Professional Documents
Culture Documents
Leader development models [1], [7]-[10] are based on the the critical electric field strength E0 used in leader
physical breakdown process of long air gaps which consists development models of CIGRE [1], Pigini et al. [8] and
of three phases: corona inception, streamer propagation and Motoyama [9], [10] and finally the critical disruptive effect
leader propagation. Thus, the time to flashover, tc, is DE, minimum voltage U0 and constant K used in the
determined by the expression integration method [4]-[6]. The user also selects the insulator
string flashover model to be used in simulations, by assigning
tc ti ts tl (3) a value to the parameter model selection MS, ranging from
1 to 6 as provided, together with the description of the input
parameters, in the help viewer window of the object. Values
where ti is the corona inception time commonly assumed
for the input parameters required to use the leader
equal to zero, ts is the streamer propagation time and tl is the
development models (Table I) can be estimated from
leader propagation time.
Appendix A.
When the average gradient in the gap becomes equal to a
The ISF object was applied to simulate the flashover of a
critical value, E0, the streamers are considered to bridge the
typical insulator string of the 150 kV lines of the Hellenic
gap and the streamer propagation phase is completed.
transmission system with standard lightning impulse
Subsequently, the leader starts propagating and flashover
withstand voltage level of 750 kV and length of 1.86 m.
occurs when the leader bridges the gap. However, if the
average electric field strength in the unbridged part of the gap
becomes lower than the critical value E0 the leader stops
developing and flashover does not occur. Several expressions,
derived from experimental investigations, have been
proposed yielding leader velocity as a function of the applied
voltage and length of the unbridged part of the gap. Such
expressions referring to insulator strings [1], [8] and rod-rod
gaps [7], [9], [10], are given in Table I.
III. ISF OBJECT
A new ATPDraw [11] object, called Insulator String
Flashover (ISF), has been developed by using MODELS
language [12], [13] within the ATP-EMTP [16] environment.
The ISF object implements the insulator string flashover
models detailed above by incorporating a MODEL that
controls a TACS Type 13 switch.
Fig. 1 shows the ATPDraw dialog box of the ISF object;
the user enters the input data, namely values for the insulator
string/gap length (D), the constants K1 and K2 used in Fig. 1. ATPDraw input dialog box of the developed ISF object.
Shindo and Suzuki leader development model [7], the
constant K3 used in CIGRE leader development model [1],
TABLE I
LEADER DEVELOPMENT MODELS
Fig. 4. Tower of typical 150 kV double circuit overhead lines of the Hellenic
transmission system and lightning stroke location considered in simulations.
Fig. 2. Volt-time characteristics of a 150 kV insulator string under standard parameters calculated at 500 kHz. Surge arresters were
lightning impulse voltages (1.2/50 ȝs) according to several insulator string represented by the Pinceti and Giannettoni frequency-
flashover models; standard lightning impulse withstand voltage level 750 kV, dependent model [19] as shown in Fig. 5, with parameters
insulator string length 1.86 m.
calculated based on the surge arrester characteristics given in
IV. APPLICATION OF THE ISF OBJECT FOR THE EVALUATION Table II. GIS bays were represented as lossless stub lines
OF BACKFLASHOVER SURGES IMPINGING ON SUBSTATIONS with a surge impedance of 75 ȍ [15]. The step-up transformer
The ISF object was employed in ATP-EMTP [16] was represented by a capacitance pi-circuit together with a
simulations for the evaluation of the backflashover surges BCTRAN model. Cable connections and the surge arrester
impinging on a 150 kV GIS substation, with configuration lead lengths shorter than 3 m were modeled by a lumped
shown in Fig. 3. Simulations were performed for the parameter inductance of 1 ȝH/m [15].
following worst case scenario: negative lightning is assumed Finally, simulations were performed with and without
to strike to the top of the first tower (Fig. 4) close to the surge arresters operating at the line-cable junction so as to
substation, at the time instant of positive power-frequency evaluate the protection offered against impinging surges with
voltage peak of the upper phase of the overhead transmission respect to the basic insulation level, BIL, of the GIS system
line. (750 kV), considering also a safety factor of 1.15 [20].
Lightning stroke was represented by a current source
producing a current with an amplitude of 200 kA and a
waveshape 8/77.5 ȝs with front upwardly concave and
maximum steepness calculated according to [1]. The last
section of the incoming overhead transmission line, 1.75 km
in length, was represented by a sequence of J.Marti
frequency-dependent models, considering the line span (350
m) and tower geometry (Fig. 4). Towers were modeled as
vertical lossless single-phase frequency-independent
Fig. 5. Frequency-dependent surge arrester model [19]; parameters
distributed parameter lines with a surge impedance of 167 ȍ calculated based on the surge arrester characteristics given in Table II.
calculated according to [3], [17]. Towers were terminated by
a constant grounding resistance of 10 ȍ [18]. Transmission TABLE II
SURGE ARRESTER CHARACTERISTICS
line insulator strings, with standard lightning impulse
withstand voltage level of 750 kV and length of 1.86 m, were
represented by the ISF object. The underground XLPE power
cables were represented by the Bergeron model with