S.No Descriptions Unit Rate per (6m Wide x 1m Length)
% of Unit Price A-1 Completion of Sub Granular Base Qty Unit Unit Rate Sub Total Unit Price a) Marking & Setting out 1 MTR 44.00 b) Cutting of Existing Ground Level & Disposal 1 MTR 40.00 c) Grading & Leveling of Sub Surface 1 MTR 40.00 d) Compaction 1 MTR 50.00 e) Sub Granular Base & Compaction 1 MTR 180.00 f) Test & Completion 1 MTR 10.00 364.00 37.10%
A-2 Completion of Granular Base
a) Marking & Setting out 1 MTR 44.00 b) Sub Granular Base & Compaction 1 MTR 180.00 c) Test & Completion 1 MTR 10.00 234.00 23.85%
A-3 Completion of Bitumin Base
a) Marking & Setting out 1 MTR 44.00 b) Bitumin Base & Compaction 1 MTR 190.00 c) Test & Completion 1 MTR 10.00 244.00 24.87%
A-4 Completion of Asphalt Layer
a) Marking & Setting out 1 MTR 44.00 b) Asphalt Layer & Compaction 1 MTR 85.00 c) Test & Completion 1 MTR 10.00 139.00 14.17%