CONTENTS
1. PURPOSE................................................................................................................................ 4
MINOR CIVIL CONSTRUCTION AND REPAIR
MISSION GENERAL
WORKS
SERVICES L.L.C.
Project No.
Rev. Page 3 of 10
2. SCOPE..................................................................................................................................... 4
3. RESPONSIBILITIES................................................................................................................. 4
4. RESOURCES........................................................................................................................... 4
5. METHODOLOGY...................................................................................................................... 5
1.PURPOSE
Define a procedure to provide a proper and efficient sequence of works shall be performed
in safety manner & good working practice in accordance with the project specifications,
NAWAH codes & standards.
MINOR CIVIL CONSTRUCTION AND REPAIR
MISSION GENERAL
WORKS
SERVICES L.L.C.
Project No.
Rev. Page 4 of 10
2.SCOPE
This covers the Excavation, Backfilling and Compaction activities to be carried out as per
subcontractor scope of works. This shall be read in conjunction with Construction Safety
Manual.
3.RESPONSIBILITIES
Project Engineer shall ensure that all operations have been risk assessed and
necessary control measures have been implemented to carry out the task in a safely
manner. He shall strictly implement and monitor the methodology of works.
Civil Supervisor ensure compliance by all labour and equipment operators and other
associated craftsmen to the requirements of this procedure, Project Quality Plan,
relevant drawings, HSE requirements as well as the project specifications. Secure all
necessary Work Permits.
QC-Civil Inspector shall monitor the daily activities and verifies its compliance to project
specifications. Conduct activities in accordance with the Project QA Manual and Quality
Inspection Plan.
HSE Manager & its Safety Team shall ensure that all HSE requirements are met and
implemented while executing the works. The safety supervisor shall control, supervise
and record toolbox meetings, conduct inspections, approve or reject engaged resources.
4.RESOURCES
Contractor shall deploy adequate number of resources as per requirement and quantum of
work in compliance to work schedule and resource histograms.
4.1 Equipment
Excavators & Rock Breakers (if any)
Wheel Loader
JCB’s
Dump Trucks
Vibratory Roller & Plate Compactors
Water Truck
Road Grader
Surveying Equipment & Tools
MINOR CIVIL CONSTRUCTION AND REPAIR
MISSION GENERAL
WORKS
SERVICES L.L.C.
Project No.
Rev. Page 5 of 10
4.2 Manpower
Project Engineer
Civil Supervisor
Surveyor
Contractor QC Inspector-Civil
Approved 3rd Party Laboratory Technician
Safety Supervisor
Flag man
Machinery Operators & Drivers
Foreman
Labour Crew
4.3 Safety Equipment
Fire Extinguishers
Warning Signage
Barricades/Jersey Barriers/Fences
Signage for Traffic Control & Detours
5. METHODOLOGY
5.1 Excavation and Grading
Excavation and grading shall be carried out in accordance to latest issued IFC
drawings and project specifications. The sequenced of work are as follows:
Work Permit shall be obtained by assigned personnel to the proper authority prior to
commencement of any excavation works. Documents shall be kept at site at all times
in the event of verification by any authorized personnel of the client.
Prepare and display of warning sign boards on the area to be excavated. Proper
barricade with blinker light shall be place during the night activities.
All workers shall be worn a visible reflector safety vest with complete PPE (personal
protective equipment) required on the job site.
Access tracks for equipment shall be cleared from the obstruction, abandon concrete
structures, vegetation and other parking equipment, etc.
Contractor shall ensure that the movement and swing of the equipment are free from
workers to prevent from any untoward accident that might happen.
Excavation shall commence only after the safety was confirmed to be adequate and
have been displayed and work permit was approved by the Company representative.
MINOR CIVIL CONSTRUCTION AND REPAIR
MISSION GENERAL
WORKS
SERVICES L.L.C.
Project No.
Rev. Page 6 of 10
All underground facilities shall be identified, and necessary precautions and protection
shall be taken into consideration.
In this regard, slit trenches shall be prepared by hand excavation in specific locations
to identify and locate existing services. Location and elevation of all existing
underground utility lines in the work area shall be verified prior to commencing of
excavation work.
Existing facilities and utilities, either overhead or underground shall be protected from
any possible damage.
Excavated areas shall be barricaded with warning signs, guard rails & barricades as
required by the project. A minimum of about 0.6 m clear space shall be maintained on
all sides of the trench with entry and exit points provided according to HSE Standards.
Where necessary, the surfaces of cut areas shall be sloped to prevent erosion.
Shoring shall be provided should the depth of excavation exceeded 1.20 meter in the
required areas.
Zones, if any, encountered with rock of sizes more than 1.0 m shall be fragmented
and removed by continuous drilling & wedging making the rock to the workable sizes.
Zones encountered rocks with sizes less than 1.0 m shall be loosened by excavating
to the required depths and shall be removed with the help of dozers.
All activities shall be carried out safely in accordance with MGS-HSE plan approved
by Company Representative.
5.2 Disposal
Unsuitable & excess excavated materials shall be disposed by MGS in the Area
designated by NAWAH.
5.3 Backfilling
Area to be backfilled shall be free from debris, rubbish, and other unsuitable
materials.
All the materials to be used for backfilling shall be inspected & approved by the
Client.
All the necessary basic civil testing shall be carried out by an approved third-party
technician & laboratory.
Placement of backfill material shall not be allowed unless it is moisture conditioned
within 3% of optimum moisture content.
Backfilling shall be carried out in layers as specified in the NAWAH Standard
Specifications.
MINOR CIVIL CONSTRUCTION AND REPAIR
MISSION GENERAL
WORKS
SERVICES L.L.C.
Project No.
Rev. Page 7 of 10
Fill and backfill materials shall be laid, levelled, and graded mechanically, or
manually lay or spread depending on site conditions.
Backfilling materials shall be from either on-site excavation, designated borrow
areas, or off-site resources that conforming and shall match to the geotechnical
report.
No backfill materials shall be brought to site from other sources or borrow pits unless
it was approved by the Client.
Fill materials shall be used for all fills except where 'Select Fill Material' is specified.
Fill material shall consist of material as specified in NAWAH Standard Specifications.
Fill material shall be free of frozen lumps, organic matter, trash, chunks of highly
plastic clay or other unsatisfactory material.
Water to be used for compaction of fill materials shall be free from salt, oil, acid,
alkalis, organic matter or other deleterious substances complying with the NAWAH
requirements.
All areas to receive fill, foundations, or pavement or areas to be used in the future to
support structural loads shall have the in-situ soil proof rolled and inspected, after
clearing and grubbing, for spots or loose zones.
All observed soft spots or loose zones shall be compacted in place or excavated to
firm soil and replaced with properly compacted fill.
In-place density and moisture content of soils shall be determined by the nuclear
method as per ASTM D 2922.
Acceptance testing of in-place density and moisture content (field density testing) on
compacted fill shall be performed accordingly.
Each layer of fill material shall be compacted mechanically to the required density
before filling with successive layers until the completion of fill to the required grade or
level is achieved as per IFC drawing.
Project No.
Rev. Page 8 of 10
Backfilling shall be compacted using tired roller and vibratory roller compactor or
plate load compactor or any equipment suitable to the site conditions for achieving
the required compaction specification as specified in NAWAH Specifications.
After completion of compaction works, tests shall be conducted to determine the
desired density of consolidation as required in the project specifications. All
compaction tests carried out shall be inspected, checked and certified by an
approved third-party testing agency per ITP for Excavation and Backfilling Works.
All compaction test reports shall be kept and preserved as project records for
future references.
All compaction tests and its due course during the progress of work shall properly
planned in advance and programmed with third party testing agency according to
project requirements.
Any materials and works not conforming to the NAWAH Material specifications
shall be rejected by the relevant discipline approved QC Inspector(s).
MINOR CIVIL CONSTRUCTION AND REPAIR
MISSION GENERAL
WORKS
SERVICES L.L.C.
Project No.
Rev. Page 9 of 10
Project No.
Rev. Page 10 of 10
Possible
No Work Activity Hazard Accident/Health & Existing Risk Control (If any) Additional Risk Control
Person at Risk
Noise induces Personal Protective
High Noise Level SWP for excavation
hearing impairment Equipment (PPE)
Asphyxiation, affects
Exposure to Carbon
central nervous
Di Oxide & Carbon Gas Testing Gas Respiratory systems.
system, blood and
Mono Oxide
lungs
Serious injury or
Soil Collapse Shoring SWP for excavation
death
Excavator swing Serious injury or
EXACAVATION AND Trained Excavator operator SWP for excavation
1 Into workers death
BACKFILLING
Falling into Serious injury or
Effective safety barricade Put warning sign
excavated trench death
Serious injury or Areas will be barricaded &
falls, trips & slips Housekeeping
death signages will be placed
Surface water features to be
Risk from surface diverted. De watering system,
Drowning, death Put barricades
and ground water careful analysis is required
before excavation begins
Traffic should be routed
away from the excavation.
Equipment or
Walkway at least 600 mm Any need for a plant to
materials falling Serious injury or
2 MANPOWER wide with guard rails and toe dump materials into the
into excavated death
boards where necessary excavation suitable stop
trench
blocks and a banksman
need to be provided
Assure if possible, min.
distance between an
Location of the work
Congestion on the excavation and a structure to
(proximity of roads, Death, minor and Create sufficient clearance
3 road, trucks might me more than twice the
existing or new serious injury and enough shoulder lane
crash each other excavation depth to avoid a
structures, etc.,)
potential for ground
movement