BEAMS

Estimator:
Mabajen, Marlon B. and Delos Santos, Andrey V.

Concrete Mixture: Class A


(B1) Beam 1: 0.25 x 0.35

3.2m x 3 = 9.6m
3.8m x 3 = 11.4m
4.5m x 3 = 13.5m
3.7m x 3 = 11.1m
3.85m x 1 = 3.85m
1.2m x 1 = 1.2m
2.9m x 1 = 2.9m
2.9m x 1 = 2.9m
2.9m x 1 = 2.9m
4.73 x 1 = 4.73m
2.31 x 1 = 2.31m

Total length = 66.39m


Area = 0.25 x 0.35 = 0.0875 sq.m.
Total Volume of Beam 1
66.39 x 0.25 x 0.35 = 5.81 cu.m
Quantity of Cement
5.81 x 9.0 = 52 bags
Quantity of Sand
5.81 x 0.50 = 2.91 cu.m
Quantity of Gravel
5.81 x 1 = 5.81 cu.m

(B2) Beam 2: 0.20 x 0.35

3.2m x 1 = 3.2m
2.85 x 1 = 2.85m
4.08 x 1 = 4.08m
1.73 x 1 = 1.73m
2.98 x 1 = 2.28m

Total length = 14.14m


Area = 0.20 x 0.35 = 0.07 sq.m.
Total Volume of Beam 2
14.14 x 0.20 x 0.35 = 0.99 cu.m
Quantity of Cement
0.99 x 9.0 = 9 bags
Quantity of Sand
0.99 x 0.50 = 0.495 say 0.50 cu.m
Quantity of Gravel
0.99 x 1 = 0.99 cu.m

(RB) Roof Beam: 0.20 x 0.30


3.2m x 3 = 9.6m
3.8m x 1 = 3.8m
3.85 x 1 = 3.85m
4.5 x 3 = 13.5m
3.7 x 2 = 7.4m
4.73 x 1 = 4.73m
1.5 x 2 = 3m
2.9 x 3 = 8.7m

Total length = 54.58m


Area = 0.20 x 0.30 = 0.06 sq.m.
Total Volume of Roof Beam
54.58 x 0.20 x 0.30 = 3.27 cu.m
Quantity of Cement
3.27 x 9.0 = 29 bags
Quantity of Sand
3.27 x 0.50 = 1.64 cu.m
Quantity of Gravel
3.27 x 1 =3.27 cu.m

(CB) Cantilever Beam: 0.20 x 0.35

1 x 2 = 2m
1.05 x 1 = 1.05m

Total length = 3.05m


Area = 0.20 x 0.35 = 0.07 sq.m.
Total Volume of Cantilever Beam
3.05 x 0.20 x 0.35 = 0.2135 cu.m
Quantity of Cement
0.2135 x 9.0 = 1.92 say 2 bags
Quantity of Sand
0.2135 x 0.50 = 0.11 cu.m
Quantity of Gravel
0.2135 x 1 =0.2135 cu.m

Total bags of Cement for Beam


B1 = 49
B2 =9
RB = 29
CB =2
Total = 89 Bags

Plus 5% Allowance for wastage = 4.45


Total bag of cement = 93 Bags

Total Cu.m of Sand for Beam

B1 = 2.74
B2 = 0.50
RB = 1.64
CB = 0.11
Total = 4.99 Cu.m.

Plus 5% Allowance for wastage = 0.25


Total bag of cement = 5 Cu.m.

Total Cu.m of Gravel for Beam

B1 = 5.48
B2 = 0.99
RB = 3.27
CB = 0.21
Total = 9.95 Cu.m.

Plus 5% Allowance for wastage = 0.50


Total bag of cement = 10 Cu.m.

LONGITUDINAL REINFORCEMENT OF BEAMS


B1
4-20 mm Ø Top Reinf. and 2-20 mm Ø Bottom Reinf. @ Left Support
2-20 mm Ø Top Reinf. and 4-20 mm Ø Bottom Reinf. @ Mid Support
4-20 mm Ø Top Reinf. and 2-20 mm Ø Bottom Reinf. @ Right Support

Horizontal B1 (A) = 3.2 + 3.8 + 3.85 = 10.85 m


10.85 m + 0.45 m – 0.30 m = 11 m Straight length of Longitudinal Bar
Total Number of Full-length Bars required for Continuous Beam:
11 x 8.8
= 16.13 or 16 pcs. 20 mm Ø x 6.00 m
6.00 m
(10. 8 5 m−0. 30)
Short Bar Length = 0.30 m + + 0.25 m = 3.19 m
4
Section @ Right = 3.19 x 4 = 12.76m
Section @ Midspan = (10.85 m – 0.30) x 0.60 x 3 = 18.99 m
Section @ Left = 3.19 x 4 = 12.76m
Total Number of Full-length Bars required for Short Bar:
(12.76 m+1 8.99 m+12.76 m)
= 7.42 pcs. 20 mm Ø x 6.00 m
6.00 m

Horizontal B1 (B) = 3.2 + 3.8 + 2.31 = 9.31m


9.31 m + 0.45 m – 0.30 m = 9.46 m Straight length of Longitudinal Bar
Total Number of Full-length Bars required for Continuous Beam:
9.46 x 8.8
= 13.87 or 14 pcs. 20 mm Ø x 6.00 m
6.00 m
(9.31 m− 0. 30)
Short Bar Length = 0.30 m + + 0.25 m = 2.80 m
4
Section @ Right = 2.80 x 4 = 11.2 m
Section @ Midspan = (9.31 m – 0.30) x 0.60 x 3 = 16.22 m
Section @ Left = 2.80 x 4 = 11.2 m
Total Number of Full-length Bars required for Short Bar:
(11.2 m+16.22 m+11.2 m)
= 6.44 pcs. 20 mm Ø x 6.00 m
6.00 m

Horizontal B1 (C) = 3.2 + 4.73 = 7.93 m


7.93 m + 0.45 m – 0.30 m = 8.08 m Straight length of Longitudinal Bar
Total Number of Full-length Bars required for Continuous Beam:
8.08 x 8.8
= 11.85 or 12 pcs. 20 mm Ø x 6.00 m
6.00 m
(7.93 m− 0.30)
Short Bar Length = 0.30 m + + 0.25 m = 2.46 m
4
Section @ Right = 2.46 x 4 = 9.84 m
Section @ Midspan = (7.93 m – 0.30) x 0.60 x 2 = 9.16 m
Section @ Left = 2.46 x 4 = 9.84 m
Total Number of Full-length Bars required for Short Bar:
(9.84 m+ 9.16 m+ 9.84 m)
= 4.81 pcs. 20 mm Ø x 6.00 m
6.00 m
Vertical B1 (1) = 4.5 + 3.7 = 8.2
8.2 m + 0.45 m – 0.30 m = 8.35 m Straight length of Longitudinal Bar
Total Number of Full-length Bars required for Continuous Beam:
8.35 x 8.8
= 12.25 or 12 pcs. 20 mm Ø x 6.00 m
6.00 m
(8.2 m− 0.30)
Short Bar Length = 0.30 m + + 0.25 m = 2.53 m
4
Section @ Right = 2.53 x 4 = 10.12 m
Section @ Midspan = (8.2 m – 0.30) x 0.60 x 2 = 9.48 m
Section @ Left = 2.53 x 4 = 10.12 m
Total Number of Full-length Bars required for Short Bar:
(10.12 m+ 9.48 m+10.12 m)
= 4.95 or 5 pcs. 20 mm Ø x 6.00 m
6.00 m

Diagonal B1 (4) = 2.9 + 2.9 + 2.9 + 1.2= 9.9


9.9 m + 0.45 m – 0.30 m = 10.05 m Straight length of Longitudinal Bar
Total Number of Full-length Bars required for Continuous Beam:
10.05 x 8.8
= 14.74 or 15 pcs. 20 mm Ø x 6.00 m
6.00 m
(9.9 m −0. 30)
Short Bar Length = 0.30 m + + 0.25 m = 2.95 m
4
Section @ Right = 2.95 x 4 = 11.8 m
Section @ Midspan = (9.9 m – 0.30) x 0.60 x 4 = 23.04 m
Section @ Left = 2.95 x 4 = 11.8 m
Total Number of Full-length Bars required for Short Bar:
(11.8 m+23.04 m+11.8 m)
= 7.77 or 8 pcs. 20 mm Ø x 6.00 m
6.00 m

One Span Beam H and V (B1) = 4.5 + 4.5 + 3.8 + 3.7 + 3.7 = 20.2 m
20.2 + 0.45(5) = 22.45 m
Total Number of Full-length Bars required for One Span Beam:
5 (beam) x 8(bar) = 40 pcs. 20 mm Ø x 6.00 m

Vertical B1 (1) = 1.5 + 1.5 = 3 m


3 + 0.45(2) = 3.9 m
Total Number of Full-length Bars required for One Span Beam:
2 (beam) x 8(bar) = 16 pcs. 20 mm Ø x 6.00 m
B2
2-20 mm Ø Top Reinf. and 2-20 mm Ø Bottom Reinf. @ Left Support
2-20 mm Ø Top Reinf. and 2-20 mm Ø Bottom Reinf. @ Mid Support
2-20 mm Ø Top Reinf. and 2-20 mm Ø Bottom Reinf. @ Right Support

Horizontal B2 (D) = 3.2 + 4.08 = 7.28m


7.28m + 0.45 m – 0.20 m = 7.53 m Straight length of Longitudinal Bar
Total Number of Full-length Bars required for Continuous Beam:
7.53 x 6.6
= 8.28 or 8 pcs. 16 mm Ø x 6.00 m
6.00 m
(7.28 m− 0. 20)
Short Bar Length = 0.20 m + + 0.25 m = 2.22 m
4
Section @ Right = 2.22 x 2 = 4.44 m
Section @ Midspan = (7.28 m – 0.20) x 0.60 x 2 = 8.50 m
Section @ Left = 2.22 x 2 = 4.44 m
Total Number of Full-length Bars required for Short Bar:
( 4,44 m+ 8.50 m+ 4.44 m)
= 2.90 or 3 pcs. 20 mm Ø x 6.00 m
6.00 m

Diagonal B2 (4) = 1.73 + 2.85 = 4.58


4.58 m + 0.45 m – 0.25 m = 4.78 m Straight length of Longitudinal Bar
Total Number of Full-length Bars required for Continuous Beam:
4.78 x 6.6
= 5.26 or 5 pcs. 16 mm Ø x 6.00 m
6.00 m
( 4.58 m−0. 25)
Short Bar Length = 0.25 m + + 0.25 m = 1.58 m
4
Section @ Right = 1.58 x 2 = 3.16 m
Section @ Midspan = (4.58 m – 0.25) x 0.60 x 2 = 5.20 m
Section @ Left = 1.58 x 2 = 3.16 m
Total Number of Full-length Bars required for Short Bar:
(3.16 m+5.20 m+ 3.16 m)
= 1.92 or 2 pcs. 20 mm Ø x 6.00 m
6.00 m

Diagonal B2 = 2. 98 m
2.98 + 0.45 = 3.43 m
Total Number of Full-length Bars required for One Span Beam:
1(beam) x 6(bar) = 6 pcs. 20 mm Ø x 6.00 m
RB
2-20 mm Ø Top Reinf. and 2-20 mm Ø Bottom Reinf. @ Left Support
2-20 mm Ø Top Reinf. and 2-20 mm Ø Bottom Reinf. @ Mid Support
2-20 mm Ø Top Reinf. and 2-20 mm Ø Bottom Reinf. @ Right Support

Horizontal RB (A) = 3.2 + 3.8 + 3.85 = 10.85


10.85 m + 0.45 m – 0.30 m = 11 m Straight length of Longitudinal Bar
Total Number of Full-length Bars required for Continuous Beam:
11 x 6.6
= 12.1 or 12 pcs. 20 mm Ø x 6.00 m
6.00 m
(10. 8 5 m−0. 30)
Short Bar Length = 0.30 m + + 0.25 m = 3.19 m
4
Section @ Right = 3.19 x 2 = 6.38 m
Section @ Midspan = (10.85 m – 0.30) x 0.60 x 3 = 18.99 m
Section @ Left = 3.19 x 4 = 6.38 m
Total Number of Full-length Bars required for Short Bar:
(6.38 m+1 8.99 m+6.38 m)
= 5.29 pcs. 20 mm Ø x 6.00 m
6.00 m

Horizontal RB (C) = 3.2 + 4.73 = 7.93 m


7.93 m + 0.45 m – 0.30 m = 8.08 m Straight length of Longitudinal Bar
Total Number of Full-length Bars required for Continuous Beam:
8.08 x 6.6
= 8.89 or 9 pcs. 20 mm Ø x 6.00 m
6.00 m
(7.93 m− 0.30)
Short Bar Length = 0.30 m + + 0.25 m = 2.46 m
4
Section @ Right = 2.46 x 2 = 4.92 m
Section @ Midspan = (7.93 m – 0.30) x 0.60 x 2 = 9.16 m
Section @ Left = 2.46 x 2 = 4.92 m
Total Number of Full-length Bars required for Short Bar:
( 4.92m+9.16 m+4.92 m)
= 3.17 pcs. 20 mm Ø x 6.00 m
6.00 m

Vertical RB (1) = 4.5 + 3.7 = 8.2


8.2 m + 0.45 m – 0.30 m = 8.35 m Straight length of Longitudinal Bar
Total Number of Full-length Bars required for Continuous Beam:
8.35 x 6.6
= 9.19 or 9 pcs. 20 mm Ø x 6.00 m
6.00 m
(8.2 m− 0.30)
Short Bar Length = 0.30 m + + 0.25 m = 2.53 m
4
Section @ Right = 2.53 x 2 = 5.06 m
Section @ Midspan = (8.2 m – 0.30) x 0.60 x 2 = 9.48 m
Section @ Left = 2.53 x 2 = 5.06 m
Total Number of Full-length Bars required for Short Bar:
(5.06 m+9.48 m+5.06 m)
= 3.27 pcs. 20 mm Ø x 6.00 m
6.00 m

Diagonal RB (4) = 2.9 + 2.9 + 2.9 = 8.7


8.7 m + 0.45 m – 0.30 m = 8.85 m Straight length of Longitudinal Bar
Total Number of Full-length Bars required for Continuous Beam:
8.85 x 6.6
= 9.74 or 10 pcs. 20 mm Ø x 6.00 m
6.00 m
(8.7 m −0. 30)
Short Bar Length = 0.30 m + + 0.25 m = 2.65 m
4
Section @ Right = 2.65 x 2 = 5.3 m
Section @ Midspan = (8.7 m – 0.30) x 0.60 x 3 = 15.12 m
Section @ Left = 2.65 x 2 = 5.3 m
Total Number of Full-length Bars required for Short Bar:
(5.3 m+15.12m+5.3 m)
= 4.29 pcs. 20 mm Ø x 6.00 m
6.00 m

Vertical RB (AB)= 4.5 + 4.5 = 9m


9 + 0.45 (2) = 9.9 m
Total Number of Full-length Bars required for One Span Beam:
2 (beam) x 6(bar) = 12 pcs. 20 mm Ø x 6.00 m

Vertical RB (CD)= 1.5 + 1.5 = 3m


3 + 0.45 (2) = 3.9 m
Total Number of Full-length Bars required for One Span Beam:
2 (beam) x 6(bar) = 12 pcs. 20 mm Ø x 6.00 m

Vertical RB (BC) = 3.7m


3.7 + 0.45 = 4.15 m
Total Number of Full-length Bars required for One Span Beam:
1(beam) x 6(bar) = 6 pcs. 20 mm Ø x 6.00 m

Horizontal RB (D) = 3.2m


3.2 + 0.45 = 3.65 m
Total Number of Full-length Bars required for One Span Beam:
1(beam) x 6(bar) = 6 pcs. 20 mm Ø x 6.00 m

CB
2-20 mm Ø Top Reinf. and 2-20 mm Ø Bottom Reinf. @ Left Support
2-20 mm Ø Top Reinf. and 2-20 mm Ø Bottom Reinf. @ Mid Support
2-20 mm Ø Top Reinf. and 2-20 mm Ø Bottom Reinf. @ Right Support

CB (1) = 1 m + 0.45 m – 0.20 m = 1.25 m


CB (2) = 1 m + 0.45 m – 0.20 m = 1.25 m
CB (3) = 1.05 m + 0.45 m – 0.20 m = 1.3 m

Total Number of Full-length Bars required for One-Span Beam:


3.25 x 6.6
= 3.575 or 4 pcs. 20 mm Ø x 6.00 m
6.00 m
Summary

Total number of full-length bars required for Continues Beams and One Span Beams:
= 224 pcs. 20 mm Ø x 6.00 m
Total Number of Full-length Bars required for Short Bar:
= 52.41 pcs. 20 mm Ø x 6.00 m
Total bags of Cement for Beam:
= 93 Bags
Total Cu.m of Sand for Beam:
= 5 Cu.m.
Total Cu.m of Gravel for Beam:
= 10 Cu.m.

STIRRUPS

B1: 10 mm Ø BAR SPACED 1 @ 50 mm, 6 @ 150 mm; Rest 200 mm O.C.

B1 (A) = 10.85m – 0.30 m = 10.55


1 @ 50 mm: 10.55 m – 2 (0.05 m) = 10.45 m → 2 pcs.
6 @ 150 mm: 10.45 m – 2 (0.9 m) = 8.65 m → 12 pcs.
8.6 5 m
REST @ 200 mm: = 43.25 pcs.
0. 2m
Total Number of Stirrups = 2 +12 + 43.25 = 57.25 pcs. Stirrups
Length of One (1) Stirrup = 0.35 + 0.35 + 0.25 + 0.25 + 2 (0.075) = 1.35 m
Total Number of Full-length Bars required:
57.2 5 x 1.35 m
= 12.88 or 13 pcs. 10 mm Ø x 6.00 m
6.00 m

B1 (B) = 9.31m – 0.30 m = 9.01 m


1 @ 50 mm: 9.01 m – 2 (0.05 m) = 8.91 m → 2 pcs.
6 @ 150 mm: 8.91 m – 2 (0.9 m) = 7.11 m → 12 pcs.
7.11 m
REST @ 200 mm: = 35.55 pcs.
0.2 m
Total Number of Stirrups = 2 +12 + 35.55 = 49.55 pcs. Stirrups
Length of One (1) Stirrup = 0.35 + 0.35 + 0.25 + 0.25 + 2 (0.075) = 1.35 m
Total Number of Full-length Bars required:
49.55 x 1.35 m
= 11.15 pcs. 10 mm Ø x 6.00 m
6.00 m

B1 (C) = 7.93 m – 0.30 m = 7.63 m


1 @ 50 mm: 7.63 m – 2 (0.05 m) = 7.53 m → 2 pcs.
6 @ 150 mm: 7.53 m – 2 (0.9 m) = 5.73 m → 12 pcs.
5.7 3 m
REST @ 200 mm: = 28.65 pcs.
0.2 m
Total Number of Stirrups = 2 +12 + 28.65 = 42.65 pcs. Stirrups
Length of One (1) Stirrup = 0.35 + 0.35 + 0.25 + 0.25 + 2 (0.075) = 1.35 m
Total Number of Full-length Bars required:
42.65 x 1.35 m
= 9.60 or 10 pcs. 10 mm Ø x 6.00 m
6.00 m

B1 (1) = 8.2 m – 0.30 m = 7.9 m


1 @ 50 mm: 7.9 m – 2 (0.05 m) = 7.8 m → 2 pcs.
6 @ 150 mm: 7.8 m – 2 (0.9 m) = 6 m → 12 pcs.
6m
REST @ 200 mm: = 30 pcs.
0.2 m
Total Number of Stirrups = 2 +12 + 30 = 44 pcs. Stirrups
Length of One (1) Stirrup = 0.35 + 0.35 + 0.25 + 0.25 + 2 (0.075) = 1.35 m
Total Number of Full-length Bars required:
4 4 x 1.35 m
= 9.9 or 10 pcs. 10 mm Ø x 6.00 m
6.00 m

B1 (4) = 9.9 m – 0.30 m = 9.6 m


1 @ 50 mm: 9.6 m – 2 (0.05 m) = 9.5 m → 2 pcs.
6 @ 150 mm: 9.5 m – 2 (0.9 m) = 7.7 m → 12 pcs.
7.7 m
REST @ 200 mm: = 38.5 pcs.
0.2 m
Total Number of Stirrups = 2 +12 + 38.5 = 52.5 pcs. Stirrups
Length of One (1) Stirrup = 0.35 + 0.35 + 0.25 + 0.25 + 2 (0.075) = 1.35 m
Total Number of Full-length Bars required:
52.5 x 1.35 m
= 11.81 or 12 pcs. 10 mm Ø x 6.00 m
6.00 m

One Span Beam H and V (B1) = 20.2 m – 0.30 m = 19.9 m


1 @ 50 mm: 19.9 m – 2 (0.05 m) = 19.8 m → 2 pcs.
6 @ 150 mm: 19.8 m – 2 (0.9 m) = 18 m → 12 pcs.
18 m
REST @ 200 mm: = 90 pcs.
0.2 m
Total Number of Stirrups = 2 +12 + 90 = 104 pcs. Stirrups
Length of One (1) Stirrup = 0.35 + 0.35 + 0.25 + 0.25 + 2 (0.075) = 1.35 m
Total Number of Full-length Bars required:
104 x 1.35 m
= 23.4 pcs. 10 mm Ø x 6.00 m
6.00 m

B1 (1) = 3 m – 0.25 m = 2.75 m


1 @ 50 mm: 2.75 m – 2 (0.05 m) = 2.65 m → 2 pcs.
6 @ 150 mm: 2.65 m – 2 (0.9 m) = 0.85 m → 12 pcs.
0.85 m
REST @ 200 mm: = 4.25 pcs.
0. 2m
Total Number of Stirrups = 2 +12 + 4.25 = 18.25 pcs. Stirrups
Length of One (1) Stirrup = 0.35 + 0.35 + 0.25 + 0.25 + 2 (0.075) = 1.35 m
Total Number of Full-length Bars required:
18.25 x 1.35 m
= 4.11 pcs. 10 mm Ø x 6.00 m
6.00 m

B2: 10 mm Ø BAR SPACED 1 @ 50 mm, 6 @ 150 mm; Rest 200 mm O.C.

B2 (D) = 7.28 m – 0.20 m = 7.08 m


1 @ 50 mm: 7.08 m – 2 (0.05 m) = 6.98 m → 2 pcs.
6 @ 150 mm: 6.98 m – 2 (0.9 m) = 5.18 m → 12 pcs.
5.1 8 m
REST @ 200 mm: = 25.9 pcs.
0.2 m
Total Number of Stirrups = 2 +12 + 25.9 = 39.9 pcs. Stirrups
Length of One (1) Stirrup = 0.35 + 0.35 + 0.20 + 0.20 + 2 (0.075) = 1.25 m
Total Number of Full-length Bars required:
39.9 x 1.2 5 m
= 8.31 pcs. 10 mm Ø x 6.00 m
6.00 m
B2 (4) = 4.58 m – 0.25 m = 4.33 m
1 @ 50 mm: 4.33 m – 2 (0.05 m) = 4.23 m → 2 pcs.
6 @ 150 mm: 4.23 m – 2 (0.9 m) = 2.43 m → 12 pcs.
2. 43 m
REST @ 200 mm: = 12.15 pcs.
0. 2m
Total Number of Stirrups = 2 +12 + 12.15 = 26.15 pcs. Stirrups
Length of One (1) Stirrup = 0.35 + 0.35 + 0.20 + 0.20 + 2 (0.075) = 1.25 m
Total Number of Full-length Bars required:
26.1 5 x 1. 25 m
= 5.45 pcs. 10 mm Ø x 6.00 m
6.00 m

Diagonal B2 = 2. 98 m - 0.20 = 2.78 m


1 @ 50 mm: 2.78 m – 2 (0.05 m) = 2.68 m → 2 pcs.
6 @ 150 mm: 2.68 m – 2 (0.9 m) = 0.88 m → 12 pcs.
0.88 m
REST @ 200 mm: = 4.4 pcs.
0. 2m
Total Number of Stirrups = 2 +12 + 4.4 = 18.4 pcs. Stirrups
Length of One (1) Stirrup = 0.35 + 0.35 + 0.20 + 0.20 + 2 (0.075) = 1.25 m
Total Number of Full-length Bars required:
18.4 x 1. 25 m
= 3.83 or 4 pcs. 10 mm Ø x 6.00 m
6.00 m

RB: 10 mm Ø BAR SPACED 1 @ 50 mm, 6 @ 150 mm; Rest 200 mm O.C.

RB (A) = 10.85 m – 0.30 m = 10.55 m


1 @ 50 mm: 10.55 m – 2 (0.05 m) = 10.45 m → 2 pcs.
6 @ 150 mm: 10.45 m – 2 (0.9 m) = 8.65 m → 12 pcs.
8.65 m
REST @ 200 mm: = 43.25 pcs.
0. 2m
Total Number of Stirrups = 2 +12 + 43.25 = 57.25 pcs. Stirrups
Length of One (1) Stirrup = 0.30 + 0.30 + 0.20 + 0.20 + 2 (0.075) = 1.15 m
Total Number of Full-length Bars required:
57.2 5 x 1.15 m
= 10.97 or 11 pcs. 10 mm Ø x 6.00 m
6.00 m

RB (C) = 7.93 m – 0.30 m = 7.63 m


1 @ 50 mm: 7.33 m – 2 (0.05 m) = 7.53 m → 2 pcs.
6 @ 150 mm: 7.53 m – 2 (0.9 m) = 5.73 m → 12 pcs.
5.73 m
REST @ 200 mm: = 28.65 pcs.
0.2 m
Total Number of Stirrups = 2 +12 + 28.65 = 42.65 pcs. Stirrups
Length of One (1) Stirrup = 0.30 + 0.30 + 0.20 + 0.20 + 2 (0.075) = 1.15 m
Total Number of Full-length Bars required:
42.65 x 1. 15 m
= 8.17 pcs. 10 mm Ø x 6.00 m
6.00 m

RB (1) = 8.2 m – 0.30 m = 7.9 m


1 @ 50 mm: 7.9 m – 2 (0.05 m) = 7.8 m → 2 pcs.
6 @ 150 mm: 7.8 m – 2 (0.9 m) = 6 m → 12 pcs.
6m
REST @ 200 mm: = 30 pcs.
0.2 m
Total Number of Stirrups = 2 +12 + 30 = 44 pcs. Stirrups
Length of One (1) Stirrup = 0.30 + 0.30 + 0.20 + 0.20 + 2 (0.075) = 1.15 m
Total Number of Full-length Bars required:
4 4 x 1. 15 m
= 8.43 pcs. 10 mm Ø x 6.00 m
6.00 m

RB (4) = 8.7 m – 0.30 m = 8.4 m


1 @ 50 mm: 8.4 m – 2 (0.05 m) = 8.3 m → 2 pcs.
6 @ 150 mm: 8.3 m – 2 (0.9 m) = 6.5 m → 12 pcs.
6.5 m
REST @ 200 mm: = 32.5 pcs.
0.2 m
Total Number of Stirrups = 2 +12 + 32.5 = 46.5 pcs. Stirrups
Length of One (1) Stirrup = 0.30 + 0.30 + 0.20 + 0.20 + 2 (0.075) = 1.15 m
Total Number of Full-length Bars required:
4 6.5 x 1. 15 m
= 8.91 or 9 pcs. 10 mm Ø x 6.00 m
6.00 m

Vertical RB (AB)= 9 m - 0.30 m = 8.7 m


1 @ 50 mm: 8.7 m – 2 (0.05 m) = 8.6 m → 2 pcs.
6 @ 150 mm: 8.6 m – 2 (0.9 m) = 6.8 m → 12 pcs.
6.8 m
REST @ 200 mm: = 34 pcs.
0.2 m
Total Number of Stirrups = 2 +12 + 34 = 48 pcs. Stirrups
Length of One (1) Stirrup = 0.30 + 0.30 + 0.20 + 0.20 + 2 (0.075) = 1.15 m
Total Number of Full-length Bars required:
48 x 1. 15 m
= 9.2 pcs. 10 mm Ø x 6.00 m
6.00 m
Vertical RB (CD)= 3 m - 0.30 m = 2.7 m
1 @ 50 mm: 2.7 m – 2 (0.05 m) = 2.6 m → 2 pcs.
6 @ 150 mm: 2.6 m – 2 (0.9 m) = 0.8 m → 12 pcs.
0.8 m
REST @ 200 mm: = 4 pcs.
0.2 m
Total Number of Stirrups = 2 +12 + 4 = 18 pcs. Stirrups
Length of One (1) Stirrup = 0.30 + 0.30 + 0.20 + 0.20 + 2 (0.075) = 1.15 m
Total Number of Full-length Bars required:
18 x 1.15 m
= 3.45 pcs. 10 mm Ø x 6.00 m
6.00 m

Vertical RB (BC)= 3.7 m - 0.30 m = 3.4 m


1 @ 50 mm: 3.4 m – 2 (0.05 m) = 3.3 m → 2 pcs.
6 @ 150 mm: 3.3 m – 2 (0.9 m) = 1.5 m → 12 pcs.
1.5 m
REST @ 200 mm: = 7.5 pcs.
0.2 m
Total Number of Stirrups = 2 +12 + 7.5 = 21.5 pcs. Stirrups
Length of One (1) Stirrup = 0.30 + 0.30 + 0.20 + 0.20 + 2 (0.075) = 1.15 m
Total Number of Full-length Bars required:
21.5 x 1.15 m
= 4.12 pcs. 10 mm Ø x 6.00 m
6.00 m

Horizontal RB (D) = 3.2 m - 0.30 m = 2.9 m


1 @ 50 mm: 2.9 m – 2 (0.05 m) = 2.8 m → 2 pcs.
6 @ 150 mm: 2.8 m – 2 (0.9 m) = 1 m → 12 pcs.
1m
REST @ 200 mm: = 5 pcs.
0.2 m
Total Number of Stirrups = 2 +12 + 5 = 19 pcs. Stirrups
Length of One (1) Stirrup = 0.30 + 0.30 + 0.20 + 0.20 + 2 (0.075) = 1.15 m
Total Number of Full-length Bars required:
19 x 1.15 m
= 3.64 or 4 pcs. 10 mm Ø x 6.00 m
6.00 m

CB: 10 mm Ø BAR SPACED 1 @ 50 mm, 6 @ 150 mm; Rest 200 mm O.C.


CB (1) = 1.25 m
1 @ 50 mm: 1.25 m – (0.05 m) = 1.2 m → 2 pcs.
6 @ 150 mm: 1.2 m – (0.9 m) = 0.3 m → 12 pcs.
0.3 m
REST @ 200 mm: = 1.5 pc.
0.2 m
Total Number of Stirrups = 2 +12 + 1.5 = 15.5 pcs. Stirrups
Length of One (1) Stirrup = 0.35 + 0.35 + 0.20 + 0.20 + 2 (0.075) = 1.25 m
Total Number of Full-length Bars required:
15.5 x 1.25 m
= 3.23 pcs. 10 mm Ø x 6.00 m
6.00 m

CB (2) = 1.25 m
1 @ 50 mm: 1.25 m – (0.05 m) = 1.2 m → 2 pcs.
6 @ 150 mm: 1.2 m – (0.9 m) = 0.3 m → 12 pcs.
0.3 m
REST @ 200 mm: = 1.5 pc.
0.2 m
Total Number of Stirrups = 2 +12 + 1.5 = 15.5 pcs. Stirrups
Length of One (1) Stirrup = 0.35 + 0.35 + 0.20 + 0.20 + 2 (0.075) = 1.25 m
Total Number of Full-length Bars required:
15.5 x 1.25 m
= 3.23 pcs. 10 mm Ø x 6.00 m
6.00 m

CB (3) = 1.3 m
1 @ 50 mm: 1.3 m – (0.05 m) = 1.25 m → 2 pcs.
6 @ 150 mm: 1.25 m – (0.9 m) = 0.35 m → 12 pcs.
0.35 m
REST @ 200 mm: = 1.75 pcs.
0. 2m
Total Number of Stirrups = 2 +12 + 1.75 = 15.75 pcs. Stirrups
Length of One (1) Stirrup = 0.35 + 0.35 + 0.20 + 0.20 + 2 (0.075) = 1.25 m
Total Number of Full-length Bars required:
15.75 x 1.25 m
= 3.28 pcs. 10 mm Ø x 6.00 m
6.00 m

Summary

Total Number of Full-length Bars required for Stirrups:


= 168.53 say 169 pcs. 10 mm Ø x 6.00 m
Total Number of Stirrups for Beam 1:
= 368.2 pcs.
Total Number of Stirrups for Beam 2:
= 84.55 pcs.
Total Number of Stirrups for RB:
= 298.25 pcs.
Total Number of Stirrups for CB:
= 46.75 pcs.

TIE WIRES:

B1: Number of Stirrups = 368.2 pcs.


Number of Joint = 22
Total Number of Tie Wires = 368.2 x 22 = 8,100.4 pcs.

B2: Number of Stirrups = 84.55 pcs.


Number of Joint = 18
Total Number of Tie Wires = 84.55 x 18 = 1,521.9 pcs.

RB: Number of Stirrups = 298.25 pcs.


Number of Joint = 18
Total Number of Tie Wires = 298.25 x 18 = 5,368.5 pcs.

CB: Number of Stirrups = 46.75 pcs.


Number of Joint = 18
Total Number of Tie Wires = 46.75 x 18 = 841.5 pcs.

Total Tie Wires for Beam:


8,100.4 + 1,521.9 + 5,368.5 + 841.5 = 15,832.3

Using a 30 cm long tie:


15,832.3 x 0.30 = 4749.69 say 4750 m G.I. wire

Converting to Kg: 1 kg of No.16 G.I. wire = 53 m long

4750 m
= 89.62 say 90 kg No.16 G.I. wire
53 m