1. Cryogenic content & coverage in refers to which ASME code?

A. B31.1
B. B31.3
C. B31.4
D. B31.8

2. Tightness test definition?


3. Preheat for A335 Gr. P-5 material is?
 10
 80
 As per WPS
 175
4. Who is whole responsible for plant piping?
 Owner
 Erector
 Designer
 manufacturer
5. After a weld repair (found in additional sample) what is next step?
 1 more set of sample
 2 more set of sample
 3 more set of sample
 All to be examined..
6. Chloride content in SS piping is?
 50 PPM
7. When using old qualification from previous employer, Which is not true ?
 Sign & endorse by employer
 Verify data as per ASME IX
 Welder old employer shall provide originals
8. Impact test standard specimen size is?
 10 X 10
 8X8
 5X5
 2X2

9. Local PWHT, hardness % is?


 10
 20
 25
 100
10. Pipe thickness 8mm, socket thickness 12mm, fillet size is?
 9
 10
 11
 12
11. No. of test required for impact test is?
 1
 2
 3
 4
12. Metal Ball valves-flanged, threaded and welding end refers to?
a. API-600
b. API-602
c. API-603
d. API-608
13. Percentage accuracy between two pressure gage
a. 5%
b. 10%
c. 25%
d. none
14. As per B31.3 requirement for visual examination for category-D fluids
a. 5%
b. 10%
c. 25%
d. None of the above
15. WPS for process piping to be qualified for the fabrication of fitting a joint as per ?
a. B31.3
b. Sec IX
c. Not required to qualify for the fitup
d. None

16. Heating of a portion to a sufficient temp below the transformation temp range to relieve the
major portion of the residual stresses, followed by uniform cooling slowly to minimize the
development of new residual stresses?
a. Stress relief
b. PWHT
c. Tempering
d. None
17. As per B31.3 hardened material has been heated to increase the toughness?
a. Quenching
b. Tempering
c. Normalizing
d. Annealing
18. Which statement is not true for the performance qualification by ASME B31.3?
a. Welder and welding operator shall be used only for specific pipe and tubes
b. The employer shall have the WPS that was followed during qualification
c. The record shall show the name of the employer, the welder with date of the qualification
19. What P&ID
A) Piping and Instrumentation Diagram
B) Piping and Instrumentation Drawing
C) Both A & B
D) None of the above
20. Who is responsible for delivering the material, components and workmanship as per ASME
B31.3 Boiler and Pressure Vessel Design Code
A) Owner
B) manufacturer
C) Fabricator
D) Manufacturer, Fabricator, Erector
21. What are the International standards for pipe
a. API5L
b. ASTM A 106
c. ASTM 333
d. All the above

22. What is the standard for Metallic Gasket material


a. B16.11
b. 16.20
c. 16.9
d. 16.5

23. Pipe having a helical seam with either butt, lap or lock seam joint.
 ERW
 ESW
 Spiral weld
 Fusion weld
24. Standard for Surface Finish
A) MSS SP-25
B) MSS SP-6
C) MSS SP-51
D) NONE OF THE ABOVE
25. Impact testing is not required above which Design temperature for CS
A. -104C/-155F
B. -29C/-20F
C. -48C/-55F
D. NONE OF THE ABOVE
26. Consumable insert – definition
27. Tie in temperature measure at
 Existing to new pipeline
 Placed valve between
 Pipeline String to string or to anchor
28. Pipe ratio of connecting branch tee as per ASME B 16.25
A)+-3mm
B)+-10mm
C)+-3 MM
D) None of the above