C1
Cl
Cl
Cj
Cj
td
ci
C1
C1
0]
C]
i
Cd
Ed
6/11/87
Ga
Cl
C1
C1
C1
C1
i)
Cl
C1
Cl
Cl
C]
HVAC Section 15050 - Piping/Sasic Materials and Methods
Location of equipment on flow diagrams should be realistic to
relation in building. All control valves, sectioning valves and
accessories to be shown on flow diagrams. Show equipment and
accessory valving only on items not detailed. Indicate reference
to special equipment and accessory details on flow diagram.
Show al] piping system sectionalizing valves on drawings.
Group valves and accessories and equipment for easy access.
Check for access door or panel requirements for same. Coordinate
with Architect.
Check a1] piping over exposed areas such as balconies, canopies,
or in unheated tunnels, passages, etc., for freezing. Provide
insulation, electric pipe line heating or heating elements in
cavity area as required to prevent freezing.
Do not design piping to run in or through electrical rooms,
telephone rooms, elevator equipment rooms, or elevator shafts.
Piping in existing shafts converted to elevator shafts has to be
removed.
Run condensate piping below floor in a trench (preferred) or
split T.C. to asingle, remote condensate pump for kitchens,
Jaundries, etc., in lieu of numerous small pumps located on floor
at equipment. ‘Check for possibility of lifting condensate to
ceiling ~ can usually be done with bucket or Tift trap, if steam
pressure is high enough.
Carefully review clearance for ceiling mounted steam reheat coils
for proper condensate return (see standard trap piping details).
Condensate cannot be lifted from coil discharge and must flow by
gravity from coil to return main.
Steam supply to steam atomizing burners should be connected to
top of steam header, and not to boiler steam drum, to avoid
excessive moisture.
Provide demand limiter when using steam absorption refrigeration
on purchased steam.
For all purchased steam systems, contact utility to review all
service piping and to obtain dimensional requirements for meter
and expansion and contraction dimensions and arrangements.
‘Steam supply to laundry ironers should have 3/4 inch globe valve
bypass around main supply valve for warmup of ironer.
IE-16 of 31HVAC Section 15050 - Piping/Basic Materials and Methods (Cont'd).
a
CJ
iE
[p)
ca
Cl
te
cl
Cl
Ci
|
i)
2 3
C10]
C101
Citi
C10)
£10]
Citi
C1Cl]
C101
EJ LI
C10)
Cit)
6/11/87
Check for relief or three-way valve requirements at end of
multiple two-way control valve circuits. Include in ATC.
Check head of existing pumps when connecting to existing systems
and check hydraulics of existing system.
When using three-way valves to reset hot water supply to multiple
zones, do not combine zone returns until after they have passed
the control valve,
Do not combine reheat system piping (140°F. max.) with seasonal
heating system piping, Use separate systems and pumps.
Multiple cooling towers with common supply and suction headers
must have an equalizing line between towers with shutoff valves
to each tower for maintenance. Water level for all towers must
be the same. Check Tlevel carefully when adding new toner to
existing installations
If chiller has to be started with cold tower water (i.e.,
winterized water), provide damper control of air on tower, or
provide means to throttle flow, bypass tower or bypass chiller so
chiller can be started up easily.
If three-way valve is used to bypass cooling water flow from
tower to suction side of pumps, provide check valve to prevent
backflow and/or system draining; in tower suction if tower outlet
js below top of three-way valve; on discharge of three-way valve
if tower outlet is above valve.
Pipe refrigerant relief valves from halon protected computer room
AC equipment to outdoors. (A refrigerant leak at this relief
valve can cause the halon system to discharge.)
Safety Code for Mechanical Refrigerant requires that all
refrigerant relief valves (and rupture disc openings) be piped to
outdoors except when equipment is installed in large mechanical
rooms. You can have a problem, however, even in larger rooms if
equipment is large. Pipe all to outdoors.
In alteration work, clarify on drawings and in specifications
whether or not drain pans are to be provided under existing
piping over electrical equipment, or if it is to be relocated,
etc.
Do not use bullhead tees.
IE-17 of 31Section 15050 - HVAC Piping/Basic Materials and Methods (Cont'd).
18
L1CIC£ 1 Verify reviewing agency's interpretation ‘of plumbing
condensate drainage from fan coil, heat pump, etc.,
e.
.,. need for drainage type "Y" fittings at branch connections,
"Y" Fittings and cleanouts at changes in direction, cleanouts at
base and intermediate floors of vertical drain lines
have Plumbing design and shown on their drawings.
agency's ruling in writing.
C1L1L 1 For Hospitals, refer to HHS "Plumbing" section for limitations on
“drainage” piping in or over sensitive areas.
L1L1£1 There must be 7 feet minimum clearance over boiler walkways.
6/11/87 IE-18 of 3112 3
C101t)
Citic)
C1010]
ficici
6/11/87
Section 15140 - HVAC Pumps
Do not locate condensate return pumps in kitchens and laundries
(See HVAC Section 15050).
Specify Mechanical seals on pumps serving systems using glycol-
water solutions.
Select pumps with impeller size not more than 85% of maximum
impeller size that will fit in pump casing.
Pumps in Parallel: calculate not only the gpm and head condition
when all pumps are operating, but also the gpm and head condition
when one pump is operating by itself. Select a pump that can
operate satisfactorily at both points on its performance curve
and show both operating conditions in the pump schedule or add a
Griswald flow control valve in order to prevent surge conditions
and motor overloading when only one pump is running.
IE-19 of 31123
EJGJCI
Cifiti
Clcit]
CICICI
6/11/87
HVAC Section 15210 - Vibration and Noise Control
Consider noise and vibration in selecting and locating equipment.
Check inertia pad requirements for all equipment. Usually
required for all pumps, compressors, high pressure fans, etc.,
above ground floor, Sometimes required for floor on grade.
For curb mounted rooftop equipment, evaluate potential for noise
transmission through bottom of unit and roof into space below.
Consider providing air space and either acoustical material,
Vightweight concrete or standard weight concrete between roof and
bottom of unit.
Analyze the effect that noise generated by cooling tower,
evaporative cooler, condensing unit and other outdoor and/or
rooftop equipment may have on adjacent buildings. Building
owners are being sued by their neighbors for disruptive noise
being caused by such equipment.
1E-20 of 314 2 oe
LdGICI
C1cicti
Clcic]
C1Ci01
6/11/87
HVAC Section 15250 - Insulation
Insulate hot stacks, breechings, smoke vents, emergency generator
engine exhaust, etc., to minimize potential for injury due to
accidental contact and to reduce heat gain to equipment room or
occupied space through which it passes.
Insulate hot exhaust ducts (e.g., laundry dryer, range hood)
located in occupied spaces or ceiling air plenums to reduce heat
gain to space/plenum.
Insulate cold exhaust ducts (e.g., truck dock exhaust) running in
or through heated spaces to prevent condensation on exterior
surface and to reduce heat loss from space.
Consider need for insulation of exhaust ductwork from kitchens,
dishwashers, laundries and similar hot or high humidity areas to
minimize condensation on interior of ducts.
IE-21 of 3112 4
Cicf3 0]
CJCICI
C1cici
6/11/87
HVAC Section 15342 - Chemical Water Treatment
Get chemical analysis of domestic water supply from Plumbing to
determine need for water softeners and chemical treatment.
Specify chemical treatment on boiler feedwater and other HVAC
piping systems.
Provide suitable water treatment for water supply to once through
steam jennies/boilers. Hardness in the water can cause
maintenance problems with the heating element or surface.
Coordinate with plumbing.
IE-22 of 3112 3
CILI04
Ciciti
C1Ci01
CILICt
CICI0I
fa C309
6/11/87
HVAC Section 15600 - Power or Heat Generation
Check boiler feed system and deaerator flow quantity. Must
usually provide a surge tank for discharge.
Determine need for manhole pits for fuel oi] tanks to be provided
with drain lines connected either to a French drain (preferred)
or toa storm drain line. In latter case, design must be such
that storm water cannot back up into pit. Where large pits are
required use multiple access openings so that cover can be lifted
by one man.
Check code requirements for boiler walkways. Required in
Pennsylvania and frequently necessary in other locations for
boilers with top more than & feet above floor.
Boiler walkways must clear all boiler access doors, cleanout
doors, etc. There must be 7 feet minimum clearance over boiler
walkways.
Pennsylvania Boiler Code requires that relief valve from low
pressure steam boiler of greater than 500 pounds per hour
capacity be piped to outdoors for boilers serving places of
public assembly or apartment houses of five or more families.
Specify high water cut off and alarm, jin addition to low water
devices, or high pressure boilers.
1€-23 of 31212 8
C1010)
Cicicti
Cicicti
CiCi01
ClCic]
LICIC]
6/11/87
HVAC Section 15650 - Refrigeration
liherever possible, use high efficiency chillers. Analyze the use
of reduced gpm for condenser water, e.g., 2 gpm/ton rather than 3
gpm/ton. Although this will increase chiller kW/ton and cooling
tower size, these increases can often be offset by savings in
condenser pump energy consumption.
Consider the use of two speed motors on cooling towers. Verify
proper water distribution at low speed. The tower will operate
on low speed approximately 90% of the time with horsepower only
about 15% of nameplalte rating. Operation at low speed will also
reduce the noise level of the tower.
Specify cooling towers for ambient air WB design at least 1° F.,
higher than ASHRAE 1% summer peak WB condition.
Check cooling tower location for short circuiting of discharge
air to intakes. Raise tower, provide discharge duct, etc.
When specifying packaged equipment with DX coils, compressors and
air cooled condensors carefully determine condensing temperature
you wish to use. Manufacturers can provide equipment having
condensing temperatures in the range of approximately 118° to
130°, If not specified, they will probably use 130° with a
resultant low EER. here the project budget allows, specify
condensing temperature of 118° to 120° to improve efficiency of
unit.
Note on drawings that refrigerant relief from chiller(s) is to be
piped to outdoors. Indicate size and show location of run if,
equipment room does not have an outside wall.
IE-24 of 31124
C1010]
CILIC9
CIGIC
CIE]
CIEI Ca
CICICI
C1cicti
6/11/87
HVAC Section 15700 - Heat Transfer
On job built units, provide sufficient clearance between cooling
and reheat coils to prevent moisture carryover and reevaporation
on surface of reheat coil.
When using "Incremental" units in hospitals, the following items
must be incorporated in the design:
1. Outside air damper closes on power failure or when unit is
turned off.
2, Condenser fan must run on both heating and cooling cycle to
provide ventilation all times unit is in operation.
3. Provide either direct exhaust from room (through toilet or
separate exhaust system) or specify special exhaust
accessories with unit.
4, Provide self-contained control valve for heating control.
5. Provide silent solenoid valve on heating supply. Valve to
be normally open type and is to open on power failure, -when
unit is turned off, and when unit is placed in heating
cycle.
Select converters for 2 psig and consider channel heads.
Wall fresh air intakes for fan coil units must have snow baffles.
Avoid fresh air intakes if possible by providing ducted
ventilation air to room or unit.
Verify that fan coil unit enclosure has sufficient space to
install control valves and shutoff valves. Some manufacturers do
not, especially for 4 pipe systems.
Analyze the relative humidity of heat recovery coil exhaust air
in relationship to the temperature of the water in the coil to
determine whether or not there is the possibility of condensation
on the heat recovery coil. If so, coil must be located in a
vertical position with horizontal air flow and provided with a
drain pan and drain piping for collecting the condensate.
Review humidifier installation "Do's and Don't's" in “The
Armstrong Humidification Handbook". For humidifiers upstream of
coils, fan inlets and discharge grilles, elbows, etc., increase: 3
feet minimum to 6 feet minimum, 8 feet preferred, if air
temperature is less than 80° F, Indicate the minimum dimension
by notes on drawings.
1E-25 of 31HVAC Section 15700 - Heat Transfer (Cont'd)
Pet
c1cicti
C1cicti
CICIC4
ClCictl
Cicicti
6/11/87
When sizing humidifiers, consider both the "winter" condition and
‘the "economy cycle" condition. The “free cooling" available
during the “economy cycle" can result in a need for more
humidification than during the "winter" condition at minimum
outdoor air (Refer to data in "The Armstrong Humidification
Handbook".). Depending on the cost per kilowatt-hour for chiller
operation and the cost per thousand pounds of steam, it may be
less expensive to run the chiller than to use the "economy
cycle", but get Owner approval before making this decision.
Philadelphia Fire Code requires that unit heaters in garage
buildings be no less than 8 feet off floor.
Do not use short pieces of radiation under long windows. Use low
capacity radiation so that finned surface extends full length at
glass. Provide individual room control if this results in excess
radiation capacity.
Manual damper on all perimeter radiation if individual room
control is not provided. Coordinate with Architect if enclosure
is by G.C
When gas fired equipment is used on roof, utility companies often
require permanent access to roof, walkways from acess to
equipment and overhead weather protection (lean-to) at equipment.
Check with Utility Company and coordinate with Architect.
Where multiple coils are used on built-up units, note on drawings
that coils are to be installed so as to be individually
removable.
1E-26 of 31citi
Cit]
Citi
cicl
cic)
tic]
Cit]
C10]
ciel
6/11/87
Cl
ti
Cl
Cl
Cl
Cal
C1
Cj
C1
HVAC Section 15800 - Air Distribu
on
Review "Industrial Ventilation" manual for applicability.
Verify applicability of NFPA 90A. Even if not applicable, comply
with requirements that are not in contradiction to applicable
Building, Mechanical and Fire Codes.
Do check code requirements for smoke dampers and for fire dampers
in one hour rated corridors. (BOCA, Life Safety Codes)
Show all fire and smoke dampers on drawings. Verify conformance
to applicable codes - Building, Mechanical, Fire, Life Safety.
For plaster and similar inaccessible ceilings be certain that an
access panel is provided in the ceiling for access to the damper.
Appendix C of NFPA 90A (not a part of code) recommends that
supply and exhaust ducts for a smoke control system not pass
through another smoke zone and recommends minimum duct gauges
when this is unavoidable of: 24 ga for ducts up to 8 inches, 22
ga for 8 inches to 18 inches, 20 ga for 18 inches to 30 inches
and 18 ga for over 30 inches. Note this on drawings or in
specifications.
NFPA 90A requires fire dampers in outside air intakes which are
“high hazard". By an administrative ruling, the City of
Philadelphia considers any outside air intake which is within 35
feet of grade or an adjacent building or a parking lot or similar
hazardous areas as “high hazard" and therefore these outside air
intakes require fire dampers.
Show duct mounted smoke detectors in a location of relatively
nonturbulent air flow and within the rated operating range
(verify, usually 300 to 4,000 fpm). Whenever possible locate
detectors a minimum of six duct widths downstream from bends or
inlets, so that dampers do not restrict air flow at the detector
location, downstream of filters, upstream of humidifiers and
cooling ‘coils, where they can be conveniently observed and
readily serviced.
Kitchen exhaust systems must comply with applicable Building,
Mechanical and Fire Codes and with NFPA 96. Note requirements
for enclosure of both horizontal and vertical ducts and
coordinate with Architect. Comply fully with all requirements
for minimum duct and hood velocities.
Comply with Air Management Services requirements for garage
ventilation. (In Philadelphia 450 cfm per car min. for one level
garage.)
IE-27 of 31HAC Section 15800 - Air Distribution (Cont'd. )
12
C10]
Citi
C101
Cit]
Citi
citi
Citi
cicd
citi
C10]
C101
Citi
6/11/87
3
Cl
fa
Ca
ol
Cl
Cl
t]
C1
ca
Cl
Cl
C1
Consider space required for making standing seams and for
installing insulation when laying out and sizing ductwork -
particularly important in concrete structures.
There should be a minimum of 8 inches to 12 inches clearance
either above or below all ducts run in ventilating ceilings or
ceiling return air plenums.
Determine whether or not smudge rings required at diffusers.
Provide drain pans under all roof intake or exhaust hoods, etc.
Where such items are duct connected or installed at the top of a
shaft, provide drains in the bottom of the vertical duct or
shaft.
Provide skimmer exhaust registers at ceiling in dishwasher area
jn addition to ducts to dishwasher - see Industrial Ventilation
for cfm and arrangement. Drawings for dishwasher exhaust ducts
should call for watertight construction of aluminum and show the
duct pitched for drainage.
Ventilate (30AC min.) equipment rooms for recessed sterilizers
and provide exhaust registers (stainless steel) over doors of
recessed sterilizers to transfer exhaust to equipment room.
Coordinate with hood. Usually registers and hood by GC, but
Architect must be advised to provide same. Check Architectural
Drawings for confirmation.
Do not use any part of the building structure to form any
pressure part of a built-up air-conditioning unit apparatus
casing. Building structure can be used to form part of casing
only for outside air intake.
Try to avoid using "building structure" for air shafts. Refer to
AABC data for more information.
Indicate all streamlined ductwork on the drawings.
On multiple zone units, the flexible connection should be located
after the first elbow, not on the unit discharge. Show balancing
damper for each zone duct. | Show access doors in ducts for
balancing dampers and unit zone dampers.
Fan discharge diffuser plates must have 1-1/2 inch holes.
Built-up cooling coils require casing length of approximately 4
feet 4 inches in direction of air flow.
IE-28 of 31HVAC Section 15800 - Air Distribution (Cont'd.)
Cit)
Cit]
c1c1
Citi
Cicd
EAC
citi
cle)
titi
tic)
Citi
C1cl
6/11/87
Cl
Cl
Ci
Cd
Cl
C1
C1
C1
Ed
C1
fa
01
Coils and related piping in built-up units should be indicated as
removable on drawings. Section of casing should also be noted as
removable if necessary.
Provide minimum outside air dampers for all systems handling over
10,000 cfm outside air.
Supply and exhaust ducts to Radiology Rooms may require lead
protection. Be certain that this is covered either by Architect
fin his specifications or by HVAC drawings and specifications.
Consider: using lead lined return grilles (Atomic Industries,
Inc.); running vertical ducts on room side of room lining.
For electrically shielded, grounded, isolated rooms, connect
grilles and diffusers to ductwork with canvas connections void of
any wire to ensure that there are no electrically conductive
pathways from the ductwork to the shielded room.
Verify that radiological hoods have absolute filters or provide
same in duct at hood connections.
Hospitals: Verify use of ethylene oxide sterilizers. Provide
proper exhaust. Make sure Plumbing knows about how to handle
drainage properly.
On high and medium pressure duct systems, all apparatus casings
and all supply ductwork up to and including at least the first
fire damper in each supply duct must be of high pressure
construction.
Use standard block sizes for grilles, diffusers, etc., in block
walls that are not to be finished with plaster or tile.
If duct or casing access doors are not of standard size (see
specifications), show size on drawings.
For vaneaxial controllable pitch fans, show duct access doors on
both sides of the fan to get to the controls and bearings that
must be serviced.
Exhaust ducts from laundries should have a large number of access
doors shown throughout the run of the duct to provide access for
cleaning.
Laundry exhaust ducts from dryers must have means of trapping
Tint.
1E-29 of 31HVAC Section 15800 - Air Distribution (Cont'd.)
i 2
TCT EICI
GICd
C10)
Citi
C10)
C10]
C10)
Citi
Fatd
C101
Clcl
6/11/87
3
C1
C1
Ci
Cd
C]
Cy
C1
C1
Cl
Exhaust ductwork discharge from hot and humid areas, such as
Kitchens and Laundries, should be exhausted through the roof and
should be located ‘to minimize aesthetic problems due to
condensation from their exhausts in cold weather.
Use totally enclosed motors on barn exhaust fans which have the
motor in the air stream (acid from animal urine gets into air
stream and may corrode motor on an open motor).
Coordinate discharge and intake louvers with Architect for size,
type, SP drop and insect screens. Check Architectural and
Mechanical Drawings for correctness. No insect screens at louver
on the following:
1. Qutside air intakes to units that have filters.
2. Exhaust outlets having automatic or gravity dampers.
3. Outside air intakes that have dampers mounted at the louver.
Provide filters on outside air intakes that serve or are located
so that air will pass through electrical equipment rooms.
For outside air intakes with dampers which are not either
provided with filters or ducted to unit with filters, specify and
show on drawings a removable insect screen on room side of
damper.
Use volume balancing dampers, not splitter dampers. Show all on
drawings. (Refer to ductwork design standards.)
For large systems with volume control boxes, constant volume or
VAV. Provide volume damper or orifice at least 12 feet upstream
of box if inlet SP will be greater than 3 inch wg.
Do not design ductwork not specifically related to the room to
run in or through electrical rooms, telephone rooms, elevator
equipment rooms.
Do not run ductwork in or through elevator shafts.
Determine air balance for each system, each floor and total
building. Total building must be under positive pressure.
Check location of all kitchen refrigeration equipment. Check
exhaust requirements with manufacturer and provide ducted
exhaust.
IE-30 of 31Teese)
CILIGI
Ciciti
Ciciti
C1010)
C1010]
CICICI
t1C1C]i
f7CICI
6/11/87
HVAC Section 15900 - Controls and Instrumentation
Make all automatic controls as simple as possible to meet job
requirements
Show 11 room thermostats and humidistats on the Drawings.
Review thermostat and humidistat locations and types, HVAC zones,
etc., with Owner.
Include plumbing controls under ATC where feasible.
Dual temperature piping systems require safety changeover
controls from heating to cooling to prevent hot water from
reaching chiller.
Show location of all local and central control panels on
drawings. Coordinate local locations with Architect and Interior
Designer.
Provide automatic control valves to close when outdoor exceeds
65° F. when connecting "Heating Only" equipment to a 4 pipe
system heating circuit. | Select equipment for appropriate low
water temperature.
A steam to water convertor with conventional steam control valve
cannot be used for generating domestic hot water except in
jnstances where there is no danger of scalding by personal or
animal contact, such as in dishwasher booster heaters or perhaps
even cage washers, because the time lag on the control is such
that scalding water temperatures can be reached, particularly
when flows are small. All domestic hot water heating systems for
"people" or animal use must have either a control system that
anticipates the domestic water demand or storage.
IE-31 of 31C10)
cea
EXER
C1cti
C101
C10)
Cit]
Clic]
Citi
6/11/87
01
tl
C]
Cl
C1
C1
Cl
Cl
C1
HVAC Electrical Coordination
Coordinate control, alarm and power wiring with Electrical and
HVAC specifications. Clarify who does alarm wiring - Electrical
or HVAC Contractor.
Coordinate locations of starting switches for manually started
equipment, e.g., remote start/stop push button station with pilot
Tight for exhaust fans. Use maintained contact control for fans
or equipment which should be automatically restarted after a
power failure, e.g., exhaust fan for flammable liquid storage
room. Consider locating switch in room the equipment serves,
e.g., range hood exhaust fan switch located near hood, or
adjacent to the main ATC panel or Motor Control Center and/or
including the remote start/stop on the ATC panel. Review all
with Owner to determine his requirements/preferences.
Prepare Electrical coordination sheet, review with Electrical and
review HPE drawings. Often forgotten are: water treatment, ATC
compressor, heaters for oil tanks, snow melting fill pum,
control panels.
Advise Electrical of location of plenum barriers for pressurized
ceilings. This is to ‘include portions of normal building
construction which form a part of the barrier. Be sure that the
barriers are shown on the Electrical Drawings and that Electrical
Department covers sealing of all penetrations on their drawings
or specs.
Exhaust fan for emergency generator must be supplied with power
from the emergency system. (Used when generator exhaust is not
ducted to outside.)
District steam meter needs electrical service. Coordinate with
Electrical as to who furnishes and wires.
Dimensionally coordinate underground mechanical and electrical
work if they are close to or cross each other
Dimensionally coordinate ductwork at crossings of electrical
cable tray/bus duct.
Verify that emergency generator is located so that you can get
radiator cooling air into and out of room. If the generator is
so located that it is not possible to get radiator air into and
out of the generator room for an air cooled unit, but can get
enough air to offset engine radiation losses (approximately 50%
of total), then use a remote radiator with antifreeze circulating
system and circulating pump. The pump must be tied into the
emergency generator, as well as the remote radiator fan. Provide
design, sketches, specifications for mechanical items associated
with generators per company policy.
1E-8 of 31HVAC Electrical Coordination (Cont'd. )
Tez
Cicicti
C1icici
tic1c1
£IEICI
LICICI
Clcit
EIbICI
Citic)
6/11/87
Provide lighting in large job built AC unit casings.
Coordinate smoke detectors and smoke dampers, especially control
of smoke partition dampers, with Electrical.
Do not run any piping or ductwork in or through electrical rooms,
telephone rooms, elevator equipment rooms, that are not
specifically related to that room. Coordinate any unavoidable
conditions with Electrical and Architect. (Provide "roof" over,
electrical room, drain pan under piping, etc.)
Do not run piping over Electrical equipment in Mechanical Rooms
(add note on HVAC drawings) or over electrical panels.
Coordinate unavoidable conditions with Electrical and Architect.
Advise Electrical of electric pipe line tracing required to
prevent HVAC piping from freezing.
Coordinate heating of electrical equipment rooms, elevator
equipment rooms - steam/hot water by Heating contractor or
electric by Electrical Contractor. —
Determine need from kitchen consultant of range hood exhaust (and
makeup air) interlock with hood fire protection system.
Coordinate with Electrical and ATC.
Codes usually require that Boiler Rooms be provided with an
emergency shutoff switch near exits to shut off the boiler(s)
(and oil fired domestic water heaters) in the event of an
emergency situation. Coordinate with Electrical on each project
to be certain that it is properly covered by HVAC or Electrical.
Coordinate with Plumbing if room also has domestic water heater.
IE-9 of 31