You are on page 1of 2

Memo No.

CAMCE-DWASA-DESWSP-P2-LC0005-2108
August 22, 2021
To:
Md. Mahmudul Islam
Superintending Engineer & Project Director
Dhaka Environmentally Sustainable Water Supply Project (DESWSP)
Dhaka Water Supply and Sewerage Authority
WASA Bhaban, 98, Kazi Nazrul Islam Avenue (2nd Floor)
Kawran Bazar, Dhaka-1215.

Subject: Handover of the right of way.

Project Title:
Dhaka Environmentally Sustainable Water Supply Project (DESWSP),
Contract Title and Number:
Package 2, Treated Water Pipeline (Contract No.: ICB-3.0/TWP/DESWSP/2018)

Dear Sir,

We are thankful to you being received the advanced payment both BDT. and USD part. We are
preparing our survey team for route survey and bathymetric survey along with required Geo-Technical
Survey. We are on the way to mobilize our Project Management & Technical Teams with equipment. We
are ready to install our site office soon.

So, you are requested to handover the right way ASAP.

With Best Regards,

Chen Ran
Contractor’s Representative
China CAMC Engineering Co., Ltd.

CC:
1. Mr. Nigel Osmaston
Team Leader, Management, Design & Supervision Consultant (MDSC)
2. Mr. Pierre Racine,
Senior Resident Engineer, Management, Design & Supervision Consultant (MDSC)