank Guarantee acceptable to the Employer of the type presented
in the Bidding Documents.
The Performance security form shall be in the format of Bidding Document,
Section 9 Contract forms.
135
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
GCC 71.2 The date by which “as built” drawings are required is Within Thirty (30)
days after issuance of Certificate of Completion.
The amount to be withheld for failing to produce “as built” drawings is: NRs:
500,000.00 (Five Lakh).
GCC 72.3 (i) The maximum number of days is: 200 Days.
GCC 80 The Project Manager has to obtain the specific approval of the Employer for
taking any of the following actions :
a. Approving subcontracting of any part of the works under General
Conditions of Contract Clause 13;
b. Certifying additional costs determined under General Conditions of
Contract Clause 50;
c. Determining start date under General Conditions of Contract Clause 1;
d. Determining the extension of the intended Completion Date under
General Conditions of Contract Clause 35;
e. Issuing a Variation under General Conditions of Contract Clause 1 and
46, except in an emergency situation, as reasonably determined by the
Project Manager; emergency situation may be defined as the
situation when protective measures must be taken for the safety of life
or of the works or of adjoining property.
f. Adjustment of rates under General Conditions of Contract Clause 45;
136
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
This Section contains forms which, once completed, will form part of the Contract. The forms for
Performance Security and Advance Payment Security, when required, shall only be completed by
the successful Bidder after contract award.
137
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
Letter of Intent
[on letterhead paper of the Employer]
Title: ……………………………………………….
CC:
[Insert name and address of all other Bidders, who submitted the bid]
138
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
Letter of Acceptance
[on letterhead paper of the Employer]
Date: ……………………..
You are hereby instructed to contact this office to sign the formal contract agreement within 15
days with Performance Security of NRs. ………. in accordance with the Conditions of Contract,
using for that purpose the Performance security Form included in Section X (Contract Forms) of
this Bidding Document.
139
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
Contract Agreement
THIS AGREEMENT made the ...............................dayof…..between……………………. name
of the Employer ………………(hereinafter “the Employer”), of the one part, and
……………………………name of the Contractor …………………(hereinafter “the Contractor”),
of the other part:
WHEREAS the Employer desires that the Works known as ……………………….... name of the
Contract ..............................should be executed by the Contractor, and has accepted a Bid by
the Contractor for the execution and completion of these Works and the remedying of any defects
in the sum of NRs …..........…..[insert amount of contract price in words and figures including
taxes](hereinafter “the Contract Price”).
2. The following documents shall be deemed to form and be read and construed as part of this
Agreement.This Agreement shall prevail over all other Contract documents.
(a) the Letter of Acceptance;
(b) the Letters of Technical and Price Bid;
(c) the Addenda Nos ................................... Insert addenda numbers if any ……………
(d) the Special Conditions of Contract;
(e) the List of Eligible Countries that was specified in Section V of the bidding document,
(f) the General Conditions of Contract;
(g) the Specification;
(h) the Drawings;
(i) Bill of Quantities (or Schedules of Prices for lump sum contracts), and
(j) Table of Price Adjustment Data
(k)List of Approved Subcontractors [For GoN funded project]
(l) .......................................................[Specify if there are any other document]
4. The Employer hereby covenants to pay the Contractor in consideration of the execution and
completion of the Works and the remedying of defects therein, the Contract Price or such other
sum as may become payable under the provisions of the Contract at the times and in the manner
prescribed by the Contract.
IN WITNESS whereof the parties hereto have caused this Agreement to be executed in
accordance with the laws of Nepal on the day, month and year indicated above.
Signed by ………………………….
for and on behalf the Contractor in the presence of
Signed by…………………………..
for and on behalf of the Employer in the presence of
140
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
In accordance with GCC Sub-Clause 13.1,The following Subcontractors are approved for
carrying out the work as specified below.
Name of Value/Percentage
Description of Works
Subcontractors of subcontract
141
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
Date:
Contract No:
Name of Contract :
To:
Signature Signature
Name : Name :
Designation: Designation:
142
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
Performance Security
(On letterhead paper of the Commercial Bank or Financial Institution eligible
to issue Bank Guarantee as per prevailing Law in Nepal.)
We have been informed that ... ... [insert name of the Contractor] (hereinafter called "the
Contractor") has been notified by you to sign the Contract No. ……………….. [insert reference
number of the Contract] for the execution of ……….. [insert name of contract and brief
description of Works] (hereinafter called "the Contract").
At the request of the Contractor, we... .................................. . [insert name of the Bank] hereby
irrevocably undertake to pay you any sum or sums not exceeding in total an amount of ...............[insert
name of the currency and amount in figures*] (... .......... .. insert amount in words) such sum
being payable in Nepalese Rupees, upon receipt by us of your first demand in writing accompanied
by a written statement stating that the Contractor is in breach of its obligation(s) under the Contract,
without your needing to prove or to show grounds for your demand or the sum specified therein.
…………………………………………
Seal of Bank and Signature(s)
Note:
All italicized text is for guidance on how to prepare this demand guarantee and shall be deleted from the final
document.
The Guarantor shall insert an amount representing the percentage of the Contract Price specified in the
Contract in Nepalese Rupees.
** Insert the date thirty days after the date specified for the Defect Liability Period. The Employer should note
that in the event of an extension of the time for completion of the Contract, the Employer would need to
request an extension of this guarantee from the Guarantor. Such request must be in writing and must be
made prior to the expiration date established in the guarantee. In preparing this guarantee, the Employer
might consider adding the following text to the form, at the end of the penultimate paragraph: “The Guarantor
agrees to a one-time extension of this guarantee for a period not to exceed [six months], in response to the
Employer’s written request for such extension, such request to be presented to the Guarantor before the
expiry of the guarantee”.
143
Nepal Electricity Authority Chainpur Seti Hydroelectric Project (210 MW)
Engineering Services Directorate Bidding Document
We have been informed that ………………has entered into Contract No. ..... Name and Address
of Employer………………name of the Contractor…………… (hereinafter called "the
Contractor")..reference number of the Contract……………dated …………… with you, for the
execution of ...contract and brief description of Works ……………. (hereinafter called "the
Contract").
……………………………………………………
Seal of Bank and Signature(s)
Note:
All italicized text is for guidance on how to prepare this demand guarantee and shall be deleted from the final document.
*The Guarantor shall insert an amount representing the amount of the advance payment in Nepalese Rupees of the
advance payment as specified in the Contract.
** Insert the date Thirty days after the expected completion date. The Employer should note that in the event of an
extension of the time for completion of the Contract, the Employer would need to request an extension of this
guarantee from the Guarantor. Such request must be in writing and must be made prior to the expiration date
established in the guarantee. In preparing this guarantee, the Employer might consider adding the following text to the
form, at the end of the penultimate paragraph: “The Guarantor agrees to a one-time extension of this guarantee for a period
not to exceed [six months], in response to the Employer’s written request for such extension, such request to be presented
to the Guarantor before the expiry of the guarantee”.
144
NEPAL ELECTRICITY AUTHORITY
Durbarmarg, Kathmandu
BIDDING DOCUMENTS
FOR
CONSTRUCTION OF ADIT TUNNELS
(III,V&VI)
VOLUME – II SPECIFICATIONS
June, 2022
KATHMANDU, NEPAL
Bid Document Specifications
1
Bid Document Specifications
Contents
1 PRELIMINARIES AND GENERAL PROVISIONS ..................................................................................... 8
1.1 Reference to other Clauses ........................................................................................................... 8
1.2 The Site.......................................................................................................................................... 8
1.3 Use of Land and Right-of-Way ...................................................................................................... 8
1.4 Access to Site ................................................................................................................................ 8
1.5 Health and Safety .......................................................................................................................... 8
1.5.1 Health, Safety, Environmental and Social Management (HSES) ............................................ 8
1.5.2 Safety Measures..................................................................................................................... 8
1.5.3 Traffic Management............................................................................................................... 9
1.5.4 Medical Services..................................................................................................................... 9
1.6 Environmental Protection ........................................................................................................... 10
1.6.1 General Requirements ......................................................................................................... 10
1.6.2 Spoil Disposal ....................................................................................................................... 10
1.6.3 Erosion Protection ............................................................................................................... 10
1.6.4 Water Pollution .................................................................................................................... 10
1.6.5 Reinstatement of the Site .................................................................................................... 10
1.7 Employer's Use of Contractor's Temporary Works..................................................................... 11
1.8 Materials, Plant and Workmanship ............................................................................................ 11
1.9 Drawings and Design ................................................................................................................... 11
1.10 Site Meetings ............................................................................................................................ 12
1.11 Site Register .............................................................................................................................. 12
1.12 Contractor's Camps, Offices, Canteen, Workshops etc. ........................................................... 12
1.13 Contractor's Other Temporary facilities ................................................................................... 13
1.13.1 Water Supply...................................................................................................................... 13
1.13.2 Sewerage System ............................................................................................................... 13
1.13.3 Solid Wastes ....................................................................................................................... 13
1.13.4 Power Supply ..................................................................................................................... 13
1.13.5 Communication .................................................................................................................. 14
1.13.6 Explosives ........................................................................................................................... 14
1.14 Dewatering ................................................................................................................................ 14
1.15 Equipment and Materials ......................................................................................................... 14
1.16 Quality Assurance and Testing .................................................................................................. 15
1.16.1 General ............................................................................................................................... 15
1.16.2 Quality Assurance Procedure ............................................................................................. 15
2
Bid Document Specifications
3
Bid Document Specifications
4
Bid Document Specifications
5
Bid Document Specifications
6
Bid Document Specifications
7
Bid Document Specifications
The Contractor shall obtain the approval of the Employer for the sitting of all camps, offices,
workshops, temporary roads, etc. necessary for the execution of the Contract. All other use of
land is subject to the approval of the Employer.
8
Bid Document Specifications
a) Provision of proper safety and emergency regulations for the prevention of accidents related
to fire, gas, electricity, traffic, work operations, working environment and other, and for
response to such accidents, should they occur.
c) Safe shoring and suitable barriers and warning signs for any excavation pits.
d) Provision of effective safety clothing including safety helmets and safety boots for all
personnel including the Engineer, the Employer's staff and representatives and any authorized
visitors to the site.
e) Proper control of water including provision of ample dewatering and stand-by pumping
plant.
f) Provision and maintenance of suitable lighting to ensure that the Works are adequately
illuminated at all times, including appropriate spares and stand-by equipment.
g) Provision and maintenance of safe and effective lifting equipment, including ropes, slings,
pulleys and other lifting tackle, each appliance having a valid testing certificate, as appropriate.
i) Provision of notices written in Nepali and English to be erected at points likely to be used by
the public, which shall warn the public of the existence of the Works. These notices shall be in
addition to any statutory requirements demanded of the Contractor.
The plan and procedures shall as a minimum address the following issues:
Access control to the site
Adequate signs and information boards
Speed limits
The traffic management plan and procedures shall be approved by the Engineer.
The Contractor shall have an agreement with at least one of helicopter companies in Kathmandu
for quick evacuation in case of serious accidents.
9
Bid Document Specifications
The first aid station shall be established latest 30 days after the Commencement Date. Prior to
this, Contractor shall provide temporary medical facilities as required for the preliminary and
initial works at site.
The Contractor may dispose of spoil at locations not indicated for such purpose on the Drawings
only after approval by the Engineer. In such case, the Contractor shall submit to the Engineer
in due course a plan for the disposal including detailed drawings as indicated above. All permits
required for spoil deposal from the Authorities shall be obtained by the Contractor.
The Contractor is responsible for providing necessary permits from the Authorities for surface
discharges and effluents.
10
Bid Document Specifications
in accordance with the Contract all his temporary Site installations and structures, surplus
materials, construction plant and equipment, and all rubbish, debris and scrap. The Contractor
shall leave the Site in a clean and tidy condition in all respects to the approval of the Engineer.
Should the Contractor fail to complete this work within 90 days of the issue of the Taking over
Certificate, the Employer may decide to have the work carried out by others and the expense
incurred by the Employer in so doing shall be deducted from the Contractor's final payment.
The Contractor shall keep at his site office a copy of all relevant standards and codes referred
to in the Specifications.
Where the Contractor is not bound by the Contract to a particular standard or code, he shall,
free of charge, furnish the Engineer with two English language copies of the Standard or Code
of Practice according to which he intends to supply materials or carry out work. If not supplied
by the Contractor in due time, Engineer may request such documents. The copies shall then be
provided within 21 days of the request being made. Where proprietary products are specified,
similar products from other manufacturers will be permitted only if the Contractor demonstrates
the product's equivalence to the specified product to the satisfaction of the Engineer.
Where required, the Contractor shall submit for the approval by the Engineer samples and test
reports of proposed materials. Such samples shall be kept by the Employer for reference.
Materials or plant approved by the Employer shall not be replaced by other similar materials or
plant from the same manufacturer or from other manufacturers or suppliers without the prior
approval of the Engineer.
If in the judgement of the Engineer any materials or articles brought onto the Site are found to
be of inferior quality to that required by the Contract or in any way unsuitable, such materials
or plant shall forthwith be removed from the Site.
Certain of the temporary works shall be designed by the Contractor himself. This applies to:
11
Bid Document Specifications
Contractor’s design of such works shall be presented to the Engineer for approval at least 20
days before the work starts.
Minutes will be issued by the Engineer and submitted to the Contractor at Site. If no comments
are given in writing within 7 days from the receipt, the Minutes are deemed to be accepted by
the Contractor.
- Weather conditions
- Visitors.
The exact location and layout of the camp site, buildings and any other facilities as may be
required in connection with the camp shall be approved by the Employer. The Contractor shall
obtain the necessary approval from the relevant authorities in connection with the establishing
of such camps, buildings and other temporary facilities.
Unless otherwise instructed, the Contractor shall dismantle and remove all such structures and
facilities upon completion of the Contract after receiving approval in writing from the Engineer,
12
Bid Document Specifications
and shall restore the site, as far as practicable, to its original condition and leave it neat, tidy
and stable to the satisfaction of the Engineer.
The temporary water supply system shall be designed, constructed, operated and maintained
by the Contractor throughout his work.
Power supply for construction, contractor’s own needs and for general use in offices and
working areas shall be paid in lump sum basis as specified in BoQ .
At the completion of the Works, the temporary power supply facilities and temporary
distribution lines shall be removed unless they are transferred to and taken over by the
Employer.
13
Bid Document Specifications
The location of the diesel generator sets shall be at proper place, but in any case shall not be
within reasonable distance of any housing or accommodation area or public or domestic
buildings unless the Contractor installs special sound insulation to reduce the noise level in any
such area to the satisfaction of the Engineer. All generator plants shall in any case be adequately
silenced and located so as to keep the noise level at the nearest housing or office area below 65
dB(A).
The Contractor shall operate and maintain the diesel generators for uninterrupted construction
power supply and shall store adequate quantity of fuel at the site. Payment for the electric power
supply from the diesel generating equipment shall be made as according to the Bills of
Quantities. The mode of payment includes:
1st Installment = 30 % of the total cost after supply, delivery, installation and Operation of
three (3) generators at Site.
2nd Installment = 30% of the total cost after completion of 400m excavation of Adit tunnels as
certified by the Engineer/Employer.
3rd Installment = 25% of the total cost after completion of 750m excavation of Adit tunnels as
certified by the Engineer/Employer.
After successful completion of construction of adits, the DG sets shall be the property of
contractor.
1.13.5 Communication
The Contractor shall be responsible for the installation, operation, and maintenance throughout
the duration of the Contract of a reliable communication system for his own need on the Site.
This shall include communication between the Site offices, between the offices and the work
places, and externally to the public network.
1.13.6 Explosives
The Contractor shall provide suitable storage and transport for explosives to be used. The
Contractor has full and sole responsibility also during blasting operations and shall adhere to
all relevant laws and regulations of Government of Nepal.
1.14 Dewatering
The Contractor shall plan, design, construct and maintain all necessary works for drainage and
dewatering in order to keep the tunnel face dry and the access in the tunnel in good condition
at all times. The Contractor may enter into an agreement with the main contractor for taking
over the dewatering arrangement. Otherwise the Contractor shall remove all temporary works
for dewatering at completion of his works. The Contractor shall not interfere with the natural
flow of water for any purpose whatsoever without the approval of the Engineer.
14
Bid Document Specifications
dewatering equipment and other key plant and equipment required to ensure progress of the
tunnelling work. The stock of general supplies and construction materials at Site shall always
be sufficient for 15 days uninterrupted operation.
The procedures shall comply with the quality systems the Contractor proposes for use on the
Contract. The procedures shall include as a minimum.
The proposed contract management structure includes identifying personnel responsible for the
overall management and control of the Contract, and the site representatives responsible for
quality control.
1.16.4 Subcontractors
Description of how the quality standards of subcontractors, if any, will be supervised and
monitored.
1.16.5Materials
Description of how materials suppliers will be controlled to ensure that only materials
complying with quality standards are produced and delivered to site, and methods for
identifying and removing from the site any non-conforming materials.
1.16.7 Non-Conformance
Details of how materials or Works, which do not conform to specified requirements, will be
identified, corrective action determined, evidence of corrective action being taken and methods
to avoid future non-conformance.
15
Bid Document Specifications
The Contractor shall provide required tools, consumables, forms, etc. and shall have the
responsibility of carrying out all testing of materials according to the Specifications and as
directed by the Engineer, and shall supply the Engineer with two copies of the results of each
test on approved printed forms. A third copy of the results shall be retained in the laboratory.
The Engineer will witness the testing at his own discretion. At the commencement of the Works
all testing equipment shall be calibrated to ensure accuracy of the testing in accordance with
the relevant Standards. The Contractor shall perform additional calibration from time to time
to ensure correctness and accuracy of the equipment and shall ensure that all equipment is kept
in good working order.
A) Laboratory Test: This tests includes the test at laboratory. The Contractor may set the
testing equipments at the site office allocated for these type of tests. The numbers of
test include:
16
Bid Document Specifications
B) Insitu Tests
Dialatometer Test
Block Shear Test
Core Drilling Works
Any required testing works where no provision have been made for testing in the site laboratory
shall be carried out at a qualified government or commercial laboratory in Nepal as approved
by the Engineer. Contractor shall arrange and pay for the test and no separate payment will
done for such works. The payment of such laboratory works shall be made as specified in the
Bills of Quantities after the completion of tests.
2nd Installment = 80 % after the completion of all tests of the project as certified by
Engineer/Employer.
1.19 Road
Access roads should be constructed for adit III at Rumalia Gad, adit V at Basti Gaun and adit
VI at left bank of Sitalikhola. At least one vehicle should easily pass along the road. The
payment of access road shall be done in running meter basis as specified in the Bill of
Quantities.
17
Bid Document Specifications
2 SURVEYING WORK
2.1 Scope
This chapter specifies requirements for all surveying works, above ground and underground.
General surveys will not be paid separately. Costs for all the survey works shall be included in
the unit rates of the Priced Bill of Quantities.
Based on these data, the Contractor shall establish all additional control points and benchmarks
necessary to determine the exact alignment of the access tunnel. It is the Contractor's
responsibility to maintain all control points. Control points shall be the centre of a 12 mm
diameter pin set to protrude 3 mm above the top of a 0.25 x 0.25 x 0.30 m deep concrete block,
embedded 0.25 m into the ground. The level and/or other markings shall be painted on the
surface of the concrete block as directed by the Engineer.
The Contractor shall set out the lines and levels of surface excavation and earth works at
intervals of not more than 25 m or as required for constructing the works. For the tunnel
excavation the Contractor shall establish, and continuously extend, an at all time available
alignment and benchmark control system for checking the location of the working face and
setting out the next round. A properly maintained laser based system is required. Tunnel control
surveys, based on the GPS basic control network, shall be carried out when the tunnel has been
excavated through the curve and further 200 m of the straight alignment. A comprehensive
report from such basic controls shall be presented to the Engineer.
18
Bid Document Specifications
During excavation the Contractor shall use a continually operating laser-based guidance
system. Geometric control shall take place as soon as possible after excavation, and before any
application of sprayed concrete.
The Contractor shall put chainage marks on the tunnel wall at 10m intervals. The chainage
marking shall be carried out with clearly visible spray paint, and the accuracy shall be within
250 mm.
The Contractor shall take full responsibility for the correctness and accuracy of his survey work
and for the actions of the personnel engaged in it. He shall supply all such stakes, templates,
ranges, gauges, precision survey instruments and other tools and materials required, and all
labour necessary in setting out and checking any part of the work.
The Contractor shall submit comprehensive reports on all his survey and setting-out work, for
control and approval by the Engineer. Any control by the Engineer shall not relieve the
Contractor of his full responsibility for the accuracy of measurements and for structures, and
parts thereof, having positions and dimensions within the tolerances specified.
e) Provide materials, tools, stakes, marks and an adequate number of assistants as directed by
the Engineer
f) Clear bushes, remove obstacles and level off ground to a required extent for the Engineer's
auxiliary surveys
Permanent survey points and benchmarks shall be firmly anchored to solid rock or to concrete
structures by grouted bolts. A clearly visible template in stainless steel shall, similarly, be
anchored next to the point where the number, designation and geodetic data of the point are
19
Bid Document Specifications
clearly and durably engraved. Exact location and installation details shall be presented for and
approved by the Engineer.
The Contractor shall carry out and provide all personnel, equipment and materials required to
effectuate surveys and to determine the quantities of work performed. Measurement of existing
surface profiles, intermediate and final excavation and fill lines and related fieldwork shall be
carried out as specified in the Contract or as required for proper documentation of records or
and as approved by the Engineer.
All the survey works required in works items shall be included in the rate of work items in the
bill of quantities. No separate pay shall be made under the heading of surveying works.
20
Bid Document Specifications
3 EARTHWORKS
3.1 General
Earthworks shall refer to site clearance and work carried out in earth (soil) and rock materials.
Rock excavation is treated in Chapter 5.
Unless otherwise specified, the Contractor shall carry out all earthworks in accordance with
direction of the engineer. The Contractor shall be responsible for the management and sorting
of all excavated and borrowed materials to enable the placement and disposal of materials in
accordance with the Contract. Excavated materials shall, according to their nature and to the
Contractor's materials management plan, be placed as fills in their final locations in the Works,
stockpiled for later placement, or removed to a nominated or approved spoil disposal area. All
excavated materials belong to the Employer and no material shall be removed from the Site
without the written approval of the Engineer.
The design lines and levels of excavations shall be defined as those shown on the Drawings or
specified in the Contract, or as adjusted or otherwise determined by the Engineer.
Excavations shall be taken to the design lines and levels or to such other limits as the Contractor
may require enabling him to construct the Works in accordance with the Contract. Excavation
beyond the design lines and levels made without the Engineer's direction or approval, including
but not limited to, excavation to provide working space and excavation below approved
stripping levels, shall be backfilled with approved material unless otherwise specified or
approved, and at the Contractor's expense. Save and except as specified below, the Contractor,
having due regard for safety and stability considerations, shall bear sole responsibility for
determining the method and extent of all excavations, and no warranty is given or implied by
the Employer that excavations will be stable under all conditions if excavated to the design
lines and levels. The exceptions to the foregoing shall be the following works, in respect of
which the Engineer shall specify the final extent of excavations:
Permanent batters of excavations;
Foundations surfaces for structures and fills forming part of the Permanent Works.
3.1.1 Definitions
The following definitions shall apply to earthworks:
1) Topsoil is defined as the top layer of soil containing fine roots and decomposed organic
matter.
21
Bid Document Specifications
2) Soil is defined as all materials other than topsoil or rock. Weathered rock that can be
excavated by thirty tons excavator with backhoe with teeth, or equivalent equipment, and
blocks less than 1 m³ shall be classified as soil.
3) Rock is defined as all materials which require blasting, or the use of compressed air drilling,
or the use of pneumatic tools for their removal, and which cannot be excavated by thirty tons
excavator with backhoe with teeth, or equivalent equipment. Boulders larger than 1 m3 shall
be considered as rock.
4) Fill includes the supply, hauling, placing and compaction of suitable soil or rock materials
as backfill, embankments etc. Fill shall include the supply, hauling, placing, compaction and
placing suitable soil or rock materials in backfill or embankment fill, in accordance with these
Specifications and to the lines, levels, grades, dimensions and cross sections shown on the
drawings or as required by the Engineer.
a) Suitable material shall comprise all material that is acceptable for use in the works and which
is capable of being compacted to form a stable fill in accordance with the Specifications having
side slopes as indicated on the Drawings.
c) Structural backfill shall comprise blasted rock or sandy gravel. The material shall be well
graded. Contents of fines (passing sieve size 0.075 mm) shall be maximum 5%. Maximum
stone size shall be 2/3 of the thickness of each compaction layer and maximum 300 mm.
d) Rockfill shall comprise blasted rock of high permeability. Contents of fines (passing sieve
size 0.075 mm) shall be maximum 5 % and maximum stone size 2/3 of the given layer
thickness. High Quality Rockfill shall be defined as rockfill produced from rock with a uniaxial
compressive strength of minimum 40 MPa and weathered to a degree not more than “slightly
weathered”.
e) Drainage zones shall consist of processed blasted rock or gravel/stones of size 50 - 100 mm.
f) Filter zones shall consist of 0 - 60 mm blasted rock or sandy gravel with maximum 2 % fines
passing sieve size 0.075 mm (non-cohesive). Filters next to core materials in earth or rockfill
dams shall be in accordance to the filter criteria of ICOLD, Bulletin 95, 1994.
g) Low permeability materials shall comprise clayey or silty materials with 20 - 75% passing
sieve size 0.075 mm and maximum particle size 100 mm and placed at a moisture content at
approximately 2 % above the optimum water content (AASHTO T99).
22
Bid Document Specifications
The list of standards for Earthworks includes, but is not limited to, the following standards:
BS 6031 Code of Practice for Earthworks
BS EN 1997-1 Eurocode 7: Geotechnical Design – Part 1: General Rules
AASHTO T99 Standard Method of Test for the Moisture-Density Relations of
Soils Using a 2.5 kg Rammer and a 305 mm Drop (modified Proctor test)
AASHTO T193 Standard Method of Test for the California Bearing Ratio
3.1.3 Documents
The Contractor shall prepare and submit documents to the Engineer in accordance with
requirements in Chapter 1 Preliminaries and general provisions, and the following Table 3-1:
23
Bid Document Specifications
Attention is directed to the Contractor's obligations under Nepalese law and under this Contract
with regard to damage, particularly with regard to protection of property and landscape and to
responsibility for damage claims.
Existing roads, property, utilities, services and areas designated for preservation shall be
protected from damage that could result from the Contractor's operations.
3.2.2 Clearing
Clearing shall consist of the removal and disposal of everything above ground level including
overhanging branches except those items the Engineer directs to be left undisturbed. The
material to be cleared shall include, but not be limited to trees, stumps, logs, bushes,
undergrowth, grass, crops, loose vegetable matter and structures unless provided for elsewhere.
Felling, trimming or removal of trees shall be restricted to the minimum practicable for the
execution of the Works. The Contractor shall protect from damage all trees designated by the
Engineer. Except for large trees, clearing shall not extend more than 3 m beyond the limits of
excavation or fill without the Engineer's written permission. The Contractor shall demolish,
break up and remove any structure and superficial obstructions on the Site that could be in the
way for or otherwise affect the Works, unless such structures or obstructions are designated for
preservation. He shall clear each part of the Site at such times and to the extent required and
approved by the Engineer. Materials removed in clearing operations shall be burned to their
minimum practical volume and buried in spoil disposal areas with a minimum cover of 500
mm of earth and/or rock spoil, or shall be otherwise disposed of or stored according to the
Environmental Management and Action Plan or as approved by the Engineer. Burning of
cleared materials shall be done in such a manner and in such locations as to cause the least fire
risk. The Contractor shall take special precautions to prevent fire from spreading and shall have
available at all time’s suitable equipment and supplies to prevent and suppress any fire.
3.2.3 Grubbing
Grubbing shall consist of the removal and disposal of stumps and roots to a depth of at least
200 mm below cleared level. Any holes left below permanent level after grubbing of stumps,
roots etc. shall be backfilled with suitable material and compacted in accordance with these
specifications. Grubbing of channels and ditches will be required only to the depth necessitated
by the excavation within these areas.
24
Bid Document Specifications
The stockpiled topsoil shall be used for reinstatement of excavated areas and for landscaping
as directed by the Engineer.
The Contractor shall notify the Engineer sufficiently in advance of the beginning of any
excavation so that profiles and measurements may be taken of the undisturbed ground.
These measurements shall be performed by the Contractor. The natural ground adjacent
to the planned excavations shall not be disturbed without permission of the Engineer.
Excavated materials shall, according to their nature and to the Contractor's materials
management plan, be placed as fills in their final locations in the Works or stockpiled for
later placement, or removed to a nominated or approved spoil disposal area. Boulders
and rock suitable for erosion protection shall be sorted out and stored separately for later
use as instructed by the Engineer. All excavated materials belong to the Employer and no
material shall be removed from the Site without the written approval of the Engineer.
Any excess excavation outside the design limits shall be made good by backfilling with
suitable material compacted in accordance with the Specifications, and at the
Contractor's expense.
Boulders, logs and other unsuitable and non-approved material encountered in excavation shall
be removed.
The cut slopes shall be cleared of all loose and unstable stones and boulders. Excavations shall
be cleaned of all loose and disturbed material and cut to a firm surface, either levelled or
terraced, as specified or shown on the Drawings or directed by the Engineer.
Stones and boulders that jut out of the excavated surface with more than 100 mm are not
acceptable in permanent cut slopes. The Contractor shall remove such stones and boulders to a
depth of min. 500 mm normal to the slope line and build up the resulting hollows with materials
approved by the Engineer so as to ensure an even and solid surface. Demolition by drilling and
blasting or by hydraulic chisel hammer may be necessary before excavation and shall be
included in the prices for the excavation work. Necessary ditches shall be excavated together
with the main excavation. The Contractor shall make all necessary precautions to take care of
surface water during the construction period without causing erosion damage. All ditches shall
have proper gradient towards natural run-off, ditches or pump sumps. Reference is made to
Chapter 8 Drainage and erosion protection.
Shaping of the excavated surfaces, including removal of stones and boulders as specified above,
25
Bid Document Specifications
and compaction of the bottom when required shall be included in the prices for the excavation
work.
No warranty is given or implied by the Employer that temporary excavations will be stable
under all conditions if excavated to the design lines and levels.
All the necessary measures, efforts and actions to ensure sufficient stability and safety of
temporary excavations/slopes for which the Contractor is responsible shall be included in the
prices for the excavation work.
Proposed excavation plan, stability calculations and possible measures to ensure satisfactory
stability of the temporary cuts and satisfactory safety conditions shall be submitted to the
Engineer for approval minimum 21 days prior to the start of excavation.
Special care shall be taken not to disturb the bottom of the excavation. When, in the opinion of
the Engineer, the foundation material is soft, dirty or otherwise unsuitable, such material shall
be replaced by suitable compacted structural backfill material or concrete as specified or shown
on the Drawings or directed by the Engineer. If foundation fill material is required, such
material shall be placed and compacted in layers not more than 150 mm thick to minimum 100
percent MDD (AASHTO T 99).
No excavated suitable material other than surplus to requirements shall be spoiled or removed
from the Site except on the direction of the Engineer. Should the Contractor be permitted to
remove suitable material from the Site to suit his operational procedure then he shall make good
at his own expense any deficit of filling that might arise there from.
Where excavation reveals a combination of suitable and unsuitable materials and the Engineer
considers it practicable, the Contractor shall carry out the excavation in such a manner that the
26
Bid Document Specifications
suitable materials are excavated separately for use in the works without being contaminated by
the unsuitable materials.
All materials considered as unsuitable by the Engineer shall be removed from road subgrades
or final excavated or filled levels to such a depth as the Engineer directs and replaced with
suitable material compacted in compliance with the Specifications.
a) Clearing and Grubbing shall not be measured for payment. Costs for cleaning and grubbing
shall be deemed to be included in the pay items stated in the Bill of Quantities.
b) Soil excavation shall be measured by volume in its natural state. Measurement of soil
excavation shall be made based on cross sections of the terrain after topsoil excavation and to
the exposed and cleaned rock surface where relevant, and to the lines, grades, dimensions, and
cross section shown on the Drawings or directed by the Engineer.
The quantities measured as specified in b) to above shall be paid at the contract prices included
in the Bill of Quantities, which prices and payment shall constitute full compensation for
furnishing all materials and works required to complete the specified work items according to
the requirements of the contract.
For all earthworks shaping, cleaning and other finishing of surfaces in cut and fill shall be
deemed to be included in the excavation or fill except where a separate item is included in the
Bill of Quantities for such work. Furthermore, all loading and transport to fill or spoil, and all
works required at the place of disposal, shall be inclusive. Any extra handling of materials if
required will not be measured and paid.
27
Bid Document Specifications
4.1 Scope
4.1.1 Coverage
This chapter specifies requirements for drilling of holes for ground water and seepage control
and all exploratory drilling and grouting in order to explore and modify the properties of the
rock through which the Works are to be constructed. The extent of such work depends on the
properties of the rock encountered during the tunnel excavation and shall be carried out as
directed by the Engineer.
4.3.1 Documents
The Contractor shall prepare and submit documents in accordance with Table 4-1.
28
Bid Document Specifications
The Engineer’s approval does not relieve the Contractor of his sole responsibilities for efficient
and successful execution of the work.
The Engineer’s approval does not exempt the Contractor of his sole responsibilities for efficient
and successful execution of the work.
Drilling of holes for exploratory drilling and grouting from the tunnel front or from elsewhere
in the tunnel at any angle as instructed by the Engineer.
Grouting works will be performed in the tunnel for control of permeability and influx of water
or for consolidation.
Grouting may be done either as cement grouting or as chemical grouting. Grouting operations
are not designed and specified in detail at the tender stage. The grouting works will be decided
and designed by the Engineer in co-operation with the Contractor during excavation.
The Contractor shall at any time during the progress of the Works provide and maintain
adequate equipment and materials with stand-by reserves to be able to carry out any drilling
and grouting operation ordered by the Engineer.
The grouting shall be supervised by an engineer with documented grouting and drilling
experience from similar works. At least one additional crew member shall document
appropriate experience.
29
Bid Document Specifications
The Contractor shall keep daily updated records and logs of all drilled holes, flexible grouting
tubes, water pressure tests and grout takes. The results shall be presented in numerical and
graphical format, comprising every borehole and every flexible tube with results of water
pressure tests, grout takes at the various depth intervals, and data for performance and applied
pressures. The boreholes and tubes shall be given a number, identifying location as well as
direction.
Equipment units for excavation and rock support work may be used when satisfying the above
requirements.
Water flushing shall be used during drilling of all grout holes. The use of grease or lubricants
on drill rods or use of mud for drilling is not permitted.
After drilling, the hole shall be flushed with water and air. Pumps for supply of air and water
for flushing shall be capable of delivering a pressure of minimum 10 bar.
The tolerance for collaring of drill holes is 0.20 m and for alignment deviation the tolerance is
4% of the depth of the hole.
All drill holes not designated for further use extending beyond planned excavation perimeter
shall be grouted with shrink compensated mortar.
Ground water monitoring shall be performed. Ground water levels shall be recorded twice a
shift for each hole during drilling operation.
30
Bid Document Specifications
4.5.4 Grouting
Equipment both for cement grouting and chemical grouting shall be available and in working
order at any time at the site.
Each unit of equipment for cement grouting shall include, but are not limited to:
Grout mixer
Grout agitator
Grout pump
Flow meter, pressure gauges for air, water and grout supply lines, grout
supply, valves, packers and fittings to supply a continuous flow of grout and an
accurate pressure control
The Grout Mixer shall be a high-speed colloidal grout mixer. The mixer shall be capable of
mixing grouts with water/ cement ratios between 0.4 and 10. An accurate measurement of
materials shall take place at the mixer so that mix proportions can be exactly controlled. Cement
may be added to the mixer by weight or by volume. Each component added to the mixer shall
be measured to an accuracy of +/- 5 %. Minimum mixer capacity shall be 250 l.
The Grout Agitator shall be capable of keeping grout of specified water-cement ratios (between
0.4 and 10) in suspension. It shall be equipped with screen to remove particles not passing a
4.75 mm sieve. The sump shall be graduated to metric standards so that the volume of grout
injected into a hole can be measured accurately. The capacity of the agitator shall not be less
than twice that of the mixer.
The grout pumps shall be a progressive cavity, pulse free type, capable of handling thin and
viscous grouts with no pulse. The capacity shall be at least 0.08 m3 grout per minute at a
discharge pressure of 50 bar, and minimum 0.05 m3 per minute at 100 bar. The pump shall be
equipped with a pressure regulating device securing a maximum grouting pressure within ± 10
% of the required pressure. Required working pressure shall be maximum 120 bar.
Pressure gauges shall be Bourdon type or similar of heavy duty quality and shall measure
pressures as appropriate to the range of grouting pressure employed. Two pressure gauges shall
be supplied for the grouting plant, one at the header and one at the pump. In addition a pressure
recording unit shall be connected to the pressure line from the grout pump. The dial size of the
pressure gauge shall not be less than 150 mm. The pressure recording unit shall record the
pressure within ±1 bar. The records may be in analogue or digital form and with the possibility
of pressure readings every minute. The Contractor shall supply a calibrated master gauge for
each pressure range for checking the accuracy of all gauges used.
The pump and the connected agitator shall be located at a distance of maximum 30 metres from
any hole being grouted.
Packer dimension and construction of the packer shall correspond to the diameter of the drill
hole, to the drilling method used to produce the hole, and to the applied pressure. Double
31
Bid Document Specifications
packers and single packers shall be available. Disposable packers may be used if approved by
the Engineer.
For chemical grouting, suitable pumps as well as necessary accessories shall be available.
Required working maximum pumping pressure is 250 bar. Equipment shall be compatible with
grout data as given by manufacturer. Pumping capacity shall as a minimum be 4 l/min.
All grouting units shall at all times be clean and in proper working condition. The Contractor
shall supply sufficient operating personnel, supervision, labour, spare parts and tools to operate
the units at full capacity and top efficiency. A minimum of three grouting units of each type
shall be available at site.
The grouting plant shall be provided with satisfactory storage for supplies of grouting material
so that the operations may proceed without interruptions. The plant shall be provided with
suitable housing for protection against rain and direct sunshine. Flexible grouting tubes, both
for chemical and for cement grouting, will be required for contact grouting. Acceptable brands
are FUKO 2 for cement grouting and Multitect (ULTRA) or FUKO 1 for chemical grouting, or
equivalents.
4.7 Grouting
4.7.1 Grouting Materials
4.7.1.1 Water
Water for concrete, mortar, grout or curing shall be clean, fresh and free from matter in solution
or suspension that may adversely affect the strength, durability or appearance of the Works or
cause corrosion on reinforcement and embedded items.
4.7.1.2 Cement
The cements to be used shall be fresh Portland Cements. Transport, handling and storage shall
conform to the requirements in the corresponding clauses of the specifications for cement to be
used in concrete or as recommended by the manufacturer.
Grout type A:
Portland Cement conforming to ASTM C150 and having a specific surface of not less then 400
m2/kg (Blaine Value) with not more than 1% by weight being retained on a sieve 200 and with
stabilising and plasticising admixtures of micro silica (Elkem Materials Multi Grout Grout
Aid or equivalent) and superplasticisers (Sika-SP 40 or equivalent). The maximum bleeding
value shall conform to the recommendations of ISRM Commission on Rock Grouting, which
32
Bid Document Specifications
state that the grout suspension (with all additives) is considered stable when the sedimentation
rate ∆H/H after 2 hours remains under 5%. Water cement ratio: Typically 0.45 - 1.2. Marsh
funnel viscosity: 36-50 sec.
Grout type B:
The cement to be used shall be micro fine Portland cements with a specific surface of not less
than 650 m2/kg (Blaine Value), with not more than 1 % by weight being retained on sieve 30.
The maximum bleeding value shall conform to the recommendations of ISRM Commission on
Rock Grouting, which state that the grout suspension (with all additives) is considered stable
when the sedimentation rate ∆H/H after 2 hours remains under 5% Water cement ratio: Typical
0.45 - 1.2. Marsh funnel viscosity: 36 - 50 sec.
Grout type C:
A quick setting, fine grained grout with a pot life that can be regulated in a controlled manner
between 10 minutes and 1 hour for a mix in proportion 1:1, water/cement (weight) at 25o C.
Type: Accelerator aided mix designs or premixed blocker agents as Thermax + C-Max (Elkem
Materials-MultiGrout) or equivalent.
4.7.1.3 Admixtures
The Engineer may require the addition of materials other than those specified above in order to
improve the properties of cement grouts with respect to stability, pumpability, acceleration and
retarding, and penetration ability. Such admixtures shall include, but are not limited to, micro-
silica powder, as well as expanding, water reducing, accelerating and stabilising admixtures.
Grout type E: Epoxy grout with extended potlife - Mapepoxy BI-R (Rescon Mapei) or similar.
Alternative products with documented similar properties will be accepted and may be offered
by the Contractor.
For rock mass grouting at the tunnel face all holes drilled shall be grouted. Control holes shall
be drilled between grouted holes when the grout agents have set, and the grouting will continue
in a split spacing system until control holes demonstrate that the required permeability is
reached unless otherwise ordered by the Engineer. It will be assumed that the required
33
Bid Document Specifications
permeability is reached when the gross grout take in the control hole is below the limit defined
by the Engineer. Packer intervals shall be as directed by the Engineer.
The grout material shall be adequately set (cured) prior to blasting into a grouted area. The
Contractor shall specify the manufacturer and type of grout he intends to use.
Chemical grout may be required in cases penetration of cement grouts turns out insufficient to
achieve the intended control of influx of water into the tunnel.
The Contractor shall specify the manufacturer and type of grout he intends to use for Grout
Type D and E.
Payment for the measured quantities as specified in a) to d) shall include all deliveries, and
work described in the Specifications, directed by the Engineer or as required to complete the
grouting work according to modern methods and recognised good practice. For grouting works
at the tunnel face, time dependent costs are paid as a separate item.
b) Cement pressure grouting shall include flushing between drilled holes and will be measured
as follows:
34
Bid Document Specifications
- Dry weight of consumed cement in the volume of grout of specified type as injected into the
rock mass at each packer setting or tube connection in accordance with Specifications or as
directed by the Engineer.
- Grout by kg of chemical material (i.e. water not included) injected into the rock mass or tube
setting in accordance with the Specifications or as directed by the Engineer.
d) Time for grouting shall cover all other direct and indirect costs and shall be measured and
paid for per shift hour. Grouting time shall be measured from start of grout pumping to end of
normal setting time or extended as described under 4.7.2 Cement Grouting.
Time for general grouting underground is to be measured and recorded from the start of grout
pumping to the end of the normal setting time for the last hole or pipe/tube grouted. Time lost
due to any technical or mechanical break-down of equipment is the Contractor’s own
responsibility and expense. The price shall be based on three separate mixing and pumping
lines.
Use of admixtures, micro-silica powder, expander, accelerator and water reducing, stabilising
or other chemical admixtures shall be included in the unit prices listed.
The quantities measured as specified will be paid at the contract prices included in the Payment
Schedules (Bill of Quantities). Prices and payments shall be valid independent of the final
amount of work on each item compared to the quantities listed in the Bill of Quantities. No
other payments will be approved.
35
Bid Document Specifications
5 ROCK EXCAVATION
5.1 Scope
5.1.1 Coverage
This Chapter specifies requirements for all underground and above ground rock excavation
works. Any excavation method that would fulfil the specified requirements may be used, i.e.
drill and blast method and mechanical excavation methods.
The Contractor shall provide all material, labour and equipment and carry out all works,
temporary works and tests required for completion of excavation.
The Contractor shall assume full and sole responsibility for safe working conditions in all
excavations, and the health and safety of all workers and visitors to the worksite. See also
definition in Chapter 6 Rock Support. In addition to any special provisions for safety included
in these specifications, all of Contractor’s operations shall conform to all applicable laws and
regulations.
Boulders larger than 1m3 shall be classified as rock. Boulders less than this shall be classified
as soil.
All types of materials found in rock formations underground shall be classified according to
the rock mass quality classification listed below.
The Engineer shall decide if the material shall be classified and measured as Rock, and his
decision shall be final.
36
Bid Document Specifications
5.2.2 Documents
The Contractor shall prepare and submit documents in accordance with Table 5-1.
37
Bid Document Specifications
The Engineer’s approval does not exempt the Contractor of his sole responsibilities for efficient
and successful execution of the work.
The Contractor shall be responsible for the management and sorting of all excavated materials
to enable the placement and disposal of materials in accordance with the Contract. Excavated
materials shall, according to their nature and to the Contractor's materials management plan, be
placed as fills in their final locations in the Works, stockpiled for later placement, used for
aggregate production, or removed to a nominated or approved spoil disposal area. All excavated
materials belong to the Client and no material shall be removed from the Site without the
written approval of the Engineer.
Excavation in rock shall achieve stable, reasonably regular rock slopes and surfaces with as
little over-break as possible.
The Contractor may choose his own methods for drilling, blasting and transporting the rock.
Except where otherwise specified, perimeter blasting shall form the final surfaces in
underground openings. Charging of drill holes as well as type of ignition, drilling patterns etc.,
shall be according to modern methods and recognised good practice.
The Contractor shall observe and carry out all excavation works according to rules and
regulations regarding the import, transport, storage and use of explosives issued by and public
authority having jurisdiction in respect of the same. Detailed records shall be kept by the
Contractor and submitted daily to the Engineer giving the types and quantities of explosives
used, delivered and in stock. The Contractor shall not later than 6 weeks ahead of start of
blasting works, provide the Engineer with a list of blasting licence holders. Only qualified
persons shall be permitted to conduct blasting operations.
Where firing is carried out electrically the Contractor shall take all precautions necessary to
prevent premature explosions. During thunderstorms and other electrical disturbances charging
and firing is not permitted and warning shall be given to all operators when charging is in
progress.
An instrument measuring static electricity levels shall be installed at the tunnel portal. The
instrument shall be connected to an easily visible warning device.
All metal mains, ducts and tracts shall be properly earthed at the tunnel entrance. After
excavation of soil material, the rock surface shall be sufficiently cleaned for drilling and placing
of explosives to the satisfaction of the Engineer.
Excavations shall follow the theoretical rock contour lines and levels or such other limits as the
Contractor may require to enable him to construct the Works in accordance with the Contract
considering collaring accuracy and hole deviation specified. Excavation beyond the theoretical
38
Bid Document Specifications
rock contour lines and levels made without the Engineer's direction or approval, including but
not limited to, excavation to provide working space and excavation below approved stripping
levels, shall be backfilled with concrete at the Contractors expense unless otherwise specified
or approved.
The Contractor shall be solely responsible for all damage or accidents resulting from blasting
of temporary, permanent or subsidiary works, or to the property of the Client or of others, as
well as for injury to persons.
The Contractor is responsible for covering and required protection in connection with blasting.
Debris from blasting and spill from transportation are not allowed outside the excavation area.
The Contractor has to clean up such material as the Engineer finds it necessary. The Contractor
shall regularly inspect the excavated faces of all works under his jurisdiction, including
temporary and permanent access roads and shall forthwith remove and dispose of any material,
which the Engineer and/or the Contractor deem loose or unsafe.
Blasting in the vicinity of completed, or partially completed, concrete structures shall be subject
to the Engineer’s consent. Normally, blasting shall not take place in the vicinity of newly
concreted structures until 10 days after concreting. The restriction does not apply to blasting
close to installed rock support in underground openings.
Before commencing the rock excavation work, the Contractor shall prepare and present to the
Engineer a quality assurance plan that ensures that the rock excavation work is performed
according to the Contract requirements.
The rock surface shall be inspected after each blast, and action for immediate securing at the
face shall be taken as required. The Engineer shall have access to the face and, if considered
appropriate, carry out mapping of the rock conditions revealed. In cases of adverse rock
conditions or significant deterioration of the conditions the Engineer shall be notified
immediately.
In case of very difficult places for excavation of rock, heading and benching method will be
adopted as direction and instruction of engineer. The payment for this type of work shall be
made as specified in bill of quantities. No other payments will be approved.
5.3.2 Ventilation
The ventilation system shall be efficient and reliable during the excavation period in order to
provide a safe and comfortable working environment inside tunnels and caverns. When
reaching and penetrating carbonaceous rock the Contractor shall perform measurement of
methane gas levels and provide sufficient protection and ventilation against such gases.
Air velocity shall always be higher than 0.3 m/s in the cross sectional area of tunnels and
caverns. The air breathed by persons shall contain not less than 19% of oxygen by volume. The
environment inside the tunnel will be governed by seasonal variations in temperature, humidity,
rock temperature and by work activities ongoing within the tunnel. The fan shall be robust and
efficient and be capable of providing variable airflow to suit the construction sequence and
activity level inside the tunnel as work progresses. The fan shall be supplied complete with all
necessary components for commissioning and use. All components of the duct system shall be
non-flammable.
39
Bid Document Specifications
The ducting shall be of a safe robust material. Flexible ducting shall have a high tear resistance
and shall be appropriately reinforced and maintained.
The Contractor shall describe the details of the systems, which will be used.
The Contractor shall install and maintain a system of telecommunication at the work fronts.
The Contractor shall maintain all temporary and permanent transport roads in good and dry
conditions to facilitate efficient and quick transportation aboveground as well as under-ground.
5.3 Survey
All surveying shall be carried out as specified in Chapter 2 Surveying work.
The contractor shall also furnish, install, maintain and operate all necessary piping and other
watering and dewatering equipment for construction activities. All parts of surface and
underground works shall be maintained free of water as required or instructed by engineer.
Care of water during construction of any volume and discharge in tunnels and also in open cut
shall be maintained for the safe working condition by the contractor. Appropriate handling of
water that may arises during excavation shall be made by the contractor by adequate pumping
or any other draining provision. There shall be no separate measurement and payment other
than specified in the bill of quantity.
The slopes of permanent batters are assumed to be vertical unless other slopes are directed by
the Engineer.
In the Bill of Quantities rock excavation is divided into the following categories:
Bulk rock excavation, and
Trench/ditch rock excavation with bottom width less than 2.0 m
The excavation procedure shall always be adapted to the local rock mass conditions. When
40
Bid Document Specifications
traversing weakness zones or other areas of heavily jointed or otherwise incompetent rock, pilot
tunnelling, dividing of the section, and/or advancing with shorter pull than normal may become
necessary. Spiling, immediate application of sprayed concrete, reinforced sprayed concrete
lining, pressure grouting or other support measures, further described in Chapter 4 and Chapter
6, may also be required. The methods to be used for excavation and support shall be subject to
the Engineer's approval.
A rigid template of the same shape and dimensions as the theoretical cross-section shall pass
through. Deviation of the theoretical cross section from the centre line will not be approved.
Any subsequent slashing, wedging or re-drilling of rock that may be necessary in order to meet
the above requirements is the responsibility and cost of the Contractor. Control of compliance
with the design requirements shall be carried out by the Contractor at regular intervals as
directed by the Engineer.
Before commencing any drilling and blasting the Contractor shall submit for the Engineer's
approval the drilling-, charging- and ignition patterns he proposes to use. Such approval shall,
however, not exempt the Contractor of the full liability of any blasting operations. The drilling
equipment shall include a device for measuring the direction of drilling.
In order to minimise over-break and requirements for rock support, perimeter blasting (soft
blasting smooth contour blasting technique) shall be used on all final rock surfaces. The length
and size of blast rounds shall be regulated according to the prevailing rock conditions. When
deemed necessary from stability considerations, the Engineer can order reduced round lengths
and/or subdivision of the cross section.
When deemed necessary from stability considerations, the Engineer can order change in
excavation shape, both the arch height and the symmetry, within the given cross-sectional area.
Design drawings show the theoretical rock contour. Special rock mass conditions may require
cross-section adjustments, which shall be decided and/or approved by the Engineer.
If the Contractor considers it necessary to request for excavation outside theoretical contour to
obtain access for his own purpose, such request shall be forwarded to the Engineer and the
work shall be at the Contractor cost and time.
41
Bid Document Specifications
This includes drilling of contour holes c/c 700 mm with max. diameter Ø51 mm and use of
special low strength explosives. The row next to contour holes may also require charge
limitations.
As a general rule the distance between the perimeter and the nearest row of holes of the main
round shall be 1.3 times the spacing of perimeter holes for smooth blasting. The selection of
these and other pertinent parameters shall be based on experience gained from the initial rounds,
and shall be subject to the approval of the Engineer.
The method is based on closely spaced contour holes, with reduced charges to be fired as a
final clean-blast after the main round on the last number of delays. The method shall prevent
extensive fracturing of the rock mass beyond the contour.
5.8.1 General
Excavation and rock support procedures shall be adapted to the mass conditions encountered
in the tunnel. When traversing unfavourable rock masses, suitable combinations of excavation
methods and rock support methods described in the Contract shall be used.
42
Bid Document Specifications
The rates for excavation shall include, but are not limited to:
All scaling and cleaning necessary for drilling and placing of explosives
The use of non-electric ignition system
Normal over-break
Any required slashing or wedging of rock protrusions inside the theoretical rock
contour
Excavation beyond the theoretical contour and backfilling of the same with approved
concrete or otherwise as the Engineer may direct unless the excavation is ordered by
the Engineer or caused by abnormal over break (applicable in areas that are to be
concrete lined)
Mucking out and transport of excavated material (including over-break, scaled
materials or other materials) to fill and/or spoil deposit areas. Work at the fill and/or
spoil deposit areas are covered by Chapter 3 Earthworks
All shaping, cleaning and other preparation of the excavation except when a separate
pay item is included in the Bill of Quantities
Construction and maintenance of temporary services such as adequate roadways,
drainage including all pumping as necessary, all pipes, cables, ventilation, illumination,
lightning protection, earthing and fire protection, communication systems etc. except if
separate pay item is included in the Bill of Quantities.
Scaling as required after each round before mucking out
Scaling as required after mucking out (See definition below)
Weekly inspection and scaling as required of previously excavated openings as a regular
safety precaution (See definition below)
Removal of all temporary service installations with fixtures
All required surveying works.
Abnormal over-break shall mean which in the opinion of the Engineer cannot be prevented in
spite of reasonable care by the Contractor. Over-break shall mean the geologically unavoidable
over break and must be verified by the geologist. Abnormal over-break shall mean over-break
beyond 0.5 m of the net dimensions of the tunnel, i.e., beyond the theoretical rock contour
required as shown on the Drawings, and which in the opinion of the Engineer cannot be
prevented in spite of reasonable care by the Contractor. Abnormal over-break shall be measured
as volume in its natural state beyond the limits stated above of the theoretical rock contour
except that abnormal over-break in the floor of open cuts, tunnels or other excavations inclined
at less than 30º shall not be measured. The rate shall cover all works required, such as loading,
transport and tipping etc. Filling of over-break shall be done by contractor.
The payment of Abnormal overbreak shall be normal as the bills of quantity for the tunnel
excavation.
43
Bid Document Specifications
Trench excavation shall apply for rock excavation with a bottom width less than 2.0 m.
Foundation excavation will unless otherwise shown on drawings or instructed by the Engineer
be measured as defined above. Bracing of the sides if required will not be measured and shall
be included in the rate for the excavation. Rock excavation for mobilisation areas and temporary
works will not be measured for payment.
No extra payment will be made for water handling, including keeping all excavation fronts dry
and free of water.
All subdivision of rounds, all construction and maintenance of temporary services and all
scaling and cleaning of slope and foundation surfaces shall be included in the unit price for
rock excavation if separate items for such work are not listed.
Rock excavation for mobilisation areas and temporary works for the Contractor’s own purpose
will not be measured for payment.
All excavation unit rates and all other rates given by the Contractor shall be valid independent
of any change in the orientation of the tunnel.
The measurement for the hauling materials shall be measured as of its natural state before
excavation as specified in the drawing, specification and field survey as directed and approved
by the engineer. Payment for haulage of the excavated materials of underground and surface
excavation shall not be made separately for the transportation and disposal up to tunnel portal
area and haulage beyond portal area shall be made for the hauling as specified in the bill of
quantity.
44
Bid Document Specifications
6 ROCK SUPPORT
6.1 Scope
6.1.1 Coverage
This Chapter comprises all work intended to support and stabilise the rock whether of initial or
permanent nature, in open cuts or in underground openings.
The Contractor shall provide all material, labour and equipment and carry out all works,
temporary works and tests required for completion of the work.
The Contractor shall assume full and sole responsibility for safe working conditions for all
excavations and the health and safety of all workers and visitors to the work during the
construction period. In addition to provisions for safety included in these specifications and
elsewhere in the Contract, all of Contractor’s operations shall conform to all applicable laws
and regulations.
“Initial rock support” shall mean support work necessary to ensure safe working conditions and
to maintain the shape of the rock excavation during the construction period.
“Additional rock support” shall mean all support work necessary to ensure the permanent long-
term stability of the excavations.
"Support work at the face" shall mean all support work interrupting the normal excavation
cycles, except that all support work carried out in caverns and above ground, in open cuts etc.,
shall be regarded and measured as support work behind the face.
"Support work behind the face" shall mean all support work not being measured as carried out
at the face.
The rock support consists of combinations of scaling, rock bolts, sprayed concrete, several
forms for reinforcement for the sprayed concrete including lattice girders and full concrete
lining.
45
Bid Document Specifications
6.3.2 Documents
The Contractor shall prepare and submit documents in accordance with Table 6-1.
Table 6-1: Submittals of Documents - Rock support
Item Issue for Issue for Issue
approval info time
46
Bid Document Specifications
The Engineer’s approval does not exempt the Contractor of his sole responsibilities for efficient
and successful execution of the work.
The Contractor shall make tests and prepare and submit test reports in accordance with Table
6-2.
Table 6-2: Submittals of Test Reports
6.3.4 Certificates
The Contractor shall submit manufacturers’ and suppliers’ certificates of compliance with the
relevant standards.
6.4 General
6.4.1 Inspection of Tunnel, Marking of Chainage, Wash-down
The Contractor shall inspect the rock face jointly with the Engineer as soon as practical after
excavation of each round of blasting. Further, inspections with use of a mobile platform shall
be done with no longer intervals than 2 weeks and shall cover sections/areas where the
Contractor has completed the bi weekly scaling during this period.
The Contractor shall clearly mark the chainage of the tunnels for every 10 m. The chainage
marking shall be done with red spray paint on the right tunnel wall, 1.5 - 2.0 m above the invert.
The accuracy of the chainage marking shall be within ±250 mm. The maximum distance
between the tunnel face and the last chainage mark shall be 25 m. If the marking due to wear
and dirt becomes difficult to read, it shall be washed and/ or repainted.
47
Bid Document Specifications
Wash-down of excavated surfaces by water flushing shall be done after mucking of each round.
The Engineer’s geologist will regularly after blasting perform geological mapping of the rock
mass. This mapping will normally be done after mucking and will not disturb the Contractor’s
work. In special cases, the Engineer will order suspension of excavation works in order to
perform more thoroughly mapping or investigations.
The terms initial rock support and additional rock support are used only for a classification of
rock support works in regard to responsibility for decision making, and may both occur at the
face and behind the face and shall not influence on measurement and/or payment. The terms
“at the face” and “behind the face” are used for differentiation of payment of rock support
works.
Initial rock support will normally consist of scaling, end anchored and/or fully grouted rock
bolts, rock straps, wire mesh, sprayed concrete or combination of these methods. In cases of
very poor and extremely poor rock mass quality lattice girders in combination with sprayed
concrete will be needed.
Additional rock support will normally consist of cement grouted rock bolts and/or sprayed
concrete with various reinforcement methods. Cast in place concrete lining might also be
required. For additional long-term support fully grouted rebar bolts (dowels) may be used.
The initial support shall be incorporated in the long-term support. Materials for initial rock
support shall therefore be of a long-term quality. The Contractor shall inspect rock surfaces
jointly with the Engineer as soon as practical after blasting/excavation and shall recommend to
the Engineer the type and extent of initial support. The type, extent and details of support to be
installed shall be subject to the Engineer’s consent. The Engineer may consent to the
Contractor’s proposals or may direct the Contractor to increase the amount of support or change
the type of support as part of the additional rock support. The Engineer will define additional
rock support prior to completion of the excavation work.
The failure of the Engineer to consent to the Contractor’s recommendations on rock support
does not exempt the Contractor of his responsibility for the safety of the work. No statement in
this Specification shall be construed to exempt the Contractor from the sole responsibility for
safe working conditions in the underground openings or from liability for injuries or to deaths
of persons or to damage to property. Consent to a reach as unsupported shall in no way exempt
the Contractor of responsibilities or liabilities and will not preclude the Engineer from requiring
supports in the reach at a later stage if signs of instability of the rock mass are indicated.
If at any time the Contractor has reason to believe that additional support, beyond that
previously consented to by the Engineer, may be necessary for the safety and integrity of any
rock surface, the Contractor shall promptly bring the matter to the Engineer’s attention together
with the Contractor’s recommendation as to the type and extent of additional necessary support.
48
Bid Document Specifications
The scheduling for installation of rock support shall be the responsibility of the Contractor, and
is subject to the consent of the Engineer. Additional rock support of long-term duration shall
be installed behind the tunnel face where the work does not cause delays in the excavation
progress. The Engineer might in special cases request such support to be applied at or
immediately behind the working face.
If the Contractor considers it necessary to request excavation outside the theoretical contour to
obtain access for his own purposes, such request shall be forwarded to the Engineer, and the
work, including all initial as well as all additional support, shall be at the Contractor’s cost and
time. The Engineer may also require such excavations backfilled with concrete, at the
Contractor’s cost and time.
6.5 Scaling
6.5.1 General
Scaling works are classified into basic scaling and additional scaling. Both the basic scaling
and the additional scaling are to be performed in accordance with the best prevailing practice.
It is required that the Contractor keeps available equipment in efficient working order for the
scaling works, such as:
scaling rods scaling platform to be mounted on shovel
hydraulic scaling hammer to be mounted on the boom of an excavator equipment for
cleaning/scaling by high-pressure water flushing
Bi-weekly scaling:
All scaling needed in walls and roof for the section excavated during the last 2 weeks, plus an
overlap of 30 m of the former bi-weekly scaling section. A measure for completed scaling is
that there are no stones larger than 0.001 m3 (1 dm3) which are possible to remove by manual
use of scaling rods, or as instructed by the Engineer. If the bi-weekly scaling is not performed
satisfactorily, the Engineer may request the blasting works stopped until the scaling is found
acceptable.
Final scaling:
Before handing over the Work of the work site for other activities. The required level for
completed scaling is as described under
a) Extra scaling:
Extra scaling comes in addition to the basic scaling in order to comply with the requirement
defined under b), at the face or behind the face.
49
Bid Document Specifications
c) Chisel scaling:
All loose and drummy rock (hollow sound) is to be removed to the degree, which is possible
by chisels.
All bolts shall serve as permanent support and shall normally be fully grouted with cement
mortar, but resin end anchored and fully resin-grouted bolts may be approved as permanent
support, if corrosion protected in accordance with clause 2 in the list below. The Engineer shall
approve all bolt types to be proposed and used by the Contractor. Permanent rock bolts shall
conform to the following requirements:
1) Deformed steel bars and plain steel bars shall conform to ASTM A 615M, Grade 4500 having
minimum yield-point strength of 500 N/mm2.
3) Threaded rock bolts shall be provided with rolled threads of min. 150 mm length of the same
corrosion protection or better than the bolt itself. The threaded part shall withstand a force equal
to the actual ultimate load of the rebar. If the threaded part is separate and to be connected to
the rock bolt, the rock bolt and the threaded part shall be connected by friction welding
according to BS 6223. The friction weld shall have the same corrosion protection or better than
the bolt and threaded part. The friction weld shall withstand a force equal to the actual ultimate
load of the rebar.
4) All type of bolts shall be provided with a 200 mm square plate or equivalent diameter dished
anchor plates of 6 mm thickness, semi-spherical washers and nuts. The assembly shall adjust
to angular displacement from normal up to 45º. The steel quality of the anchor plates shall
conform to ASTM A 36/A 36M. Other accessories shall be of steel quality compatible with the
quality of the rock bolt.
Bottom part of bolts for end-anchoring with polyester resin anchoring shall be provided with a
50
Bid Document Specifications
spring or other device for efficient mixing of the polyester resin. Polyester resin capsules shall
be of quality giving sufficient bond strength to comply with requirements for pull tests.
The cement mortar used for grouting of rock bolts shall comply with the following
requirements:
Resin end anchored bolts shall be hot-dip zinc and epoxy coated. Fully grouted rock bolts shall
as a minimum be hot dip zinc coated. Additional epoxy coating will be required unless the
grouting material for bolting has been verified not to cause undesired chemical reactions with
the zinc coating.
The tensioning of all the rock bolts in the corresponding reach shall be checked as part of the
bi-weekly scaling. In case of loose bolts, the bolts shall be re-tensioned. In case of overbreak
around other bolts ends, re-drilling and/or resetting of bolts shall be done.
6.6.2 Accessories
The Contractor shall provide all necessary accessories, additional boreholes where required or
other items necessary for installation and anchoring or grouting of the bolts.
6.6.3 Execution
6.6.3.1 Drilling and Installation of Resin End-anchored Bolts
Resin-end anchored bolts shall be installed in accordance with the manufacturer's issued written
instruction.
The bolts shall have an anchored length of minimum 250 mm in high strength rock types
(unconfined compressive strength, UCS, >150 MN/m2) and 500 mm in medium strength rock
types (50<UCS< 150 MN/m2). For low strength rock types the minimum anchored length shall
be 1 m. The diameter of the boreholes' inner end shall be 10 to 12 mm larger than the bolt
diameter.
1) Rock bolts may be installed in a systematic and predetermined pattern, or as spot bolts as
directed by the Engineer. Rock bolts shall be installed perpendicular to the rock perimeter, or
otherwise as directed by the Engineer.
51
Bid Document Specifications
4) Rock bolts shall be cleaned to remove dirt, grease or any other impurities
before installation.
5) The entire hole shall be filled with mortar (grout) before installation of the bolt.
6) In upward slanting boreholes measures shall be taken to prevent loss of mortar. The bolt
shall then be secured by wedges or other means to prevent movement during hardening of the
mortar.
7) Bolt ends shall not protrude more than 50 mm outside nuts if not otherwise decided by the
Engineer.
8) Anchor plate, washers and nuts may be located outside or within the reinforced sprayed
concrete. In conjunction with welded wire fabric or rock straps, the rock bolts shall be installed
in depressions of rock surface if possible.
9) The nut of grouted rock bolts shall be tightened to achieve a force at anchor plate of
approximately 20 kN. Tightening can be carried out when minimum 2 MPa grout strength has
been obtained.
10) For grouted expansion-shell bolts, the maximum working load shall be limited to 50% of
the ultimate load, when pre-stressed before grouting.
6.6.4 Testing
Documentation of properties of grouts to be used for grouting of rock bolts shall be submitted
to the Engineer. The grout properties to be documented will comprise, but are not limited to,
consistency, setting time, strength after 1, 7 and 28 days, porosity, expansion and permeability
of hardened grout.
The Contractor shall fill in Quality Control forms which state type of rock bolts and accessories,
condition of corrosion protection, installation method and tensioning.
The Contractor shall perform quality control of rock bolt installation according to the Quality
Control Procedure described by the Engineer. The Engineer’s control engineer shall have free
access to participate in the quality control.
End anchored rock bolts are to be tested by pull test. Installation procedure for grouted rock
bolts is to be verified by test grouting of rock bolts in plastic tubes. The following control
categories shall be included in the Quality Control Procedure:
Visual control of corrosion protective coatings on rock bolts and accessories to be carried out
prior to installation. In case of any damage to epoxy/ polyester coating, mending is to be
performed with a result complying with the requirements for epoxy/polyester coating. In case
the damage penetrates the zinc layer, rock bolts or accessories will not be accepted.
52
Bid Document Specifications
Pull tests shall be carried out by use of hydraulic jack with a pull force of 80% of the yield
strength. Required number of tests for a given bolted area and required number of acceptable
results for approval of the bolted area are defined below. The number of accepted test bolts
required for approval of the given area or tunnel interval is defined below.
6.6.5 Criteria for Assessment of Test Numbers and Acceptance of Test Results
The method for selection of test bolts shall comply with International Standard ISO 2859- 1
“Sampling procedures and tables for inspection by attributes”. The Engineer will choose the
areas or the tunnel reaches to be tested. The Engineer will define bolt groups in the range from
200 to 500 bolts as lots for inspection (testing). Number of test samples will be decided in
accordance with ISO 2859-1, Table I, general inspection level II. A lot comprising 151 - 280
bolts require sample size G of 32 bolts for normal or tightened control, or 13 bolts for reduced
control.
Evaluation of results will be in accordance with Table IIA (single normal control) or Table IIB
(single tightened control), with Acceptable Quality Level AQL 2.5. With normal inspection
(testing), only 2 test failures are acceptable for a size G sample. Upgrading from normal to
tightened control regime is done (according to ISO 2859-1) “when two out of five or less tested
lots have been non-acceptable on original inspection (that is, ignoring re-submitted lots or
batches for this procedure)”. With tightened control only 1 test failure is accepted for sample
size G. “When tightened inspection is carried out, normal inspection shall be reverted to when
five consecutive lots have been considered acceptable on original inspection”. Procedures for
switching from normal to reduced testing and from reduced to normal testing are described in
ISO 2859-1.
If the test results for a given group of grouted rock bolts do not satisfy the requirements stated
by AQL 4.0 in ISO 2859-1, the payment for the bolts in that group will be reduced by 25%,
and the Engineer will require additional bolting at the Contactor’s cost to correct the deficiency
in quality.
The dowel shall be fully cement grouted and tightened by the base plate and nut bolts. The
material for deformed bar, cement grouting, nut bolts, base plate shall be same as that of rock
bolt as specified in the specification.
6.8 Spiles
Reinforcing of the rock mass ahead of the tunnel face with long rock bolts (spiles) is termed
spiling. This support method may be applied for particularly unstable rock, to restrict
deformation of the surrounding rock, and to prevent cave-ins following the subsequent rounds.
53
Bid Document Specifications
The spiling holes shall be drilled from the perimeter of the tunnel face, slanting outwards into
the rock surrounding the tunnel stretch ahead. Deformed steel bars shall be placed in the holes
and fully grouted.
The spile length is decided based on the length of the blasting round. Minimum spile length is
2 times the length of the next round.
Spacing and inclination of the spiles shall be as agreed upon by the Engineer.
Rock straps shall be combined with the radial bolts for securing protruding ends of spiles
against vibrations and over-break.
Spiles are subject to quality requirements as specified for rock bolts above.
Sprayed concrete shall be applied plain or reinforced with steel fibres as directed by the
Engineer. All plant and methods for spraying shall be approved by the Engineer. Application
of sprayed concrete shall be carried out by experienced operators only. The Contractor shall
keep well suitable equipment at site for catching and measuring the quantity (by weight) of
rebound material.
For scheduled work the Contractor shall give the Engineer at least 12 hours notice about the
location of areas planned for spraying. When sprayed concrete is as initial tunnel support, the
Engineer shall be informed at the latest 1 hour in advance. When a major part of the surface is
to be covered, sufficient time shall be allowed for the Engineer to record the geological features
before concrete is sprayed.
Micro silica (silica fume) may be included in the mix for better pumpability and to improve
cohesive consistency, restricted to 10% by weight of the Portland clinker content. This limit
also applies to other admixtures with high pozzolanic effect, and also to the total content of
such materials. The total contents of such materials and other types of pozzolana directly mixed
into the cement and added during concrete production shall not exceed 25% of the total weight
of Portland cement and pozzolanic materials, including silica fume. Fly ash, if used, shall meet
the requirements in ASTM C618, and shall be tested and reported accordingly. Pozzolana shall
be ordered, handled and stored similarly to cement.
54
Bid Document Specifications
When sulphate content in ground water exceeds 150 ppm, sulphate resistance may be achieved
by use of micro silica (minimum 5 percent, maximum 10% of the cement weight) and a low
ratio ((≈0.45) of: (water)/(cement + silica)). The amount of water in the concrete includes added
water, sand moisture and water from additives, silica slurry etc.
The aggregate shall be well-graded sand with a maximum content of 10 % (by weight) of grains
of size larger than 8 mm. Particle size shall not exceed 16 mm.
Admixtures and other materials for concrete shall be so selected that the total content of
chlorides does not exceed 0.4% by weight of the Portland clinker. Full account should be taken
to effects of admixtures to the finished sprayed concrete and there should be sufficient data
about their suitability, including previous experience with the actual admixtures. Records
concerning details of the performance of such admixtures shall be maintained. As early as
possible, the required sprayed concrete trial mix design shall be batched, applied and tested
according to the standards referred to below for the Engineer's approval of the mixes and
methods to be used.
Unless otherwise specified, the sprayed concrete shall meet the requirements of concrete
strength class C25 and the condition of environmental exposure shall be Moderate, both
according to EN 206. To determine that the concrete meets the requirements to compressive
strength, the in-situ strength requirements given in Table 9.1.2 of the EFNARC Specification
shall be met, which are based on a 50 mm diameter by 100 mm long core and include a 0.85
reduction factor to allow for effects of in-situ curing, the sprayed concrete operation itself and
the use of accelerator (rapid hardening agent). Unless otherwise specified, the rate of hardening
should be:
Fibre reinforced sprayed concrete of strength class C25 used for ordinary rock support shall
have a flexural strength of minimum 3.95 MPa as specified in EFNARC Section 9.2.
The toughness requirements of the fibre reinforced sprayed concrete of strength class C25 shall
comply with residual strength class 2 as given in Figure 9.3.1 and Table 9.3.1of the EFNARC
Specification. Testing shall be in accordance with the description of the beam test as given in
EFNARC Section 10.
The Engineer may order adjustment of the mechanical parameters of sprayed concrete.
Documentation of these properties will then be required.
6.9.2.3 Methods/Execution
Sprayed concrete shall be applied plain or reinforced as shown in the drawings or agreed
between Contractor and the Engineer.
55
Bid Document Specifications
Before commencement of work the crew shall be instructed so as to obtain a sprayed concrete
quality, which is in accordance with the Specification and requirements made. The Engineer
may require that a volume estimate shall be made prior to application of sprayed concrete an
area, based on the specified average thickness and the roughness of the rock surface. The
roughness is defined by an empirical factor which gives an overall characteristic of the actual
surface. It takes into consideration the volume required to fill hollows and cracks. Furthermore,
the roughness factor will vary with the sprayed concrete thickness, resulting in a higher value
for thinner layers. The Contractor and the Engineer shall jointly, prior to spraying of the area,
decide on the roughness factor and agree on the required volume to produce the specified
thickness. The estimated volume shall also compensate for the assumed volume of rebound.
Additional sprayed concrete shall be applied if measurements show that the rebound quantity
is considerably higher than the pre-estimated value.
All surfaces to be sprayed shall be thoroughly scaled and then cleaned by water flushing and,
if required, by sand blasting until all dust, traces of dirt, oil, grease, rebound material and other
harmful matter have been removed. During spraying the nozzle position shall be at right angles
to the rock surface. Any crevices shall be filled first. Before spraying additional layers curing
membranes that may affect the bond strength shall also be removed. Surface preparation may
be omitted in very poor rock. The surface shall be kept moist, but not wet, until the sprayed
concrete is applied. Water seepage on the surface to be sprayed that may be detrimental to the
quality of the work shall be controlled by drainage or grouting before spraying starts. The
sprayed concrete shall be kept moist for at least 7 days by water sprinkling or covering. On
final surfaces a curing membrane shall be used if the curing conditions are deemed
unsatisfactory. Any curing compound shall comply with EN 206. Rapid drying at the end of
the curing period is to be avoided. Natural curing may be considered if the atmospheric
conditions surrounding the sprayed concrete are satisfactory, i.e. sufficient high relative
humidity.
All rebound sprayed concrete and all overspray shall be removed upon completion of the
sprayed section.
6.9.2.4 Thickness
When thickness is stated, the sprayed mean thickness shall be at least the specified thickness.
The sprayed minimum thickness on protruding rock shall be at least 50 % of the specified
thickness.
The bond shall be checked at random by knocking on the sprayed concrete with a scaling rod.
A dull response (hollow sound) indicates areas of no bond. The control shall be documented
by a written report and carried out at a frequency of at least one knock per 5 m2. Areas of dull
response shall be clearly marked and the Engineer shall make an assessment of additional
support required, which shall be performed at the Contractor's expense. The checking shall be
56
Bid Document Specifications
carried out covering the total area of sprayed concrete. The bond requirement does not apply in
fault zones and in highly weathered rock mass.
The thickness shall be checked by drilling through the hardened concrete in a grid of 2.0 x 2.0
m. Drilling shall be performed in hollows as well as at high points. The number of drill holes
for each check shall be at least 25. The frequency of thickness testing shall be at least once per
each 100 m2 of sprayed surface.
The control of fibre content shall be carried out from cored specimens in accordance with
EFNARC Section 10.9.1. The test shall be carried out for each sprayed volume of 50 m3 fibre-
reinforced sprayed concrete.
6.9.2.6 Documentation
A minimum of 2 weeks before commencement of sprayed concrete work, the Contractor shall
submit for the Engineer’s approval applicable data for fibres, cement and admixtures for the
sprayed concrete. Reports on testing shall be executed according to the applicable standards
(and the agreed Quality Plan).
Steel fibres of approved type conforming to ASTM A 820, with a minimum fibre length of 18
mm and an aspect (length/thickness) ratio >40. The length of the steel fibres shall not exceed
0.7 of the internal diameter of the pipes or hoses used unless a test has proven that longer fibres
can be sprayed without blockage.
Welded wire fabric shall be of dimension 100 x 100 x 4.0 mm. Corrosion protection and
concrete cover thickness to be specified in each particular case.
Fibre glass reinforcement shall only be used as approved by the Engineer. Reinforcement for
sprayed concrete ribs shall be one of the following two types:
Deformed rebars of minimum 16 mm diameter tied together by transverse pieces of
deformed rebars of minimum 20 mm diameter. The transverse ties shall be fixed to
radial rock bolts.
Prefabricated lattice girders made from deformed rebars shall be bolted to the rock
surface. The girders shall comply with the following requirements: Section modulus:
Wx > 75 cm3
6.9.3.2 Method/Execution
Steel fibres shall be added according to the achieved results from the testing of trial mixes
complying with the specified toughness/flexural tensile strength requirements. Steel fibres shall
be stored in a dry environment. Corroded steel fibres shall not be used. Before mounting welded
wire fabric the first layer of sprayed concrete shall be applied in order to smooth the surface.
57
Bid Document Specifications
Welded wire fabric shall be installed so that it follows irregularities of surface closely and with
one pitch of overlap. Additional bolts shall be installed for fixing of welded wire fabric with at
least one fixing point per 2.5 m2. For two layers of welded wire fabric reinforcement separate
bolts shall be installed for each layer. Minimum one layer of sprayed concrete is required
between two layers of wire mesh. Welded wire fabric shall be covered by a minimum 50 mm
thick sprayed concrete layer to provide satisfactory corrosion protection.
Rib- or lattice girder reinforcement shall be installed in accordance with given profile lines
and as close to the actual rock surface as possible. Prior to installation, the rock surface shall
be covered by a minimum 60 mm thick layer of fibre reinforced sprayed concrete. Girders shall
be fixed to the rock by means of rock bolts. The girder sections shall be bolted together.
Sprayed concrete shall be used to ensure a good and evenly distributed load transfer. Blocking
and wedging will not be permitted.
6.10.2 Materials/Equipment
6.10.2.1 Materials and Admixtures for Concrete
The following requirements apply:
Portland Cement Type I, complying with ASTM C 150 Portland Cement, shall be used.
Pozzolanic admixtures may be used at the Engineer’s approval. The total content of
such materials directly mixed into the cement and added during concrete production
shall not exceed 35 % by weight of the cement’s total content of Portland clinker and
pozzolana. Silica fume may constitute a part of the pozzolanic materials, but not more
than 10 percent by weight of the Portland clinker content. This limit also applies to other
admixtures with correspondingly high pozzolanic effect, and to the total content of such
materials.
When the sulphate content in ground water exceeds 150 ppm, sulphate resistance shall
be ensured by the use of microsilica (min 5% and maximum 10% of cement weight)
and a low ratio (≈0.45) of (water)/(cement silica). The water ratio includes added water,
moisture in the aggregates, slurry etc.
The mixing water shall meet the requirements given in Sub-section 9.4.4.
The aggregates shall be in accordance with the requirements in Sub-section 9.4.3.
Admixtures and other materials for concrete shall be so selected that the total content
of chlorides does not exceed 0.4 percent by weight of the Portland clinker. See Sub-
section 9.4.5.
To avoid damage due to alkali-silica reaction one of the two following measures shall
be taken:
Using aggregate, which by testing at an approved laboratory has proved not to be
susceptible to destruction by alkalis.
58
Bid Document Specifications
Limiting the alkali content of the concrete mix, accumulated from all sources to 3.0
kg/m3 of Na2O equivalent. As early as possible, the necessary trial concrete designs
shall be batched and tested according to the standards referred to below, for the
Engineer’s agreement of the mixes and methods to be used.
6.10.2.2 Reinforcement
The reinforcement material shall be in accordance with ASTM A185 and ASTM A 615M, as
applicable.
Unless otherwise specified, the condition of exposure shall be Moderate and the concrete
compressive strength shall meet the requirements of grade C35 concrete according to BS 5328.
Unless otherwise specified, the rate of the hardening shall be:
6.10.2.4 Methods/Execution
Normally, plain concrete shall be used. Reinforcement may be required for special purposes or
by poor rock conditions. The actual minimum thickness of the concrete shall be 300 mm, unless
otherwise specified.
It may be required that the rock surface shall be trimmed so that a reasonable homogenous
thickness of the concrete is ensured. Where no specific requirements are given, the concrete
contour shall be 200 mm inside the theoretical contour of the excavated tunnel cross section.
Loose material shall be removed from the invert along the walls, so that the concrete support
footing rests on rock.
Where concrete rock support at the face is required, concreting shall be carried out immediately
after mucking out.
6.10.3 Tolerances
The position of completed concrete surface shall not deviate more than +/- 50 mm from the
planned position.
59
Bid Document Specifications
Control procedure shall be prepared in each particular case. Production control shall be carried
out for each shift of concrete works. When using ready-mixed concrete, the production control
may be deleted provided, that the manufacturer can document adherence to the requirements.
Control and testing procedures shall be prepared in each particular case referring to relevant
standards. For determination of consistency and compressive strength BS 1881 shall apply.
6.10.5 Documentation
Not later than 2 weeks before planned commencement of any concrete work, the Contractor
shall submit for the Engineer’s approval applicable data for cement and admixtures for
concrete, as well as proposed design mix for the various concrete qualities.
Reporting on testing shall be executed according to the applicable standard and the agreed
Quality Plan.
60
Bid Document Specifications
Any combination of rock support methods included in the Bill of Quantities shall be paid by
adding the rates for the individual methods.
Rock support is specified as either at the tunnel work face or behind the tunnel work face.
Down-time of workforce and machinery due to scaling/rock support works required at the
tunnel face shall be incorporated in the unit prices.
Any extra cost incurred by the Contractor by disturbance in his work cycles due to scaling/rock
support works shall be included for in the Contractor’s unit rates and/or prices or sums.
Initial and additional rock support will be paid for provided materials and installation are in
accordance with the Specifications.
Quality control as specified shall be included in the unit prices listed. In case of rejection of
work due to breach of quality requirements, correction measures as determined by the Engineer
shall be performed at the Contractor’s cost and time. Payment for the measured quantities shall
include all deliveries, work, and other requirements described in the Specifications, shown on
the Drawings or directed by the Engineer and as required for the rock support to be installed as
specified. Backup storage of all materials and equipment required for rock support shall be kept
ready for use and in an amount sufficient to avoid delays, unless otherwise agreed with the
Engineer. Complete outfit for spraying concrete shall be available. Should the supplies
necessary for installation of rock support in a timely manner not be maintained, the Contractor
shall be responsible for provision of such temporary support as may be required for the safety
and protection of the work. The temporary support shall be exchanged with the initially
intended support as soon as possible, or the tunnel advance may be stopped. Cost for any
temporary rock support work done with materials which do not meet the quality defined in the
contract, will not be compensated.
The payment of rock support works will be paid according to the Bills of quantities.
Wire mesh or chain linked mesh or welded wire fabric shall be as per specification and
measured by installed area same as that of wire mesh heading specified in bill of quantities.
61
Bid Document Specifications
The rates include the drilling if required, short steel wires and rods and grouting if required for
anchoring, supply delivery and installation chain link mesh or wire mesh with necessary
overlap. The rates also include removal of mesh/fabric not covered by sprayed concrete. No
separate payment will be made for overlap.
Rock Bolts
Rock bolts are to be measured according to the number of bolts installed as prescribed and
complying with specifications. The length of bolts is measured as the length from the end of
the bolt in the hole to the rock surface. The rates and prices given in payment Schedules/Bills
of Quantities are to be valid for any bolt numbers and orientation decided by the Engineer.
The payment for rock bolts shall be made in meters under the item rates specified in Bill of
Quantities. The rates include the drilling in required length and diameter as specified, flushing
of holes, installation and grouting with specified grouting materials and mixes and supply and
installation with base plate, with washer and nut as well as testing, tensioning as specified in
specification including re-drilling, re-tensioning and re-grouting (if required) all complete as
required.
Measures to be taken in case of rejection of bolts when tested are as described below: If the test
results for a defined group of end anchored rock bolts do not satisfy the requirements, control
of all bolts in the group will be required. All bolts, which do not pass the pull test, with a pull
force of 80 % of the yield strength, will have to be replaced by the Contractor at his own cost.
If the test results for a given group of grouted rock bolts do not satisfy the demands defined by
AQL 4.0 in ISO 2859-1, the rates and prices for the bolts in that group will be reduced by 25
% and the Engineer will require additional bolting in order to correct for the deficiency in
quality at the Contractor’s own expense and time. The size of rock bolts stated in drawing.
Rock Dowels
The payment for rock dowels shall be made in meters length of specified diameter under the
item rates specified in Bill of Quantities. The rates include the drilling in required length and
diameter as specified, flushing of holes, grouting with specified mixes and supply and
installation with base plate, with washer and nut as well as testing as specified in specification
all complete as required. The size of rock dowels stated in drawing.
Unless otherwise specified, the strength grade of sprayed concrete shall meet the requirements
of concrete minimum strength class C25 as specified in EN-206-1. The core cylindrical strength
sprayed at site in panel of size 60*60*15 cm shall not be less than 85% of cylindrical strength
as specified above. The core size shall be 5 cm diameter and 10 cm long core sample. The
condition of environmental exposure shall be Moderate. Fibre reinforced sprayed concrete of
minimum strength class C25 used for ordinary rock reinforcement shall have a flexural strength
as specified in EFNARC.
62
Bid Document Specifications
The Engineer will present a system for the control of sprayed concrete volume delivered at the
work site. Use of accelerator or other additives is to be included in the unit prices. Cleaning of
the rock surface by high pressure water flushing or in special contaminated areas with sand
blasting prior to spraying is to be included in sprayed concrete unit prices given in Bills of
quantities. This also applies when new layers of sprayed concrete are applied as additional
support at the end of the construction period. If more than one layer is to be sprayed, the costs
for cleaning of any coating, rebound matter or other loose material before spraying of the next
layer are to be included for in the sprayed concrete unit prices.
The Contractor shall manage all the control mechanism to prevent the rebound losses. No extra
payment will be made for rebound losses as it is already included in the unitrates. The thickness
of shotcrete stated in drawings.
Cleaning of rock surfaces with high-pressure water as well as drainage of water leakages is to
be included in the unit prices above.
When abnormal over-break is accepted for payment, additional concrete volume in support
works and lining required to fill such volume will be measured by m3 and paid for
as concrete cast at the face or behind the face as the case may be. Reinforcement will be
measured and paid as in Chapter 9 Concrete works. Unless otherwise specified, the condition
of exposure shall be Moderate and the concrete compressive strength shall meet the
requirements of grade C35 concrete according to BS 5328.
1. All materials for steel support sets shall be subject to approval of the Engineer before the
order is placed.
2. Material for steel supports shall be equal to or stronger than ASTM A36, steel. All bearing
plates, beams, posts, blocking, wedging, general hardware and all lagging required shall be of
sound material free from defects that will affect structural strength when used in conjunction
with the structural steel support systems.
3. Steel supports shall consist of steel ribs (ISWB 150, 13.5 kg/m*100@1.20 m c/c for class V
and ISWB 150, 13.5 kg/m*100@1.00 m c/c), foot-plates, concrete foot blocks, lagging, liner
plates, and other suitable structural steel members, complete with bolts, nuts, wedges, tie rods
and spreaders, and other accessories required for assembling the steel supports and supporting
them in place.
63
Bid Document Specifications
4. Wedges, lagging, and blocking may be timber; however, fibre reinforced shotcrete shall be
used to replace traditional wedges, lagging, and blocking to the maximum practicable extent.
6.12.2 Execution
1. Steel ribs with or without struts shall be installed where approved, as soon as practicable
following excavation. Ribs shall be set on foot blocks which shall rest on suitable foundations.
Ribs shall be securely wedged into place using fibre reinforced shotcrete or bags of fast-set
mortar. Where fibre reinforced shotcrete or bags of fastest mortar are inadequate for this
purpose, additional supports consisting of lagging, blocking wedges, bars and the like shall be
installed against the rock face as required to transfer the rock load to the steel ribs.
2. Wedges not covered by shotcrete shall be periodically checked and tightened and such
checking and tightening shall also be done immediately before placement of the concrete lining.
3 Steel ribs shall be set to provide a minimum concrete clearance of 200 mm, and shall
be left in place permanently.
1. Steel support sets will be measured for payment by weight in tonne installed as approved
under the item rates specified in Bill of Quantities.
2. Steel support sets will be paid for at the unit price each quoted therefore in the Bill of
Quantities. The price paid shall include full compensation for furnishing and installing the steel
supports, regardless of size, together with all steel wedges, all blocking and lagging, tie rods
and bracing, and other miscellaneous steel required.
64
Bid Document Specifications
The Contractor is responsible for providing necessary assistance in connection with geological
mapping, surveying and rock stress measurements, conducted by the staff of the Engineer.
Sufficient information about the geological conditions along the tunnel is depending on access
for the geologist for mapping of geological features before the tunnel surface is covered by
sprayed concrete. This means that there will be stop periods to allow access for the geologist
for doing his mapping, or for doing other investigations.
To obtain the necessary information for making design decisions in due time, it is important
that necessity of these works is understood and that the Contractor contribute to smooth
operation. The Contractor shall contribute to efficient preparations and accomplishment of the
investigations by close collaboration with the Engineer. The Engineer’s geologist shall be given
access to the tunnel face for a period of 30 minutes for each blast round, after mucking and
prior to commencement of concrete spraying at the face. Additional stops may be instructed by
the Engineer.
65
Bid Document Specifications
The Contractor is responsible for taking care of surface water run-off from the surface around
the tunnel entrance and for taking necessary measures to prevent surface water draining from
the hillside above from entering the tunnel and divert any potential flow away from the tunnel
entrance as necessary.
He shall establish such measures as he find necessary and maintain them until he has completed
his work. The cost for this shall be included in his remuneration for temporary works and will
not be subject for separate measurement and payment. He shall implement necessary measures
for drainage and minimise erosion of tunnel spoil deposits from draining water. This shall also
include measures to safely carry water away from the areas to minimise erosion and eroded
materials being carried into water courses.
The Contractor shall maintain and repair all drainage facilities, slopes, and slope protection
structures so that they operate as required for protecting the works and surrounding areas.
The payment on care of water during construction shall be made forty percent (40%) of the
lump sum price as stated in Bill of Quantity when the contractor has completed the installation
of all equipments and facilities designated in the plan which is proposed by the contractor and
approved by engineer. Remaining 30% will be paid on the progress of work and remaining
thirty percent (30%) will be paid when the contractor has completed the removal or hand over
of equipment and facilities as required or instructed by engineer. The pump with the auxiliary
instruments will be handed over to client after the completion of work. The price shall constitute
full compensation of cost of manpower, tools, equipment and materials including, design,
furnishing, construction, installation, operation, maintenance and subsequently removal of
watering and dewatering system and other items necessary to complete the works.
66
Bid Document Specifications
9 CONCRETE WORKS
9.1 Coverage
This Chapter contains requirements for:
manufacture, transportation, placement, finishing, curing and repair of concrete
supply and placing of reinforcement
formwork
joints, joint materials, joint treatment and bearing pads
all other work associated with cast-in-place and pre-cast concrete
67
Bid Document Specifications
(Gravimetric) of Concrete
ASTM C 142 Standard Test Method for Clay Lumps and Friable Particles in Aggregates
ASTM C 143 Standard Test Method for Slump of Portland Cement Concrete
ASTM C 150 Standard Specification for Portland Cement
ASTM C 151 Standard Test Method for Autoclave Expansion of Portland Cement
ASTM C 171 Standard Specification for Sheet Materials for Curing Concrete
ASTM C 172 Standard Method of Sampling Freshly Mixed Concrete
ASTM C 173 Standard Test Method for Air Content Of Freshly Mixed Concrete by
the Volumetric Method
ASTM C 186 Standard Test Method for Heat of Hydration of Hydraulic Cement
ASTM C 192 Standard Practice for Making and Curing Concrete Test Specimens in
the Laboratory
ASTM C 227 Standard Test Method for Potential Alkali Reactivity of Cement
Aggregate Combinations (Mortar-Bar Method)
ASTM C 231 Standard Test Method for Air Content Of Freshly Mixed Concrete
By the Pressure Method
ASTM C 260 Standard Specification for Air Entraining Admixtures for Concrete
ASTM C 289 Standard Test Method for Potential Reactivity of Aggregates (Chemical
Method)
ASTM C 309 Standard Specification for Liquid Membrane-Forming Compounds for
Curing Concrete
ASTM C 441 Standard Test Method for Effectiveness Expansion of Concrete
Due to the Alkali-Silica Reaction
ASTM C 494 Standard Specification for Chemical Admixtures for Concrete
ASTM C 566 Standard Test Method for Total Moisture Content Of Aggregate By
Drying
ASTM C 595 Standard Specification for Blended Hydraulic Cements
ASTM C 617 Standard Practice for Capping Cylindrical Concrete Specimens
ASTM C 618 Standard Specification for Fly Ash and Raw or Calcined Natural
Pozzolana for Use as a Mineral Admixture in Portland Cement Concrete
ASTM C 989 Standard Specification for Ground Granulated Blast-Furnace Slag for
use in Concrete and Mortars
ASTM C 1017 Specification for Chemical Admixtures for Use in ProducingFlowing
Concrete
ASTM D 75 Standard Practice for Sampling Aggregates
68
Bid Document Specifications
9.3 Reinforcement
9.3.1 Steel
Steel reinforcement shall unless otherwise specified, be deformed high yield steel bars to
ASTM Specifications or equivalent, having a minimum yield-point stress of 400 N/mm2 and
500 N/mm2 as shown on the Drawings.
Plain round mild steel bars and fabric reinforcement to ASTM specifications or equivalent
having a minimum yield-point stress of 240 N/mm2 shall be used only where specifically
specified or shown on the Drawings.
The Contractor shall obtain from his suppliers certificates of the mechanical and physical
properties of the reinforcement and shall submit them to the Engineer for approval.
The Contractor shall provide facilities on the Site for cutting and bending reinforcement
whether he is ordering his reinforcement pre-cut and bent or not, and shall ensure that a
sufficient amount of straight bars is available on the Site for bending. Before being fixed in
position all reinforcement shall be cleaned of all mill scale, rust, dried grout, paint, oil, grease,
earth or any other substance, which may impair the bond between the reinforcement and the
concrete.
The bars shall be bent cold in strict accordance with the relevant ASTM Specifications and the
bending schedules. No bar except links and stirrups shall be bent to a smaller radius than four
times its diameter. After bending, reinforcement shall be securely bundled and labelled with
weatherproof tags or shall be marked with other approved signs by which it can readily be
identified.
The reinforcement shall be fixed in strict accordance with the Drawings as regards cover,
spacing and position, and suitable precautions shall be taken by the Contractor to prevent the
displacement of reinforcement during the placing and compaction of concrete. Where required
to support and retain the reinforcement in its correct position the Contractor shall provide
templates, pre-cast concrete blocks, stools or other supports to ensure the correct cover
thickness. Pre-cast concrete support blocks shall be manufactured from 2:1 sand/cement
mortar. They shall be well cured before use and carefully stored on the Site to avoid
contamination.
69
Bid Document Specifications
All intersections of bars in walls and slabs, all connections between binders or links and main
bars in columns or beams and all concrete blocks or other supports shall be tied with soft iron
wire ties or with fixing clips which shall not be allowed to make contact with the formwork or
to project materially into the specified cover.
All bars, which are lapped to secure continuity, shall, unless otherwise stated, overlap not less
than 40 times the diameter of the smaller bar to be lapped. Where not specifically detailed on
the Drawings the laps of reinforcement shall be staggered so that they do not fall on one plane.
Special care must be taken to comply with this requirement when using sliding formwork.
Unless shown on the drawings, or permitted by the Engineer, welding of bar reinforcement at
intersections or for the joining of bars is prohibited. Where permission is granted, the steel shall
be of weld able quality and welding shall be carried out in accordance with the
recommendations of the Institute of Welding for the welding of reinforcing bars for reinforced
concrete construction. Where galvanized reinforcement or anchor bolts are used, any damage
to the galvanizing shall be made good by application of an approved galvanizing formulation
before concrete placing is commenced. If the cement used in the concrete is de-chromatized,
one of the following measures shall be taken:
The concrete mortar in contact with the galvanized steel should be added Natrium Dichromate
in the mix (0.5 l/m3 of 10% NaCr2 solution), or The galvanized steel should be covered by a
suitable material, which prevents direct contact between the concrete mortar and the steel.
The permissible tolerance on the specified cover is minus 0 mm and plus 10 mm.
9.4 Concrete
9.4.1 Cement
Cement for concrete shall, unless otherwise specified, comply with ASTM C 150 Type I.
Cement Type II and III to ASTM C 150 or use of fly ash cement shall be used only on approval
from Engineer. Unless the concrete aggregates are proved to be completely innocuous as to
alkali reactions, all cement shall be of the low-alkali type with a maximum alkali-content of
0.6 % expressed as sodium-equivalent (Na2O + 0.658 K2O).
The Contractor shall as soon as possible after the Commencement Date notify the Engineer
from which mill or mills he intends to purchase cement and whether the cement will be supplied
in bulk or bags. Purchase orders or contracts for supply of cement shall contain quality
requirements and quality control procedures to be approved by the Engineer, and factory test
certificates shall be delivered with all shipments. Cement shall be fresh when delivered to Site
and the consignments shall be used in the order of their delivery. The Contractor shall mark the
date of delivery on each consignment and each consignment shall be stored separately and in
such manner as to be easily accessible and identifiable.
No cement in bags or other containers shall be used unless these and the manufacturer's seals
are intact at the time of mixing. If the cement is delivered in bags it shall be stored Bid
Document Specifications in a waterproof shed or building at a temperature of not less than 8ºC
and the bags shall be placed on dry boards above the floor to prevent deterioration or
70
Bid Document Specifications
contamination from any cause. Bulk cement may be used providing it is stored in an approved
waterproof container.
The Contractor shall not use cement, which has hardened into lumps, but subject to removal of
the lumps by screening, the Engineer may allow such cement to be used in non-structural
concrete mixes. Cement having been stored on the Site for more than four months shall not be
used unless proved to be satisfactory.
The Contractor shall obtain test certificates from his suppliers of all consignments and shall
submit them to the Engineer for approval.
9.4.2 Pozzolana
Not applicable
9.4.3 Aggregates
Concrete aggregates shall be sound and durable natural sand and gravels and/or crushed rock
complying with the requirements of ASTM C33 in all respect unless otherwise stated. The
Contractor shall document all requirements stated in this standard and in this Sub-chapter by
relevant test results.
The proportions of the various sizes of aggregates shall be selected so as to obtain the required
classes of concrete. Fine aggregates are particles passing through a sieve with aperture size 4.76
mm; coarse aggregates those particles not passing through that sieve.
The acceptance or rejection of the aggregate shall be based on a total evaluation of the test
results.
Coarse aggregates for concrete Class E shall have a percentage of wear by the Los Angeles
Abrasion test (AASHTO T96) of not more than 30 per cent. The equipment and methods used
for processing of aggregates shall be such that the contents of flaky or elongated particles are
minimized. The Engineer may order adjustments to the crushing process to secure acceptable
particle size. The sieving and washing facilities, and the number of fractions available for
composing the aggregate, shall be such that deviations from the desired particle size distribution
curve is kept within the permitted limits.
The contents of flaky/flat and/or elongated particles shall not exceed 20% within any size group
tested. A flat particle is defined as one having a ratio of width to thickness equal to or greater
than three. An elongated particle is defined as one having a ratio of length to width equal to or
greater than three.
The chloride content expressed as anhydrous calcium chloride shall be less than 0.1% in the
fine aggregates and 0.05% in the coarse aggregates, respectively. The sulphate content of all
aggregates shall not exceed 0.4%.
By petrographic examination according to ASTM C 295 it shall also be shown that the sand
does not contain more than 10% by count (i.e. 1% by volume) of free mica. The total amount
of sulphide minerals shall be less than 0.5%.
71
Bid Document Specifications
If the petrographic examination reveals the presence of any minerals or rock types, which may
be suspected of causing alkali reactions in concrete, the reactivity shall be tested in accordance
with RILEM AAR-1 - Final Draft, RILEM/TC-ARP/02/. In such cases the cement may be
ordered substituted by a different type or brand.
If a proposed aggregate has an absorption of 2% or more and/or a density of less than 2.60, as
determined by the methods described in ASTM C 127 and 128, the Contractor shall
demonstrate by trial mixes and tests that the strength and durability of the concrete is not
adversely affected and that adequate workability can be maintained during the placing and
compacting processes.
The particle size distribution curve for fines (defined as the part of the aggregate smaller than
4.76 mm, and including fines in the coarse aggregate) shall be within the area shown below,
permitted deviations included. The final curve shall be produced with the following maximum
deviations from the curve agreed upon after test mixes:
The particle size distribution curve for total aggregate shall be continuous. Maximum deviation
for retained percentage on a given sieve size 5 mm and larger shall be ± 10% of that agreed
upon as result of test mixes.
Samples of the proposed aggregates and a report on the method of production and processing
including details on actual screen sizes to produce each aggregate shall be submitted for
approval by the Engineer.
Aggregates shall be processed and transported separately and stored on the Site in separate
stockpiles so arranged as to prevent the intermingling of the various sizes of aggregates. The
stockpiles shall be suitably protected to prevent contamination of the aggregates from the
ground, rubbish, or by leaves, dust or other windblown materials. Any aggregate so
contaminated shall not be used in the Works, and the bottom 300 mm layer of any stockpile
shall only be used if approved.
72
Bid Document Specifications
9.4.4 Water
Water for concrete, mortar, grout or curing shall be clean, fresh and free from matter in solution
or suspension that may adversely affect the strength, durability or appearance of the Works or
cause corrosion on reinforcement and embedded items.
9.4.5 Admixtures
Admixtures to be used shall be approved by the Engineer. Trial mixes and continuous
monitoring of the concrete properties are necessary to determine quantities and type of water
reducers and retarders to be used. The use of calcium chloride or admixtures containing chloride
shall not be permitted.
Where:
w=total amount of water in the mix, including water contents of aggregates, kg/m3
73
Bid Document Specifications
Class A is a concrete of low heat, low slump and low permeability for massive structures such
as the dam and intakes and some sections of the powerhouse. Approved water reducers shall
be added to obtain high workability. The content of aggregates < 0.250 mm should not be less
than 8% of the 0/8 mm fraction. A low content may be compensated by the use of pozzolana.
Class B is a concrete for certain structures without exposure other than atmospheric. The
workability shall be medium to high and water reducers may be used.
Class C is a high-strength concrete of low permeability for liquid-retaining and certain other
structures. Water reducers shall be added to obtain very high workability. The content of
aggregates < 0.250 mm should not be less than 8% of the 0/8 mm fraction. A low content may
be compensated by the use of pozzolana.
Class D is a high-strength concrete for pre-cast members. Super-plasticisers and silica fume
shall be used to obtain very high workability.
Class E is a special high-strength concrete with high abrasive resistance for use in the lower
parts of radial gate openings. Super-plasticisers and silica fume shall be used. The slump values
given in Table 9-1 are for guidance only. Actual slump values shall be determined from trial
mixes and adjusted as required at the Site. For blinding concrete and for temporary Works the
prescribed mixes given in Table 9-2 may be used.
74
Bid Document Specifications
Expected characteristic 12 20
strength 1) (N/mm2)
The characteristic strength at 28 days of the mix, xc, based on testing of n samples may be
determined from the formula:
xc = xm – ks
where xm and s are the mean and the standard deviation of the test results respectively. The
coefficient k which is a function of the number of samples, has the following values:
n 3 4 5 6 7 8 9 10
k 2.50 2.14 1.96 1.86 1.79 1.74 1.70 1.67
n 12 15 20 25 30 >30
k 1.62 1.58 1.53 1.49 1.47 1.45
The relationship between the class of concrete and the characteristic strength as measured on
cylinders shall accord with Table 9-3.
75
Bid Document Specifications
1day
7 days 28 days
(boiling)
A 10 15 20
B 10 15 20
C 16 23 30
D 25 33 40
E 30 40 50
The trial mix shall be deemed as approved if the characteristic strength, xc, so determined is
greater than the specified compressive strength. For concrete of Class A and C trial mix samples
shall in addition satisfy the requirements of permeability as specified in 9.4.7.
Notwithstanding the individual requirements to cement, aggregates and water, no concrete for
permanent works shall contain more soluble chlorides (as NaCl) than 0.4%, and not more
soluble sulphates (as SO3) than 4.0%, all by weight of the cement.
Batch mixing machines shall be provided in such numbers and of such capacity as to ensure a
continuous supply of freshly mixed concrete with at least one standby unit at all times during
construction. Continuous mixing machines shall not be used.
The aggregates and the cement shall be thoroughly mixed in a clean mechanical mixer until a
uniform mixture is obtained and the water added on basis of the approved mix design. The
mixing shall continue for at least 1 1/2 minutes after all the water has been added.
Mixers shall be completely emptied before receiving materials for the succeeding batch. Mixers
must be kept clean and shall be washed out after stopping work and at the end of each shift.
On commencing the work with a clean mixer the first batch shall contain only two thirds of the
normal quantity of coarse aggregate for the batch to compensate for the fine material and
cement which adheres to the drum. This batch shall also be mixed for at least one minute longer
than the normal specified time. This batch shall be used in Permanent Works only if approved
by the Engineer.
Concrete must be so transported and placed that contamination, segregation or loss of the
constituent materials does not occur. During transport concrete shall be carried in purpose-
made agitators operating continuously.
76
Bid Document Specifications
Concrete shall not be placed in water except with the written consent of the Engineer, nor shall
any concrete be subjected to running water until the concrete has hardened. All faces against
which concrete is to be placed shall be clean and free from oil, dirt, mud, saw dust, shavings or
other debris. Formwork, reinforcement and inserts, which may have become encrusted with
mortar or grout during previous placing of concrete, shall be cleaned of all such mortar and
grout.
Immediately before placing of concrete commences, all surfaces against which concrete is to
be placed shall be moistened and hosed down by the use of high velocity air/water jets.
Temporary openings in the formwork shall be provided to drain off excess water and any debris.
Where required, sufficient drains or dewatering plant shall be provided to keep the area where
concreting is in progress free from running or standing water. Such drains, hoses, pipes, pumps
or other plant shall be securely fastened to prevent disruption during placing of concrete.
Where other structures than liquid-retaining structures are to be placed, preparation of rock
surfaces for concreting may be relaxed to removal of all loose material by means of high
velocity air/water jets only, if approved by the Engineer.
Rock surfaces shall be kept continuously moistened for at least 24 hours before placing of
concrete. Rock surfaces sloping less than 15° shall immediately before placing of concrete
commence be treated with a thin layer of mortar of the same cement/water ratio as that of the
concrete to be placed.
Concrete when deposited shall have a temperature of not less than 5°C and not more than shown
in Table 9-4. It must be compacted in its final position within 30 minutes of discharge from the
mixer unless carried in purpose-made agitators, operating continuously, when the time will be
77
Bid Document Specifications
within 1 hour of the introduction of water to the mix and within 30 minutes of discharge from
the agitator.
Concrete shall be placed continuously over the area between construction joints to uniform
levels in layers not exceeding 500 mm in such a manner as to avoid segregation. In liquid-
retaining structures the concrete shall not be allowed to rise faster than 0.5 m/h and not slower
than 0.15 m/h.
Fresh concrete shall not be placed against in situ concrete, which has been in place for more
than 30 minutes, unless approved retarders have been applied or a construction joint is formed.
When in situ concrete has been in place for more than 4 hours, no further concrete shall be
placed against it for a further 20 hours or such other period of time as directed. Concrete shall
not be dropped from a height greater than 2.0 m. If certain sections of the Works require
concrete to be deposited from a greater height, the concrete shall be deposited through a tremie
or other approved pipes or chutes.
Each concreting team shall include a competent steel fixer and a carpenter who shall check that
the reinforcement, formworks, and other fittings are in the correct position before pouring, and
who shall be in attendance to ensure that reinforcement, formworks and fittings remain in
position while the placing and compacting of concrete is being carried out.
The time limits for placing and compacting concrete given above are based on a mix without
any additives. The Engineer may relax those limits when approved plasticizers giving
retardation or retarders are applied.
9.4.11.2 Compaction
Unless otherwise directed, all concrete shall be compacted by means of approved immersion
type internal vibrators with a minimum immersed frequency of 120 Hz and sufficient amplitude
to consolidate the concrete adequately. At least one spare vibrator shall be kept at the location
of every pour during concrete placement. Vibrators shall be operated in a near vertical position
and shall not be used to transport concrete within the forms.
Each layer of concrete shall be carefully rammed and vibrated allowing the vibrator to penetrate
into the previous layer until trapped air bubbles are released and stone pockets are eliminated
and until a homogenous dense mass of concrete is obtained with no honeycombing, pitting or
planes of weakness. Spatulas of adequate length shall be used to ensure that the concrete is well
rammed between the reinforcement and the formwork, around embedded items and into the
corners of forms. The number and size of vibrators shall be such as to ensure vibration
throughout the entire volume of the concrete and shall be applied to points uniformly spaced
and at such distance apart that their cones of influence shall overlap and the whole mass of the
concrete shall become plastic. Care must be taken to ensure that the concrete is not over-
vibrated causing excess water and laitance to form on top of the concrete. Any water
accumulating on the surface of newly placed concrete shall be removed by approved means
and no further concrete will be placed thereon until such water is removed.
Vibrators shall not be applied to, or have any contact with, reinforcement or formwork but shall
be carefully inserted to avoid contact with reinforcement and formwork as far as is practicable.
78
Bid Document Specifications
Additives for underwater concreting shall be used to reduce segregation and wash-out of the
concrete during casting. Concrete shall not be placed in flowing water. Underwater concrete
shall be placed in position by a tremie or other approved pipelines. The casting should proceed
continuously and with one casting front.
During and after concreting underwater, pumping or dewatering operations in the immediate
vicinity shall be suspended until the Engineer permits them to be continued. Water shall not be
allowed to flow over or exert any unilateral pressure against concrete until at least 48 hours
after deposition.
The temperature in the concrete when placed shall always be as low as possible, and shall under
no circumstances exceed the values of Table 9-4.
a) All aggregate stockpiles, water lines and tanks as well as the mixer shall be protected from
direct sunshine.
c) Mixing water shall be cooled by the addition of ice to the storage tanks. The Contractor shall
have available at Site a suitable plant for ice production. Where the above++ precautions are
inadequate concreting shall be carried out during the cooler parts of the day or during the night
as may be directed by the Engineer. Ambient temperature, aggregate temperature, concrete
79
Bid Document Specifications
transport length and type of vehicles will be influential as to what temperature the concrete
should have when leaving the mixer. The contractor shall provide sufficient transportation
capacity to ensure a continuously casting. The Contractor is responsible for ensuring further
cooling, if necessary. Heat reflecting rather than absorbing concrete containers should be used
for transport. The Contractor shall describe in detail the means and equipment to be used. The
Contractor shall evaluate the effects of curing temperatures and thermal gradients, and take this
into account in the construction. Thermal gradients greater than 30oC per 300 mm thickness
are normally not acceptable. Severe thermal gradients shall be limited by providing cover and
insulation of freshly exposed concrete. In order to reduce premature drying of the concrete
during transport and placing, all chutes, shuttering and reinforcement shall be cooled by
watering when possible, or shall otherwise be shaded from direct sunlight. Any water so used
shall be removed by setting with compressed air before placing the concrete.
No traffic or constructional loads shall be permitted on newly placed concrete until it has
hardened sufficiently to take such traffic or load without surface damage or deformation. A
curing membrane shall be applied on horizontal surfaces continuously, after final levelling of
the top surface. During the following curing period horizontal surfaces shall be protected from
evaporation of water by either watering or covering with hessian, canvas or an impermeable
sheet, as soon as covering can be performed without leaving prints on the surface.
Vertical surfaces shall be protected from excessive evaporation of water due to sun and wind
by keeping the formwork in close contact with the concrete until continuous application of
water or covering can be performed. Under extreme conditions covering and watering after
stripping may prove necessary so that no damage occurs to the surface of the concrete. Covering
with an absorbent material kept damp or an impermeable sheet close enough to the surface to
prevent excessive circulation of air shall be used. Liquid curing membranes are not considered
as sufficient alone. Concrete shall be protected as described for at least seven days unless
otherwise approved by the Engineer.
80
Bid Document Specifications
The QA-system is subject to approval from the Engineer, and shall contain:
Organization plan showing position and responsibilities for persons who have influence on
quality of the concrete and of the work. Record of past experience from similar demanding
concrete work, and education in this respect, shall be given.
Description of the facilities at disposal for producing and transport of the concrete (and its
constituents, where relevant), and controlling its quality, to the extent necessary to demonstrate
capability to comply with the requirements.
- Transport, storage and dosage facilities for aggregates, cement, pozzolana, additives and
water.
- Cooling facilities for water. Ice production facilities. System, if needed, for cooling
aggregates.
- Mixers. Type and capacity. Means of controlling and recording actual mix data. Calibration
of scales and volumeters. (Printout giving all mix data, planned and actual, shall follow each
batch)
- Aggregate production plant. Facilities for crushing, sieving, washing and storage.
- Backup facilities.
Description of the internal control system that the Contractor will propose for his activities, and
of the system for reporting to the Engineer, that will ensure sufficient guarantee for meeting the
requirements.
Testing shall be performed according to the relevant ASTM standards or other relevant
standards. The Contractor's testing shall be carried out in the materials testing laboratory
established at Site, ref. Chapter 1.
Test reports shall record all data required for sample and batch identification and test results
shall be presented in a format approved by the Engineer and which shall include the location in
the Works of the concrete presented by the sample. Two copies of each test result shall be
submitted to the Engineer within 24 hours of the test being completed. In addition a weekly
summary report of the main data shall be presented to the Engineer. Testing shall be carried out
as often as the Engineer considers necessary to confirm the conformance of the concrete work
to the Contract. Unless otherwise approved, the minimum frequency of testing of the concrete
shall be as specified in Table 9-5.
81
Bid Document Specifications
Slump tests according to ASTM C 143 at the point of mixing and at the point of placing shall
be carried out as often as necessary to verify and control consistency, and when required by the
Engineer. Slump tests shall be made and recorded at least once for every section of concrete
being placed. For every 10 m3 of sprayed concrete placed, four samples shall be taken to be
cured and tested in the laboratory. Two samples being tested at 7 days and the other two samples
at 28 days. The concrete cylinders tested at 7 days are intended to be indicative of the strength
only, whereas the cylinders tested at 28 days shall be taken to represent the sprayed concrete
placed in the works. The concrete shall be accepted if the 28 day
characteristic strength determined exceeds the specified compressive strength.
Any such further tests or the removal of condemned concrete, replacement, including the
removal and replacement of any satisfactory concrete necessarily removed as a result of the
remedial measures directed by the Engineer, shall be at the Contractor's responsibility.
9.5 Joints,
9.5.1 Waterstop and Jointing Materials
Waterstop and jointing materials shall be obtained from an approved manufacturer. All
waterstop and jointing materials, which are not required for immediate use, shall be stored at
all times in a cool, damp environment.
Waterstop shall be manufactured from P.V.C. (polyvinyl chloride). The tensile strength shall
be minimum 12.5 N/mm2 and elongation before rupture minimum 300 %. Unless otherwise
specified, the waterstop shall be 200 mm wide.
No waterstop shall be shipped from the factory until certified test reports have been approved
by the Engineer. Supplementary samples of the waterstop shall be taken after delivery to the
Site and tested, at the Contractor's expense, in a laboratory approved by the Engineer.
82
Bid Document Specifications
Intersections and junctions shall be obtained prefabricated from the approved manufacturer.
All site joints shall be welded strictly in accordance with the manufacturer's recommendations.
Waterstop shall be located and maintained accurately in position, and details of the proposed
method of fixing shall be submitted to the Engineer for approval. On no account shall waterstop
be secured by nails or by any other means involving puncture of or damage to the waterstop
material. Waterstop shall, unless otherwise specified, have minimum 70 mm concrete cover.
Joint filler shall be manufactured of natural bonded cork or other approved material. Joint filler
shall be cut and trimmed accurately to suit the joint profile and shall be maintained accurately
in position by means of an approved adhesive.
Joint sealing compounds shall be approved rubber/bituminous compounds suitable for sealing
joints in horizontal and vertical/sloping concrete surfaces as appropriate. Sealing compounds
shall be applied strictly in accordance with the manufacturer's instructions and shall completely
fill the joint recess.
If further joints are required, the Contractor shall submit for approval proposals for the layout
of construction joints before concreting is started.
Where vertical construction joints are required the joint face of the first cast concrete shall be
finished against a stopping off board, or vertical end formwork suitably notched to pass the
reinforcement. The surface film of the first cast concrete shall be removed before the concrete
has hardened to expose the aggregate and leave a sound, clean irregular surface. Just before
concreting is resumed, the roughened joint surface shall be thoroughly cleaned and freed from
loose mortar, moistened and then treated with a thin layer of mortar of the same sand/cement
ratio as the concrete to be placed worked well into the surface. The Contractor must take
precautions to avoid segregation of the concrete along the joint plane and to obtain thorough
compaction. For horizontal joints a layer of mortar shall not be used, but the paste content shall
be slightly increased in the first layer.
Horizontal construction joints shall have a gentle slope for drainage, and shall be left free from
protruding rock, vibrator holes and other irregularities. Before concreting is continued, and as
late as feasible, the weak surface paste, film and contamination shall be removed to expose a
fresh, clean mortar and aggregate surface. This shall be done by use of high pressure water jet
of at least 40 MPa (approx. 6000 psi), or, when necessary for concrete having reached higher
strength, by sandblasting, as directed by the Engineer. Degreasing agents shall be used to
remove any oily impurities, "Green cutting" i.e. removing of film and laitance when the
concrete approaches final set, shall only be done when explicitly permitted by the Engineer,
and shall be done with great caution so as not to damage the concrete and reduce the strength
of the paste near the surface. After treatment, any loose material, sand and water shall be
removed before concreting.
83
Bid Document Specifications
9.7.2 Concrete
Measurement of concrete shall be made in cubic metres placed in accordance with the line and
levels indicated on the Drawings or as required by the Specifications, or directed by the
Engineer. No deductions shall be made for the volume occupied by reinforcement, or individual
voids or embedded materials less than 0.05 m3, rebates, fillets and the like. No additional
measurement will be made for additives, admixtures, pouring restrictions or requirements,
consolidation, curing materials or methods, tests or hand finishing or making good where
directed.
Blinding concrete shall be measured by the net area, and the specified thickness shall be the
minimum thickness.
The rates for concrete shall include costs for any admixture whether ordered by the Engineer
or not.
If separate items are provided in the Bill of Quantities for finishing of top surfaces to Class UA,
UB or UC, the area measured shall be the net area shown on the Drawings or directed by the
Engineer including holes and openings in the finished surfaces each less than 0.5 m2 in area.
84
Bid Document Specifications
10 GABION WORKS
Gabions are wire mesh boxes filled with selected gravel or rock of suitable size and shape to
facilitate packing. The grain size of the gravel or rock shall be greater than about 1.5 times the
diameter of the mesh openings, but at least 10 cm. The standard type gabion shall be fabricated
from flexible hot-dip galvanised wire and/or wire mesh plastic coated type and sizes specified
below, with a selvedge as specified in the following.
The mesh shall be hexagonal woven mesh, the joints formed by twisting each pair of wires
through three half turns. The size of the mesh shall conform to the standard specification issued
by the manufacturer and shall be not greater than 1/3 of the smallest stone filled in the gabion.
All wire used in the fabrication of the gabions and in the wiring operations during construction
shall be "Mild Steel Wire", i.e. wire having an average tensile strength of 44 kg per square
millimetre. The diameter of the wire used in the fabrication of the mesh shall be 3.0 mm
according to the engineering requirements. Test shall be made on the wire before fabrication of
the gabions on a sample 30 cm long. Elongation shall not be less than 12 %. All wires used in
the fabrication of the gabions and in the wiring operations during construction shall be
galvanised. The minimum weight of the zinc coating shall be 275 gr/m2.
All edges of the standard gabions including end panels and the diaphragms, if any, shall be
mechanically selvedge in such a way as to prevent unravelling of the mesh and to develop the
full strength of the mesh. The wire used for the selvedge shall have a diameter greater than that
of the wire used to form the mesh. The size of the mesh wire, and selvedge wire shall be 10
SWG, 8 SWG respectively. And the size of binding wire shall be 12 SWG.
All wire used in the fabrication of gabions and wiring operations during construction shall
comply with the requirements of NS: 169-2045. The wires shall be galvanized with heavy
coating of zinc.
- Length = 3.0 m
- Width = 1.0 m
- Height = 1.0 m
- Diaphragm= every 1m
Sufficient lacing and connecting wire shall be supplied with the gabions for all wiring
operations to be carried out in the construction of the gabion work. The quantity of such wire
is estimated to be 8 percent of the gabions supplied. Gabions shall be packed carefully and tight
by hand to ensure long term stability of gabion structure. According to the engineering
requirements, the gabions might incorporate diaphragms to form cells having a length not
greater than one time and half the width of the gabion. A tolerance on the diameters of all wire
in the above paragraphs of ±2.5 percent is permitted. The length of the gabions is subject to a
tolerance of ±3% and the height and the width to a tolerance of ±5%.
In case stabilization and anchoring of gabions are required, such stabilization and anchoring
85
Bid Document Specifications
The tightness of the twisted joints shall be such that a force of not less than 1.7 kN is required
when pulling on one wire to separate it from the other wire, provided each wire is prevented
from turning under the applied forces, and the wire is all in the same plane. The wire mesh
dimensional layout is as per the diagram below:
X(mm) Y(mm)
80 100
86
Bid Document Specifications
If otherwise not specified in the contract, no separate measurement and payment shall be made
for sampling samples and testing of materials, trials and construction control. It shall be deemed
to have included in the rates.
87
528 000 E 528 100 E 528 200 E 528 300 E 528 400 E
9+200
3 280 100 E
0
9+250210
AK40
5
2 07 0
50 200
20
25 5
20 197
0+425
9+300
0+400
0+375
T-5
3 280 000 E
0+350
0+325
820.40
0+300
50
AK-2
19
75
0+2
0
25
0+
9+350
5
22
0+
0
20
0+ 1925
0
75
.0
50
1
0+
R1
9+400
50
3 279 900 E 0+ 1 1845
1840
5
0+12 0
1 90 18 3
5
9+450
0
0+10 1830
5
0+07
4.00
4.00 1825
9+500 0
0+05 4.00
3 279 800 E
0
182
5
0+02
5
181
9+550
0
0+00
0+0
0+0
0
00
0+0
20 Kh 181
10
ols
0+030 i
0+0 0
04
50
0+
60
0+0
0
07
0+
9+600 08
0
0+
3 279 700 E 0 90
0+
0+
1 00 DETAIL B
110 SCALE 1:250
0+
120
0+
9+650 130
0+
136
0+
SCALE 1:2000
LONGITUDINAL SLOPE
TUNNEL INVERT LEVEL
GROUND LEVEL (MASL)
2050
2075
2100
1800
1825
1850
1875
1900
1925
1950
1975
2000
2025
CONSULTANT :
1818.090 1877.82 0+025
SCALE 1:2000
1820.340 1968.16 0+250
ADIT 3 PROFILE
Prepared By:
Surveyed By:
1821.090 2021.06 0+325
2066.98 0+475
2068.27 0+500
Title
PROFILE
ADIT TUNNEL III
Sheet. No.
1829.57
5 5
1 1821.80 1
4 M LONG, 25 MM DIA.
4.00
ROCK BOLTS @ 2 M C/C
4.00
1817.80
SECTION A-A
5
1
1821.80
4.00
1817.80
1:100
8.00
3 279 775 E
0+0
00
0+
3 279 750 E
01
0
0+0
20
0+030
0
04
0+
50
0+0
0
06
3 279 725 E
0+
0
07
0+ 08
0
0+
0
09
0+
3 279 700 E
0
10
0+
0
11
0+
0
12
0+
3 279 675 E
0
13
0+
6
13
0+
3 279 650 E
2050
2025 ALIGNMENT DIRECTION N310°
2000
1975
1950
1925
1900
1850
1825 LEVEL
1:100
1800
0+000
0+025
0+050
0+075
0+100
0+125
0+150
0+175
0+200
0+225
0+250
0+275
0+300
0+325
0+350
0+375
0+400
0+425
0+450
0+475
0+500
CHAINAGE (m)
2000.48
2021.06
2041.10
2053.56
2059.28
2063.94
2066.28
2066.98
2068.27
1833.01
1877.82
1897.62
1907.67
1917.35
1939.50
1952.57
1940.25
1948.57
1957.14
1968.16
1983.63
GROUND LEVEL (m amsl)
+7
00
12
0
185
+7
50
75
0+2
OW
12
FL
+8
18
25
00
50
0+2
18
00
0+22
12
5
17
+8
75
50
0+
20
0
17
50
12
0+
+9
17
5
00
172
0+
15
5
0
12
+9
50
0+
17
12
00
5
13
0+
+0
10
16
00
0 DETAIL AT B
75
16 0+ SCALE 1:200
50 07
13
5
+0
50
0+
05
0
16
1611.50
25
13
0+
+1
02
00
5
0+
16
00
00
0
13
+1
SO
50
P1
1575
1605.50
4 M LONG, 25 MM DIA.
ROCK BOLTS @ 2 M C/C
5.50
5.00
1600.00
PLAN
SCALE 1:2000
3.75 5.00 3.75 1.50 1.20 2.00
1.10 0.43
1850
1825
1800 5
1
1775
1750
1725 5
1
1700
5.50
1675
1650
10.00
1625
1600
1:100 DETAIL A
SCALE 1:200
1575
CHAINAGE (M)
0+000
0+025
0+050
0+075
0+100
0+125
0+150
0+175
0+200
0+225
0+250
0+275
0+300
0+325
1600.098 1612.05
1600.348 1631.08
1600.598 1653.70
1600.848 1678.17
1601.098 1695.82
1601.348 1712.39
1601.598 1728.73
1601.848 1755.66
1602.098 1786.77
1602.348 1812.89
1602.598 1832.87
1602.848 1850.28
1860.17
GROUND LEVEL (MASL)
LONGITUDINAL SLOPE
LONGITUDINAL PROFILE
SCALE 1:2000
1850
1825
1800
1775
1750
1725
1700
1650
1625
1600
1:100
0+000
0+025
0+050
0+075
0+100
0+125
0+150
0+175
0+200
0+225
0+250
0+275
0+300
0+325
CHAINAGE (m)
1612.05
1631.08
1653.70
1678.17
1695.82
1712.39
1728.73
1755.66
1786.77
1812.89
1832.87
1850.28
1860.17
GROUND LEVEL (m amsl)
PLAN
SCALE 1:200
1500
1475
1450
1425
1400
1375
1350
-0+075
-0+050
-0+025
0+000
0+025
0+050
0+075
0+100
0+125
0+150
0+175
0+200
0+225
0+250
CHAINAGE (M)
1392.21
1390.04
1393.24
1407.05
1419.78
1444.30
1464.68
1477.13
1478.97
1474.92
1474.92
1475.74
1478.17
1479.33
GROUND LEVEL (MASL)
1396.611
1394.611
1392.611
1390.611
1388.611
1386.611
1384.611
1382.611
1380.611
1378.611
TUNNEL INVERT LEVEL
(MASL)
LONGITUDINAL SLOPE
LONGITUDINAL PROFILE
SCALE 1:2000
2
1
5
1
5.50
19.00
LONGITUDINAL PROFILE
DETAIL B
SCALE 1:200
ALIGNMENT DIRECTION
N90°
1500
1450
1425
1400
1375
-0+075
-0+050
-0+025
0+000
0+025
0+050
0+075
0+100
0+125
0+150
0+175
0+200
0+225
0+250
CHAINAGE (m)
1392.21
1390.04
1393.24
1407.05
1419.78
1444.30
1464.68
1477.13
1478.97
1474.92
1474.92
1475.74
1478.17
1479.33
GROUND LEVEL (m amsl)
2.00 1.20
0
1.5
4.20
4.00
4.00
4.00
4.10
150mm THICK
50 mm THICK SFR SHOTCRETE 100 mm THICK SFR SHOTCRETE WIREMESH SHOTCRETE
4.00
4.00
4.00
RIB AT SPACING 1.2m
4.10 4.20 4.40
200mm THICK
WIREMESH SHOTCRETE
5.75
5.70
5.60
5.50
5.50
5.50
150mm THICK
5.00
WIREMESH SHOTCRETE
100mm THICK
SFR SHOTCRETL RIB (ISWB 150, 18.5 kg/m
*100 @ 1.0m c/c)
5.00 5.00
In order to attain these objectives, Works should be itemized in the Bill of Quantities in sufficient detail to
distinguish between the different classes of Works, or between Works of the same nature carried out in different
locations or in other circumstances which may give rise to different considerations of cost. Consistent with
these requirements, the layout and content of the Bill of Quantities should be as simple and brief as possible.
Content
The Bill of Quantities should be divided generally into the following sections:
(a) Preamble;
(b) Work Items (grouped into parts);
(c) Day works Schedule;
d) Provisional Sums; and
(d) Summary.
Preamble
The Preamble should indicate the inclusiveness of the unit prices, and should state the methods of measurement
which have been adopted in the preparation of the Bill of Quantities and which are to be used for the
measurement of any part of the works.
Work Items
The items in the Bill of Quantities should be grouped into sections to distinguish between those parts of the
Works which by nature, location, access, timing, or any other special characteristics may give rise to different
methods of construction, or phasing of the Works, or considerations of cost. General items common to all parts
of the works may be grouped as a separate section in the Bill of Quantities.
Day work Schedule
A Day work Schedule should be included only if the probability of unforeseen work, outside the items included in
the Bill of Quantities, is high. To facilitate checking by the Employer of the realism of rates quoted by the
Bidders, the Day work Schedule should normally comprise the following:
(a) A list of the various classes of labor, materials, and Constructional Plant for which basic day work rates
or prices are to be inserted by the Bidder, together with a statement of the conditions under which the
Contractor will be paid for work executed on a day work basis.
(b) Nominal quantities for each item of Day work, to be priced by each Bidder at Day work rates as bid. The
rate to be entered by the Bidder against each basic Day work item should include the Contractor’s profit,
overheads, supervision, and other charges.
Provisional Sums
A general provision for physical contingencies (quantity overruns) may be made by including a provisional sum
in the Summary Bill of Quantities. Similarly, a contingency allowance for possible price increases should be
provided as a provisional sum in the Summary Bill of Quantities. The inclusion of such provisional sums often
facilitates budgetary approval by avoiding the need to request periodic supplementary approvals as the future
need arises. Where such provisional sums or contingency allowances are used, the Contract Data should state
the manner in which they will be used, and under whose authority (usually the Project Manager’s).
Summary
The Summary should contain a tabulation of the separate parts of the Bill of Quantities carried forward, with
provisional sums for Day work, for physical (quantity) contingencies, and for price contingencies (upward price
adjustment) where applicable.
These Notes for Preparing Specifications are intended only as information for the Employer or the person
drafting the Bidding documents. They should not be included in the final documents.
Bill of Quantities
1 Provisional Sum
Procument Item Details
SL.
Item Description Unit Quantity Unit Rate(NPR) Amount(NPR)
No
1 Provisional sum for required unforeseen works as P.S. 1.0 500000.0 500,000.00
assigned by Project Manager (rate of such items will be
based on Day Works schedule submitted during
bidding).
2 Construction work
Procument Item Details
Skilled Manpower
67 Manday 300.0
Unskilled manpower
68 Manday 600.0
Aggregrate
69 m3 30.0
Cement
70 Ton 1.5
Reinforcement
71 Mt 1.5
Sand
72 m3 25.0
Dialatometer Test
77 Set 1.0
VAT
Grand Total