Ground floor
1) A= 2.75x3.85=10.6 sqm
C=10.6x0.675=7.15 bags
S=10.6x0.0375=0.396 cu.m
G=10.6x0.075=0.80cu.m
2) A= 3.10x3.85=11.9 sqm
C=11.9x0.675=8.06 bags
S=11.9x0.0375=0.446 cu.m
G=11.9x0.075=0.89 cu.m
3) A= 2.60x3.35=8.71 sqm
C=8.71 x0.675=5.88 bags
4) A= 2.75x3.85=10.6 sqm
C=10.6x0.675=7.15 bags
S=10.6x0.0375=0.396 cu.m
G=10.6x0.075=0.80 cu.m
5) A= 2.75x3.85=10.6 sqm
C=10.6x0.675=7.15 bags
S=10.6x0.0375=0.396 cu.m
G=10.6x0.075=0.80 cu.m
6) A= 2.60x4.00=10.4 sqm
C=10.4x0.675=7.15 bags
S=10.4x0.0375=0.396 cu.m
G=10.4x0.075=0.80 cu.m
TOTAL:
Cement
10%=4.254
Sand
10%=0.193
Gravel
10%=0.474
Reinforcement
Ground floor
1) A. (2.75/0.6)+1=5.5/6pcs 6m bar
Excess:6-2.70=3.3m 6 pcs
B. (3.85/0.6)+1=7.42/8pcs 6m bar
Excess:6-3.85=2m 6pcs
Excess:6-2.60=3.3m 7pcs
B. (3.85/0.6)+1=7.42/8pcs 6m bar
Excess:6-3.85=2m 8pcs
3) A. (2.60/0.6)+1=5.3/6pcs 6m bar
Excess:6-2.60=3.3m 6pcs
B. (3.35/0.6)+1=6.58/7pcs 7m bar
Excess:7-3.35=3m 7pcs
4) A. (2.75/0.6)+1=5.5/6pcs 6m bar
Excess:6-2.70=3.3m 6 pcs
B. (3.85/0.6)+1=7.42/8pcs 6m bar
Excess:6-3.85=2.2m 6pcs
Excess:6-2.60=3.3m 7pcs
B. (3.50/0.6)+1=6.83/7pcs 6m bar
Excess:7-3.50=3m 7pcs
6) A. (2.60/0.6)+1=5.3/6pcs 6m bar
Excess:6-2.60=3.3m 6pcs
B. (4.00/0.6)+1=7.67/8pcs 6m bar
Excess:6-4=2m 6pcs
Tie wire
1st floor
Weight=14.4/53=0.2716981132kg
Weight=14.4/53=0.2716981132kg
Weight=14.4/53=0.2716981132kg
Weight=14.4/53=0.2716981132kg
Total:
Tie wire
10%=0.06113207547
0.1086792453+1.086792453=1.195471698=1.5kg
2nd floor:
1) A= 2.85x3.85=11.0 sqm
C=11.0x0.675=7.43 bags
S=11.0x0.0375=0.413 cu.m
G=11.06x0.075=0.83 cu.m
2) A= 3.10x3.85=11.9 sqm
C=11.9x0.675=8.06 bags
S=11.9x0.0375=0.446 cu.m
G=11.9x0.075=0.89 cu.m
3) A= 2.70x3.35=9.05 sqm
4) A= 2.85x3.50=10.0 sqm
C=10.0x0.675=6.75 bags
S=10.0x0.0375=0.375 cu.m
G=10.0x0.075=0.75 cu.m
5) A=3.10x3.50=10.9 sqm
C=10.9x0.675=7.36 bags
S=10.9x0.0375=0.409 cu.m
G=10.9x0.075=0.82 cu.m
6) A= 2.70x4.00=10.8 sqm
C=10.8x0.675=7.29 bags
S=10.8x0.0375=0.405 cu.m
G=10.8x0.075=0.81 cu.m
TOTAL:
Cement
10%=0.43
Sand
10%=0.238
Gravel
10%=0.478
Reinforcement
Ground floor
1) A. (2.85/0.6)+1=5.8/6pcs 6m bar
Excess:6-2.85=3.2m 6 pcs
B. (3.85/0.6)+1=7.42/8pcs 6m bar
Excess:6-3.85=2.2m 6pcs
2) A. (3.10/0.6)+1=6.2/7pcs 3.3m bar
Excess:6-2.60=3.3m 7pcs
B. (3.85/0.6)+1=7.42/8pcs 6m bar
Excess:6-3.85=2.2m 8pcs
3) A. (2.70/0.6)+1=5.5/6pcs 6m bar
Excess:6-2.70=3.3m 6pcs
B. (3.35/0.6)+1=6.58/7pcs 7m bar
Excess:7-3.35=3.7m 7pcs
4) A. (2.85/0.6)+1=5.7/6pcs 6m bar
Excess:6-2.70=3.3m 6 pcs
B. (3.50/0.6)+1=5.17/6pcs 6m bar
Excess:6-3.85=2.2m 6pcs
Excess:6-3.10=2.9m 7pcs
B. (3.50/0.6)+1=6.83/7pcs 6m bar
Excess:7-3.50=3.5m 7pcs
6) A. (2.70/0.6)+1=5.5/6pcs 6m bar
Excess:6-2.70=3.3m 6pcs
B. (4.00/0.6)+1=7.67/8pcs 6m bar
Excess:6-4=2m 6pcs
Tie wire
2nd floor
Weight=14.4/53=0.2716981132kg
Weight=14.4/53=0.2716981132kg
Weight=14.4/53=0.2716981132kg
Weight=14.4/53=0.2716981132kg
Total:
Tie wire
10%=0.06113207547
0.1086792453+1.086792453=1.195471698=1.5kg