Professional Documents
Culture Documents
SAP CO Variance Analysis
SAP CO Variance Analysis
Variance Categories
284
SAP CO-PRODUCT COSTING & MATERIAL LEDGER
Variance Categories
The following variance categories are shown based on key figures and/or original cost elements.
Variances are divided into variance categories on the input side and variance categories on the output side.
side
Material 1 10 10
Machine 2 10 20
Labor 3 15 45
285
SAP CO-PRODUCT COSTING & MATERIAL LEDGER
1).Material
1).Material Price Variance
Material 1 12 12
Machine 2 10 20
Labour 3 15 45
286
SAP CO-PRODUCT COSTING & MATERIAL LEDGER
Here total variance is here 77-75 = 2 (due to material price changes happened)
This 2 will comes under Input Price Variance
Settlement
FI Entry
287
SAP CO-PRODUCT COSTING & MATERIAL LEDGER
2).Activity
).Activity RATE Variance
Here Activity rates changes 12 and 18 machine & Labor respectively. Raw Material Price changed to12, while doing
goods issue this price suppose 12, then
Material 1 10 10 Material 1 10 10
Machine 2 10 20 Machine 2 12 24
Labour 3 15 45 Labour 3 18 54
288
SAP CO-PRODUCT COSTING & MATERIAL LEDGER
Here total variance is here 88-75 = 13 (due to material price changes happened)
This 13 will comes under Input Price Variance
Settlement
FI Entry
289
SAP CO-PRODUCT COSTING & MATERIAL LEDGER
If you want to see input quantity variances and input price variances, you must make the following settings:
o Select the Material origin indicator in the costing view of the material master record.
o Select the Record quantity indicator in the cost element.
Material 1 10 10 Material 3 10 30
Machine 2 10 20 Machine 2 10 20
Labour 3 15 45 Labour 3 15 45
290
SAP CO-PRODUCT COSTING & MATERIAL LEDGER
291
SAP CO-PRODUCT COSTING & MATERIAL LEDGER
Material 1 10 10 Material 1 10 10
Machine 2 10 20 Machine 4 10 40
Labour 3 15 45 Labour 5 15 75
Settlement
FI entry
292
SAP CO-PRODUCT COSTING & MATERIAL LEDGER
Resource-
Resource-usage variances
Resource-usage variances are caused by the use of different materials and activities than were planned.
The system calculates resource-usage variances if:
o The target costs of a cost element, origin group, or origin are not zero while the actual costs of the same
cost element, origin group, or origin are zero.
o The target costs of a cost element, origin group, or origin are zero but the actual costs of the same cost
element, origin group, or origin are not zero.
293
SAP CO-PRODUCT COSTING & MATERIAL LEDGER
Machine 2 10 20 Machine 2 10 20
Labour 3 15 45 Labour 3 15 45
294
SAP CO-PRODUCT COSTING & MATERIAL LEDGER
Standard Cost
Material 1 10 10
Machine 2 10 20
Labour 3 15 45
295