GENERAL NOTES
1. ABOVE CEILING CONSTRUCTION OF THIS FLOOR
. ABOVE CEILING CONSTRUCTION OF FLOOR BELOW
. AT CEILING OF THIS FLOOR
. AT CEILING OF FLOOR BELOW
ABOVE FLOOR
BELOW FLOOR
|. OFFSET AT 45,
. CAP _OR PLUG SERMICE(S) FOR FUTURE EXTENSION.
. CONTRACTOR SHALL VERIFY LOCATION, MATERIAL, SIZE, DEPTH
"AND. INVERT ELEVATION OF EXISTING ‘UTILITY SERVICE AT THIS POINT.
IF ANY DESCREPANCY EXISTS, HE SHALL NOTIFY THE ARCHITECT THEREOF
IN WRITING PRIOR TO PROCEEDING WITH THE WORK.
10. EXISTING FIXTURE, EQUIPMENT SERVICE,,OR FACILITY TO REMAIN.
11. EXISTING FIXTURE, EQUIPMENT. SERVICE, OR FACILITY TO BE REMOVED.
12. EXISTING FIXTURE, EQUIPMENT, SERVICE OR FACILITY TO BE RELOCATED.
13. EXTEND AND CONNECT TO NEAREST APPROVED SERVICE AS REQUIRED.
14, REMOVE sees } BACK BEYOND FINISHED ieee AND CAP.
15. REMOVE SERVICE(S) BACK TO ACTIVE POINT AND C/
16. EXISTING FLOOR DRAIN TO BE PLUGGED, STRAINER “REMOVED AND DRAIN
FILLED WITH CONCRETE.
17. EXISTING SERVICE TO BE ABANDONED IN PLACE.
18, REMOVE EXISTING VENT THRU ROOF.
19. CONNECT NEW SERVICE TO EXISTING SERVICE AS REQUIRED.
WO YOORUN
NOTE: ALL GENERAL NOTES MAY NOT 4PPEAR ON DRAWINGS.
“24
i
Job:
ee
Date:
Gas Data
Size, location and depth of all gas mains fronting on the
site or serving the site?
Btu content and pressure of gas available?
Gmount of work done by the gas company? amount of work
Gone by the gas company and paid for by the contractor?
Eauipment furnished by the gas company and to be in-
stalled by the contractor?
Approximate load: Btu/h
Size of service?
Size of meter?
a nepecta2 gas company requirements regarding location
of meter or others?
ibe of pipe, fittings, and valves normally used?
Required? Coating? Cathodic protection?Job:
—
Date:
Sewer Data
2. Size, location, ané depth (including manhole locations
of aii sewers fronting on or serving the site? Sanitary?
Storm water? Combined?
2. If no sewers, how to dispose of sanitary sewage? storm
water drainage? If dry wells or sewage disposal systen
topographical map and type of soil at varying depths?
3. If street sewer manholes are required, by whom? If by
Sener department, at whose cost? If by owner, any special
standard detail?
4. Any specia? standard detail required for house sewer nan-
holes?
5. Are street sewer connections preferred at or between man-
holes? If between manholes, are there existing spurs?
Are there any minimum or maximum limitations on size or
depth?
6. Any other special requirements?fe aie gaggia eget eeE
Date:
Water Data
Size, location, and depth of all water mains and fire
hydrants fronting on the site or serving the site?
Water pressure at a given elevation?
Water meter: by water company? Purchased from water
company or by owner? ‘Type? Strainer? Water meter pit?
If so, by whom? Standard pit details?
Fire hydrants: by water company or by owner? Type?
Amount of work done by water company? Amount of work
done by water company and paid for by the contractor?
Minimum cover required on water lines?
Any other special requirements?
Water analysis.
Type of pipe, fittings and joints normally used?
Required?INDEX
DESIGN CHECK LIST
PLUMBING, DRAINAGE AND FIRE PROTECTION
Item
Agency Approvals 3
Architectural Coordination 4
Electrical Coordination 6
HVAC Coordination 7
Structural Coordination 9
General Design 10
Section 15050--Piping and Basic Naterials and Methods 12
Section 15210--Vibration and Noise Control 14
Section 15300--Special Systems 15
Section 15400--P1umbing Systems 16
Section 15450--Plumbing Fixtures and Trim uv
Section 15500--Fire Protection 18
Section 15900--Controls and Instrumentation a9
1/1/81 ID-2 of 19CIC]
CII
Citi
Citi
citi
tit)
Cit)
Citi
Cit)
City
7/1/87
01
Cj
C1
Cl
Cl
C1
C1
C1
Cl
Cl
Plumbing Agency Approvals
Local Plumbing Inspector's Signed Approval
NFPA (Fire Marshal)
Owner's Insurance Agency
Labor and Industry
Department of HHS
Department of Environmental Resources/Protection
Air Pollution Agency (Incinerators)
Public Health Service
County Health Department
Township Health Department
10-3 of 19C1
£4
C1
C1
C1
ED
ti
i)
ka
Cl
C1
C1
tl
C1
01
C1
Gd
ced
C1
ti
Cl
ti
C]
Ct)
01
a)
7/1/87
Cj
Cl
Cl
C1
01
C1
cd
Cl
Cl
Cj
C1
Cy
1
Plumbing/Architectural Coordination
Correct al1 drawings for Architectural changes. Show all room
numbers and column numbers on drawings.
Advise Architect of Plumbing/OSHA code requirements for number of
fixtures required, (Architect will determine occupation count
and final number of fixtures to be used.)
Coordinate and differentiate EWC and DF.
Coordinate access panel/door locations for concealed valves,
equipment, etc., | above/behind plaster/drywall _—ceilings/
shaftwalls/furring. Cross reference access panels or doors
provided by general contractor. Coordinate with reflected
ceiling plans...
Coordinate whether plumbing contractor or general contractor is
to provide sprinkler heads and flushing valves in laundry and
trash chutes - frequently specified with chutes by Architect.
Coordinate locations of hose bibs, fire hose cabinets, etc. with
Architect.
Recess for equipment (fire hose cabinets, etc.) in shaft, stair
and similar fire rated walls must be designed so that the fire
rating of the wall behind the equipment is maintained. For
nonrated walls, recesses must be designed to maintain integrity
of wall.
Coordinate special equipment with Architect, (Owner's equipment,
laboratory, kitchen, pneumatic doors, etc.)
Determine who provides compressed air for pneumatic doors. Large
system, e.g., hospital patient room doors, should have compressor
and piping by plumbing.
Coordinate need for, and location of, floor drains for condensate
drainage from walk-in freezers, coolers, cold rooms, incubators,
etc.
Coordinate location of roof drains, Select roof drains for
Architect. Also, see Structural Coordination re: roof drains.
Coordinate size and location of access spaces for plumbing
fixtures.
Check with Architect to determine whether or not building will be
constructed in "phases". If it is, design Plumbing Systems
accordingly.
ID-4 of 19Plumbing/Architectural Coordination (Cont'd.)
dees.
Cicici
CI£ICF
CILICI
C1CI0]
Cicicl
Citicd
Citici
7/1/87
Determine location of waterproofed floors and walls from
Architect. If there is any doubt that Plumbing Contractor will
know where they are located, indicate same on Plumbing drawings.
Pay particular attention to Penthouse floors and Equipment Room
floors. All sleeves through such floors and walls must be
waterproof type with flashing ring (detail same on drawings) and
all floor drains must have flashing clamp.
Wihen the Architect revises the grading ona site with existing
underground utilities and services, check all utilities and
services for proper cover. Relocate utilities and services or
have Architect revise grading as required to maintain proper
cover.
Advise Architect of design requirements for halon protected
rooms: walls and partitions must extend from floor to structure
above, and sealed in tight at their joints and at the floor and
structure above; floor and structure above must be of airtight
construction; all doors to outside the halon protected area, and
doors separating one halon zone from another, must be weather
stripped and provided with sweeps; some halon systems, depending
on manufacturer of heads (plumbing to verify) require that lay-in
ceilings be provided with clips; all penetrations through walls,
Floors and structure above (including electrical) must be sealed
air tight.
All floors in parking and service garages must pitch adequately
to floor drains. Do not allow Architects or structural to design
without adequate pitch.
Obtain Architect's (and Owner's) approval of plumbing fixtures
and trim - verify need for showers in bath tubs.
Some Owners and Construction Managers do not use our standard
General (and Supplementary) Conditions and do not use all of our
Division 1 sections. When this is the case, coordinate with the
Architectural specification writer to verify that the items in
our standard Division 1 sections (especially 01045, 01090, 01300
or 01340, 01600 or 01630, 01656, 01660 and 01700} pertaining to
Division’ 15 are either included in the General (and
Supplementary) Conditions or other portions of the “white pages".
If not, add the appropriate portions to Section 15050 of the
specifications.
Determine whether or not sprinkler heads are to be shown on
reflected ceiling plans. If yes, verify need for Fire Protection
Contractor to submit reflected ceiling plan for review and edit
specification Section 15500 accordingly,
10-8 of 1912 3
C1001
Cictitl
C1cCit]
ahatd
C1010)
C1citl
cicicti
EYETCI
Citici
c1citi
71/7/87
Plumbing/Electrical Coordination
Coordinate and differentiate EWC and DF.
Coordinate alarm, control and power wiring with Electrical and
Plumbing specifications, e.g., fire protection alarm valve,
deluge valve, monitored shutoff valves; medical gas control
alarm, pressure alarms for oxygen, nitrous oxide, air, vacuum,
Ste. Clarity who provides alarm device and who does alarm wiring
= Electrical or Plumbing contractor.
Prepare Electrical coordination sheet, review with Electrical and
review HPE drawings.
When using wall-hung electric water coolers, advise Electrical to
Jocate receptacle directly under the cooler so that the cord and
receptacle are hidden.
Dimensionally coordinate underground plumbing and electrical work
if they are close to or cross each other.
AN] emergency generators must have energy sources which will be
available to the emergency generator during a total area power
blackout. Thus, if we are going to use a gas-driven generator,
we must. get written confirmation from the Gas Company that they
will have gas available during a total power blackout and if we
fare going to use City water-cooled engines, we must have similar
information from the Water Company.
Advise Electrical of electric pipe line tracing required to
prevent plumbing pipes/traps from freezing.
Do not run any piping in or through electrical, telephone or
elevator equipment rooms that is not specifically related to that
room. Coordinate unavoidable conditions with Electrical and
Architect. (Provide "roof" over electrical room, drain pan under
piping, etc.)
Do not run piping over Electrical equipment in Mechanical Rooms
(add note on plumbing drawings) or over electrical panels.
Coordinate unavoidable conditions with Electrical and Architect.
Refer to NFPA 30 (Par. 4-3 of 1983 issue) regarding oi! fired
water heating. | Verify if applicable and coordinate with
electrical as to who is to furnish. Coordinate with HVAC if room
also has a boiler.
ID-6 of 19LIC)
Ciel
Cicd
C101
Cita
Citi
C1t1
Citi
Cita
Cicd
CIC]
C1cl
Cicl
7/7/81
01
Ci
C1
tl
C)
C]
td
(ee)
Cl
Cl
tl
C1
Cl
Plumbing/HVAC Coordination
Obtain HVAC domestic water requirements, e.g., cooling tower
makeup, system fill lines, makeup water for computer room AC unit
and other humidifiers. Coordinate location of services, start
and stop points of HVAC and PD contracts.
Same as above for gas.
Domestic water piping to HVAC system must have backflow
preventer. Coordinate location with HVAC and determine who
provides it - HVAC or Plumbing, usually Plumbing at one location
jn each Mechanical Room. Show on drawings.
Give chemical analysis of water supply to HUAC.
Obtain location of plenum barriers for pressurized ceilings from
HVAC. Show and identify same on Plumbing drawings. This is to
include portions of normal building construction which forms a
part of the barrier. Include note on drawings referring to
Specifications for sealing of sleeves through the barriers or the
roof above.
Coordinate locations and requirements for roof and floor drains
for HVAC equipment. Verify need for automatic trap primer for
seasonally used drains such as at computer room AC units.
Wherever possible, do not locate floor drains in equipment
casings. If unavoidable, must provide special trap with seal at
Yeast 4" deeper than maximum static pressure in casing.
Obtain from HVAC Department location of floor drains which will
be carrying cold condensate from cooling coils, etc. — Specify
insulation for body of all such floor drains and horizontal drain
piping from same.
Coordinate horizontal piping with HVAC.
Dimensionally coordinate underground work with HVAC.
Advise HVAC of steam requirements for plumbing items, e.g.:
steam and water mixing valves, domestic hot water heaters.
Coordinate control requirements for steam domestic hot water
heaters and domestic hot water circulating pumps; by Plumbing
Contractor, by equipment manufacturer, by Section 15900. Refer
to P15400 re: instantaneous heaters.
Advise HVAC of smoke vent requirements for direct-fired (gas,
oi1) plumbing equipment.
ID-7 of 19Plumbing/HVAC Coordination (Cont'd.)
(Revised 2/26/88)
Betas
EICi C2
C1cicd
Catigd
C1cici
1/1/87
Advise HVAC of heating requirements to prevent plumbing piping
from freezing, e.g.: tunnels, normally unheated passages,
ceiling cavity of overhangs/canopies, etc.
Obtain boiler walkway locations from HVAC and maintain required
headroom.
Coordinate writing of Specification Sections 15050, 16140, 15210,
15240, 15250, and 15900.
*Coordinate locations of plumbing system vents, medical-surgical
vacuum system vents, etc., with location of HVAC system fresh air
intakes per plumbing code, DHHS No. (HRS-M-HF) 84-1, etc.
Typically must be 25 feet from fresh air intakes, but can be
located as close as 10 feet if vents are extended above top of
fresh air intake.
1D-8 of 19
*Revised 2/26/88C1
Cl
C1
C1
C1
Cl
C1
Cl
C1
C1
C]
Cl
Cl
C]
Cl
Cd
C1
C1
C1
C]
Cl
It
Lie
tJ
Cl
Cl
C]
C1
az
C1
6/11/87
*Revised
Cl
Cl
C1
C1
Cl
Cl
ed
C]
C1
Cl]
C1
Cl
HVAC/P1umbing Coordination
Revised 2/26/88
Advise Plumbing of all HVAC domestic water requirements, e.g.,
system fill, cooling tower makeup, humidifier for computer room
AC units, other water humidifiers. (Cooling tower = 3% based on
1% evaporation, 1% bleed, 0.1% drift and safety.) Coordinate
Jocation of services and start stop points of HVAC and PD
contracts.
Same as above for gas.
Domestic water piping to HVAC system must have backflow
preventer. Coordinate location with Plumbing and determine who
furnishes. same - HVAC or Plumbing, usually Plumbing at one
location in each Nechanical Room.
Advise Plumbing of location of plenum barriers for pressurized
ceilings. This is to include portions of normal building
construction which forms a part of the barrier.
Coordinate locations and requirements for roof and floor drains
for HVAC equipment. Determine need for automatic trap primer for
seasonally used drains, such as at computer room AC units.
Wherever possible, do not locate floor drains in equipment
casings. If unavoidable, must provide special trap with seal at
least 4" deeper than maximum static pressure in casing.
Advise Plumbing Department which floor drains will be carrying
cold condensate from cooling coils, etc.
Kitchens usually have one or more steam and water mixing valves.
Check Plumbing for location and provide steam connection (with
PRV if required).
Dimensionally coordinate underground work.
Obtain energy requirements from Plumbing for water heating.
Provide smoke vents for direct fired plumbing equipment.
Coordinate with Plumbing for makeup water treatment for high
makeup steam jennies/boilers - by Plumbing or Section 15342.
Treatment required to minimize maintenance.
Advise Plumbing of boiler walkway location.
Coordinate writing of specification sections 15050, 15140, 15210,
15240, 15250, 15900.
*Coordinate location of fresh air intakes with plumbing system
vents. (Refer to Section ID page 8 of 19.)
IE-10 of 31
2/26/88Cl
Cl
t)
Cl
Cd
Cl
C)
ed
cz
Cj
Ci
C1
Cl
Cj
Ci
|
1
Cl
C)
Cj
C1
01
1/7/87
C1
Cr
{i
Cl
01
o]
Cl]
Cj
i)
0]
C1
Plumbing/Structural Coordination
Coordinate equipment weight and size of all equipment pads with
Structural Department. Where oversized pads are required to
distribute load, locate and size dimensionally in the drawings.
Determine need for Type 2 foundation pad. Show on drawings.
Advise Structural of any depressed slab requirements for toilets,
kitchen, etc.
Coordinate detail for installation of floor drains in pan
construction.
Consult with Structural for location of roof drains in flat
roofs, precast roofs, etc. to be sure that drains are not at high
points.
Coordinate location of sleeves through structural members.
Consult with structural for pitching of floors in parking and
service garages to floor drains. Do not allow Architect or
Structural to design without adequate pitch.
Pipe Anchors must be approved by Structural.
Coordinate location of all underground piping with Structural
footings, grade beams, etc.
When bar joist construction is used (avoid where possible)
coordinate and detail location and method of support for
suspended piping and equipment.
Coordinate method of support for piping/equipment from existing
concrete structures.
10-9 of 19Citi
ba Go
cad
C1cj
cic)
CIed
EE
Dac]
CIE]
Citi
c1td
Cats
Tid tol
1/1/87
Cl
Cl
i]
{1
Ct
C1
tl
Cj
Cl
Ct]
Cl
Cl
Cl
Plumbing General Design
Get chemical analysis of domestic water supply to determine need
for water softeners and chemical treatment.
Be sure that all mechanical equipment can be moved into and out
of the building after structure is completed. Check door sizes,
provide knockout panels, etc. as required.
Consider sleeving of structural members where space is limited.
Coordinate with structural.
Where building construction will occur in "phases", consider
Owner's intended use of each phase in designing for connection of
new systems to existing, removal or abandonment of existing
systems and equipment, etc. System should be designed so that
each phase can be operable independently of other phases and will
not be affected by construction or changes in other phases.
Coordinate with Architect.
Furnish Estimator with complete data for all equipment and
furnish them with prices where special equipment, controls, etc.
will be used.
Review all special or new construction details with Quality
Assurance Engineer before showing same on drawings.
AN] floors in parking and service garages must pitch adequately
to floor drains. Do not allow Architects or Structural to design
without adequate pitch.
Show north arrow on all drawings.
Follow standard legends exactly and use schedule headings.
Use a minimum of horizontal above ground piping in complicated
buildings, such as hospitals and laboratories.
Prepare a brochure of manufacturer's cuts for all plumbing
fixtures and trim to be used. Obtain approval of same from
Architect and Owner.
Do not do any site work without a proper and accurate site survey
from the Architect.
Do not use the phrases "By Plumbing Contractor", or “By Heating
Contractor", "By General Contractor", etc. In all such phrases
unavailable use the work "Section" instead of the word
"Contractor".
ID-10 of 19Plumbing General Design (Cont'd.)
12 3
ciciti
cicicti
C1Cit1
7/1/87
Make notations on the drawings to indicate provisions for future
expansion so we do not have to guess if we do the expansion.
When building is designed structurally for vertical expansion,
plumbing risers should also be so designed.
For laundries average rates of 4 to 6 gallons of water per pound
of laundry are satisfactory to use when designing an overall
water supply system or when selecting storage type hot water
heaters. When designing the piping adjacent to the washers and
when selecting instantaneous type heaters for the washers obtain
the fill rate of the washer from the equipment manufacturer and
design accordingly. For example, a fill rate of 300 gallons in
1-1/2 minutes requires design for a flow rate of 200 gallons per
minute even though the fill cycle may occur only once every 30
minutes.
‘Above concept also applies to: dishwashers, glass washers, cage
washers, etc.
ID-11 of 19ccd
citi
C101
C10]
C1td
[eee Oat
C101
C10)
CICY
LIC)
Citi
Citi
C11
1/1/87
0
C)
C1
cd
C1
C1
Cl
C1
Gd
C
Plumbing Section 15051
Use a minimum of horizontal above ground piping in complicated
buildings, e.g., hospitals and laboratories.
Group valves and accessories and equipment for easy access.
Check for access door/panel requirements for same.
Location of equipment on flow diagrams should be realistic to
relation in building. All control valves, sectionalizing valves
and accessories to be shown on flow diagrams. Show equipment and
accessory valving only on items not detailed. Indicate reference
to special equipment and accessory details on flow diagrams.
Show all piping system sectionalizing valves on drawings.
Check all piping, including traps on sanitary and storm piping,
over exposed areas such as balconies, tunnels, canopies,
passages, etc. for freezing. Provide insulation and electric
pipe line heating or have HVAC provide heating elements in cavity
as required to prevent freezing.
Do not design piping to run in or through electrical rooms,
telephone rooms, elevator equipment rooms, or elevator shafts.
Piping in existing shafts converted to elevator shafts has to be
removed.
When a pressure pumping system is provided in a building with a
dual water supply, both supplies must be connected to the suction
side of the pumping system.
Provide approved backflow preventer in domestic water connection
to lawn sprinkler systems.
Provide connections and sprinklers and flushing valves in laundry
and trash chutes. (Note: Valves are often specified with the
chutes. Coordinate with Architects.)
There must be a minimum of 7'- 0" clearance under piping over
boiler walkways.
For Hospitals, verify use of ethylene oxide sterilizers and
provide proper drainage. Advise HVAC.
For Hospitals, refer to HHS requirements on drainage piping in or
over sensitive areas.
10-12 of 19Plumbing Section 15050--Piping/Basic Materials and Methods (Cont'd.)
12 3
LILIL J] Indicate location of water hanmer arrestors (shock absorbers) for
jaundry equipment on drawings. Consult manufacturer with regard
to sizing and location. General Note “Provide water hammer
arrestors (shock absorbers) as required" is often
satisfactory.
L1£11£1 In locating laundry water hammer arrestors, provide one at both
the hot and cold water connection to the washer as a minimum, and
investigate need at changes in direction of the piping
near the washers.
1/7/87 ID-13 of 19123)
FICI£CF
CiCitl
Ciciti
1/7/87
Consider noise and vibration in selecting and locating equipment.
Check inertia pad requirements for all equipment. Usually
required for pumps, compressors, etc., above ground floor.
Sometimes required for floor on gradi
Include isolation requirements in specification
or drawing
schedules.
ID-14 of 19tg
cicictd
CIG16)
CUCIe!
1/1/87
Plumbing Section 15300--Special Systems
All incinerators and certain sizes of other fuel burning
equipment must have approval of Air Pollution Agency. Check code
regulations and obtain approval as required.
Provide suitable water treatment for water supply to electrically
operated sterilizers. Hardness in the water can cause spotting
on the instruments and maintenance problems with the heating
element.
Above applies to once through electrically-operated steam
Jennies/boilers - coordinate with HVAC.
ID-15 of 19a)
C1010)
CxerLd
C1070)
1/1/87
Plumbing Section 15400--Pumbing Systems
Kitchens usually require steam and water mixing valves, at least
in can wash area. Check with Architect. Specify proper valve
h_hosé
Use Lawler 2059 or equivalent pressure equalizer on water piping
to Beauty Salons.
A. steam-to-water convertor with conventional steam contro] valve
can not be used for generating domestic hot water except in
Gnstances where there is no danger of scalding by personal or
animal contact, such as in dishwasher booster heaters or cage
washers, because the time lag on the control is such that
scalding water temperatures can be reached, particularly when
flows are small. All domestic hot water heating systems for
people or animal use must have either a control system that
anticipates the domestic water demand or storage.
ID-16 of 1912 3
ticici
C1010]
C1010)
Cae
CitjACI
CiCit)
Ciciti
tific
7/1/87
Plumbing Section 15450--Plumbing Fixtures and Trim
Junior water closets in Elementary Schools.
Provide service sink in all large Boiler and Mechanical Rooms.
Health codes usually require “Mixing” faucets in lavs used by
restaurant kitchen help.
Check depressed slab requirements for toilets, kitchens, etc.
Coordinate with Architectural/Structural.
Check plumbing trim specifications on tubs with Architect to see
if showers are required.
Provide sediment (barium, plaster) traps in X-Ray Rooms.
Obtain Owner and Architect approval for types of fixtures and
trim to be used. Reconmended access space for single battery of
wall-hung fixtures is 2 feet, and 3 feet for double battery.
Minimum dimensions for above are 1 foot 8 inches and 2 feet 6
inches, respectively. Locate riser to allow access into pipe
space from access doors.
Access space must be provided for concealed type flush valves.
10-17 of 19aHieuHs
a ETEI
C1Cit]
Coc f7
7/1/87
Plumbing Section 1! ire Protection
Provide sprinklers in linen and trash collecting rooms.
Underwriters require bypass around fire pumps.
Show location of drain points for sprinkler systems. Provide and
show hub drains as required to pick up drain points.
1D-18 of 191 2 @
C1CI0]
1/1/87
Review Plumbing automatic controls with HVAC and incorporate in
ATC Section of HVAC where feasible, e.g.: controls for domestic
hot water recirculating pump and its occupied/unoccupied control;
domestic water heater controls not provided by equipment
manufacturer.
10-19 of 19HVAC/PLUMBING COORDINATION
PROJECT
JOB. NO,
DATE
ELEC, PLUMBING
MAKE-UP WATER TO LOCATION PM
HVAC EQUIPMENT
To:
CONDENSATE DRAINS
FROM: : LOCATION DISCHARGE TO
FLOOR OR FUNNEL DRAINS LOCATION
FOR HVAC EQUIP. DRAINS
FOR: : :
BOILER WATER OR STEAM :
HEATED HW GENERATORS REQUIRED RECOVERY STEAM ‘BOILER WATER
GPM IN. OUT
3 =f
GAS-FIRED ‘i LOCATION BTU INPUT
HEATING EQUIPMENT10.
li:
2,
13.
4
ARCHITECTURAL/ PLUMBING COORDINATION
Location and type of plumbing fixtures to be installed.
Location of any Hhumures tn te ase ty Hhaadiensyed serous.
Requirements for any equipment to be furnished by Architect or Owner, and
requiring plumbing services.
Location and size of pipe chases.
Location of vents thru roof.
Location of roof drains. z t
h sinks to be installed in case work.
Confirmation of who will fur
Details of floor “or deck construction where waterproofing or’ finish surface may
requite special drains.
Name’ of Owners! insuring agency, when fire suppressions systems are required.
Coordination regarding flashing, excavation, final grading: and concrete pads or
foundations. ag
‘i t
Location of any equipment such as control panels, alarm panels, valve boxes, to be
recessed in walls. =
Floor.elevations and finished grade elevations surrounding the building.
Responsibility for foundation drainage system, when required.
Review fire suppresion system requirements contained in Building Codes.
= i