ATTACHMENT - 1

ESTIMATED COST

LAYING OF MDPE NETWORK, GI/CU/MLC INSTALLATION AND MRS FABRICATION IN NCT OF DELHI, UP, HARYANA & RAJASTHAN

SEGMENT - B : MEERUT, SHAMLI & MUZAFFARNAGAR, KANPUR, FATEHPUR & HAMIRPUR, HARYANA & RAJASTHAN
Unit Rate Total Amount
Quantity (All inclusive prices except GST) (All inclusive prices except GST)
(in INR) (in INR)
Item No. Description Unit

UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan

(1) (2) (3) (4) (5) (6) (7) (8) (9) = (3) X (6) (10) = (4) X (7) (11) = (5) X (8)

PART-I MDPE SECTION

Route survey of allotted areas and Preparation /Submission of detailed route plan for approval by EIC in AutoCAD format.
Receiving, handling, loading, transportation and unloading of owner supplied MDPE pipes & fittings and other free issue items
from IGL's designated stock yards to Contractor's own stock-yards/ work-sites. Proper storing, stacking, identification, providing
security and insurance cover for the materials.
Liaisoning with Landowning agencies / statutory authorities and obtaining permission from them (Separately payable as per SOR
Item No. 9), making trial pits to determine the underground utilities/ services etc., restoration of the abandoned excavation/ trial
pits (excavated to depth of 1.5 m or more as per satisfaction to EIC / Site-in-charge) to original condition, barricading the work
area as per the procedures & drawings provided in the tender and as per the directions of EIC / Site-in-charge; uncoiling /
stringing of pipes, jointing of the pipe ends/ fittings / Transition fittings/ valves by qualified personnel, using approved electro
fusion techniques as per specification.

Laying using any method (Open trench, Moling and HDD) with or without casing; it includes survey of the under ground utilities,
submission of pre & post HDD profile for approval, execution of the work as per specification (as per trench dimension Drg No
15792-10-03--27), including excavation of pits, moling with hole size not exceeding 20% of the the carrier / casing pipe dia.
jointing and insertion of the carrier pipe in casing pipe (on case to case basis) and subsequent padding with soft soil, laying of
warning mat in open trench only, backfilling, compaction, submission of as built drawing, as graphs as per attached specification
and instruction of ElC / Site Engineer of Owner. Includes laying of pipeline in all type of surface including Kutcha, metal,
concrete (PCC/RCC), bituminous, tiled, brick lined etc. after raking up of hard surface of any type; Roads, Pavement, Footpaths
etc. shall be made motorable once the pipeline is laid.

In case, it is impractical to provide 1.0-meter cover due to physical constrain, additional protective measures such as concrete
slab or high impact resistance plastic sheet shall be installed (for the minimum top cover of 600 mm) by the contractor in
consultation with EIC / Site-in-charge. EIC / Site-in-charge after examining thoroughly and considering the PNGRB Guidelines
may allow the contractor. However, the contractor has to raise technical deviation for approval before commence of work. All
the technical deviation shall be submitted with the RA bills.
Supply & installation of Gl Sleeves, 2.5" NB x 300 mm length GI pipe Sleeve / Half Round Concrete Sleeves for domestic
connections, 3" NB x 300 mm length Gl Sleeve for commercial and industrial installations (as per GI Pipe Sleeve Drg No 15792-10-
03--18), and 1/2 Round concrete sleeve, Drg No 15792-10-03--33) excavation, breaking through any obstructions, insertion of
pipe, sealing the annulus, fixing of the sleeves with concrete mix, preparation of pedestal & restoration of excavated pits within
the size of pedestal & the same pit with the laying of 20/32 mm dia MDPE pipe as defined in technical specification and
instruction of ElC.
Flushing, cleaning ,Pneumatic testing, purging with nitrogen and commissioning as per specification and approved procedures
providing all tools and tackles, nitrogen, instruments, manpower and other related accessories and as per instructions of the
Engineer-in charge.
Maintaining the completed pipelines / installation for any defect, failures during defect liability period .
Handing over the completed works to IGL for their operation/ use, returning of all surplus material to IGL stores, reconciliation of
free issue material area wise and obtaining no objection certificate.
On completion of gas charging of pipelines, preparation and submission of As built drawings, crossings details, termination,
utility graphs and deviation statements.
Submission of all documents required for contract closure in numbers as mentioned in contract.
Note- Supply & installation of GI Sleeve / Half round Concrete sleeve and warning mat (open trench excavation) shall be
included in laying of MDPE pipe.(Refer Drg No. 15792-20-03--18);
Laying in Brick trench shall not payable in this SOR; In such cases SOR No. -20 is valid.
MDPE Pipe line laying in Soft soil & all type of surface (Including PCC/RCC Top Surface - Upto 12") , Open Cut / Moling or any
1
other methodology ; Clear cover to pipeline min 1.0m; (Refer Drg No 15792-10-03-27))
1.1 20 mm Dia M 54746 35736 359489 318.14 304.17 302.65 1,74,16,892.44 1,08,69,819.12 10,87,99,345.85
1.2 32 mm Dia M 271617 252257 1028847 319.55 305.51 303.99 8,67,95,212.35 7,70,67,036.07 31,27,59,199.53
1.3 63 mm Dia (Excluding HDD with casing) M 241673 144472 376790 374.39 357.95 356.17 9,04,79,954.47 5,17,13,752.40 13,42,01,294.30
1.4 125mm dia (Excluding HDD with/without casing) M 26863 60934 158918 481.67 460.52 458.23 1,29,39,101.21 2,80,61,325.68 7,28,20,995.14
1.5 180 mm dia (Excluding HDD with/without casing) M 1281 4193 49213 586.04 560.32 557.53 7,50,717.24 23,49,421.76 2,74,37,723.89
MDPE Pipe line laying in common trench.
1.6 32 mm Dia (in common trench with 63/125/180 mm Dia MDPE Pipe) M 2985 2566 10466 106.52 101.84 101.33 3,17,962.20 2,61,321.44 10,60,519.78
1.7 63 mm Dia (in common trench with 125/180 mm Dia MDPE Pipe) M 2446 1474 3845 124.80 119.32 118.72 3,05,260.80 1,75,877.68 4,56,478.40
1.8 125mm dia (in common trench with 180 mm Dia MDPE Pipe) M 655 983 2563 160.56 153.51 152.74 1,05,166.80 1,50,900.33 3,91,472.62

Page 1 of 14
ATTACHMENT - 1
ESTIMATED COST

LAYING OF MDPE NETWORK, GI/CU/MLC INSTALLATION AND MRS FABRICATION IN NCT OF DELHI, UP, HARYANA & RAJASTHAN

SEGMENT - B : MEERUT, SHAMLI & MUZAFFARNAGAR, KANPUR, FATEHPUR & HAMIRPUR, HARYANA & RAJASTHAN
Unit Rate Total Amount
Quantity (All inclusive prices except GST) (All inclusive prices except GST)
(in INR) (in INR)
Item No. Description Unit

UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan

All service lines left out initially during mainline laying, shall be laid under above mentioned SOR within six months of gas
charging of a particular area by the same contractor. In Open trench method/ moiling, no extra rate shall be payable for casing
installation. Roads, Pavement, Footpaths, Kutcha etc. shall be made motorable once the pipeline is laid.

2 MDPE Pipe line laying by HDD Method, with Casing


Survey of the under ground utilities, submission of HDD profile for approval (excluding road and nalla crossings), execution of
the work as per the standard procedure attached, including excavation of the pits, Jointing of casing and carrier pipe and
insertion of the carrier pipe in casing of dia ranging from 110mm to 160mm for 63 mm, 200mm to 250 mm dia for 125 mm dia
MDPE and 250 mm to 315 dia for 180 mm MDPE, subsequent sealing, backfilling, compaction, submission of as built graphs,
final HDD profiles as per attached specification and the instruction of EIC / Site Engineer of Owner. The other activities are as
per SOR Item No. 1 and as detailed in specification and as per the instructions of the EIC / Site engineer of Owner.
The payment shall be made for length of casing pipe laid in HDD, remaining carrier pipe length without casing shall be paid under
SOR item no.1
2.1 63 mm Dia HDD with casing M 489 1474 3845 481.67 460.52 458.23 2,35,536.63 6,78,806.48 17,61,894.35
2.2 125 mm Dia HDD with casing M 1310 983 2563 1,189.92 1,137.67 1,132.01 15,58,795.20 11,18,329.61 29,01,341.63
2.3 180 mm Dia HDD with casing M 29 11 128 1,428.21 1,365.50 1,358.70 41,418.09 15,020.50 1,73,913.60

3 MDPE Pipe line laying by HDD Method, without Casing


Survey of the under ground utilities, submission of profile for approval, execution of the work as per the standard procedure
attached, including excavation of the pits, Jointing and insertion of the carrier pipe, subsequent backfilling, compaction,
submission of as built graphs and final HDD profiles as per attached specification and the instruction of EIC / Site Engineer of
Owner. The other activities are as per SOR Item No. 1 & 2 and as detailed in specification and as per the instructions of the EIC /
Site engineer of Owner
3.1 125 mm Dia HDD without casing M 36691 35381 92275 602.70 576.23 573.37 2,21,13,665.70 2,03,87,593.63 5,29,07,716.75
3.2 180 mm Dia HDD without casing M 1602 1256 14738 806.94 771.52 767.68 12,92,717.88 9,69,029.12 1,13,14,067.84
Laying of MDPE pipeline by HDD method ( Maximum length 200m)-
This SOR may be applicable only for spans less than 200m where additional mobilization of HDD m/c is required & HDD is the
3.3 only option to execute the same.
Note: There should be no consecutive HDD laying in upstream/downstream within a span of 1KM & This SOR would be
applicable for allocations less than 200 m in a single stretch
3.3a 63 mm by HDD method ( with casing) Nos. 3 5 5 74,877.26 71,590.70 71,234.53 2,24,631.78 3,57,953.50 3,56,172.65
3.3b 125 mm by HDD method( with/ without casing) Nos. 3 5 5 1,20,540.46 1,15,246.90 1,14,673.54 3,61,621.38 5,76,234.50 5,73,367.70

4 MDPE Service Line laying in old Projects / O&M areas


Includes laying of pipeline (for 20 & 32mm) in all type of surface i.e. Kutcha, metal, concrete (PCC/RCC), bituminous, tiled,
brick lined etc. after raking up of hard surface of any type by any methodology. Roads, Pavement, Footpaths etc. shall be made
motorable once the pipeline is laid. Supply & installation of GI Sleeve / Half round Concrete sleeve shall be included in laying
rates. All other activities mentioned in SOR no.1 are applicable.

Supply & installation of Gl Sleeves, 2.5" NB x 300 mm length Half Round Concrete Sleeves for domestic connections, 3" NB x 300
mm length Gl Sleeve for commercial and industrial installations (as per Drg No15792-20-03--18)) excavation, breaking through
any obstructions, insertion of pipe, sealing the annulus, fixing of the sleeves with concrete mix, preparation of pedestal &
restoration of excavated pits within the size of pedestal & the same pit with the laying of 20/32 mm as defined in technical
specification and instruction of ElC.The rates shall include liaison rates with statutory bodies and no separate rates are payable
under this SOR. Wherever service lines are to be laid as per Dwg.- 15792-10-03-46A.

Note:-
1. Old Project area shall be defined as an area where MDPE line is already been laid by another contractor (currently not
working in respective zone), only service line connectivity shall be done by the contractor.
2. Additional rate for construction of RCC structure for protection of service line shall be payable under SOR no. 4.3
3. Compliance to Health, Safety & Environment (HSE) during laying of service line, additional rate shall be payable under SOR
no. 10.1

4.1 For pipe length up to 8 meters Nos 7917 447 3538 4,586.81 4,385.40 4,363.58 3,63,13,774.77 19,60,273.80 1,54,38,346.04
4.2 Per meter rate for pipeline more than 8 meters ( Per meter additional rate shall be payable above SOR item no. 4.1) M 22277 704 4016 318.14 304.17 302.65 70,87,204.78 2,14,135.68 12,15,442.40

Page 2 of 14
ATTACHMENT - 1
ESTIMATED COST

LAYING OF MDPE NETWORK, GI/CU/MLC INSTALLATION AND MRS FABRICATION IN NCT OF DELHI, UP, HARYANA & RAJASTHAN

SEGMENT - B : MEERUT, SHAMLI & MUZAFFARNAGAR, KANPUR, FATEHPUR & HAMIRPUR, HARYANA & RAJASTHAN
Unit Rate Total Amount
Quantity (All inclusive prices except GST) (All inclusive prices except GST)
(in INR) (in INR)
Item No. Description Unit

UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan

Construction of RCC structure for protection of service line (20/32 mm dia. ) for drain/nallah (adjecent to house / Boundry
4.3
walls / Multistory Buildings) crossing as per Dwg.- 15792-10-03-46A

The scope includesconstruction providing and laying reinforced cement concrete of M-25 grade ( Concrete shall be design
mix/nominal mix) with 20mm & down size graded crushed stone aggregates in Non suspended slabs/pavement slabs including
pedestal/ramp etc., laying in alternate panels to required slopes, all necessary form work and finishing the top surface Nos. 1704 640 6345 2,482.49 2,452.83 2,440.63 42,30,162.96 15,69,811.20 1,54,85,797.35
rough/smooth as required in any position, shape, level and thickness etc. The rates includes grouting of pockets, supply of
material, tools, shuttering, Reinforce ment etc.

5 Excavation in Special Conditions:


Excavation of trench or pits in Malba/Multiple layers of asphalt/ brick / PCC/RCC etc. The rates are payable over and above the
5.1
Laying rates as per relevant SOR item no 1

Cutting of PCC/RCC surface with thickness more than 12" or more than 24" continuous asphalt multi-layer/Malba/Brick/Boulders
. M 27376 23344 81532 210.02 207.51 206.48 57,49,507.52 48,44,113.44 1,68,34,727.36
(Malba shall be considered as a strata where soil is in mixed form of debris/building rubbish or discarded pieces of bricks/stones )
5.2 Excavation of Hard Rock:
Trenching of Hard Rock is defined as trench material with a single piece of rock, dimension exceeding 1 meter in any direction,
which requires cutting only by use of manual/pneumatic chisel/drill or sledge hammer and chisel or removal of same by
additional techniques and supply of approved coarse sand (Size 0.6-2 mm as per IS 383) free from any impurities like clay, mica Cu.M 1456 1092 84586 3,309.58 3,164.27 3,148.52 48,18,748.48 34,55,382.84 26,63,20,712.72
and soft flaky pieces for padding of 150 mm above and below laid pipeline as per the specifications ; The rates are payable over
and above the Laying rates as per relevant SOR item no 1
5.3 Excavation in Congested Area:
Congested area shall be defined as an area where MDPE pipeline has to be laid in narrow lanes ( Less than 4.5 M including
footpath/drains) & houses in such locations have only one side entrance i.e. there is no backlane between two back to back
M 51872 20038 70997 51.41 50.80 50.55 26,66,739.52 10,17,930.40 35,88,898.35
houses & pipeline has to be laid in front of the house. The rates are payable over and above the Laying rates as per relevant SOR
item no 1. ( These rates are not applicable on HDD method)
5.4 Excavation in continuous water seepage area:
The water seepage area shall be defined as an area where the MDPE pipeline has to be laid, in such locations where continuous
water seepage occur during trench activity and the same shall not be possible. In that case, the contractor shall have to deploy
additional equipment i.e. de-watering pumps etc. for continuous de-watering so that waterlogging shall be avoided. The rates M 2738 2334 8153 21.78 21.90 21.90 59,633.64 51,114.60 1,78,550.70
are payable over and above the Laying rates as per relevant SOR item no 1. ( These rates are not applicable on HDD/Moling
method)

6 Restoration of trenches

Restoration to original conditions of dismantled surface like Asphalted/Bituminous Road, Concrete Pavement, Agra /Kota Stones
/ Tiles (Chequered/interlocking etc.), Dry Brick Pavement as per the technical specifications attached in the tender after laying of
pipeline in Built- Up surface, as per the directions of EIC / Site lncharge. Scope includes supply of the approved quality material,
6.1 Cu.M 944 678 4176 3,889.84 3,774.84 3,762.30 36,72,008.96 25,59,341.52 1,57,11,364.80
testing of materials by third party agencies as per technical specification / CPWD / IRC Standards, submission of the restoration
reports, obtaining no objection certificates from the concern local authorities /land owners / third party inspection agencies
designated by land owing agencies and Owner.

Providing & laying, Fixing, of cement concrete interlocking paver blocks of approved size, design shape as per the directions of
6.2 EIC / Site lncharge. Scope includes supply of the approved quality material, testing of materials by third party agencies as per Sq.M 750 9000 1500 859.35 859.35 859.35 6,44,512.50 77,34,150.00 12,89,025.00
technical specification / CPWD / IRC Standards.

7 Survey
7.1 GPR survey M 30576 25389 87576 10.68 10.68 10.68 3,26,551.68 2,71,154.52 9,35,311.68
7.2 GIS Survey

Page 3 of 14
ATTACHMENT - 1
ESTIMATED COST

LAYING OF MDPE NETWORK, GI/CU/MLC INSTALLATION AND MRS FABRICATION IN NCT OF DELHI, UP, HARYANA & RAJASTHAN

SEGMENT - B : MEERUT, SHAMLI & MUZAFFARNAGAR, KANPUR, FATEHPUR & HAMIRPUR, HARYANA & RAJASTHAN
Unit Rate Total Amount
Quantity (All inclusive prices except GST) (All inclusive prices except GST)
(in INR) (in INR)
Item No. Description Unit

UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan

● Purchasing Base Map (Raster Data) and crea on of Land Base (Vector Data) of the area of work (as per specifica ons provided
by IGL)
● Mapping of the pipeline on the land base created based on construc on drawing.
M 728000 546000 2136000 14.00 14.00 14.00 1,01,92,000.00 76,44,000.00 2,99,04,000.00
● Above Ground asset coordinate capturing a er commissioning and finalising en re network a er commissioning.
● Submission of network and land base data in CAD and SHAPE File as per IGL Data Model along with associated Topological &
Connectivity Rules

8 Fabrication & Installation of Pipeline Markers:


Supply and Installation of Stone Route Markers, Powder Coated Plate / Pole Markers as per the attached drawings, along the
route / along boundary wall, lamp posts including all associated civil works such as excavation and construction in all types of
soils, construction of pedestals and grouting with concrete, cleaning, supply and application of approved colour and quality of
primer and paint, stencil letter cutting of numbers, direction, chainage etc., restoration of area to original condition and
performing all works as per drawings, specification and instruction of Engineer-in-Charge. The rates shall include liaison rates
with statutory bodies and restoration rates and no separate rates are payable under this SOR.
8.1 Stone Route Markers as per Drg No15792-10-03--29) Nos 8154 6770 23354 553.61 537.24 535.46 45,14,135.94 36,37,114.80 1,25,05,132.84
8.2 Pole markers with foundation as per Drawing No. Drg No15792-10-03-30 & 15792-10-03-31) and specification. Nos 2225 1773 5176 2,651.26 2,572.88 2,564.34 58,99,053.50 45,61,716.24 1,32,73,023.84
8.3 Plate marker as per Drg No Drg No 15792-10-03--28) Nos 17041 6403 63453 248.32 240.99 240.19 42,31,621.12 15,43,058.97 1,52,40,776.07

9 LIASONING WITH LAND OWNING AGENCIES FOR PERMISSION


Submission of applications as per approved drawings provided by owner / owner's representative (Initial Route
Survey,Preperation of Drawings, measuring and providing details of surface type shall be in scope of Contractor with approval
from Owner / Owner's representative), obtaining & submission of demand note, Coordination, Liaisoning, Obtaining written
permissions from Land owing agencies like MCD, PWD, DDA, NDMC, NHAI, AAI, GDA, GNDA, GNN, Forest Dept, NHAI, Indian
Railways, other government agencies who maintains the public lands and Private lands i.e. Apartments/institutions etc. Note:
Service lines in SOR item no. 4 are not applicable;
9.1 For All sizes - Actual length of network laid against written permission M 259896 289435 1015882 66.55 63.01 63.01 1,72,96,078.80 1,82,37,299.35 6,40,10,724.82
9.2 For All sizes - Actual length of network laid where written permissions are not available M 122304 152334 534214 33.28 31.51 31.51 40,70,277.12 48,00,044.34 1,68,33,083.14
9.3 For reserved/ Protected / Unprotected Forests M 626 502 1410 178.00 178.00 178.00 1,11,428.00 89,356.00 2,50,980.00

10 Charges for compliance to Health, Safety & Environment (HSE) as detailed in Scope of Work.

MDPE Section-PPE, Contineous Barricades along the trenches as per approved drawing in tender, Use of Safety Boots, Hand
10.1 gloves, Reflective jackets, Hard hats(helmets), Safety shoes, eye and ear safety equipments, Fire extinguishers and as per the M 728000 546000 2136000 16.57 16.57 16.57 1,20,62,960.00 90,47,220.00 3,53,93,520.00
detailed scope of work in tender specifications.
GI Section- Safety requirement per Rise- Use of Fall arrestor/ petzl, Ascendors/descendors, PPE, Barricades/ Warning Boards (03
Nos. ) connected with warning/Caution tapes in areas where piping work is in progress , Use of Safety shoes, Walky talky, Hand
gloves, Reflective jackets, Hard hats(helmets), eye and ear safety equipments, Fire extinguishers and as per the detailed scope of
10.2 work in tender specifications; Nos 7356 17127 167400 515.85 515.85 515.85 37,94,592.60 88,34,962.95 8,63,53,290.00
In case of non compliance- Refere SCC clause - for applicable penalty .
Upto 4th GI (G+4) floor full body safety harness & assessories shall be of KARAM or equivalent make.
Note- This SOR is applicable for Non LMC length of GI Section only.
GI Section- Safety requirement per Rise-Use of Fall arrestor/ petzl, Ascendors/descendors, PPE, Barricades/ Warning Boards (03
Nos. ) connected with warning/Caution tapes in areas where piping work is in progress , Use of Safety shoes, Walky talky, Hand
gloves, Reflective jackets, Hard hats(helmets), eye and ear safety equipments, Fire extinguishers and as per the detailed scope of
10.3 work in tender specifications; Nos 3197 4956 23600 1,241.38 1,241.38 1,241.38 39,68,691.86 61,52,279.28 2,92,96,568.00
In case of non compliance- Refere SCC clause - for applicable penalty .
GI (G+5) and above including high rise Above 4th floor full body safety harness & assessories shall be of PETZL is compulsory.
Note- This SOR is applicable for Non LMC length of GI Section only.

PART II GI / COPPER SECTION


11 Supply & Installation of Powder Coated GI Service Pipe & Fittings

Page 4 of 14
ATTACHMENT - 1
ESTIMATED COST

LAYING OF MDPE NETWORK, GI/CU/MLC INSTALLATION AND MRS FABRICATION IN NCT OF DELHI, UP, HARYANA & RAJASTHAN

SEGMENT - B : MEERUT, SHAMLI & MUZAFFARNAGAR, KANPUR, FATEHPUR & HAMIRPUR, HARYANA & RAJASTHAN
Unit Rate Total Amount
Quantity (All inclusive prices except GST) (All inclusive prices except GST)
(in INR) (in INR)
Item No. Description Unit

UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan

Assessment of material requirement for installation at site, Order placement and Purchasing of Powder coated Gl Pipes, GI
fittings, Copper pipes & fittings, Brass Fittings from approved vendors of IGL, Scheduling, Planning of material & Forwarding
inspection call, getting dispatch clearance, handling, loading, transportation and unloading of these items at respective
contractor's store. Receiving, taking over, handling, loading, transportation and unloading of owner supplied above ground
fittings such as regulators, meters, Isolation Valves & appliance valves and other free issue items as defined in specification
from Owner's designated stock yards to Contractor's own stores / work sites, proper storing, stacking, identification,
providing security and insurance cover. Preparation and approval of sketches, schedules & execution procedures. Finalising
optimum route with consent of customer from transition fitting to cooking oven / appliance and ensuring installations in well
ventilated area. Making temporary but stable platforms/ scaffolding/ rope ladders and supply of all other safety devices. Portal
entry for new connections - New registration tracking and feasibility survey and its updation as per IGL defined TAT;printing of
stationary as per approved IGL formats required during connections. Followup and attend complaints receives from customer
regarding delay in new connection (ReferDrg No 15792-20-05--01, 02, 03)

Installation of GI service pipes & fittings, regulators, Valves etc. including NPT threading, as specified, Drillings of holes through
the walls (Brick, RCC), Granite, Marble, Wood Cutting, Glass Cutting with proper heavy duty hammer drill machine, tools &
tackles, using proper sealant/grout material and colours to match the original replacement of the damages during drilling,
restoring the area to the original condition, Painting of scratched length of powder coated pipe and fittings after proper surface
finish by one coat of approved primer paint and two coats of approved synthetic enamel paint. Restoring the wall surface to
original conditions.
Supply & fixing of approved clamps & nylon rawl plugs with SS 304 2" screws, grout material, suitable thread sealant i.e. Teflon
Tape, Joining of transition fitting to above ground service GI pipes, testing, purging and commission of the complete installation.
The rates in connections also includes meter installation, tap off rates. The GI installation in already gas charged areas, planning
& coordinating with existing consumer's for New tap offs from existing riser with or without tee, testing of these existing risers
and commissioning of these connections with newly tapp offs etc.is inclusive.
NON LMC
11.1 Supply & installation powder coated 1/2" Gl Pipe from TF to regulator. Nos 30037 44121 190000 430.75 414.26 412.45 1,29,38,437.75 1,82,77,565.46 7,83,65,500.00
Supply & Installation of powder coated 1/2" Gl Riser from regulator isolation valve to lateral isolation valve for G+3 Apt and
11.2 M 345424 507396 2185000 391.59 376.59 374.95 13,52,64,584.16 19,10,80,259.64 81,92,65,750.00
Individual kothi /Bungalow. Refer Drg No 15792-20-05--02)
Supply & installation of powder coated 3/4" Gl Riser from regulator isolation valve to lateral isolation valve for Apt more than
11.3 M 33041 44121 190000 398.66 383.39 381.72 1,31,72,125.06 1,69,15,550.19 7,25,26,800.00
G+3 floors. Refer Drg No 15792-20-05-02)
Testing & Commissioioning of already installed Risers / Laterals ( Including installation of regulator), replacement of defective
11.4
fittings, installation of GI pipe up to 2 meter, if required.
11.4 GI / Copper Pipe ( 1/2" / 3/4" / 12mm ) M 757 552 2375 55.23 53.11 52.88 41,809.11 29,316.72 1,25,590.00

12 LMC
12.1 PNG CONNECTIONS IN PROJECT AREA-LOWRISE
Supply and installation from lateral isolation valve to appliance along with meter installation, The cumulative length of 1/2 "GI
within 2 m & Cu/MLC within 2m or (GI + Cu/MLC) within 4m after lateral isolation valve upto appliance along with installation of
Nos 21250 41867 186000 2,657.13 2,555.38 2,544.25 5,64,64,012.50 10,69,86,094.46 47,32,30,500.00
meter, Additional quantity above 4 Meters (GI + Cu/MLC) shall be payable only in case cumulative length exceeds 4 m. Payment
against additional length of (GI + Cu/MLC) shall be as per item 13 of SOR.
12.2 PNG CONNECTIONS IN O&M AREA (ON EXISTING RISER)
Basic Rate- Supply and installation from existing riser to appliance along with meter installation - Supply and installation from
lateral isolation valve to appliance along with meter installation, The cumulative length of 1/2 "GI within 2 m & Cu/MLC within
2m or (GI + Cu/MLC) within 4m after lateral isolation valve upto appliance along with installation of meter . Additional quantity Nos 8787 2255 4000 3,321.41 3,194.22 3,180.31 2,91,85,229.67 72,02,966.10 1,27,21,240.00
above 4 Meters (GI + Cu/MLC) shall be payable only in case cumulative length exceeds 4 m. Payment against additional length
of (GI + Cu/MLC) shall be as per item 13 of SOR.

13 Powder coated GI and Cu installations for pipes more than 4 m per connection
13.1 1/2" Powder coated GI M 40730 59829 257640 338.21 325.27 323.85 1,37,75,293.30 1,94,60,578.83 8,34,36,714.00
13.2 12mm Copper Pipe/MLC Pipe - Inside kitchen location only M 601 882 3800 344.76 331.55 330.11 2,07,200.76 2,92,427.10 12,54,418.00
Note: 1.GI, Cu/MLC, brass fittings shall not be counted separately. It shall be measured along with GI & Cu/MLC pipe.
2. If Cumulative length of GI & Cu/MLC increases specified lengths in connection rate SOR 12, extra piping shall be paid
considering installation as done in Flats or bungalows as per SOR item no. 13.

Page 5 of 14
ATTACHMENT - 1
ESTIMATED COST

LAYING OF MDPE NETWORK, GI/CU/MLC INSTALLATION AND MRS FABRICATION IN NCT OF DELHI, UP, HARYANA & RAJASTHAN

SEGMENT - B : MEERUT, SHAMLI & MUZAFFARNAGAR, KANPUR, FATEHPUR & HAMIRPUR, HARYANA & RAJASTHAN
Unit Rate Total Amount
Quantity (All inclusive prices except GST) (All inclusive prices except GST)
(in INR) (in INR)
Item No. Description Unit

UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan

Collection of registration forms duly filled with required supporting documents, Submission to IGL marketing on schedule as
14 Nos 2500 2500 10000 240.28 237.76 236.73 6,00,700.00 5,94,400.00 23,67,300.00
decided by IGL; This SOR may be used only after instruction of EIC/Site-in-Charge.

PART III Civil Works


15 Foundation works
15.1 Excavation, Providing and Laying Reinforced Cement Concrete (M-20))
Excavation in any plane & dimension including disposal of excavated earth up to any lead in all conditions, backfilling using
serviceable earth and disposal of surplus and unserviceable earth. Soil to be levelled and properly compacted complete in all
respect as per scope of work, technical specification and directions of EIC / Site-in-charge. Providing and laying REINFORCED
CEMENT CONCRETE OF M-20 Grade (Concrete shall be design mix / nominal mix) with 20mm & down size graded crushed stone
aggregates in NON SUSPENDED slabs/pavement slabs including pedestals, ramps etc., laying in alternate panels to required CU.M 48 162 162 11,463.04 11,124.14 11,087.20 5,50,225.92 18,02,110.68 17,96,126.40
slopes, all necessary form work and finishing the top surface rough or smooth as required and directed, providing
pockets/openings etc. including vibrating, tampering, curing, rendering and making smooth if required in any position,
shape, level and thickness etc. as specified and directed by EIC / Site-in-charge. The rates include grouting of pockets, supply of
material, shuttering, tools & tackles, Reinforcement etc.

15.2 Providing and Laying Plain Cement Concrete (1:4:8)

Providing & laying, Fixing, Centering and Shuttering of plain cement concrete with nominal mix 1:4:8 by mass (1 cement: 4
CU.M 5 10 10 5,597.54 3,609.27 3,597.29 27,987.70 36,092.70 35,972.90
coarse sand: 8 coarse stone/ aggregates/ gravels) with 20 mm down size graded etc as specified in specifications .

16 Shifting and Installation of Field Regulating Station (For weights ranging from 1 Ton to 10 Ton)

Dismantling/loading from IGL site/store and its transportation to IGL store/Site with its unloading and installation of FRS/MRS as
16.1 per the instructions of Site In-charge/ EIC. The shifting of FRS/MRS skids on the platform / foundation shall be done using cranes Nos 5 20 20 32,796.06 32,378.49 32,217.41 1,63,980.30 6,47,569.80 6,44,348.20
/ hydra as required by the site condition.
Disconnection, Loading, Laisoning, Transportation, of wall mounted MRS from IGL's designated site to another site and all others
necessary documentation. Also includes unloading of the systems, storage of system (wherever required), Painting as required,
16.2 Nos 3 5 5 9,304.93 11,545.65 11,488.21 27,914.79 57,728.25 57,441.05
replacement of meter/regulator (wherever required), Re-installation of MRS at IGL's designated site, as required by the site
conditions.

17 Supply & Installation of Half round concrete sleeve (Crush Guard)


Installation of half round concrete sleeve for service line shall be done by sealing the annulus between pipe & sleeve, firm fixing
of concrete sleeve by concrete mix pedestal, clamping, sand filling etc. Half round concrete sleeve shall be made as per drawing
no 15792-10-03-33. Installation shall be done after instruction of IGL/PMC.
17.1 Project Nos 182 119 1198 557.74 541.26 539.46 1,01,508.68 64,409.94 6,46,273.08
17.2 O&M (existing regulator piece) Nos 100 200 200 585.13 567.84 565.95 58,513.00 1,13,568.00 1,13,190.00

18 Supply & Installation of RCC Slab 100 mm thk X 300 mm width


Supply & Installation of RCC (M20) Slab 100 mm thk X 300 mm width; This SOR may be used only after instruction of EIC / Site-in-
M 250 300 300 345.86 335.65 334.54 86,465.00 1,00,695.00 1,00,362.00
charge.

19 Installation of Valve Chambers:


All civil works including supply of materials, excavation of pit, piping supports including all PCC, RCC and Brick works for valve
pits, sand filling to cover valve body, pedestals with insert plates as required, sealing of pipes in pits, providing cover etc.,
finishing, clean up and restoration. The work shall be executed as per specification. Also providing water proofing agents
internal and external plaster of chamber to avoid water seepage. Refer Drg No 15792-20-03-- 20, 21, 22, 23, 24, 25 & 26)
19.1 Brick Valve Chambers- Size (L x W)- 2m x 1 m Nos 16 13 42 26,868.33 26,073.98 25,987.40 4,29,893.28 3,38,961.74 10,91,470.80
19.2 RCC Valve Chambers- Size (L x W)- 2m x 1 m Nos 16 13 42 36,887.02 35,796.48 35,677.62 5,90,192.32 4,65,354.24 14,98,460.04
19.3 Brick Valve Chambers- Size (L x W)- 1.5m x 1 m Nos 79 66 210 21,963.34 21,314.01 21,243.24 17,35,103.86 14,06,724.66 44,61,080.40
19.4 RCC Valve Chambers- Size (L x W)- 1.5m x 1 m Nos 291 243 771 27,113.10 26,311.52 26,224.15 78,89,912.10 63,93,699.36 2,02,18,819.65
19.5 Brick Valve Chambers- Size (L x W)- 1 m x 1 m Nos 26 22 70 13,511.19 13,112.34 13,069.05 3,51,290.94 2,88,471.48 9,14,833.50
19.6 RCC Valve Chambers- Size (L x W)- 1 m x 1 m Nos 79 66 210 18,549.25 18,001.68 17,942.25 14,65,390.75 11,88,110.88 37,67,872.50
19.7 RCC Valve Chambers- Size (L x W)- 0.85 m x 0.85 m Nos 11 9 28 14,000.00 14,000.00 14,000.00 1,54,000.00 1,26,000.00 3,92,000.00
19.8 RCC Valve Chambers- Size (L x W)- 0.6 m x 0.6 m Nos 11 9 28 13,000.00 13,000.00 13,000.00 1,43,000.00 1,17,000.00 3,64,000.00

Page 6 of 14
ATTACHMENT - 1
ESTIMATED COST

LAYING OF MDPE NETWORK, GI/CU/MLC INSTALLATION AND MRS FABRICATION IN NCT OF DELHI, UP, HARYANA & RAJASTHAN

SEGMENT - B : MEERUT, SHAMLI & MUZAFFARNAGAR, KANPUR, FATEHPUR & HAMIRPUR, HARYANA & RAJASTHAN
Unit Rate Total Amount
Quantity (All inclusive prices except GST) (All inclusive prices except GST)
(in INR) (in INR)
Item No. Description Unit

UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan

20 Brick Work
Providing brick work with brick class designation M-7.5 of IS:1077 in cm1:4 (1 cement : 4 sand) in steps, walls, retaining walls and
load bearing structures drains, or any shape with all lead, depths & height including curring, scaffolding, etc., as per CU.M 25 50 50 7,809.25 7,809.25 7,809.25 1,95,231.25 3,90,462.50 3,90,462.50
specifications and drawings with all bye-works and direction of the Enfineer-incharge.
Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all materials such as minimum 43 grade
cement, bricks, finishes, bitumen, other minor constrcution materials, shuttering, staging, masonry work, plastering, painting etc.
with all bye-works and sundry works).
Note: The quantites of individual item can varied as per site requirement.The payment will be made as per actual certified
measurement at site.

Construction of trenches in Builder segment / Private Property i.e Multistory buildings / apartments with no movement of
21
Heavy Vehicles, surrounded with Boundary wall)

Construction of dedicated trench (as per approved drawing) with removable top cover, scope includes excavation of trench,
21.1 construction of brick wall, waterproofing of trench, installation of precast RCC slab covers (including supply) Ref. drawing 15792- M 3808 1954 400 5,599.52 5,433.97 5,415.93 2,13,20,732.35 1,06,15,803.79 21,66,372.00
10-03--34 Tench Dimension- 0.6m x 0.66m x 1.0m ( d x w x l)

Construction of dedicated trench (as per approved drawing) with removable top cover, scope includes excavation of trench,
construction of brick wall, waterproofing of trench, RCC slab (150mm thick and 300mm width) at the top and RCC slab (100mm
thick and 300mm width) at bottom. However, where MDPE laid on the basment top, roof of basment shall be treated as the
bottom.
21.2 M 381 195 40 4,261.75 4,135.76 4,122.03 16,23,726.75 8,06,473.20 1,64,881.20
There shall be sand filling across three sides of the line pipe of 100mm each shall be required to be taken by contractor in
consultation with EIC / Site-in-charge as per latest PNGRB Guidelines.
Minimum pipe top cover of 375 mm is required and the line pressure shall not exceed 110mbar. Tench Dimension- 0.375m x
0.66m x 1.0m ( d x w x l)
Excavation of trench and installation of 6" GI Pipe C Class by any method ( Open /Moiling) , and restoration for road crossing upto
21.3 7.0 m inside society as 15792-10-03-43 M 381 195 40 2,537.54 2,384.75 2,376.83 9,66,802.74 4,65,026.25 95,073.20
Note- In case of restoration SOR Item no. 6 shall be applicable over and above this SOR.
Sand Filling in any type of trenches in builder segment only; Scope includes supply of coarse sand ( Size 0.6 To 2.0mm ) as per IS
21.4 383 free from impurity like clay, mica and soft flaky pieces as per instruction of EIC / Site-in-charge. Cu.M 571 293 60 868.42 842.74 839.94 4,95,867.82 2,46,922.82 50,396.40
Note- Actual qty.( Cu.m) of sand filling for 20.1, 20.2 & 20.3 shall be claimed in this SOR

PART IV HIGH RISE SEGMENT ( 14 Storey & Above)


MDPE Pipe line laying (20mm / 32 mm / 63mm ) in already excavated trench in Builder segment / Private Property i.e
22
Multistory buildings / apartments with no movement of Heavy Vehicles, surrounded with Boundary wall)

Laying in already excavated trench with or without casing ; it includes execution of the work as per specification (as per trench
dimension Drg No 15792-10-03-16), laying, electrofusion joints and insertion of the carrier pipe in casing pipe (on case to case
basis) laying of warning mat and re-installation of pre cast slabs as per specification and instruction of ElC / Site Engineer of M 3808 1954 400 228.35 214.49 213.78 8,69,465.46 4,19,027.66 85,512.00
Owner.
In Case of sand filling required as instructed by EIC/IGL representative SOR no. 20.4 shall be paid over and above this rate.

23 Supply & Installation of Welded Riser - Non LMC


23.1 Installation of welded riser 1/2 inch upto isolation valve M 879 676 1200 558.31 527.06 524.76 4,90,754.49 3,56,292.56 6,29,712.00
23.2 Installation of welded riser 3/4 inch upto isolation valve M 90233 149066 45200 605.03 571.15 568.66 5,45,93,671.99 8,51,39,045.90 2,57,03,432.00
23.3 Installation of welded riser 1 inch upto isolation valve M 13974 25275 7000 677.63 639.70 636.91 94,69,201.62 1,61,68,417.50 44,58,370.00
23.4 Installation of welded riser 2 inch upto isolation valve M 1996 6466 1000 1,260.71 1,190.13 1,184.94 25,16,377.16 76,95,380.58 11,84,940.00

24 LMC
24.1 PNG CONNECTIONS IN PROJECT AREA
For Project Area - Supply and installation from riser (lateral isolation valve) - The cumulative length of 1/2" powder coated GI
pipe within 2 m & Cu/MLC pipe within 2m or (GI + Cu/MLC) within 4m after lateral isolation valve up to appliance along with
installation of meter, meter regulator. Additional quantity above 4 Meters (GI + Cu/MLC) shall be payable only in case if Nos 9519 4884 8000 3,596.40 3,395.05 3,380.27 3,42,34,131.60 1,65,81,424.20 2,70,42,160.00
cumulative length exceeds 4 m.
Note-Payment against additional length of (GI / Cu/MLC) shall be as per item 25 of SOR.

24.2 PNG CONNECTIONS IN O&M AREA (ON EXISTING RISER)

Page 7 of 14
ATTACHMENT - 1
ESTIMATED COST

LAYING OF MDPE NETWORK, GI/CU/MLC INSTALLATION AND MRS FABRICATION IN NCT OF DELHI, UP, HARYANA & RAJASTHAN

SEGMENT - B : MEERUT, SHAMLI & MUZAFFARNAGAR, KANPUR, FATEHPUR & HAMIRPUR, HARYANA & RAJASTHAN
Unit Rate Total Amount
Quantity (All inclusive prices except GST) (All inclusive prices except GST)
(in INR) (in INR)
Item No. Description Unit

UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan

For O & M Area - Supply and installation from riser (lateral isolation valve) - The cumulative length of 1/2" powder coated GI
pipe within 2 m & Cu/MLC pipe within 2m or (GI + Cu/MLC) within 4m after lateral isolation valve up to appliance along with
Nos 10444 994 2000 3,596.40 3,395.05 3,380.27 3,75,60,801.60 33,74,679.70 67,60,540.00
installation of meter, meter regulator. Additional quantity above 4 Meters (GI + Cu/MLC) shall be payable only in case if
cumulative length exceeds 4 m. Note-Payment against additional length of (GI / Cu/MLC) shall be as per item 25 of SOR.

25 Powder coated GI and Cu installations for pipes more than 4 m per connection.
25.1 1/2" Powder coated GI M 39926 11756 20000 363.01 342.69 341.20 1,44,93,537.26 40,28,663.64 68,24,000.00
25.2 12mm Copper/MLC Pipe - Inside kitchen location only M 3993 1176 2000 435.62 411.23 409.44 17,39,430.66 4,83,606.48 8,18,880.00
Note: 1.GI, Cu/MLC, brass fittings shall not be counted separately. It shall be measured along with GI & Cu/MLC pipe.
2. If Cumulative length of GI & Cu/MLC increases specified lengths in connection rate SOR 24, extra piping shall be paid
considering installation as done in Flats or bungalows as per SOR item no. 25.

26 NG conversion for domestic connection


Providing services for NG conversion, monitoring the pendency and conversion of stoves including the supply of material
required for conversion of appliance/stove + Tools & Tackles required, Printing of JMR sent by IGL In-charge on email, scanning Nos. 50000 50000 200000 358.54 358.54 358.54 1,79,27,000.00 1,79,27,000.00 7,17,08,000.00
of signed JMR and submission to In-charge, completion of NG conversion within the defined TAT.

27 Installation of Service Regulator


Receiving, taking over, handling, loading, transportation and unloading of owner supplied items such as Service Regulators &
Isolation Valves and other free issue items as per technical specification from Owner’s designated stock yards to Contractor’s
stores / work sites.
Fabrication, Erection, Welding, Testing & Installation of Service Regulators as per drawing no. Drg No 15792-20-05-37), Rev 0.
Supply and installation of regulator boxes including fabrication as per drawing no. Drg No 15792-20-05-42), and painting as per
technical specification.
Any other material & activities not mentioned/covered above, but otherwise required for satisfactory completion/safety of work
as defined in tender has to be supplied / done by contractor with in specified schedule at no extra cost to owner.
Service Regulator with regulator cover and Transition Fittings installation Nos 283 224 1012 8,809.94 8,427.38 8,399.39 24,93,213.02 18,87,733.12 85,00,182.68

28 Foundations works for Service Regulator


Providing and laying of Plain Cement Concrete (PCC - 1:2:4)

Providing, Fixing, Centering, Shuttering and laying of Cement Concrete with concrete of nominal mix 1:2:4 by mass (1 cement 2
coarse sand 4 coarse stone/aggregates/gravels) with 20 mm down size graded crushed stone / aggregates / gravels as per
technical specification. Nos 283 224 1012 5,285.96 5,056.43 5,039.64 14,95,926.68 11,32,640.32 51,00,115.68
Any other material & activities not mentioned/covered above, but otherwise required for satisfactory completion/safety of work
as defined in tender has to be supplied / done by contractor with in specified schedule at no extra cost to owner.

PART V MRS FABRICATION AND INTERNAL PIPING WORKS FOR INSTALLATION OF INDUSTRIAL & COMMERCIAL CONNECTIONS

29 MRS Installation

Connection rates for installation of CS MRS with 1/2" & 1" pipe & fittings, pressure regulation of 21/300/500 mbar with
29.1 Nos. 3 3 3 18,795.65 22,166.96 22,070.43 56,386.95 66,500.88 66,211.29
Diaphragm meter installation G-1.6, G-4 as per dwg no. 11 with supply of MS Clamps/supports.

Connection rates for installation of CS MRS with 1-1/2" pipe & fittings, pressure regulation of 300/500 mbar with Diaphragm
29.2 Nos. 158 210 69 28,574.15 24,298.40 24,192.58 45,14,715.70 51,02,664.00 16,69,288.02
meter installation G-4, 6, 10, 16, 25 as per dwg no. 12 with supply of MS Clamps/supports.

Connection rates for installation of CS MRS with 2" pipe & fittings, pressure regulation of 2 bar with RPD meter installation G-
29.3 Nos. 62 173 18 27,494.25 34,742.45 34,591.15 17,04,643.50 60,10,443.85 6,22,640.70
10,16, 25 as per dwg no. 14 with supply of MS Clamps/supports.

Page 8 of 14
ATTACHMENT - 1
ESTIMATED COST

LAYING OF MDPE NETWORK, GI/CU/MLC INSTALLATION AND MRS FABRICATION IN NCT OF DELHI, UP, HARYANA & RAJASTHAN

SEGMENT - B : MEERUT, SHAMLI & MUZAFFARNAGAR, KANPUR, FATEHPUR & HAMIRPUR, HARYANA & RAJASTHAN
Unit Rate Total Amount
Quantity (All inclusive prices except GST) (All inclusive prices except GST)
(in INR) (in INR)
Item No. Description Unit

UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan

Connection rates for installation of CS MRS with 2" pipe & fittings, pressure regulation of 2 bar with RPD meter installation G- 40,
29.4 65,100 as per dwg no. 15 with supply of MS Clamps/supports. The rates shall include supply, installation of SS tubing Nos. 21 103 3 43,749.98 42,415.63 42,230.91 9,18,749.58 43,68,809.89 1,26,692.73
1/2"/1.5"/2" ( As per requirement) with connectors, welding of socolets for installation of connectors.

Connection rates for installation of CS MRS with 1-1/2" pipe & fittings, pressure regulation of 500 mbar with RPD meter
29.5 Nos. 3 3 3 49,149.48 50,941.39 50,719.53 1,47,448.44 1,52,824.17 1,52,158.59
installation G-16, 25 as per dwg no. XX with supply of MS Clamps/supports.

Note:
a. Supply & Installation of required size of brass fittings in all type of meters supplied by IGL shall be in scope of contractor.
B. Supply & installation of SS Tubing with fitting shall be in scope of contractor; Maximum length is 2.0m per MRS installation
C. 10% payment shall be released only after instllation of caging

CS Common Headers for MRS installation - Supply, Erection, welding & Installation of CS pipes & fittings (all types) except Ball
30
Valves as common headers along with branching for commercial connections.

In addition to other activities under SOR item no. 01 and as detailed in specification and as per the instructions of the EIC / Site
engineer of Owner. Erection, Fabrication, Welding & Installation of common headers of CS pipes & Fittings till isolation valves for
fixing of numerous meters through a single header and includes connecting of common Regulators on headers, NPT threading,
Radiography, as specified, Drillings of holes through the walls Brick, RCC, Granite, Marble, Wood Cutting, Glass Cutting with
proper heavy duty hammer drill machine, tools & tackles, using proper sealant/grout material and colors to match the original
replacement of the damages during drilling, restoring the area to the original condition, Painting of entire length of pipe along
with fittings after proper surface finish by one coat of approved primer paint and two coats of approved synthetic enamel paint.
Restoring the wall surface to original conditions, Supply & fixing of approved MS angle clamps, Ceiling clamps & dowel plugs with
screws, supply and insertion of insulation material i.e. PVC, PTFE sheet between pipe/ meter support and pipe/ meter, grout
material, suitable thread sealant i.e. Teflon Tape / lock tight, Supply of different sizes 1" to 4", 150# spiral wound gasket, studs &
bolts (various sizes with wire sealing arrangement wherever required), Joining of transition ftg. to above ground CS pipes, testing,
purging and commission of the complete installation. Supply and installation of STANDARD Y TYPE FLANGE END STRAINER
between T.F. I.V. to Regulator Inlet. Strainer size may be 1'', 2'', 3'' & 4'' corresponding to installed TF size. The payment for
supply and installation of Y type strainer is included in MRS fabrication. The meters installed on tap offs from common header
will be paid separately as per SOR No. 30.3 to 30.7

30.1 2" pipes & fittings RM 280 280 168 1,933.02 2,110.12 2,100.93 5,41,245.60 5,90,833.60 3,52,956.24

30.2 4" pipes & fittings RM 600 600 300 2,679.23 3,911.19 3,894.16 16,07,538.00 23,46,714.00 11,68,248.00

Connection rates for installation of CS MRS with 1/2" & 1" pipe & fittings, pressure regulation of 21/300/500 mbar with
30.3 Nos. 2 2 2 17,270.84 22,166.96 22,070.43 34,541.68 44,333.92 44,140.86
Diaphragm meter installation G-1.6, G-4 as per dwg no. 16 with supply of MS Clamps/supports.

Connection rates for installation of CS MRS with 1-1/2" pipe & fittings, pressure regulation of 300/500 mbar with Diaphragm
30.4 Nos. 10 10 5 22,479.19 24,298.40 24,192.58 2,24,791.90 2,42,984.00 1,20,962.90
meter installation G-4, 6, 10, 16, 25 as per dwg no. 17 with supply of MS Clamps/supports.

Connection rates for installation of CS MRS with 2" pipe & fittings, pressure regulation of 2 bar with RPD meter installation G-
30.5 Nos. 6 6 3 33,590.28 34,742.45 34,591.15 2,01,541.68 2,08,454.70 1,03,773.45
10,16, 25 as per dwg no. 19 with supply of MS Clamps/supports.

Connection rates for installation of CS MRS with 2" pipe & fittings, pressure regulation of 2 bar with RPD meter installation G- 40,
30.6 65,100 as per dwg no. 20 with supply of MS Clamps/supports. The rates shall include supply, installation of SS tubing Nos. 6 6 3 33,590.28 42,415.63 42,230.91 2,01,541.68 2,54,493.78 1,26,692.73
1/2"/1.5"/2" with connectors, welding of socolets for installation of connectors.

Connection rates for installation of CS MRS with 1-1/2" pipe & fittings, pressure regulation of 500 mbar with RPD meter
30.7 Nos. 2 2 2 38,989.78 50,941.39 50,719.53 77,979.56 1,01,882.78 1,01,439.06
installation G-16, 25 as per dwg no. XX with supply of MS Clamps/supports.

Page 9 of 14
ATTACHMENT - 1
ESTIMATED COST

LAYING OF MDPE NETWORK, GI/CU/MLC INSTALLATION AND MRS FABRICATION IN NCT OF DELHI, UP, HARYANA & RAJASTHAN

SEGMENT - B : MEERUT, SHAMLI & MUZAFFARNAGAR, KANPUR, FATEHPUR & HAMIRPUR, HARYANA & RAJASTHAN
Unit Rate Total Amount
Quantity (All inclusive prices except GST) (All inclusive prices except GST)
(in INR) (in INR)
Item No. Description Unit

UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan

Note:
a. Supply & Installation of required size of brass fittings in all type of meters supplied by IGL shall be in scope of contractor.
B. Supply & installation of SS Tubing with fitting shall be in scope of contractor; Maximum length is 2.0m per MRS installation
C. 10% payment shall be released only after installation of caging

30.8 Supply & Installation of Pressure Gauges 0 0 0


30.8a RANGE 0-1 BAR - 4"- DIAL SIZE Nos. 56 35 35 1,212.73 1,332.15 1,326.35 67,912.88 46,625.25 46,422.25
30.8b RANGE 0-4 BAR - 4"- DIAL SIZE Nos. 42 26 26 1,314.24 1,612.43 1,605.41 55,198.08 41,923.18 41,740.66
30.8c RANGE 0-6 BAR - 4"- DIAL SIZE Nos. 6 3 3 1,415.75 2,544.94 2,533.85 8,494.50 7,634.82 7,601.55
30.8d RANGE 0-100 MBAR - 4"- DIAL SIZE Nos. 4 2 2 1,415.75 1,332.15 1,326.35 5,663.00 2,664.30 2,652.70
30.9 Supply & Installation of FLANGE END BALL VALVES, MAOP- 4 BAR
30.9a 4" Nos. 11 7 7 14,686.64 27,282.42 27,163.60 1,61,553.04 1,90,976.94 1,90,145.20
30.9b 3" Nos. 42 26 26 12,526.84 20,035.82 19,948.56 5,26,127.28 5,20,931.32 5,18,662.56
30.9c 2" Nos. 42 26 26 7,343.32 12,255.77 12,202.40 3,08,419.44 3,18,650.02 3,17,262.40
30.9d 1-1/2” Nos. 42 26 26 5,183.52 8,312.61 8,276.41 2,17,707.84 2,16,127.86 2,15,186.66
30.9e 1" Nos. 12 8 8 2,441.65 5,115.45 5,093.18 29,299.80 40,923.60 40,745.44
30.10 Supply & Installation of FLANGE END GLOBE VALVES, MAOP- 4 BAR
30.10a 2" Nos. 28 18 18 9,670.50 12,575.49 12,520.72 2,70,774.00 2,26,358.82 2,25,372.96
30.10b 1-1/2" Nos. 359 226 226 6,603.59 8,312.61 8,276.41 23,70,688.81 18,78,649.86 18,70,468.66
30.10c 1" Nos. 56 35 35 3,186.78 6,447.60 6,419.52 1,78,459.68 2,25,666.00 2,24,683.20
30.11 Supply & Installation of FLANGE END BRASS ISOLATION VALVE
30.11a 2" Nos. 28 18 18 2,375.78 2,930.73 2,917.96 66,521.84 52,753.14 52,523.28
30.11b 1-1/2" Nos. 359 226 226 1,943.82 2,397.87 2,387.43 6,97,831.38 5,41,918.62 5,39,559.18
30.11c 1 Nos. 1331 8 8 691.14 1,918.29 1,909.94 9,19,907.34 15,346.32 15,279.52
30.11d 1/2" Nos. 56 35 35 487.03 756.66 753.37 27,273.68 26,483.10 26,367.95
30 WELDING OF JOINTS - Butt Weld Joints
30.12a 4" Nos. 34 22 22 344.49 1,758.44 1,750.78 11,712.66 38,685.68 38,517.16
30.12b 3" Nos. 34 22 22 290.49 1,545.29 1,538.56 9,876.66 33,996.38 33,848.32
30.12c 2" Nos. 70 44 44 290.49 1,428.06 1,421.84 20,334.30 62,834.64 62,560.96
30.12d 1-1/2" Nos. 38 24 24 279.69 1,332.15 1,326.35 10,628.22 31,971.60 31,832.40
30.12e 1" Nos. 17 10 10 74.51 959.15 954.97 1,266.67 9,591.50 9,549.70
30.12f 1/2" Nos. 20 13 13 74.51 799.29 795.81 1,490.20 10,390.77 10,345.53
30.13 Fillet Joints & Supply of Socolet
30.13a 1" Nos. 28 18 18 951.39 959.15 954.97 26,638.92 17,264.70 17,189.46
30.13b 1/2" Nos. 36 23 23 858.52 852.58 848.86 30,906.72 19,609.34 19,523.78
30.14 RADIOGRAPHY OF JOINTS
30.14a 4" Nos. 3 2 2 764.57 746.00 742.75 2,293.71 1,492.00 1,485.50
30.14b 3" Nos. 3 2 2 575.59 586.15 583.59 1,726.77 1,172.30 1,167.18
30.14c 2" Nos. 7 4 4 669.54 586.15 583.59 4,686.78 2,344.60 2,334.36
30.14d 1-1/2" Nos. 4 3 3 575.59 554.17 551.76 2,302.36 1,662.51 1,655.28
30.14e 1" Nos. 2 1 1 480.56 479.57 477.49 961.12 479.57 477.49
30.14f 1/2" Nos. 2 1 1 480.56 479.57 477.49 961.12 479.57 477.49
30.15 SUPPLY/ INSTALLATION OF CLAMPS, SUPPORTS FOR ERECTION OF ALL SIZES OF PIPELINE
30.15a TYPE-1, SIDE WALL MOUNTED AS PER DRAWING KG 627 395 395 110.15 191.83 190.99 69,064.05 75,772.85 75,441.05
30.15b TYPE-2, GROUND BASED AS PER DRAWING KG 269 169 169 110.15 170.52 169.77 29,630.35 28,817.88 28,691.13
30.15c TYPE-3, CEILING MOUNTED AS PER DRAWING KG 95 60 60 110.15 191.83 190.99 10,464.25 11,509.80 11,459.40
30.16 SUPPLY OF THREADED END BALL VALVES
30.16a 1" Nos. 11 7 7 691.14 2,397.87 2,387.43 7,602.54 16,785.09 16,712.01
30.16b 1/2" Nos. 11 7 7 487.03 1,651.87 1,644.67 5,357.33 11,563.09 11,512.69
30.17 SUPPLY OF FLANGES AS PER SPECIFICATIONS
30.17a WNRF 3" Nos. 120 74 74 1,074.50 1,193.61 1,188.41 1,28,940.00 88,327.14 87,942.34
30.17b WNRF 2" Nos. 405 252 252 804.53 905.86 901.92 3,25,834.65 2,28,276.72 2,27,283.84
30.17c BLRF 3" Nos. 13 8 8 664.14 1,012.43 1,008.02 8,633.82 8,099.44 8,064.16
30.17d BLRF 2" Nos. 117 73 73 498.91 511.55 509.32 58,372.47 37,343.15 37,180.36
30.17e Spectacle Blind 3" Nos. 13 8 8 2,105.80 937.83 933.75 27,375.40 7,502.64 7,470.00
30.17f Spectacle Blind 2" Nos. 117 73 73 1,889.82 490.23 488.10 2,21,108.94 35,786.79 35,631.30
30.18 SUPPLY OF REDUCERS
30.18a 3" x 2" Nos. 13 8 8 242.98 777.98 774.59 3,158.74 6,223.84 6,196.72

Page 10 of 14
ATTACHMENT - 1
ESTIMATED COST

LAYING OF MDPE NETWORK, GI/CU/MLC INSTALLATION AND MRS FABRICATION IN NCT OF DELHI, UP, HARYANA & RAJASTHAN

SEGMENT - B : MEERUT, SHAMLI & MUZAFFARNAGAR, KANPUR, FATEHPUR & HAMIRPUR, HARYANA & RAJASTHAN
Unit Rate Total Amount
Quantity (All inclusive prices except GST) (All inclusive prices except GST)
(in INR) (in INR)
Item No. Description Unit

UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan

30.18b 2" x 1-1/2" Nos. 86 54 54 145.79 703.37 700.31 12,537.94 37,981.98 37,816.74
Note: Supply of fittings below 2" shall be included under SOR item no. 29 & 30 for MRS fabrication and Installation of common
header.

31 Internal Piping - Supply, Erection & welding of CS pipes & fittings (all types) except Ball Valves for commercial connections.

Assessment of material requirement for installation at site, Order placement for purchasing of CS Pipes & fittings from anyone of
approved vendors of IGL, Scheduling, Planning of material & Forwarding inspection call, Dispatch clearance, handling, loading,
transportation and unloading of these at respective contractor’s store. Receiving, taking over, handling, loading, transportation
and unloading of contractor supplied material as defined in specification from Contractor’s designated stock yards to IGL's work
sites, proper storing, stacking, identification, providing security and insurance cover. Preparation and approval of sketches,
schedules & execution procedures and all others necessary documentation. Finalising Piping location with optimum route in
consent of customer from Meter Outlet till Customer's Appliance. Making temporary but stable platforms/ scaffolding/ rope
ladders and supply of all other safety devices.

Supply, Erection, Welding, Radiography & Testing of CS Seamless A 106 Gr-B, (thickness shall be as per PNGRB T4S Regulation)
Pipeline. It includes supply of all type of fittings (except ball valves), Supply Of Consumables Like Spiral Wound Gaskets
31.1
(Winding ANSI 304 Graphite Centering Ring Cs), Stud Bolts (ASTM A 193 B 7, Hexagonal Nuts, ASTM A194 Gr 2H) and is
inclusive in rates.

31.1.1 4" NB RM 84 53 53 2,646.83 3,463.59 3,448.50 2,22,333.72 1,83,570.27 1,82,770.50

31.1.2 3" NB RM 26 16 16 2,268.87 3,250.44 3,236.29 58,990.62 52,007.04 51,780.64

31.1.3 2" NB RM 1428 899 899 1,897.38 2,717.58 2,705.75 27,09,458.64 24,43,104.42 24,32,469.25

31.1.4 1-1/2" NB RM 1881 1184 1184 1,517.26 2,110.12 2,100.93 28,53,966.06 24,98,382.08 24,87,501.12

31.1.5 1" NB RM 139 88 88 1,139.29 937.83 933.75 1,58,361.31 82,529.04 82,170.00

Supply, Erection, Welding, Radiography & Testing of CS ERW API 5L GR-B Pipeline. It includes supply of all type of fittings
31.2 (except ball valves), Supply Of Consumables Like Spiral Wound Gaskets (Winding ANSI 304 Graphite Centering Ring Cs), Stud
Bolts (ASTM A 193 B 7, Hexagonal Nuts, ASTM A194 Gr 2H) and is inclusive in rates.

31.2.1 4" NB RM 149 94 94 2,267.79 3,250.44 3,236.29 3,37,900.71 3,05,541.36 3,04,211.26

31.2.2 3" NB RM 40 25 25 1,943.82 2,930.73 2,917.96 77,752.80 73,268.25 72,949.00

32 Supply & Installation of Safety Devices as per PNGRB gudelines

32.1 Solenoid Valves

32.1.1 1" Solenoid Valves Nos. 11 7 7 9,065.76 13,321.49 13,263.48 99,723.36 93,250.43 92,844.36

32.1.2 1.5" Solenoid Valves Nos. 11 7 7 12,418.85 15,559.50 15,491.74 1,36,607.35 1,08,916.50 1,08,442.18

32.1.3 2" Solenoid Valves Nos. 3 2 2 14,405.86 17,904.09 17,826.11 43,217.58 35,808.18 35,652.22

32.1.4 2.5" Solenoid Valves Nos. 3 2 2 19,249.21 19,502.66 19,417.73 57,747.63 39,005.32 38,835.46

Page 11 of 14
ATTACHMENT - 1
ESTIMATED COST

LAYING OF MDPE NETWORK, GI/CU/MLC INSTALLATION AND MRS FABRICATION IN NCT OF DELHI, UP, HARYANA & RAJASTHAN

SEGMENT - B : MEERUT, SHAMLI & MUZAFFARNAGAR, KANPUR, FATEHPUR & HAMIRPUR, HARYANA & RAJASTHAN
Unit Rate Total Amount
Quantity (All inclusive prices except GST) (All inclusive prices except GST)
(in INR) (in INR)
Item No. Description Unit

UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan

Gas Detector for natural gas detection in CGD applications, with integral hooter and alarm indicators indicating power on,
32.2 Nos. 28 18 18 12,483.64 23,339.25 23,237.61 3,49,541.92 4,20,106.50 4,18,276.98
failure and gas detection, 230 VAC power supply, max. 8A relay output, IP42 or better, Enclosure material Aluminium / CPVC.

32.3 Shutoff valve

32.3.1 1" Shutoff valve Nos. 11 7 7 11,490.13 13,321.49 13,263.48 1,26,391.43 93,250.43 92,844.36

32.3.2 1.5" Shutoff valve Nos. 11 7 7 15,887.48 19,715.81 19,629.95 1,74,762.28 1,38,010.67 1,37,409.65

32.3.3 2" Shutoff valve Nos. 3 2 2 21,112.04 21,847.25 21,752.10 63,336.12 43,694.50 43,504.20

32.3.4 2.5" Shutoff valve Nos. 3 2 2 31,668.06 25,843.69 25,731.14 95,004.18 51,687.38 51,462.28

33.0 Modifications & Installation of Meters & Regulators in existing MRS/Skids/DRS:


Assessment of material requirement for installation at site, Order placement for purchasing of CS Pipes & fittings from anyone of
approved vendors of IGL, Scheduling, Planning of material & Forwarding inspection call, Dispatch clearance, handling, loading,
transportation and unloading of these at respective contractor’s store. Receiving, taking over, handling, loading, transportation
and unloading of owner supplied above ground fittings like regulators, meter & Isolation Valve and other free issue items as
defined in specification from Owner’s designated stock yards to Contractor’s own stores / work sites, proper storing, stacking,
identification, providing security and insurance cover. Preparation and approval of sketches for modification, schedules &
execution procedures and all others necessary documentation. Making temporary but stable platforms/ scaffolding/ rope
ladders and supply of all other safety devices.

Taking shutdown of existing MRS, dismantling meters/regulators, replacement/fixing of meters/regulators with associated inlet
and outlet connections / fittings, supply of pipes & fittings (excluding flange end Ball Valve), pipe cutting, threading, welding,
testing, Radiography of Joints & firmly fixing with approved meter clamps/brackets and other supports by proper grouting and
necessary documentation. Restoring the area to the original condition as per the specifications and to complete satisfaction of
consumer and EIC. The rates includes all as above along with testing of joints till re-commissioning.

33.1 Diaphragm meter Nos. 9 6 6 5,079.85 5,115.45 5,093.18 45,718.63 30,692.72 30,559.05

33.2 RPD Meter Nos. 9 2 6 6,603.59 6,607.46 6,578.68 59,432.28 13,214.92 39,472.11

33.3 Turbine Meter Nos. 13 9 2 5,079.85 6,607.46 6,578.68 66,038.03 59,467.14 13,157.37

33.4 300 mbar regulator Nos. 13 9 9 5,079.85 3,197.16 3,183.23 66,038.03 28,774.42 28,649.11

33.5 500 mar regulator Nos. 4 2 9 6,603.59 3,410.30 3,395.45 26,414.35 6,820.60 30,559.05

33.6 2 bar regulator Nos. 4 2 2 7,081.98 3,410.30 3,395.45 28,327.92 6,820.60 6,790.90

33.7 Butt Weld Joints

33.7.1 8" Nos. 5 3 3 2,371.46 8,525.75 8,488.63 11,857.30 25,577.25 25,465.89

33.7.2 6" Nos. 8 5 5 1,947.06 7,246.89 7,215.33 15,576.48 36,234.45 36,076.65

33.7.3 4" Nos. 31 19 19 1,614.45 5,968.03 5,942.04 50,047.95 1,13,392.57 1,12,898.76

33.7.4 3" Nos. 18 12 12 1,279.68 5,541.74 5,517.61 23,034.24 66,500.88 66,211.32

33.7.5 2" Nos. 453 285 285 1,422.23 5,222.02 5,199.28 6,44,270.19 14,88,275.70 14,81,794.80

Page 12 of 14
ATTACHMENT - 1
ESTIMATED COST

LAYING OF MDPE NETWORK, GI/CU/MLC INSTALLATION AND MRS FABRICATION IN NCT OF DELHI, UP, HARYANA & RAJASTHAN

SEGMENT - B : MEERUT, SHAMLI & MUZAFFARNAGAR, KANPUR, FATEHPUR & HAMIRPUR, HARYANA & RAJASTHAN
Unit Rate Total Amount
Quantity (All inclusive prices except GST) (All inclusive prices except GST)
(in INR) (in INR)
Item No. Description Unit

UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan

33.7.6 1-1/2" Nos. 488 307 307 953.55 5,008.88 4,987.07 4,65,332.40 15,37,726.16 15,31,030.49

33.7.7 1" Nos. 16 10 10 953.55 2,664.30 2,652.70 15,256.80 26,643.00 26,527.00

33.8 Supply & Installation of CS Piping (Seamless A 106 Gr-B)

33.8.1 8" RM 4 3 3 6,142.47 7,513.32 7,480.60 24,569.88 22,539.96 22,441.80

33.8.2 6" RM 6 4 4 5,199.72 5,829.48 5,804.10 31,198.32 23,317.92 23,216.40

33.8.3 4" RM 9 6 6 3,969.71 4,348.13 4,329.20 35,727.39 26,088.78 25,975.20

33.8.4 3" RM 10 7 7 3,363.89 3,676.73 3,660.72 33,638.90 25,737.11 25,625.04

33.8.5 2" RM 70 44 44 2,840.14 2,962.70 2,949.80 1,98,809.80 1,30,358.80 1,29,791.20

33.8.6 1-1/2" RM 63 39 39 2,275.35 2,291.30 2,281.32 1,43,347.05 89,360.70 88,971.48

33.8.7 1" RM 14 9 9 1,701.92 1,705.15 1,697.73 23,826.88 15,346.35 15,279.57

Note:-
Modifications/ replacements (meter or regulator or both) in existing MRS/Skids/DRS using threaded fittings/ flanged end
(same size or bigger) shall be payable through 33.1 to 33.6.

Modifications/ replacements (meter or regulator or both) in existing MRS/Skids/DRS using welding (same size or bigger upto
3.00 mtrs) shall be payable through 33.7

Modifications/ replacements (meter or regulator or both) in existing MRS/Skids/DRS using welding (in case, erected length
after modification is more than 3.00 mtrs) shall be payable through 33.8

The payments of flange end ball valve shall be paid as per SOR no. 30.9

34 Conversion of Commercial Appliances:

Conversions of all types of commercial appliances to NG based appliances. Supply & changing of the nozzles /jets and associated
controls for Non-domestic appliances (imported appliances included) with proper tools and tackles. Cleaning and performing
34 minor maintenance, greasing etc. of the appliance. Testing and showing the performance to the customer, signing of joint meter Nos. 273 518 111 1,511.86 1,492.01 1,485.51 4,12,737.78 7,72,861.18 1,64,891.61
records (JMR) and instructing the customer on use & safety norms, complete as per specifications & to satisfaction of owner /
Engineer in Charge and includes supply of reinforced rubber hose with requisite pressure rating.

Note: The payments of conversion shall be as per burners.

35 Supply & Fabrication & Erection of Wired cages for MRS

Page 13 of 14
ATTACHMENT - 1
ESTIMATED COST

LAYING OF MDPE NETWORK, GI/CU/MLC INSTALLATION AND MRS FABRICATION IN NCT OF DELHI, UP, HARYANA & RAJASTHAN

SEGMENT - B : MEERUT, SHAMLI & MUZAFFARNAGAR, KANPUR, FATEHPUR & HAMIRPUR, HARYANA & RAJASTHAN
Unit Rate Total Amount
Quantity (All inclusive prices except GST) (All inclusive prices except GST)
(in INR) (in INR)
Item No. Description Unit

UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan UP-2 Haryana Rajasthan

Assessment of material requirement for installation at site, Order placement for purchasing of MS Angle, Flat, wire mesh &
fittings from anyone of approved vendors of IGL, Scheduling, Planning of material & handling, loading, transportation and
unloading of these at respective contractor’s store. Receiving, taking over, handling, loading, transportation and unloading of
contractor supplied material as defined in specification from Contractor’s designated stock yards to IGL's work sites, proper
storing, stacking, identification, providing security and insurance cover. Finalising Cage location with in consent of customer &
IGL. Making temporary but stable platforms/ scaffolding/ rope ladders and supply of all other safety devices. Supplying & Fixing 4
mm thick MS welded wire mesh (30 mm x 75 mm) by welding/bolting with structural steel elements (Angle & Flat) for making
covers for MRS and various other equipments for protection of equipments. Rates to include one coat of primer and two coats of
synthetic enamel paint (both side of wired cages), labour, material, transportation, loading/ unloading of material, welding
charges etc complete in all respects. For fabrication of cage structure, all the essential jobs viz. cutting, welding, grinding,
finishing, painting including all materials like Angle, channel, wire net, support sheet, hardware, electrode, grinding wheel, gas
cylinder, paint, primer, grouting, equipment, tools, generator for power, welding machine etc. is under contractor’s scope

Supply (Angle 65 mm x 65 mm x 6 mm, Flat 50 mm x 6 mm & Wire Mesh 75 mm X 30 mm X 4 mm), fabrication, painting,
35.1 transportation and installation of MRS cages for SKID by welding/bolting with structural steel elements for making covers for Sq. M 82 155 33 3,153.31 3,730.02 3,713.77 2,58,256.09 5,79,645.11 1,23,668.54
industrial/ commercial PNG meter-regulator systems as per detailed scope of work & Drawing.

Supply (Angle 40 mm x 40 mm x 5 mm, Flat 25 mm x 4 mm & Wire Mesh 75 mm X 30 mm X 4 mm), fabrication, painting,
35.2 transportation and installation of MRS cages for WALL MOUNTED MRS by welding/bolting with structural steel elements for Sq. M 1892 3590 769 2,696.51 3,250.44 3,236.29 51,01,500.30 1,16,68,234.49 24,89,451.36
making covers for industrial/ commercial PNG meter-regulator systems as per detailed scope of work & Drawing.

Note:- SOR Item No. 35 shall be applicable only for Installation of wired cages for MRS.
36 Supply & Installation Crash Guard for Cage Protection.
Supply, fabrication, painting, transportation and installation of Crash Guard for protection of cages for industrial/ commercial
MT 33 62 13 1,05,000.00 1,05,000.00 1,05,000.00 34,39,800.00 65,26,800.00 13,98,600.00
PNG Wall Mounted meter-regulator systems as per detailed scope of work & Drawing.

TOTAL (INR) 88,05,21,657.57 87,93,34,238.67 3,13,34,36,344.56


GST @ 18%(INR) 15,84,93,898.36 15,82,80,162.96 56,40,18,542.02
TOTAL COST INCLUDING GST (INR) 1,03,90,15,555.93 1,03,76,14,401.63 3,69,74,54,886.58
TOTAL (Amount in Crore) 577.41

Page 14 of 14