Survey Estimate of Janjgiri Diversion Scheme

"A" Preliminary
Details of Quantity
S. SOR Particulars of items Unit Dimensions Quantity
No item No. L B D
No.
01 02 03 04 05 06 07 08 09
1 204 (i) (a) Chain and compass survey (i) Head
Works

Base Line m 1 400.00 400.00

Cross Section (Above 15 m) m 35.00 410.00 14350.00

Total 14750.00
14.75Km
(ii) Canal
Base Line m 1 7000.00 7000.00

Cross Section (Above 15 m) m 116 30.00 3480.00


Total 10480.00
Km 25230.00 m
G.Total 25.23 km
2 206 (a) Levelling (b) Head Works (iii) more than 10
but up to 15 m interal
(iv) Above 15 m interal km As per above item 14.75 km
Canal
(ii) Above 15 m interval km As per above item 25.23 km
3 207 (b) Double levelling for transfer of bench
marks-
(b) above 15 m interval
AS per item no 1 m 1 25230.00 - - 25230.00
Total 25230.00
km 25.23 km
4 210 Benchmark as per type design 6 of Water
Resources Department.
(a) Bench mark stone of size 15x15x75 cm Each 5 5
of 1:2:4 RCC including cost of steel
(b) Erection and fixing (embedding 45 cm Each 5 5
depth of stone with 15cm concrete all
around and in bottom) -
(ii) Labour for excavation (any type of soil), Each 5 5
handling and fixing of B.M. stone including
mixing, laying & curing of concrete
(iii) cost of water for mixing and curing of Each 5 5
concrete

Sub Engineer/Assistant Engineer Sub Divisional Officer


Tandula W.R.Sub Division
No 5 Durg

728892570.xlsx U-2|A-Pre|Estimate G 1 :: 4
Survey Estimate of Janjgiri Diversion Scheme
"A" Preliminary
ABSTRACT FOR COST
R = 366.92
S. SOR Particulars Qty Rate Unit Amount
No item
No.
01 02 03 04 05 06 07
1 204 (i) (a) Chain and compass 14.75 2201.52 Km 32,472.00
survey (i) Head Works
(ii) Canal 25.23 1467.68 Km 37,030.00
2 206 (a) Levelling (b) Head Works
(iii) more than 10 but up to
15 m interal

(iv) Above 15 m interal 14.75 1467.68 km 21,648.00


(b) Canal
(iv) Above 15 m interval 25.23 1174.14 km 29,624.00
3 207 (b) Double levelling for 25.23 4403.04 km 111,089.00
transfer of bench marks-
(b) above 15 m interval
4 210 Benchmark as per type
design 6 of Water
Resources Department.
(a) Bench mark stone of 5.00 119.00 Each 595.00
size 15x15x75 cm of 1:2:4
RCC including cost of steel
(b) Erection and fixing 5.00 236.00 Each 1,180.00
(embedding 45 cm depth of
stone with 15cm concrete
all around and in bottom) -

(ii) Labour for excavation 5.00 733.84 Each 3,669.00


(any type of soil), handling
and fixing of B.M. stone
including mixing, laying &
curing of concrete

728892570.xlsx A-Pre|ABS G 2 :: 4
S. SOR Particulars Qty Rate Unit Amount
No item
No.
(iii) cost of water for 5.00 366.92 Each 1,835.00
mixing and curing of
concrete
Total 239,142.00
Add 1% for contingency 2,391.00
Grand Total 241,533.00
Say Rs. 2.42 Lakh

Sub Engineer Sub Divisional Officer


Tandula W R Sub Division
No 5 Durg