General Manager,
Tarbela Dam,
Tarbela.
H # F-519 Satellite Town, Captain Aleem Shaheed Road Satellite town Rawalpindi
Email: xenehv1@gmail.com | Ph: 051-4416109 Fax: 051-4843848
NATIONAL TRANSMISSION AND DESPATCH COMPANY
EXECUTIVE ENGINEER (EHV) T/LINE “C” DIVISION-RAWALPINDI
It is submitted that 220KV Transmission Line Tarbela-Burhan Circuit-I & II are completed
and energized ON-LOAD on 25.02.2019 and 28.02.2019. The same is taken over by EHV
500KV T/Line “C” Division NTDC Rawalpindi from M/S Mecons Pvt Ltd Lahore and Handed
Over to 500KV T/L “M” Division NTDC Rawat on 28.02.2019 for further maintenance and
operation.
NAWAB KHAN
EXECUTIVE ENGINEER (EHV-I)
TLC DIVISION NTDC RAWALPINDI
Copy to:
1. Chief Engineer (EHV-I) NTDC Islamabad for information please
2. M/S MECONS Pvt Ltd Lahore for information
- Master File
H # F-519 Satellite Town, Captain Aleem Shaheed Road Satellite town Rawalpindi
Email: xenehv1@gmail.com | Ph: 051-4416109 Fax: 051-4843848