M/s CDigital,
House # 275C, Street # 13,
Chaklala Scheme-III, Rawalpindi.
051-5133790-92.
You are requested to please mobilize at site for subject cited work within
period mentioned below and ensure timely completion of the work.
The following terms and conditions shall apply which may be signed as token
of acceptance:
(i) You should mobilize at site within 03 days positively from the issuance of the work order.
(ii) The completion period for the subject work is 15 days from the date of commencement.
(iii) Income tax & sales SST on payment shall be deducted as per Government Rules in
force.
(iv) The payment will be made for the actual quantities of work done at site.
(Aamir Mughal)
CHIEF ENGINEER/PD
Signature of Contractor
Copies to:-
1. The Superintending Engineer (Civil), K-IV Project WAPDA, Karachi.
2. The Dy. Manager (A&F), K-IV Project WAPDA, Karachi.
3. The Sr. Engineer (E&M-II), K-IV Project WAPDA, Karachi.
4. The Jr. Engineer, K-IV Project WAPDA, Karachi.
5. Master File.