Professional Documents
Culture Documents
INDEX
1.0 INTRODUCTION
Background
Project Road
The project road starts at Bhavnagar (Existing Km 7.090) and ends at Talaja (Existing
Km 53.585) on NH-8E in the state of Gujarat. The total length of the project road is
48.045 Kms, key plan of the project road is shown in Figure 1.1.
In case of any specific requirements which are not covered in the Design
Basis, a technical note shall be prepared and discussed on a case to case basis before
finalizing the construction drawings.
The proposals outlined in this Design Basis are based on the broad design standards
specified in Schedule D of the Concession Agreement, pre-bid quarries and the
outcome of the Field investigation report submitted by the consultant.
2.1 General
The project highway section shall conform to the requirements of the design and
specifications set out in this Design Basis. This basis shall be read in conjunction with
the Concession Agreement and Annexure I of Schedule D of CA i.e. IRC SP 84 – 2014
“Manual of Specification and Standards for four laning of National Highways through
Public Private Partnership” published by MORTH..
The standards mentioned herein this basis have been formulated from a review of
current standards given in IRC codes, guidelines and special publications besides
MORT & H circulars as applicable to National Highways.
Considering the physical condition and cost effectiveness, the improvement proposals
are conceived and developed under the following standards:
Based on the above, the following project design standards have been formulated
and presented below in the relevant sections.
2.2.1 General
In general, the Alignment plan and profile given along with Schedule B will be followed
in most of the cases for horizontal alignment design since land acquisition and utility
clearances will be carried out using these plans.
2.2.2 Design Speed
The design speed shall be in accordance with clause 2.2 of Annexure I of Schedule D
i.e. IRC SP 84-2014. Service road will be designed at 40 kmph speed as per Clause
2.12.2.4.
Revision No – R0 3 Design Basis Report
Detailed Design for 4 Laning of Bhavnagar Talaja section of NH 8E
(Package-1) from Km 7.090 to Km 53.585 in the State of Gujarat on
Hybrid Annuity Mode
As per clause 2.9.4 of IRC SP 84-2014, the desirable minimum and absolute
minimum radii of horizontal curves for the project stretch shall be as follows:
Table 2.2: Minimum Horizontal Curve Radii
Type of Terrain Desirable Minimum Absolute Minimum
Plain and Rolling 400 250 m
Mountainous and Steep m
150 75 m
m
Above given criterion will be adopted in general except the location where there is RoW
issues or any other site constraints.
Service road will be simple offset of main carriageway hence alignment & radius in
accordance to main carriageway will be provided. For Slip Road vertical geometry will
be designed.
As per IRC: 73 - 1980 design standards, the minimum lengths of vertical curves are 60
m, 50 m and 40 m for design speeds of 100 km/h, 80 km/h and 65 km/h respectively.
At complex locations such as interchanges and major intersections the minimum lengths
of vertical curves should be designed for safe decision sight distance.
The length of a vertical curve should be calculated using the following equation:
L = K x A,
The Consultants propose minimum summit curve K values of 74, 33 and 19 for design
speeds of 100 km/h, 80 km/h and 65 km/h respectively in case of four-lane section as
mentioned in IRC: SP 23-1983.
IRC SP: 23-1983 recommends minimum K values for valley curves as 42, 26 and 18 for
design speeds of 100 km/h, 80 km/h and 65 km/h.
As per clause 2.9.3 of IRC SP 84-2014, super elevation will be limited to 7%, if radius of
curve is less than desirable minimum radius. It will be limited to 5%, if radius is more
than desirable minimum.
IRC Geometric Design Standards for Rural Highways, IRC: 73-1980, suggests that
the length of the transition curve should be the larger of the two values arrived at on
the basis of the following criteria:
Values will be suitably calculated for the project road based on the road width and
rotation axis and will be followed but with the consideration of existing site constraint,
ROW.
The cross fall w i l l be 2.0% for carriageway with Rigid pavements and 2.5% for
carriageways with Flexible pavement. The cross falls for earthen shoulders on straight
portion shall be at least 0.5% steeper than the slope of the pavement and earthen
shoulder subject to a minimum of 3.0%.
All at grade junctions are to be improved as per IRC SP-41 and Type Design for
Intersections on national Highways issued by MORTH.
2.2.10 Grade Separated Intersections
Grade Separated intersection shall be developed as per the details given in Schedule B.
The approach gradient of the grade separated structure shall not be steeper than 2.5%
(1 in 40).
As per Appendix BVIII of Schedule B, structure configuration will be as per New 6 lane
structure and criterion given in IRC SP 87-2010 “Manual for Six lanning” should be
followed.
Considering all these clauses, roadway width on grade separator will be 12.5m for Four
Lane structure and 14.5m for Six Lane structures.
For Vehicular Underpass vertical Clearance over NH/SH shall be adopted as 5.5m and
total width of structure shall be as per IRC SP 87 -2013
For Pedestrian / cattle Underpass Vertical Clearance shall be 4.5 m as per Appendix BIX
(B) of Schedule B of CA and clear width of 5 m for Pedestrian underpass as specified in
Schedule B of the CA.
As per Clause 2.14 of IRC SP-84-2014, median openings shall not be spaced closer than
2 kms. In case of built up area median openings shall not be spaced closer than 500m.
Also median opening shall not be provided in front of service road entry. Minimum distance
between service road entry and median opening shall be 150m.
Length of Median opening shall be 18 to 20m only. Also all median opening shall be
provided with additional 3.5m shelter lane.
Any additional requirement of median openings shall be dealt with on a case to case
basis.
Utility Corridor of 2.0m shall be provided as per provision in Appendix BI (typical Cross
Section) of Schedule B.
2.2.15 Drainage
An effective drainage system shall be planned for the drainage of roadway including
medians, toll plazas, way side amenities such as rest areas, truck parking areas and
bus stops. The following types of drains shall be provided for surface drainage of
roadway and ROW. Drainage design shall be done as per IRC SP-42-1994 and IRC SP-
50-1999.
The layout for Bus Bays shall be in accordance with IRC: 80-1981. Minor modifications
may be made in the layout plan for ROW constraints if any. The minimum length of
the bus bay shall be 15m. The location of Bus Bays and Bus Shelters shall be
provided as per Schedule C.
The MORT & H Guidelines for planning, construction and operation of modern toll
plazas on National Highways shall be followed for the planning and design of toll
plazas. The design is aimed at optimizing the speed and efficiency of toll collections.
An open system of toll collection is to be followed on the project corridor. The number
of service lanes shall be decided based on the traffic projections. The table below
indicates the design parameters to be adopted for the layout of the toll plaza.
1. Road side barriers at locations where the embankment height is more than 3 m
2. In high cut sections
3. Median barriers where median width is less than 2.5m.
Road side barrier shall be of metal beam single row of W section mounted on
steel post channel section and Median barrier shall be of metal beam single row of W
beam provided on both side of the post.
Side slope and earthen shoulder shall be protected against erosion by providing
vegetation cover, kerb channel, chute, stone/concrete block pitching or any other
suitable protection measures depending upon height of embankment and susceptibility of
soil to erosion. Pitching will be done above embankment height of 6m considering type
of soil available on the project stretch.
For embankments higher than 6.0m, the design of the embankments shall be done
in accordance with IRC-75:1975 “Guidelines for the design of High Embankments”.
Road markings shall be as per IRC: 35-1997. These markings shall be applied to
road centre lines, edge line, continuity line, stop lines, give-way lines,
diagonal/chevron markings, zebra crossing and at parking areas. The approach noses
of the traffic islands shall also be marked for additional guidance to traffic by means of
diagonal markings and chevrons.
The locations indicated in the table shall be verified by the consultant during the
course of the design and the detail drawings shall be submitted separately for
each location. Variable Message signs shall be provided as per the requirement of
concession agreement.
For safety and operational reasons it will be necessary to provide suitable road
furniture which includes Route Marker signs, Road Delineators, kilometer and
hectometer stones, ROW pillars, road lighting and landscaping.
Where possible these features will be provided in accordance with relevant IRC or
other standard, as detailed below. If no IRC Codes or the MORTH Specifications are
3.1 General
The design of new Flexible pavement for main carriageway shall be in accordance
with IRC 37:2012. The initial design of overlays on the existing carriageway shall be in
accordance with IRC 81-1997 using the BBD deflections. For the design of rigid
pavements IRC 58:2011 method shall be followed. The paving for bus bay and truck
lay-bye shall be with flexible pavement. The relevant clauses of Manual of four
Lanning shall be referred in this regard in conjunction with schedule-D of concession
agreement.
The table below indicates the design standards to be followed for flexible
pavement.
Table 3.1: Flexible Pavement Design Standards (Additional Lanes, Bypasses, Re-
alignments & Service Roads)
Sr.
Item Standards
No.
Main carriageway - Flexible Pavement Design
IRC 37:2015 for new construction & IRC-
1 Design Methodology
81 for overlays
2 Performance period As per concession agreement
3 Traffic on Design Lane IRC 37:2015
Corresponding to soaked laboratory CBR value as
4 Soil CBR of sub grade obtained from material investigations compacted
to 97% MDD.
Paved Shoulders
Paved Shoulder Paved shoulder shall have same thickness and
5
Composition composition as main carriageway.
Service Road –Flexible Pavement Design: Pavement shall be design as per
IRC 37:2012 for design traffic of 5 msa as per clause 5.5.5 of IRC SP 84-2014.
Table 3.2: Rigid Pavement Design Standards (for Toll Plaza Locations)
Sr.
Item Standards
No.
Rigid Pavement Design
1 Design Methodology IRC 58:2012
PQC
DLC
2 Composition of Layers
GSB
Sub grade
3 Separation Layer 125 micron thick plastic sheet
Grade for Pavement
4 Minimum M 40
Quality Concrete
Sr.
Item Standards
No.
Grade for Dry Lean Shall be M15 having minimum 10 MPa
5
Concrete strength at 7 days
Regular Contraction joints and longitudinal
6 Joints joints shall be provided. Construction joints
shall be as and when required.
Pavement design for new / widened portion with CBR 10% will be adopted. Also in
cut formation as per clause 301.6 of MORTH specifications sub grade is not required
and same will be followed wherever applicable.
In general, the hydraulic/hydrologic design for cross drainage structure shall conform
to the following codes:
IRC SP: 13-2004 –Guidelines for the design of small bridges and culverts
IRC: 5-2015 –Code of practice for Road Bridges (General features of Design)
IRC: 78-2014 –Code of Practice for Road Bridges (Design of Substructure and
Foundation)
IRC: SP-42– 1994 -Guidelines on Road Drainage
IRC: SP-50– 1999 -Guidelines for Urban Drainage
IRC: SP-84– 2014 -Manual of Specifications and Standards for Four Laning of
Highways through Public Private Partnership
Hydraulic design of bridges is an important aspect to determine the adequacy of the existing
bridges and to determine the required waterway and design High Flood Level of the bridges
proposed on the new alignments / bypasses. The various design standards which are to be
adopted for the hydrological / hydraulic design of bridges are narrated below.
Rainfall
Rainfall is to be taken from Central Water Commission Flood Estimation Report.
Return Period
100 years return period is to be adopted to calculate the discharge as per Manual of Standards
and Specifications for FourLaning.
Coefficient of Runoff
Runoff co-efficient (P) for the catchments characteristics shall be adopted from Table 4.1 of IRC:
SP-13.
Bed Slope
The energy slope which may be taken equal to the bed slope, measured over a reasonably long
reach. Bed slope of the rivers will be obtained from the topo survey data. The longitudinal
section of the river is generated through MX software.
Rugosity Coefficient
Rugosity coefficient, n shall be taken as per Table 5.1 of IRC: SP-13. However, judgment and
experience are necessary in selecting a proper value of n..
Discharge is to be calculated by various methods as specified in IRC: SP-13 and CWC Report.
The brief of various methods is as below:
Ingli's Formula
Ingli’s formula is commonly used for computation of flood discharge based on catchment area
for erstwhile Bombay Presidency the stream.
Q = 125*M/(M+10)0.5
Where:
M = Catchment area in Sq. km.
Rational Formula
Q= 0.028 PfAIC
Where:
Q = Maximum runoff in cumecs
A = Catchment area in hectares
Ic = Critical intensity of rainfall in cm/ hr.
P = Coefficient of run-off for the given catchment characteristics.
F = Spread factor for converting point rainfall into area mean rainfall.
Ic = (F/T)*(T+1) / (Tc+1)
F = Total Rainfall of T hours duration (24 hrs.) in cm corresponding to 100 yrs return period.
T = Duration of total rainfall (F) in hours= 24 hrs.
Tc= Time of concentration in hour.
Total rainfall in 24 hrs is adjusted corresponding to Tc for finding critical rainfall intensity Ic from
the rainfall distribution curve (Duration vs. conversion ratio) of CWC report.
Time of concentration
Times of concentrations (Tc) are determined by following formula.
Tc= Time of concentration in hour. = 0.87 xL / H
3 0.385
Where L is the length of catchment in km and H is the elevation difference in meter in length L.
In general practice, local enquiry HFL is used to find out the discharge by Area-Velocity method.
As mentioned above the discharge is computed by catchments area methods also.
4.6 Afflux
When the waterway area of the opening of a bridge is less than the unobstructed natural
waterway area of the stream, i.e. when bridge contracts the stream, afflux occurs. Molesworth
Formula calculates the afflux for the recommended design discharge.
h 0.015 1
17.88 a
Where, h = afflux in m,
V = average velocity of the water in the stream prior to constriction in m/s,
A = Unobstructed sectional area of the river at the proposed site in sq m,
a = Constricted area of the river at the bridge site in sq m.
Scour depth can be calculated as per Clause 703.2 of IRC: 78-2014 and as explained in IRC: SP
13. The mean depth of scour, Dsm below the highest flood level is given by the following
equation:
Where, Db = the design discharge in cumecs per meter width of effective waterway. The value
of ‘Db’ shall be the total design discharge divided by the effective linear waterway width between
abutments. For bridges with riverbed soil of stiff clay with some boulders and gravels, the depth
of scour will be less.
As per the guidelines given in the IRC-78: 2014 (Clause No. 703.2 and 703.2.2.2) the parameter
“Silt Factor” (Ksf) should not be calculated as indicated in Clause no. 703.2.2.2.
As per IRC: 78 – 2014, for the design of piers and abutments located in a straight reach and
having individual foundations without any floor protection works, the maximum depth of scour
from the highest flood level is given by:
Keeping in view the good health of the road, a proper drainage design is one of the
important aspects. Drains in rural area are to be designed as per the guidelines fixed in
IRC:SP-42 and in urban area are to be designed as per IRC:SP-50.
Open side drains are normally provided on both or one side of the roadway in order to
intercept surface water runoff on the carriageway, shoulders and verges.
Open unlined trapezoidal drain in rural area. Side slope of unlined drain shall not be
steeper than 2H:1V. These slopes can be made steeper in case of lined drains. The bed
width of unlined drain will be kept constant and the depth of the drain will vary as per
the design runoff.
Permissible flow velocity in silt and sand surface is 0.3to1.0m/sec. In stiff clay the
velocity maybe1.5m/sec. If it gets increased beyond this limit, flow channel Sneed to
be lined. This is as per IRC:SP-42.
RCC Lined Drain will be provided in urban area locations. Width of lined drain will be
kept fixed and depth of the drain would vary as per the design runoff.
For important roads like National Highways and State Highways, the frequency of the
storms hall be taken as 25years.
To estimate the amount of runoff from the carriage way, rational method is an
universally adopted empirical formula. This method has already been explained in the
section 4.4.
Once the quantity of runoff is estimated, next stage is to do the hydraulic design of the
drain. Capacity of the drain is to be determined by using Manning’s equation. The
Manning's equation has already been explained in the section 4.4.
Grade Separator 01
Major Bridge 02
Minor Bridge 27
VUP 02
PUP 04
Pipe Culverts 38
Slab/Box Culverts 30
Overpass 12
The geometric standards given in Schedule-D of the RFP document are followed. The
cross sections for minor bridges, CUPs, and Flyovers coming over the Project road
stretch shall be as mentioned in the Schedule ‘B’ of RFP document.
New 4 RCC
Lane Pier/Abutment
1 42+331 (2x27.3)+(1x9.1) 63.7 2x12.5 3x21.25 63.75 RCC T-Girder
bridge with and Pile
footpath Foundation
RCC
New 2
Pier/Abutment
2 50+687 10x24.0 240.0 1x12.5 Lane 10x24.0 240.0 RCC T-Girder
and Pile
bridge
Foundation
Existing
8.4
Bridge to
(Existing)
be
1 50+267 3x7.0 21.0 12.5 3x7.0 21.0 RCC Box
widened to
(after
2 lane
widening)
Bridge
New 6
1 10+148 1 x 6.0 6.0 2x16.0 Lane 1 x 6.0 6.0 RCC Box
bridge
New 6
2 10+594 1 x 6.0 6.0 2x16.0 Lane 1 x 6.0 6.0 RCC Box
bridge
New 6
RCC Abutment and
3 11+268 1 x 10.4 10.4 2x16.0 Lane 1 x 10.4 10.4 RCC Solid Slab
Open Foundation
bridge
New 6
RCC Abutment and
4 20+44 1x12.3 12.3 2x16.0 Lane 1x12.3 12.3 RCC Solid Slab
Open Foundation
bridge
New 6
RCC Abutment and
6 24+221 1x10.8 10.8 2x16.0 Lane 1x10.8 10.8 RCC Solid Slab
Open Foundation
bridge
New 6
7 25+227 1x7.8 7.8 2x16.0 Lane 1x7.8 7.8 RCC Box
bridge
New 6
RCC Abutment and
8 26+312 1x10.2 10.2 2x16.0 Lane 1x10.2 10.2 RCC Solid Slab
Open Foundation
bridge
New 6
RCC Abutment and
9 27+155 1x11.4 11.4 2x16.0 Lane 1x11.4 11.4 RCC Solid Slab
Open Foundation
bridge
New 6
10 27+672 1x6.8 6.8 2x16.0 Lane 1x6.8 6.8 RCC Box
bridge
New 6
13 33+224 1x7.8 7.8 2x16.0 Lane 1x7.8 7.8 RCC Box
bridge
New 6
14 33+938 1x6.0 6.0 2x16.0 Lane 1x6.0 6.0 RCC Box
bridge
New 6
15 34+126 1 x 6.0 6.0 2x16.0 Lane 1 x 6.0 6.0 RCC Box
bridge
New 6
16 34+938 3 x 6.0 18.0 2x16.0 Lane 3 x 6.0 18.0 RCC Box
bridge
New 6
17 34+991 3 x 6.0 18.0 2x16.0 Lane 3 x 6.0 18.0 RCC Box
bridge
New 6
18 36+934 1x6.0 6.0 2x16.0 Lane 1x6.0 6.0 RCC Box
bridge
New 6
19 37+113 1x6.7 6.7 2x16.0 Lane 1x6.7 6.7 RCC Box
bridge
New 6
20 37+858 1x6.2 6.2 2x16.0 Lane 1x6.2 6.2 RCC Box
bridge
21 41+138 New 4
Lane RCC Pier/Abutment
5x 5.8 29.0 2x10.8 bridge 3x 9.7 29.1 RCC Solid Slab and Open
(Service Foundation
Road)
New 6
22 41+346 2 x 5.6 11.2 2x16.0 Lane 2 x 5.6 11.2 RCC Box
bridge
New 6
RCC Abutment and
23 42+494 1x10.2 10.2 2x12.5 Lane 1x10.2 10.2 RCC Solid Slab
Open Foundation
bridge
New 4
24 46+165 1x6.4 6.4 2x12.5 Lane 1x6.4 6.4 RCC Box
bridge
New 4
25 48+323 1x6.8 6.8 2x12.5 Lane 1x6.8 6.8 RCC Box
bridge
Additional
26 50+267 3x7.0 21.0 1x12.5 2 Lane 3x7.0 21.0 RCC Box
bridge
RCC
6 lane Pier/Abutment
1 40+800 2x15.0 30.0 2x14.5 2x15.0 30.0 RCC T-Girder
Flyover and Open
Foundation
Design
Sr. no. chainage Proposed Proposed Proposed
(km) Substructure and
Size (LXH) deck Proposal Size (LXH) Superstructure
Foundation
(m) width(m) (m)
This section below outlines the standards to be adopted for the design of the
structures given in the Concession Agreement which include Flyovers, Culverts, Minor
Bridges, & CUPs.
The IRC codes/Standards/Act, MORT & H Publications, IS & BIS codes shall be
followed in the project. Design of all proposed structures shall be done in
accordance with the provisions of the following IRC Codes:
5.5 Material
Concrete
The grade of concrete shall be as per design requirement and mentioned in execution
drawings for each component of the structure. Cement and water content shall be as
Revision No – R0 30 Design Basis Report
Detailed Design for 4 Laning of Bhavnagar Talaja section of NH 8E
(Package-1) from Km 7.090 to Km 53.585 in the State of Gujarat on
Hybrid Annuity Mode
Concrete grade for various structure components shall be as per table below.
Reinforcement
Deformed or TMT reinforcement bar conforming to IS: 1786 shall be used for
components of the structures. The reinforcement grade shall be Fe500. As project is
located near to coastal area epoxy coating of reinforcement is required.
Pre-stressing tendons normally take the form of separate wires, wires spun together
helically to form strands or bars. For pre-tensioned steel, wires, strands and
occasionally bars are used, simply to permit the concrete to bond directly to
them; when post-tensioning is used, it is common practice to group the separate
tendons together, so as to reduce the number of anchorages and ducts required to
accommodate them. When grouped in this way, the tendons in each duct are usually
termed a cable.
Uncoated stress relieved low relaxation steel conforming to IS: 14268 shall only be
used for pre- stressing steel so as to reduce losses due to relaxation. Data in respect
of modulus of elasticity, relaxation loss at 1000 hours, minimum ultimate tensile
strength, stress-strain curve etc. shall necessarily be obtained from
manufacturers. Pre-stressing steel shall be subjected to acceptance tests prior
to actual use on the works. The modulus of elasticity value, as per acceptance tests,
shall conform to the design value which shall be within a range not more than 5
percent between the maximum and minimum.
Many cables with different arrangements of wires and strands and different
methods of anchorage are available as pre-stressing steel. So type and size of
cable and methods o f anchorage shall be decided on the basis of design
requirement.
Sheathing
The duct or sheath for cables to be used of Corrugated HDPE having coefficient of
friction as 0.17 and wobble coefficient per meter length of steel 0.0020. The
thickness of sheathing shall be as specified in clause 13.4.3 of IRC: 112-2011.
Bearings
Bridge bearing must be designed to transmit all the loads and appropriate horizontal
forces. From the material point of view, these bearings can be made from metal,
rubber, metal and elastomeric and even concrete. However following three types of
bearings are recommended to be used on this project.
Seismic Arrester are required as the seismic zone –III as per cl 219.9 of IRC6:2014.
Elastomeric Bearings
The basis of design is that the elastomer is an elastic material, the deflection of
which under a compressive load is influenced by its shape (shape factor). Reinforcing
plates should be bonded to the elastomer to prevent any relative movement at the
steel/Elastomer interface.
The dimension and the number of internal layers of elastomer chosen shall satisfy the
following clauses of IRC: 83(Part-II).
The elastomer shall conform to all the properties specified in table 1 of IRC: 83 (Part-
II), and tolerances in dimensions specified in table2 of IRC: 83 (Part-II).
POT/PTFE Bearings
Due to initial low cost, easy availability, maintenance free and easy replacement, for
simply supported structures elastomeric bearing shall be used. Wherever it is
Revision No – R0 32 Design Basis Report
Detailed Design for 4 Laning of Bhavnagar Talaja section of NH 8E
(Package-1) from Km 7.090 to Km 53.585 in the State of Gujarat on
Hybrid Annuity Mode
unavoidable, POT/ PTFE bearings shall be used specially in high seismic zone (zone iv
and v). However for continuous structure POT/ PTFE bearing shall be used.
The design of the POT/ PTFE bearing shall be done by the manufacturer conforming to
the provisions of material as well as design parameters IRC: 83(part-III) and shall be
got approved by the engineer. However the forces, movements and rotation etc
shall be provided by the designer of the project on the format given in appendix –1
of IRC: 83 (part-III). In support of quality assurance, acceptance specification
given in clause 928 of IRC: 83 (part-III) shall be followed.
Tar paper bearings shall be used for small span RCC solid slab superstructure due
to their cost effectiveness and speedy construction and simplicity of superstructure.
The design would be carried out using the limit state design philosophy satisfying the
requirements of IRC-112 2011. The structure would be designed to meet both the
ultimate and serviceability requirements of the code.
Ultimate limit state: This cover static equilibrium and failure of structural element or
structure as a whole when acted upon by ultimate design load.
Serviceability limit state: This deals with the condition of structure subjected to
serviceability design loads. These conditions include level of internal stress , fatigue
failure ,deflection , cracking and discomfort by vibrations.
Load Combination shall be adopted as per table 3.1 to 3.4 of IRC: 6-2014 as given
below:-
o Table 3.1 for Verification of Equilibrium.
o Table 3.2 for Verification of Structural Strength
o Table 3.3 for Verification of Serviceability
o Table 3.4 for Base Pressure and Design of Foundation
5.7 Loading
The dead load i.e. the self weight of the superstructure, substructure and foundations,
backfill will be considered as per the Cl. 203 of IRC: 6 -2014 and are summarized as
below:
Live Load:
Live load will be adopted as per IRC-6:2014 clause 204 as under.
(a) 2-lane Carriageway: One/Two lanes of IRC Class A. One lane of IRC Class 70R
(wheeled/ tracked) which ever produces worst effect for each 2 Lane
carriageway. (Ref : Table 2 of IRC: 6- 2014)
(b) 3-lane Carriageway: 3-lanes of IRC Class A or 1-lane of IRC Class 70R (wheeled/
tracked) + 1-lane of IRC Class A whichever produces worst effect for each 3-
lane carriageway. (Ref : Table 2 of IRC:6-2014)
Longitudinal Forces
The structure will be designed for a longitudinal force arises of the following.
1. Braking effects
2. Frictional resistance due to movement of free bearing
The longitudinal forces will be considered in accordance with clause 211, IRC:6-
2014.
1. Water current
The effect of water current forces will be calculated in accordance with clause 210
of IRC:6-2014 on sub-structure and foundations. High Flood level will be adopted
from details of existing structure viz a viz details of observed HFL collected from
site. The velocity through bridge will be computed on area velocity method adopting
cross section of bridge at site and bed gradient of river / terrain.
Wind Forces
Structures will be designed for wind effects as stipulated as Cl. 209 of the IRC-6:2014.
The intensity of wind force will be based on wind pressure and wind velocity given in
Table 5 of IRC-6:2014.
Seismic Effects
The following type of bridges need not be designed for seismic forces provided both the
following conditions are met: (IRC:6-2014 clause 219.1.1)
(a) Culverts and Minor Bridges up to 10 m span.
(b) Bridges in Seismic Zones II and III satisfying both limits of total length not
exceeding 60 m and spans not exceeding 15 m.
It is proposed to design all the structures as above for seismic forces as mentioned in
clause 219.3. of IRC : 6-2014.
Horizontal seismic force shall be calculated using the following formula given in clause
219.5.1 of IRC 6:- 2014:-
The fundamental natural period T (in seconds) of pier / abutment of the bridge
along a horizontal direction may be estimated by the following expression:
D
T 2.0
1000F
Where,
D = Appropriate dead load of the superstructure & live load in kN
F = Horizontal force in kN required to be applied at the centre of mass of
the superstructure for one mm horizontal deflection at the top of the
pier/abutment along the considered direction of horizontal force.
As per clause 219.3 of IRC 6:- 2014, Vertical seismic force shall be two third of
Horizontal seismic force. Vertical seismic force may be omitted for all elements in Zone
II and III, except for the following cases :
i) The seismic force due to live load shall not be considered when acting the
direction of traffic, but shall be considered in the direction perpendicular to
traffic.
ii) The horizontal and vertical seismic force shall be calculated using 20 % of live
load (excluding impact factor.
Earth Pressure
For abutment & Earth retaining structures Active earth pressure is considered as per
IRC 6-2014.
Revision No – R0 36 Design Basis Report
Detailed Design for 4 Laning of Bhavnagar Talaja section of NH 8E
(Package-1) from Km 7.090 to Km 53.585 in the State of Gujarat on
Hybrid Annuity Mode
Active Earth pressure / Earth pressure at rest will be considered to be acting on the
vertical walls of the RCC Box. The Co-efficient of such Earth pressure will be taken as
0.5.
Surcharge Pressure
All Earth retaining wall are designed for a live load surcharge pressure equivalent to 1.2
m earth fill as per IRC 6-2014.
For the computation of earth pressure, properties of backfill material having soil
properties C= 0.0 t/m2 and ø = 30 degree will be adopted.
Centrifugal Forces
Centrifugal forces are considered for spans in curved portion as per IRC 6 -
2014. Centrifugal forces shall be determined from following formula:
C= WV 2 /127R
Where,
C =Centrifugal force acting normal to the traffic. W = Live load (tones/m)
V= Design speed of vehicles (Km/ hour)
R = Radius of curvature (m)
Temperature Gradient
Effective bridge temperature shall be estimated from the isotherms of shade air
temperature given in fig 8 and fig 9 of IRC: 6-2014.. Difference in temperature
between the top surface and other levels through the depth of the structure,
where ever applicable shall be taken in accordance with clause :215.3 of IRC:6-
2014.
Crash Barriers
Flyovers
Major and Minor Bridges
Underpasses
The type of crash barriers is provided according to their applications summarized below.
The other structures which cross the national highway shall be provided with
P-2: Low Containment.
Revision No – R0 37 Design Basis Report
Detailed Design for 4 Laning of Bhavnagar Talaja section of NH 8E
(Package-1) from Km 7.090 to Km 53.585 in the State of Gujarat on
Hybrid Annuity Mode
Expansion Joints
Types of expansion joint based upon the length of span and movements are as given
below:
65mm thick bituminous wearing coat shall comprise of, Bituminous Concrete 40mm
thick overlaid with 25mm thick mastic asphalt. Before laying wearing coat the deck
surface shall be thoroughly cleaned and tack coat shall be applied. The construction
operations and bituminous mixes and tack coat shall conform to Section 500 of the
MORTH Specifications.
Edge Treatment
A drip course of 25mm shall be provided at the edge and bottom of the
cantilever of the superstructure to barricade the flow into the base of
superstructure.
Approaches
The approaches on the either side of the Flyover would generally have provisions
for viaduct spans wherever needed. Thereafter they are of earth retaining structures
or of conventional embankments a s per the site conditions. The approaches on the
either side of the Bridges would have slope protection in the form stone pitching and
turfing shall be provided on the embankment slopes. Stone pitching shall be
constructed in accordance with clause 2504.2 of the MORTH specifications. Where the
stones of required size are not economically available, cement concrete blocks in
minimum M15 grade concrete conforming to Section 1700 of MORTH or stones in wire
crates, shall be used.
The lowest course of pitching shall be started from the toe wall and built up in courses
upwards. The toe wall shall be in dry rubble masonry (un-coursed) conforming to
Clause 1405.3 of the manual of Specifications in case of dry rubble pitching and it
shall be in nominal mix cement concrete (M15) conforming to Clause 1704.3 of the
manual of Specifications in case of cement concrete block pitching.
Revision No – R0 38 Design Basis Report
Detailed Design for 4 Laning of Bhavnagar Talaja section of NH 8E
(Package-1) from Km 7.090 to Km 53.585 in the State of Gujarat on
Hybrid Annuity Mode
Approach Slab
Approach slab will dispense in case of culverts as per Clause 13.5.3 of IRC SP: 13 and
MORTH standard drawings for culvert. Wherever Approach slab is not provided proper
compaction of back filling shall be ensured in order to avoid settlement of the soil.
Reinforced concrete approach slabs, 3.5 m long and 300 mm thick, in M30 grade
concrete at either end of the bridge, will be provided. One end will be supported on
the reinforced concrete bracket projecting from the dirt wall and the other end
resting over the soil, in accordance with the guidelines issued by MORT & H. A
leveling course, 150 mm thick, in M-15 grade concrete will be laid under the
approach slabs as per MOST standard.
Drainage Spouts
Drainage spouts will be provided in accordance with MOST standard plans. The
minimum spacing shall be kept preferably as 5.0m c/c which may be adjusted to suit
span length. The drainage spouts at nalla/canal Bridge are proposed with free down fall.
Protection Works
For bridges with raft foundations, protective flooring, curtain wall and apron will be
provided for both up-stream and down-stream side as per IRC SP-13/MOST .
standard.
Filter Media
The filter material shall be well packed to a thickness of not lesser than 600mm with
smaller size towards the soil and bigger size towards the wall and provided over the
entire surface behind abutment, return wall, retaining wall, box side wall to the full
height.
Weep Holes
100mm diameter PVC pipes shall be provided as weep holes and shall extend through
full width of abutment / return wall / side wall with slope of 1 vertical: 20 horizontal
towards the draining face as per Clause 2706 of the MORTH. The spacing of weep
holes shall be 1.0m in either direction with the lowest at 150 mm above the low
water level or ground level whichever is high.
In general, the design of pile and pile cap shall conform to provisions of IRC: 78-
2014. The various specific assumptions to be made for the design of pile and pile cap
shall be as follows:
The vertical load carrying capacity of the pile shall be determined based on static
formula given in Appendix-5 of IRC:78-2014. The following limiting values shall be
considered for computation of safe load:
The vertical load carrying capacity as calculated by static formula shall be verified by
conducting initial load tests on piles conforming to IS: 2911 (Part 4).
The lateral load carrying capacity of the pile shall be determined by using empirical
formula given in IS:2911 (Part-1/Sec-2) by limiting the lateral deflection of 1% of
pile dia at cut off level considering it as fixed headed pile under normal conditions.
The capacity so evaluated will be used purely for the purpose of arriving at the upper
bound of lateral load capacity. This deflection limitation will not be applicable in
load combination with seismic conditions for which the resulting stresses and the
structural capacity of the section would be the governing criteria.
Soil stiffness for lateral loads shall be taken from IS:2911 (Part-1/Sec-2),
Appendix – C. Unconfined compressive strength shall be calculated from the
results of Geotechnical Investigation Reports. Cohesion as calculated using
unconsolidated untrained test with required modification of angle of internal
friction will be used for working out unconfined compressive strength.
The minimum thickness of pile cap shall be kept as 1.5 times the pile diameter. Top of
the pile shall project 50mm into the pile cap.
The top of pile cap shall be kept at least 500mm below the ground level in case of
urban flyovers structures or road over bridges. For bridges on rivers / streams / canals,
the bottom of pile cap shall be kept at LWL/bed level.
Pile cap will be designed either by truss analogy or by bending theory, depending
upon the spacing and number of piles in a pile group.
Pile cap will be provided with an offset of at least 150mm beyond the outer face of
the outer piles.
Revision No – R0 40 Design Basis Report
Detailed Design for 4 Laning of Bhavnagar Talaja section of NH 8E
(Package-1) from Km 7.090 to Km 53.585 in the State of Gujarat on
Hybrid Annuity Mode
Shape of pier as far as possible shall be kept as wall type slick pier.
The piers are to be designed for combined axial load and biaxial bending as per the
provisions of IRC: 112-2011.
In case the pier cap acts as a bracket, the design shall conform to provisions of IS: 456
in absence of any specific provision in IRC code for bracket design.
Analysis, design and detailing will in general conform to the stipulations of relevant IRC
codes and good engineering practice.
6.4 Superstructure
For right slabs with rectangular cross section of slab, the effective live load
moments may be calculated based on effective width method conforming to
Annexure B-3 of IRC: 112-2011. Bending moments due to other loads can be
taken to be distributed over the full width. Check for shear is not required in
this case.
For right slabs where the cross section has cantilever projections
transversely, the analysis may be carried out using grillage analogy method.
Bearings shall be provided in this case as the reaction at supports is
concentrated over a smaller width.
For skew slabs, grillage analysis shall be carried out for finding out the design
forces and moments.
Design of RCC I- Beam and Slab (Cast in situ Girder & slab)
The structure behaves as composite section for all loads since the staging is
released only after the deck slab gains strength.
The deck structure shall be analyzed for self weight manually using excel
sheet, SIDL and live loads using grillage analogy method.
The minimum dimension of various elements shall be provided conforming to the
latest IRC codes and standards. The minimum thickness of deck slab including
that at tip of the cantilever shall be 200mm. Thickness of cross girders shall not
be less than the minimum web thickness of main longitudinal girder. There shall
be at least two cross girders in any beam and slab type structure (i.e at the
ends.)
For obtaining maximum shear stress, the section at a distance equal to
effective depth from the face of the support shall be checked and the shear
reinforcement calculated at the section shall be continued up to the support.
The design of deck slab supported transversely on the girder shall be carried out
assuming un-yielding support at the girder points and using effective width
method.
Revision No – R0 41 Design Basis Report
Detailed Design for 4 Laning of Bhavnagar Talaja section of NH 8E
(Package-1) from Km 7.090 to Km 53.585 in the State of Gujarat on
Hybrid Annuity Mode
Design of PSC I Beam and Slab (Pre-cast Girder and in-situ slab)
Box is designed based on line analysis in STAAD for dead load, live load and
earth pressure.
In the design of Box Culverts effective live load moments may be calculated
based on effective width method conforming to Annexure B-3 of IRC: 112-2011.
Bending moments due to other loads can be taken to be distributed over the
full width.
Project areas come under seismic zone-III. Seismic analysis of the bridge structure is
proposed to be carried out in 2 steps.
Step-1: To carry out single mode analysis to obtain the fundamental vibration
period of the bridge in two orthogonal directions (i.e. longitudinal & transverse
direction).
Step-2: To estimate seismic forces using the spectrum response, defined in IRC: 6-
2014.
Revision No – R0 42 Design Basis Report
Detailed Design for 4 Laning of Bhavnagar Talaja section of NH 8E
(Package-1) from Km 7.090 to Km 53.585 in the State of Gujarat on
Hybrid Annuity Mode
The calculation for fundamental period can be done either by using the simplified
expression given in Annexure–D of IRC:6-2014 or else by modeling the structure
in STAAD Pro and carrying out dynamic analysis.
Vertical seismic coefficient shall be taken as “two third” of the horizontal seismic
coefficient. The vertical seismic shall be combined with the horizontal seismic in any
one direction. The seismic combination to be considered is as follows:
1. ±SX ±0.3SY ±0.3SZ
2. ±0.3SX ±SY ±0.3SZ
3. ±0.3SX ±0.3SY ±SZ
The effect of vertical components may be omitted for all elements in seismic zones II &
III except for following cases
Pre-stressed concrete decks
bearings and linkages
horizontal cantilever structural element
for stability checks and
bridges location in the ‘Near Field Regions’
1. ±SX ±0.3SZ
2. ±0.3SX ±SZ
Where SX & SZ are seismic forces in longitudinal & transverse direction respectively
while SY is the seismic force in vertical direction.
For project corridor falls in Seismic zone III ductile detailing shall be carried out
according to clause IRC 112- 2011.
6.6 Bearings
Elastomeric bearings if used for transferring in-plane horizontal forces shall be checked
using minimum frictional value and minimum vertical load, including combined effects
of horizontal of earthquake. Anchored elastomeric bearings may be used in case it is
not possible to satisfy the above criteria.
Provision of Elastomeric Bearings or POT-PTFE Bearing shall be done as per design
requirements.
In loose sands or poorly graded sands with little or no fines, vibrations due to earthquake
may cause liquefaction or excessive total and differential settlements. Since this project
is located in moderate seismic zone, hence liquefaction effect is not required to be
considered.
Revision No – R0 43 Design Basis Report
Detailed Design for 4 Laning of Bhavnagar Talaja section of NH 8E
(Package-1) from Km 7.090 to Km 53.585 in the State of Gujarat on
Hybrid Annuity Mode
Considering the number of bridges, culverts and grade separated structures are to be
built in this project following objectives have been kept in mind while choosing the
appropriate structure type:
• The construction technique shall aim to strike a balance between ‘highly mechanized’
and ‘labor intensive’ approach. A semi-mechanized approach would be desirable in
this project with strong local community involvement.
• The structural scheme shall cause least disturbance to the existing traffic, wherever
the corridor crosses an existing road.
Superstructure
Since it is observed that most of the bridges are of short to medium span range
along the corridor and therefore for a specific site, the numbers of elements are not too
high. This will involve a higher cost of transportation and launching. Cast-in-situ
solutions are considered more appropriate for this project in place of pre-cast solution
unless the site situation demands otherwise.
Substructure
For urban flyover and road over bridges, the pier shape is extremely important from
aesthetic considerations. The piers/pier cap should look lighter and less massive. It may be
useful to provide wall type pier which will not only look slender but can also reduce the
cantilever of the pier cap. In order to enhance the aesthetics, the columns may be
provided with vertical grooves.
The abutments in case of bridges on canal / streams shall be solid cantilever type having a
wall face in front. Spill through abutments may be provided in cases where the front of the
abutment is well protected by means of a suitably designed stone pitching and launching
aprons.
In case of urban flyovers the wall face of the abutment needs architectural treatment to
break the feeling of massiveness. The wall face can be used to form sculptural treatment
(say embossing logo of the concessionaire & client) or with vertical grooves.
In general, where hard strata is met with at shallow depth, open foundation shall be
provided.
The typical deck configuration for 2 -Lane carriageway ( 1 x 12.5 ) and 3 -Lane
carriageway ( 1 x 14.5 ) are presented in Figure:
For Flyover, VUP, CUP, Minor Bridge and Culvert, deck width with or without footpath to
be adopted as per the CA proposal. Typical GAD for Pipe Culvert, Box Culvert and VUP
is in Appendix A.
A
D/S U/S
SECTION B-B
SECTIONAL VIEW A-A
DETAIL-C
D/S
U/S
SECTION D-D
A
PLAN
SECTION C-C
DETAIL-A
NOTES:
U/S
D/S
X FLOW
BHAVNAGAT
C
B
FLOW
A A
SECTION B-B
B
SECTION B-B
TALAJA
C
PLAN
NOTES:
DETAIL - X
B
BHAVNAGAR TALAJA
DETAIL-1
BHAVNAGAT
DETAIL-2
SECTION B-B
PLAN AT BOTTOM
A A
PLAN AT TOP
DETAIL-1 DETAIL -2
TALAJA
PLAN
NOTES:
almondz
FOUR LANING OF BHAVNAGAR-TALAJA SECTION OF
NH-8E FROM KM 7.090 (DESIGN CH. KM 6.945) TO CHECKED BY:
GENERAL ARRANGEMENT DRAWING
C.B.
the infrastructure specialist KM 53.585 (DESIGN CH. KM 54.990) IN THE STATE OF OF VEHICULAR UNDERPASS
GUJARAT THROUGH PUBLIC PRIVATE PARTNERSHIP DESIGNED BY: C.B. FOR (NEW CONSTRUCTION)
National Highways Authority of India Almondz Global Infra-Consultants Ltd (PPP) ON HYBRID (ANNUITY) MODE.
(A wholly subsidiary of AGSL)
(Ministry of Road Transport & Highways) DRAWN BY: A.R.
(Government of India) F - 33/3, Okhla Industrial Area, Phase - II, New Delhi-110020
19-08-16 A0 FOR STUDY PURPOSE ONLY G-5 & 6, Sector 10, Dwaraka, New Delhi. STATUS SCALE: DATE: DRG. NO. AGICL/216001/B/VUP-GA-0001 REV.
SADBHAV ENGINEERING LIMITED FOR REVIEW
DATE REV DESCRIPTION OF REVISIONS BY AS SHOWN AUGUST - 2016 A0
SH.
Almondz Global Infra-Consultants Ltd.
Almondz Global Infra-Consultants Ltd.
BHAVNAGAR TALAJA
DETAIL-1
DETAIL-2
SECTION B-B
BHAVNAGAT
PLAN AT BOTTOM
A A
PLAN AT TOP
DETAIL-1 DETAIL -2
TALAJA
PLAN
NOTES:
almondz
FOUR LANING OF BHAVNAGAR-TALAJA SECTION OF
NH-8E FROM KM 7.090 (DESIGN CH. KM 6.945) TO CHECKED BY:
GENERAL ARRANGEMENT DRAWING
C.B.
the infrastructure specialist KM 53.585 (DESIGN CH. KM 54.990) IN THE STATE OF OF VEHICULAR UNDERPASS
GUJARAT THROUGH PUBLIC PRIVATE PARTNERSHIP DESIGNED BY: C.B. FOR (NEW CONSTRUCTION)
National Highways Authority of India Almondz Global Infra-Consultants Ltd (PPP) ON HYBRID (ANNUITY) MODE.
(A wholly subsidiary of AGSL)
(Ministry of Road Transport & Highways) DRAWN BY: A.R.
(Government of India) F - 33/3, Okhla Industrial Area, Phase - II, New Delhi-110020
19-08-16 A0 FOR STUDY PURPOSE ONLY G-5 & 6, Sector 10, Dwaraka, New Delhi. STATUS SCALE: DATE: DRG. NO. AGICL/216001/B/VUP-GA-0002 REV.
SADBHAV ENGINEERING LIMITED FOR REVIEW
DATE REV DESCRIPTION OF REVISIONS BY AS SHOWN AUGUST - 2016 A0
SH.