You are on page 1of 16

TYPSA GROUP

CONSULTING ENGINEERING COMPANY


OPERATIONS – PROJECT / SITE

Survey Report: Electra Surveying Engineering


Doc. Ref. No.: ESE-MS-20-03-039_C

METHOD STATEMENT:
METHODOLOGY AND EXECUTION PLAN
FOR: PER CONSTRUCTION CONDITIONAL
SURVEY

DIBBA BULK HANDLING


TERMINAL – PACKAGE 2
Material Handling Equipment and Civil Works

PROJECT OWNER ENGINEERING MAIN CONTRACTOR ENG. CONSULTANT


Fujairah Port JACOBS PHB

Revision History
Rev Date Details Prepared By Reviewed By Approved By
A 26.05.2020 Initial Issue. Jameel Y. Vijith K. Ljubica B.

This document remains the property of PHB Weserhutte. Its contents are confidential and shall not be reproduced, destroyed, or
used without written permission of PHB Weserhutte. The electronic version of this document in IMS location on designated server(s)
is the Master Copy and a controlled document. Unless specifically noted thereon, other copies of this document whether electronic
or printed are uncontrolled.
MS: < METHODOLOGY AND EXECUTION PLAN
FOR: PER CONSTRUCTION CONDITIONAL
SURVEY>
DIBBA BULK HANDLING TERMINAL – PACKAGE2
Date 20.05.2020

Contents
1.0 PURPOSE............................................................................................................................................ 3

2.0 APPLICATION OF THE STANDARDS................................................................................................ 3

2.2 CONDITION OF STRUCTURES....................................................................................................... 4

2.3 EVIDENCE TO COUNTER FRAUDULENT CLAIMS, LIABILITIES & ACTIONS..............................4

3.0 PROJECT AREA.................................................................................................................................. 5

4.0 PART-1 : INSPECTION NOTES........................................................................................................... 6

5.0 PART 2 : INTRODUCTION................................................................................................................... 7

6.0 PART 3 : DETAILED CONDITIONAL SURVEY...................................................................................8

7.0 PART 4: TERMS AND CONDITIONS................................................................................................ 13

7.1 INFORMATION FROM THE SURVEY............................................................................................13

7.2 THIS IS A VISUAL INSPECTION ONLY......................................................................................... 13

7.2.1 Scope of Report.......................................................................................................................... 13

7.2.2 Limitations................................................................................................................................... 13

7.2.3 Important Information.................................................................................................................. 13

7.3 DISCLAIMER OF LIABILITY........................................................................................................... 13

7.4 DISCLAIMER OF LIABILITY TO THIRD PARTIES.........................................................................14

7.5 REPORT DEFINITION.................................................................................................................... 14

8.0 CONTACT THE SURVEYOR............................................................................................................. 14

PAGE 3 OF 16
MS: < METHODOLOGY AND EXECUTION PLAN
FOR: PER CONSTRUCTION CONDITIONAL
SURVEY>
DIBBA BULK HANDLING TERMINAL – PACKAGE2
Date 20.05.2020

PURPOSE
The Port of Fujaraih, is currently preparing for the project of refurbishment of the bulk handling
terminal at the city of Dibba. The Project scope consist briefly of the supply and performance of a
handling system from the new platform that will be performed by others and existing jetty at the
port area, to a new stockyard.

The handling conveyor alignment runs from the port to the new stockyard area in a 4.4 Km
approximated total length. Within this length there is a 1.2 km tunnel stretch from the port to the city
suburbs. After the tunnel, the conveyor runs upon steel supports founded upon reinforced concrete
raft footings.

The purpose of this document will be describing the visual inspection on site, and produce a
pictorial and written conditional survey report. The produced report will be based on the visual
inspection only, no core drilling, testing or structural sampling will be performed on the site and
only external area will be inspected.

Most developers and government authorities require conditional surveys to be conducted and
reports prepared by a professional surveyor for all sites adjacent to the proposed development site
prior to the commencement of any construction work.
For this matter TYPSA appointed Electra Surveying Engineering on behave of PHB, to perform
conditional survey and report on current defects which include settlement, cracking and any
obvious areas of deterioration of render, brickwork and concrete etc
The deliverables of this SOW are producing an independent report known as Conditional Report
for the inspected day, who will record the pre-construction conditions on the site, adjoining the
developer site and/or which may be influence by the developer work.

APPLICATION OF THE STANDARDS

Electra Surveyors in making Conditional Survey Report will undertake


2.1 Precautionary Measure
A conditional survey outlines the current condition and any existing structural damage including
areas which may be prone to damage. This includes (but is not limited to) cracks, stresses and
water damage to walls, fence, road; cracks in brickworks, road surfaces and adjoining footpaths;
and other external fixtures or features.

The survey will provide a final report which includes detailed photographs, (video if needed) and a
written component. By engaging Electra Survey our client will be provided with an independent
report which does not hold any bias towards either party.

PAGE 4 OF 16
MS: < METHODOLOGY AND EXECUTION PLAN
FOR: PER CONSTRUCTION CONDITIONAL
SURVEY>
DIBBA BULK HANDLING TERMINAL – PACKAGE2
Date 20.05.2020

1.2 Condition of structures

By conducting a survey, prior to work commencing, client will be able to thoroughly assess
adjoining structures and ensure proper precautions are taken to minimize movement, vibration,
water overflow, loose site debris or any potential change to adjoining surfaces or features.

A conditional survey can also be used for site restoration after works have been completed. In
a case where roads, landscaping etc. need to be removed during construction the survey will
be utilized afterwards to ensure areas are returned to their original state.

1.3 Evidence to counter fraudulent claims, liabilities & actions.


Contractors and developers are often blamed for damage sustained to third party and
adjoining properties. If they failed to get a conditional survey done, then they could potentially
be liable for any damages if a claim is made.

Having a report conducted prior to commencement means that the company will have the
original site condition report as evidence to defend against any demands for damage should
they arise, and avoid expensive drawn out litigation.

Conditional survey reports are necessary for both contractors and property owners regardless
of the scale or complexity of the project.

In other words, conditional survey report is certainly not one of the more glamorous services that
Electra Surveying Engineering can offer, but none the less, this report is essential, particularly if
our client is an engineering company, contractor or developer about to embark on a new project.

PAGE 5 OF 16
MS: < METHODOLOGY AND EXECUTION PLAN
FOR: PER CONSTRUCTION CONDITIONAL
SURVEY>
DIBBA BULK HANDLING TERMINAL – PACKAGE2
Date 20.05.2020

PROJECT AREA
The proposed marine site is in port of Dibba and land site is outside of Dibba city in mountain
area. Both situated approximately 147 km NE of Dubai and 40km N of Fujairah, United Arab
Emirates (UAE).

Picture 1 “Site Location for Conditional Survey”

PAGE 6 OF 16
MS: < METHODOLOGY AND EXECUTION PLAN
FOR: PER CONSTRUCTION CONDITIONAL
SURVEY>
DIBBA BULK HANDLING TERMINAL – PACKAGE2
Date 20.05.2020

PART-1: INSPECTION NOTES


Electra Survey will carry out a conditional survey – visual inspection at Dibba Bulk Handling
Terminal location for Package 2

This report is not a structural report; however, it does include a photographic record of the main
defects visible at the time of the survey. The report intendeds to contain an exhaustive list of minor
defects that are found in surrounding buildings, walls, fence, road, footpath including existing
above ground utility (general wear and tear, minor cracking, unevenness and blemishes).

Electra Survey will be reporting on building exterior if they are coming inside the requested survey
limit. The report is exclusively for the use of Dibba Bulk Handling Terminal location for Package 2
and is not to be used for any other purpose.

No responsibility/liability is accepted as the result of the use of this report by any other party.
During the inspection, Electra will not move objects that could be covering defects in the structure.
Photographs will be provided in the report and same photographs will be from the general areas
that may be affected by the proposed construction works and do not necessarily show defects.

The Conditional Survey Report mainly will record the existing conditions of the surrounding areas
also the existing conditions of the footpaths, street and nearby fences.

The main report shall not be construed as a certificate of warranty for the area, and the main report
will not cover issues such as building services, hazardous materials, fire safety, drainage, plant,
machinery, illegal building works, nor does it consider requirements of the National Construction
Code. Certification of any building or road works is excluded from this report

The scope of this project is not to be an exhaustive study, but is to preliminarily examine the
condition and the structures of the proposed survey area for the purpose of beginning discussion
on the most appropriate advice to the client with all necessary information before the
Topographical survey and any other design stage start.

Visual inspection will be performed on area where it is safe or reasonably possible to do


inspection. We will not be inspecting any part of the area that is concealed or inaccessible and
therefore unable to report.

It is to be stressed that it is not the intention of the report to enumerate each and every item on
site but rather to identify the area for surveying to see if any obstruction will interfere in the next
process of conducting topographical survey.

We will not undertake to assess the structural design of the any buildings or element existing on
site, but we will try to provide comment upon matters of concern that are considered to require
further investigation noted during our inspection.

PAGE 7 OF 16
MS: < METHODOLOGY AND EXECUTION PLAN
FOR: PER CONSTRUCTION CONDITIONAL
SURVEY>
DIBBA BULK HANDLING TERMINAL – PACKAGE2
Date 20.05.2020

PART 2: INTRODUCTION 
The Conditional Survey Report is intended to record the current condition for Dibba Bulk Handling
Terminal - Package 2

The site inspection will be confirmed with client together, and the inspection need to be performed
in good weather conditions

This report of condition contains the following definitions and their descriptions are as follows:

 Good – No signs of wear of tear and able to perform the function for which it was installed.
 Fair – Showing signs of wear/soiling but still serviceable and functioning adequately.
 Poor – Subject to hard and long-term wear with repair and/or renovation generally
necessary.

The below tables identify the classification of cracks and their sizes in relation to building, roads.
Fence and etc.

a) Classification of Identified Defects with reference to Wall

Impact Category Description of typical defects to external areas Approximately crack wide
limit

0 Hairline cracks - walls < 0.5 mm

1 Fine cracks which do not need repair 0.5 mm to 1.0 mm

2 Cracks noticeable but easily filled. Mostly Infront 1.0 mm to 5 mm


of building entrance or road furniture and etc.
3 Cracks can be repaired and possibly a small 5 mm to 15 mm, or a
amount of section need to be replaced. number of cracks 3 mm
to 5 mm in one group
4 Extensive repair work involving breaking‐out and 15 mm to 25 mm but also
replacing of some parts. depends on number of
cracks
5 As above but worse, and requiring partial or > 25 mm
complete rebuilding.

PAGE 8 OF 16
MS: < METHODOLOGY AND EXECUTION PLAN
FOR: PER CONSTRUCTION CONDITIONAL
SURVEY>
DIBBA BULK HANDLING TERMINAL – PACKAGE2
Date 20.05.2020

b) Classification of Damage to Asphalt floors


Impact Category Description of typical defects to Approximately Change of offset
external areas crack wide limit from 3m straight
placed over defect  
0 Hairline cracks - insignificant < 0.3 mm   < 8mm   < 0.3 mm   < 8mm  
movement
1 Fine but noticeable cracks. < 1.0 mm   < 10mm < 1.0 mm   < 10mm

2 Distinct cracks < 2.0 mm   < 15mm < 2.0 mm   < 15mm

3 Wide cracks 2.0 mm - 4mm 15 mm - 25mm

4 Gaps in slab or expansion joint 5 mm - 10mm > 25 mm

PART 3 : DETAILED CONDITIONAL SURVEY


Item Photographic Evidence Assessment

01 Assessment:

GOOD x

FAIR

POOR

Impact category

1 x
2
3
4
5

Location: Auditors Comments


Northwest  General view of northwest boundary
Boundary

PAGE 9 OF 16
MS: < METHODOLOGY AND EXECUTION PLAN
FOR: PER CONSTRUCTION CONDITIONAL
SURVEY>
DIBBA BULK HANDLING TERMINAL – PACKAGE2
Date 20.05.2020

Item Photographic Evidence Assessment

02 Assessment:

GOOD

FAIR x

POOR

Impact
category

1
2 x
3
4
5

Location: Auditors Comments


Street   Gap visible between the asphalt pavement and wall.
Pavement

Item Photographic Evidence Assessment

03 Assessment:

GOOD x

FAIR

POOR

Impact
category

1
2
3

PAGE 10 OF 16
MS: < METHODOLOGY AND EXECUTION PLAN
FOR: PER CONSTRUCTION CONDITIONAL
SURVEY>
DIBBA BULK HANDLING TERMINAL – PACKAGE2
Date 20.05.2020

4
5 x

Location: Auditors Comments


Street   Cracking of the asphalt was evident outside the entrance of the property
Pavement

Item Photographic Evidence Assessment

04 Assessment:

GOOD

FAIR x

POOR

Impact
category

1
2 x
3
4
5

Location: Auditors Comments


Car Park  Cracking and indentation of a concrete section.
Entrance  Asphalt and concrete surface are not at the same level.

Item Photographic Evidence Assessment

PAGE 11 OF 16
MS: < METHODOLOGY AND EXECUTION PLAN
FOR: PER CONSTRUCTION CONDITIONAL
SURVEY>
DIBBA BULK HANDLING TERMINAL – PACKAGE2
Date 20.05.2020

05 Assessment:

GOOD x

FAIR

POOR

Impact category

1 x
2
3
4
5

Car Park Hairline cracks (approx. 1‐2mm) and chipping of concrete


Entrance were found on the surface

Item Photographic Evidence Assessment

06 Assessment:

GOOD

FAIR x
POOR

Impact category

1
2
3 x
4
5

PAGE 12 OF 16
MS: < METHODOLOGY AND EXECUTION PLAN
FOR: PER CONSTRUCTION CONDITIONAL
SURVEY>
DIBBA BULK HANDLING TERMINAL – PACKAGE2
Date 20.05.2020

Front Cracks and chipping of concrete were found on the surface -


Entrance Surface was generally in poor condition

Item Photographic Evidence Assessment

07 Assessment:

GOOD

FAIR x
POOR

Impact category

1
2
2
3
4
5

North Chipping of the concrete at the corners of the strip drain were
Boundary evident, shows signs of cracking.

Item Photographic Evidence Assessment

08 Assessment:

GOOD

FAIR x
POOR

Impact category

1
2
3
4

PAGE 13 OF 16
MS: < METHODOLOGY AND EXECUTION PLAN
FOR: PER CONSTRUCTION CONDITIONAL
SURVEY>
DIBBA BULK HANDLING TERMINAL – PACKAGE2
Date 20.05.2020

North The railing was badly damaged as it appears to be bent, most


Boundary likely due to a collision with a vehicle

Item Photographic Evidence Assessment

09 Assessment:

GOOD

FAIR x

POOR

Impact category

1
2
x
3
4
5

Carparking Minor cracking of the concrete surface was evident


throughout the basement

PAGE 14 OF 16
MS: < METHODOLOGY AND EXECUTION PLAN
FOR: PER CONSTRUCTION CONDITIONAL
SURVEY>
DIBBA BULK HANDLING TERMINAL – PACKAGE2
Date 20.05.2020

PART 4: TERMS AND CONDITIONS

Information from the Survey


The provided information in the conditional survey reports will have important value and forms an
integral part of that report.
Before any construction will start, provided information with in the conditional survey report needs
to be understandable as there will be difficulties for the surveyors to explain and guarantee that a
property is free of defects, latent or otherwise.
This information forms an integral part of the report. Any comments made in this section are
relevant only in light of the conditions present at the time of inspection.

This is a Visual Inspection only


The survey will represent visual inspection only, and it will be limited to areas and sections of the
property fully accessible and visible for the surveyors at the time and on the date of Inspection.
The Surveyor will NOT include breaking apart, dismantling, removing or moving objects including,
but not limited to, foliage, mouldings, appliances or personal possessions.
The Surveyor CANNOT see inside walls, inside roads inside the eaves, or other areas that are
concealed or obstructed. The Surveyor will NOT dig, gouge, force or perform any invasive
procedures.

Scope of Report
The Conditional Survey Report is not intended to be a certificate of compliance of the area or an
insurance policy against problems developing with the building in the future.

Limitations
No responsibility can be accepted for defects which are latent or otherwise not reasonably detected
on a visual inspection without interference with or removal of any of the structure including fixtures
Electra will not be commenting on any environmental issues, hazardous materials and the like and
did not form part of the brief

Important Information
Any person who will relies upon the contents of the Conditional Survey Report does so
acknowledging that the above clauses, definitions and disclaimers that follow define the Scope and
Limitations of the inspection and form an integral part of the report.

Disclaimer of Liability
No liability shall be accepted on account of failure of the Conditional Survey Report to notify any
problems in any area’s or sections of the subject property physically inaccessible for inspection, or
to which access for Inspection is denied by the Surveyor (including but not limited to any area’s or
section’s so specified by the Report.

PAGE 15 OF 16
MS: < METHODOLOGY AND EXECUTION PLAN
FOR: PER CONSTRUCTION CONDITIONAL
SURVEY>
DIBBA BULK HANDLING TERMINAL – PACKAGE2
Date 20.05.2020

Disclaimer of Liability to Third Parties


The Conditional Survey Report will be made solely for the use and benefit of the Client named on
the front of this report. No liability or responsibility whatsoever, in contract or tort, is accepted to
any third party who may rely on the Report wholly or in part. Any third party acting or relying on this
Report, in whole or in part does so at their own risk.

Report Definition
This report is limited to a visual inspection of areas where reasonable access is available at the
time of inspection.  It does not purport to be geological as to foundation integrity or soil conditions,
engineering as to structural, nor does it cover the condition of electrical, plumbing, gas or
motorised appliances. It is strongly recommended that an appropriately qualified contractor check
these services prior to purchase.

CONTACT THE SURVEYOR


Electra is looking forward to working with you on this project. Should you have any difficulties
in understanding any part of this document, please feel free contact us at any time.
For Electra Surveying Engineering

Ms. Ljubica Bogdanovska


Geodetic Engineer - Project Manager
Phone No.: +971-4 265 4288
Mob No: +971 55 20 40 152
Email: ljubica@electra-surveys.com
.

PAGE 16 OF 16

You might also like