QUETTA ELECTRIC SUPPLY COMPANY

OFFICE OF THE
INCHARGE LINE SUPERINTENDENT
OP: QESCO SUB OFFICE WADH

Dated:

To,
THE SUB DIVISIONAL OFFICER OP: QESCO KHUZDAR II

SUBJECT: OCCURANCE REPORT

It is for your kind information that the Following damages Occurred on 28-07-2019
Time 06:15 PM due to Heavy rain and wind storm on different feeders of this Sub office.
The details of damages are listed below.

Feeder Pin Pin for Disk Conductor


HT PCC LT PCC X.Arm Insulator insulator Insulator
Name (MTR)
Badri city 02 03 04 04 04 - -
Wadh city (FC) 02 - 08 08 08 03 -
Lope 04 - 09 20 20 06 50
Akhtar Aabad 02 - 05 12 12 03 150
Kakaheer 01 02 04 07 07 - 100
TOTAL 11 05 30 51 51 12 250

This is for your good office Please for farther information please.

INCHARGE LINE SUPERINTENDENT


OP: QESCO, SUB OFFICE WADH