# Station Document No

M3-CJV-IRF-EAR00-UGS-
1 4G1 Station
002961

2 4G1 Station M3-CJV-IRF-EAR00-UGS-003003

M3-CJV-IRF-EAR00-UGS-
3 4G1 Station
003004

4 4G1 Station Waiting for IR number

5 4C2 Station M3-CJV-IRF-EAR00-UGS-003006

6 4C2 Station M3-CJV-IRF-EAR00-UGS-003005

7 4C2 Station M3-CJV-IRF-EAR00-UGS-002932

8 4C2 Station M3-CJV-IRF-EAR00-UGS-001838


9 4C2 Station M3-CJV-IRF-EAR00-UGS-001839

10 4C2 Station M3-CJV-IRF-EAR00-UGS-002895

11 4C2 Station Hold by FAST due to comments

12 4C2 Station Hold by FAST due to comments

13 4C2 Station Hold by FAST due to comments


Document Title

Final Inspection Request for Installation of FOH (Front Of


House) Handrail & Balustrade on Staircase Area S04 & S05
(GL B-E/6-10) & Escalator Area E01, E02, E03, E04 & E05
(GL B-E/6-10) Platform Level to Concourse Level @ 4G1
station. (As per attached hig

Inspection Request for final acceptance and operational of


Installed Roller shutter door, Concourse level @ 4G1 station

Final Inspection Request for Installation of Glass cladding at


TVM area (As per highlighted attached drawing), Concourse
Level @ 4G1 station
Final Inspection request of Installed Toilet Accessories
(Wash basin / counter top and Mirrior) in MWC (B.07) &
FWC (B.08),Concourse Level (Please see attached
highlighted Drawing) @ 4G1 Station
Final Inspection Request for Installation of Glass cladding at
TVM area (As per highlighted attached drawing), Concourse
Level @ 4C2 station

Inspection Request for final acceptance and operational of


Installed Roller shutter door @ Room No: R.01 (Retail1) &
R.02 (Retail2),Concourse level @ 4C2 station

Inspection Request for Final Installation of wall & floor


mounted handrails , balustrade & final painting (2 coats) at
ROOM NO: S.01 (STAIR1) ,S.02 (STAIR2) & S.03 (STAIR3)
at 4C2 Station.

Inspection Request for Examine Condition of Structural


Surface, tolerance & Roughness of Handrails & Balustrade
for TSY rooms at ROOM NO: T.02 (LPS2), T.01 (LPS1),T.04
(PP) &  T.07 (TPS) at concourse level.
Final Inspection Request for ( Examine Condition of
Structural Surface, tolerance & Roughness , Installation
Inspection & Painting/Touch Up Inspection  ) of Handrails &
Balustrade for TSY rooms at ROOM NO: T.02 (LPS2), T.01
(LPS1),T.04 (PP) &  T.07 (TPS) at concourse level.

Inspection Request for the final Installation of glass


balustrades & handrails at staircase S.06 & S.07 from
Concourse to Platform, Around staircase S.06 ,
S.07(@Concourse Level) and Escalators 1,2,3 &
4(@Concourse Level) at 4C2 Station .

Final Inspection request of Installed Toilet Accessories


(Wash basin / counter top and Mirrior) in MWC-1 & FWC-1
room, GL V-W/12-14 ,Concourse Level (Please see attached
highlighted Drawing) @ 4C2 Station

Final Inspection request of Installed Toilet Accessories


(Wash basin / counter top and Mirrior) in MWC-2 & FWC-2
room,Concourse Level (Please see attached highlighted
Drawing) @ 4C2 Station
Inspection Request for Final Installation of FOH Handrails
including wall mounted handrails at STAIR (S08 & S10) at
4C2 Station
RAMPED Review Status RAMPED COMMENTS Remarks

Not uniform gaps


between
Code-B glasses/Alignment/sealan
t remaining

Code-A Closed

Code-A Closed

Code-A Closed

Wainting for Ramped


So it can be closed
response

On hold due to certificate


So it can be closed
from AKMI

SEALANT NOT DONE


BELOW THE STRINGER
PLATE

Code-B TOUCH UP PAINT


Code-B TOUCH UP PAINT

Not uniform gaps


between
Code-B glasses/Alignment/sealan
t remaining

On hold due to Sealant


So it can be closed
issues

On hold due to Sealant


So it can be closed
issues

On hold due to Sealant /


So it can be closed
some rectification