A Asphalt Road 6m Wide = AED 981.

00 per MTR Length Unit Price Breakdown

S.No Descriptions Unit Rate per (6m Wide x 1m Length)


% of Unit Price
A-1 Completion of Sub Granular Base Qty Unit Unit Rate Sub Total Unit Price
a) Marking & Setting out 1 MTR 44.00
b) Cutting of Existing Ground Level & Disposal 1 MTR 40.00
c) Grading & Leveling of Sub Surface 1 MTR 40.00
d) Compaction 1 MTR 50.00
e) Sub Granular Base & Compaction 1 MTR 180.00
f) Test & Completion 1 MTR 10.00 364.00 37.10%

A-2 Completion of Granular Base


a) Marking & Setting out 1 MTR 44.00
b) Sub Granular Base & Compaction 1 MTR 180.00
c) Test & Completion 1 MTR 10.00 234.00 23.85%

A-3 Completion of Bitumin Base


a) Marking & Setting out 1 MTR 44.00
b) Bitumin Base & Compaction 1 MTR 190.00
c) Test & Completion 1 MTR 10.00 244.00 24.87%

A-4 Completion of Asphalt Layer


a) Marking & Setting out 1 MTR 44.00
b) Asphalt Layer & Compaction 1 MTR 85.00
c) Test & Completion 1 MTR 10.00 139.00 14.17%

Total Unit Price for Asphalt Road 981.00 100.00%