TAMPINES N9 C15-16

8 BLOCK PHASE 1 963A,963B,963C,963D


PHASE 2 965A,965B,965C,965D UPDATE:- 19.5.2021
TP N9 C15-16 (PHS) Total mould= 6 Sep-21 Nov-21
1 LVL 4 BLOCK FIRST 4 BLOCK SECOND
MOULD MARKING SHAPE WALL INNER CORE QTY TOTAL QTY REMAKS
NEED PHASE 1 PHASE 2
3 PHS-1 SQUARE- SHAPE 200 = 1 15 1 1
3 PHS-1X 2100X1950 300 = 1 30 2 1 1
3 PHS-1T 400 = 5 1
M1 3 PHS- 1TX 250 500 = 3 2
96 5 MONTH
3 PHS-2 C-SHAPE 15 1 1
3 PHS-2X 2100X1400 30 2 1 1
3 PHS-2T 1
3 PHS-2TX 2
4 PHS-1 SQUARE 2800X1750 200 = 1 83 6 2 4
4 PHS-1T 300 = 7 6
M2 250 169 8 MONTH
4 PHS-2X C-SHAPE 2800X1200 400 = 4 75 5 4 1
4 PHS- 2TX 500 = 1 5
4 PHS-1X SQUARE 2800X1750 200 = 1 113 8 6 2
4 PHS- 1TX 300 = 7 8
M3 250 210 9 MONTH
4 PHS-2 C-SHAPE 2800X1200 400 = 4 83 6 2 4
4 PHS-2T 500 = 1 6
4 PHS -3 SQUARE- SHAPE 200 = 1 60 8 1 7
4 PHS-3X 1960X2450 300 = 1 60 8 1 7
4 PHS -3T 400 = 9 6
M4 4 PHS-3TX 250 500 = 2 6
164 8 MONTH
5 PHS - 3 15 1 1
5 PHS - 3X 15 1 1
5 PHS- 3T 1
5 PHS- 3TX 1
5 PHS- 1 SQUARE 1850X2600 200 = 1 109 8 4 4
5 PHS-1T 300 = 1 8
M5 250 202 9 MONTH
5 PHS- 2X C-SHAPE 1850X2050 400 = 6 79 6 2 4
5 PHS-2TX 500 = 2 6
5 PHS- 1X SQUARE 1850X2600 200 = 1 79 6 2 4
5 PHS-1TX 300 = 1 6
M6 250 202 9 MONTH
5 PHS- 2 C-SHAPE 1850X2050 400 = 6 109 8 4 4
5 PHS- 2T 500 = 2 8
1043 1043 77 32 45

UPDATE:- 19.5.2021
TP N9 C15-16 (PHS) Total mould= 8 Sep-21 Nov-21
1 LVL 4 BLOCK FIRST 4 BLOCK SECOND
MOULD MARKING SIZE EXCLUDE AL QTY TOTAL QTY REMAKS
NEED PHASE 1 PHASE 2
PBU-1 3 3 2 1
M1 47 3 MONTH
PBU-1A 4490X1960 41 3 2 1
PBU-1AT 3
PBU-1X 3 3 2 1
M2 PBU-1AX 4490X1960 41 47 3 2 1 3 MONTH
PBU-1AXT 3
PBU-2 14 14 8 6
M3 PBU-2A 4890X1960 181 209 14 8 6 10 MONTH
PBU-2AT 14
PBU-2X 14 14 8 6
M4 PBU-2AX 4890X1960 181 209 14 8 6 10 MONTH
PBU-2AXT 14
PBU-3 4 4 1 3
PBU-3A 56 64 4 1 3
PBU-3AT 4
M5 4715X1960 5 MONTH
PBU-5 1 1 1
PBU-5A 14 16 1 1
PBU-5AT 1
PBU-3X 4 4 1 3
PBU-3AX 56 64 4 1 3
PBU-3AXT 4
M6 4715X1960 5 MONTH
PBU-5X 1 1 1
PBU-5AX 14 16 1 1
PBU-5AXT 1
PBU-4 15 15 6 9
M7 PBU-4A 4890X1960 182 212 15 6 9 10 MONTH
PBU-4AT 15
PBU-4X 13 15 6 9
M8 PBU-4AX 4890X1960 160 186 15 6 9 9 MONTH
PBU-4AXT 13
1070 1070 148 68 80
TAMPINES N9 C15-16
8 BLOCK PHASE 1 PHASE 1 963A,963B,963C,963D
PHASE 2 PHASE 2 965A,965B,965C,965D UPDATE:- 29.6.2021
TP N9 C15-16 (SPW) Total mould= 9 Dec-21 Mar-22
1 LVL 4 BLOCK FIRST 4 BLOCK SECOND
MOULD MARKING THK QTY TOTAL QTY REMAKS
NEED PHASE 1 PHASE 2
SPW 2 - 3A 200 1 1 1
SPW 2 - 5C 200 1 1 1
SPW 2A - 3A 200 14 1 1
M1 SPW 2A - 5C 200 10 52 1 1
SPW 4 - 3A 200 1 1 1
SPW 4A - 3A 200 14 1 1
SPW 5 - 5C 200 11 1 1
SPW 1 - 3B 250 1 1 1
SPW 1 - 3C 250 1 1 1
SPW 1A - 3B 250 14 1 1
M2 40
SPW 1A - 3C 250 9 1 1
SPW 4 - 3D 250 1 1 1
SPW 4A - 3D 250 14 1 1
SPW 3 - 3BX 250 15 1 1
SPW 4 - 3B 250 15 1 1
SPW 4 - 3C 250 1 1 1
M3 SPW 4A - 3C 250 12 72 1 1
SPW 5 - 5A 250 1 1 1
SPW 5A - 5A 250 14 1 1
SPW 6A - 5AX 250 14 1 1
SPW 2 - 3B 250 1 1 1
SPW 2 - 3C 250 1 1 1
SPW 2A - 3B 250 14 1 1
SPW 2A - 3C 250 9 1 1
M4 53
SPW 3 - 3C 250 1 1 1
SPW 3A - 3C 250 12 1 1
SPW 5 - 3B 250 1 1 1
SPW 5A - 3B 250 14 1 1
SPW 2 - 3D 200 1 1 1
SPW 2 - 5A 200 1 1 1
SPW 2A - 3D 200 14 1 1
M5 45
SPW 2A - 5A 200 14 1 1
SPW 3 - 3D 200 1 1 1
SPW 3A - 3D 200 14 1 1
SPW 1 - 3D 200 1 1 1
SPW 1 - 5A 200 1 1 1
SPW 1A - 3D 200 14 1 1
SPW 1A - 5A 200 14 1 1
SPW 3 - 5AX 200 1 1 1
M6 SPW 3A - 5AX 200 14 88 1 1
SPW 4 - 5A 200 1 1 1
SPW 4A - 5A 200 14 1 1
SPW 5 - 3C 200 13 1 1
SPW 6 - 3B 200 1 1 1
SPW 6A - 3B 200 14 1 1
SPW 3 - 5BX 250 1 1 1
SPW 3 - 5C 250 1 1 1
SPW 3A - 5BX 250 14 1 1
SPW 3A - 5C 250 9 1 1
SPW 4 - 5B 250 1 1 1
M7 70
SPW 4A - 5B 250 14 1 1
SPW 5 - 5D 250 1 1 1
SPW 5A - 5D 250 14 1 1
SPW 6 - 5DX 250 1 1 1
SPW 6A - 5DX 250 14 1 1
SPW 1 - 3A 250 1 1 1
SPW 1A - 3A 250 14 1 1
SPW 3 - 3A 250 1 1 1
SPW 3A - 3A 250 14 1 1
SPW 1 - 5BX 250 1 1 1
SPW 1A - 5BX 250 14 1 1
M8 88
SPW 2 - 5B 250 1 1 1
SPW 2 - 5D 250 1 1 1
SPW 2A - 5B 250 14 1 1
SPW 2A - 5D 250 14 1 1
SPW 4 - 5DX 250 1 1 1
SPW 4A - 5DX 250 12 1 1
SPW 1 - 5C 250 1 1 1
SPW 1 - 5D 250 1 1 1
SPW 1A - 5C 250 10 1 1
SPW 1A - 5D 250 14 1 1
M9 SPW 3 - 5DX 250 1 50 1 1
SPW 3A - 5DX 250 12 1 1
SPW 4 - 5C 250 1 1 1
SPW 4A - 5C 250 9 1 1
SPW 6 - 5A 250 1 1 1

TP N9 C15-16 (PW) Total mould= 10 Dec-21 Mar-22


1 LVL 4 BLOCK FIRST 4 BLOCK SECOND
MOULD MARKING SIZE EXCLUDE AL QTY TOTAL QTY REMAKS
NEED PHASE 1 PHASE 2
PW 3 - 3A 250 15 1 1
PW 3 - 5C 250 41 3 3
M1 PW 5 - 3A 250 15 1 1
PW 5 - 3D 250 14 1 1
PW 6 - 3A 250 30 115 2 2
PW 3 - 3AX 250 11 1 1
M1a PW 3 - 5CX 250 41 3 3 1
PW 6 - 3AX 250 15 67 1 1
PW 1 - 3A 250 15 1 1
PW 1 - 5C 250 10 1 1
PW 1C - 5C 250 1 1 1
PW 4 - 3D 250 14 1 1
M2 PW 4 - 5B 250 15 1 1 3
PW 5 - 5B 250 15 1 1
PW 6 - 5B 250 15 1 1
PW 9 - 5D 250 15 2 1
PW 9 - 5DX 250 15 115 2 1
PW 1 - 3B 250 14 1 1
PW 1 - 3B - 1 250 1 1 1
PW 1 - 3C 250 43 3 1 2
PW 4 - 3B - 1 250 1 1 1
M3
PW 5 - 3C 250 13 1 1 4
PW 7 - 3B 250 14 1 1
PW 7 - 3B - 1 250 1 1 1
PW 11 - 5A 250 15 102 1 1
PW 1 - 3CX 250 43 3 1 2
M3a PW 7 - 3B - 1X 250 1 1 1
PW 7 - 3BX 250 29 73 2 1 1
PW 2 - 3A 250 15 1 1
PW 2 - 3AX 250 11 1 1
PW 3 - 3D 250 27 2 1 1
PW 3 - 3DX 250 13 1 1 4
M4
PW 3 - 5B 250 15 1 1
PW 5 - 5C 250 11 1 1
PW 7 - 5D 250 13 1 1
PW 7 - 5DX 250 15 120 1 1
PW 1 - 3D 250 15 1 1
PW 1 - 5B 250 15 1 1 8
M5
PW 1 - 5BX 250 15 1 1
PW 2 - 3D 250 15 60 1 1
PW 3 - 3C 250 13 1 1
PW 5 - 3B 250 58 4 2 2
M6
PW 5 - 3B - 1 250 2 2 2
PW 6 - 3C 250 13 86 1 1
PW 3 - 3CX 250 13 1 1
PW 5 - 3BX 250 55 4 3 1 4
M6a PW 5 - 3B - 1X 250 2 2 2
PW 5B - 3BX 250 1
PW 6 - 3CX 250 15 86 1 1
PW 2 - 3B 250 14 1 1
PW 2 - 3B - 1 250 1 1 1
PW 2 - 3BX 250 14 1 1 6
M7
PW 2 - 3B - 1X 250 1 1 1
PW 9 - 5A 250 15 1 1
PW 9 - 5AX 250 15 60 1 1
PW 2 - 5C 250 1 1
PW 3D - 3D 0 1
PW 4 - 3B 250 1 1 *no drawing yet

TP N9 C15-16 (PCKGW) Total mould= 8 Dec-21 Mar-22


1 LVL 4 BLOCK FIRST 4 BLOCK SECOND
MOULD MARKING THK QTY TOTAL QTY REMAKS
NEED PHASE 1 PHASE 2
PC - KGW - 1 250 45 3 2 1
M1 146
PC - KGW - 7b 250 101 7 5 2
PC - KGW - 1X 250 45 3 2 1
M1a 146
PC - KGW - 7bX 250 101 7 5 2
PC - KGW - 10b 250 30 2 1 1
M2 112
PC - KGW - 13b 250 82 6 5 1
PC - KGW - 10bX 250 30 2 1 1
M2a 112
PC - KGW - 13bX 250 82 6 5 1
PC - KGW - 2 250 15 1 1
M3 112
PC - KGW - 7a 250 97 7 3 4
PC - KGW - 2X 250 15 1 1
M3a 112
PC - KGW - 7aX 250 97 7 3 4
PC - KGW - 10a 250 30 2 2
M4 154
PC - KGW - 13a 250 124 9 1 8
PC - KGW - 10aX 250 30 2 2
M4a 127
PC - KGW - 13aX 250 97 7 1 6

TP N9 C15-16 (LW) Total mould= 5 Dec-21 Mar-22


1 LVL 4 BLOCK FIRST 4 BLOCK SECOND
MOULD MARKING THK QTY TOTAL QTY REMAKS
NEED PHASE 1 PHASE 2
LW 1- 5B 250 30 2 2
LW 2- 3C 250 13 1 1
M1
LW 4- 3A 250 57 4 2 2
LW 4- 3AX 250 53 153 4 2 2
LW 3- 3A 250 30 2 2
LW 3- 3A1 250 30 2 2
M2
LW 3- 3B 250 60 4 1 3
LW 3- 3C 250 13 133 1 1
LW 3- 3A2 200 15 1 1
LW 4- 3C 200 13 1 1
LW 6- 3D 200 15 1 1
LW 8- 3B 200 15 1 1
M3 LW 2- 3A1 200 15 1 1
LW 5- 3C 200 13 1 1
LW 5- 3D 200 15 1 1
LW 7- 3B 200 15 1 1
LW 8- 5B 200 15 131 1 1
LW 1- 3A 250 15 1 1
LW 1- 3B 250 15 1 1
LW 1- 3BX 250 30 2 1 1
LW 3- 3D 250 45 3 1 2
M4
LW 4- 3D 250 15 1 1
LW 5- 5B 250 15 1 1
LW 6- 5A 250 41 3 3
LW 7- 5B 250 15 191 1 1
LW 5- 3A 250 26 2 1 1
LW 9- 5B 250 15 1 1
LW 2- 3A 250 30 1 1
LW 2- 3D 250 15 1 1
M5 LW 3- 3C1 250 13 1 1
LW 4- 5B 250 30 2 2
LW 5- 5A 250 41 3 3
LW 6- 5B 250 15 1 1
LW 7- 3C 250 13 198 1 1

TP N9 C15-16 (FW) Total mould= 2 Dec-21 Mar-22


1 LVL 4 BLOCK FIRST 4 BLOCK SECOND
MOULD MARKING THK QTY TOTAL QTY REMAKS
NEED PHASE 1 PHASE 2
FW 1 100 45 3 2 1
M1 243
FW 2 100 198 14 8 6
M2 FW 3 100 192 192 14 6 8

TP N9 C15-16 (FLW) Total mould= 6 Dec-21 Mar-22


1 LVL 4 BLOCK FIRST 4 BLOCK SECOND
MOULD MARKING SIZE QTY TOTAL QTY REMAKS
NEED PHASE 1 PHASE 2
M1 FLW - 1 22 22 22 12 10 2set
M1a FLW - 1X 22 22 22 12 10 2set
M2 26
*special size

FLW - 2 26 26 13 13 2set
M2a FLW - 2X 23 23 23 10 13 2set
FLW - 2a 4 3 3
M3 8
FLW - 2aX 4 3 3
FLW - 3 2 1 1
M4 4
FLW - 3X 2 1 1