To,
Executive Engineer,
Pasrur Link Division,
Sialkot
I inspected the above cited work along with concerned Sub Engineer on 26-
Aug-2020, sub engineer is directed to enforce the contractor to supply the material at
site immediately and make ensure that material should as per specified in T.S
estimate. As worked has been allotted to contractor and the rain forecast has been
predicted by PDMA.
To,
Inspected the above mentioned work by the undersigned and you are directed to
follow the administrative department instruction and establish the camp at site
immediately moreover rain forecast has also been predicted by PDMA and MET
department. So, in order to avoid any havoc situation later on make sure material
Executive Engineer,
Pasrur Link Division,
Sialkot.
C.C.
To,
Executive Engineer,
Pasrur Link Division,
Sialkot
I inspected the above cited work along with concerned Sub Engineer on 26-
Aug-2020, sub engineer is directed to enforce the contractor to supply the material at
site immediately and make ensure that material should as per specified in T.S
estimate. As worked has been allotted to contractor and the rain forecast has been
predicted by PDMA.
To,
Inspected the above mentioned work by the undersigned and you are directed to
follow the administrative department instruction and establish the camp at site
immediately moreover rain forecast has also been predicted by PDMA and MET
department. So, in order to avoid any havoc situation later on make sure material
Executive Engineer,
Pasrur Link Division,
Sialkot.
C.C.
To,
Executive Engineer,
Pasrur Link Division,
Sialkot
I inspected the above cited work along with concerned Sub Engineer on 26-
Aug-2020, sub engineer is directed to enforce the contractor to supply the material at
site immediately and make ensure that material should as per specified in T.S
estimate. As worked has been allotted to contractor and the rain forecast has been
predicted by PDMA.
To,
Inspected the above mentioned work by the undersigned and you are directed to
follow the administrative department instruction and establish the camp at site
immediately moreover rain forecast has also been predicted by PDMA and MET
department. So, in order to avoid any havoc situation later on make sure material
Executive Engineer,
Pasrur Link Division,
Sialkot.
C.C.
To,
Executive Engineer,
Pasrur Link Division,
Sialkot
I inspected the above cited work along with concerned Sub Engineer on 26-
Aug-2020, sub engineer is directed to enforce the contractor to supply the material at
site immediately and make ensure that material should as per specified in T.S
estimate. As worked has been allotted to contractor and the rain forecast has been
predicted by PDMA.
To,
Executive Engineer,
Pasrur Link Division,
Sialkot
I inspected the above cited work along with concerned Sub Engineer on 26-
Aug-2020, sub engineer is directed to enforce the contractor to supply the material at
site immediately and make ensure that material should as per specified in T.S
estimate. As worked has been allotted to contractor and the rain forecast has been
predicted by PDMA.
To,
Inspected the above mentioned work by the undersigned and you are directed to
follow the administrative department instruction and establish the camp at site
immediately moreover rain forecast has also been predicted by PDMA and MET
department. So, in order to avoid any havoc situation later on make sure material
Executive Engineer,
Pasrur Link Division,
Sialkot.
C.C.
To,
Executive Engineer,
Pasrur Link Division,
Sialkot
I inspected the above cited work on 29-08-2020 along with concerned Sub
Engineer, the contractor is directed to make extra machinery available for filling earth
at breach site to strengthen the breach i.e. 6 No of Tractor with trolleys and 2 No
tractors with blade. Moreover, Sub Engineer Concerned is directed to note log book
To,
Inspected the above mentioned work by the undersigned and you are directed to
following instructions.
Executive Engineer,
Pasrur Link Division,
Sialkot.
C.C.