Face Sheet

Name of work: MAINTENANCE WORK OF 11kv AKHTAR ABAD FEEDER


WADH
Name of S/Division: Sub Division QESCO KHUZDAR II.

Name of Division: KHUZDAR.

Estimate framed by: SDO KHUZDAR II.

Estimate prepared by: LS In charge Sub Office Wadh.


Major Head: MAINTENANCE

Estimate Cost: Rs: 142007

HISTORY SHEET
The Estimate Has been prepared to cover Expenditure for the restoration of 11kv AKHTAR
ABAD FEEDER Sub Office Qesco WADH Under operation Sub Division Qesco Khuzdar II,
Damaged 02 NO.HT Pcc poles due to Heavy rain & wind storm on date:28/07/2019.
The Ls in-charge physically checked the site prepared the estimate under maintenance Head
for the relief of consumers of AKHTAR ABAD feeder and smooth supply of electricity in
best interest of QESCO .
This office prepared the estimate for Sanctioned Material work will be done departmentally.

SUB DIVISIONAL OFFICER EXECUTIVE ENGINEER


QESCO SUB DIVISION KHUZDAR II OPERATION DIVISION QESCO
KHUZDAR