Professional Documents
Culture Documents
PAGE
CHAPTER 14
Cold-Weather Concreting
Concrete can be placed safely without damage from concrete is placed. Thermometers and proper storage
freezing throughout the winter months in cold climates if facilities for test cylinders should be available to verify that
certain precautions are taken. Cold weather is defined by precautions are adequate.
ACI Committee 306 as a period when for more than 3 suc-
cessive days the average daily air temperature drops
below 5°C (40°F) and stays below 10°C (50°F) for more EFFECT OF FREEZING FRESH
than one-half of any 24 hour period. Under these circum- CONCRETE
stances, all materials and equipment needed for adequate Concrete gains very little strength at low temperatures.
protection and curing must be on hand and ready for use Freshly mixed concrete must be protected against the dis-
before concrete placement is started. Normal concreting ruptive effects of freezing (Fig.14-2) until the degree of sat-
practices can be resumed once the ambient temperature is uration of the concrete has been sufficiently reduced by
above 10°C (50°F) for more than half a day. the process of hydration. The time at which this reduction
During cold weather, the concrete mixture and its is accomplished corresponds roughly to the time required
temperature should be adapted to the construction proce- for the concrete to attain a compressive strength of 3.5
dure and ambient weather conditions. Preparations should MPa (500 psi) (Powers 1962). At normal temperatures and
be made to protect the concrete; enclosures, windbreaks, water-cement ratios less than 0.60, this occurs within the
portable heaters, insulated forms, and blankets should be first 24 hours after placement. Significant ultimate
ready to maintain the concrete temperature (Fig. 14-1). strength reductions, up to about 50%, can occur if concrete
Forms, reinforcing is frozen within a few hours after placement or before it
steel, and embedded attains a compressive strength of 3.5 MPa (500 psi)
fixtures must be (McNeese 1952). Concrete to be exposed to deicers should
clear of snow and attain a strength of 28 MPa (4,000 psi) prior to repeated
ice at the time cycles of freezing and thawing (Klieger 1957).
Concrete that has
been frozen just once
at an early age can
be restored to nearly
normal strength by
providing favorable
subsequent curing con-
ditions. Such concrete,
however, will not be as
resistant to weathering
nor as watertight as
concrete that had not
been frozen. The crit-
ical period after which
concrete is not seri-
ously damaged by one
Fig. 14-1. When suitable preparations to build enclosures and insulate equipment have been made,
cold weather is no obstacle to concrete construction. (69876, 43464) or two freezing cycles
239
Design and Control of Concrete Mixtures ◆ EB001
and 13°C (55°F) had relatively low strengths for the first
150 week; but after 28 days—when all specimens were moist-
cured at 23°C (73°F)—strengths for the 4°C (40°F) and
13°C (55°F) concretes grew faster than the 23°C (73°F)
100
concrete and at one year they were slightly higher.
50 Mix proportions
held constant.
Cement A Cement B
0 Casting temperature, °F
0 10 20 30 40 32 52 72 92
Casting temperature, °C 250
Percent slump at 23°C (73°F)
Casting temperature, °F
32 52 72 92 200
200
Percent final set at 23°C (73°F)
150
150
100
Mix proportions
100
50 held constant.
Cement A Cement B
50 Mix proportions 0
held constant. 0 10 20 30 40
Casting temperature, °C
Cement A Cement B
240
Chapter 14 ◆ Cold-Weather Concreting
50 7
Water to cement ratio = 0.43 Mix data:
Air content: 4 to 5% RH 6 Water to cement ratio = 0.43, Type I cement
%
40
Cement: Type I, 50 = 0.45, Type III cement
310 kg/m3 (517 lb/yd3) Air content: 4 to 5% 6
40 Cement content: 310 kg/m3 (517 lb/yd3)
F)
(7
°C
30 (7
23
°C 4 30
23 4
RH
RH
50%
20 3
%
20
0
10
100
28-day 23°C cured concrete
40
23
241
Design and Control of Concrete Mixtures ◆ EB001
AIR-ENTRAINED CONCRETE
the concrete’s temperature will tell whether the covering
Entrained air is particularly desirable in any concrete
is adequate. The heat liberated during hydration will
offset to a considerable degree the loss of heat during placed during freezing weather. Concrete that is not air
placing, finishing, and early curing operations. As the heat entrained can suffer strength loss and internal as well as
of hydration slows down, the need to cover the concrete surface damage as a result of freezing and thawing (Fig.
becomes more important. 14-10). Air entrainment provides the capacity to absorb
stresses due to ice formation within the concrete. See
Chapter 8, “Air-Entrained Concrete.”
SPECIAL CONCRETE MIXTURES
High strength at an early age is desirable in winter con-
struction to reduce the length of time temporary protec-
tion is required. The additional cost of high-early-strength
concrete is often offset by earlier reuse of forms and
shores, savings in the shorter duration of temporary
heating, earlier setting times that allows the finishing of
flatwork to begin sooner, and earlier use of the structure.
High-early-strength concrete can be obtained by using one
or a combination of the following:
1. Type III or HE high-early-strength cement
2. Additional portland cement (60 to 120 kg/m3 or 100
to 200 lb/yd3)
3. Chemical accelerators
Small amounts of an accelerator such as calcium chlo-
ride (at a maximum dosage of 2% by weight of portland
cement) can be used to accelerate the setting and early-age
strength development of concrete in cold weather.
Accelerators containing chlorides should not be used
where there is an in-service potential for corrosion, such as Fig. 14-9. Finishing this concrete flatwork can proceed
because a windbreak has been provided, there is adequate
in concrete members containing steel reinforcement or heat under the slab, and the concrete has low slump.
where aluminum or galvanized inserts will be used. (43465)
242
Chapter 14 ◆ Cold-Weather Concreting
400
Cured normally
(never frozen)
300
Percentage of the strength at 7 days
Frozen dry
200
Frozen wet
100
Fig. 14-11. Example of a concrete floor that was saturated
with rain, snow, or water and then frozen, showing the need
for air entrainment. (69869)
0
0 10 20 30 40 50 60
Number of cycles of freezing and thawing floor surface. This could also result in greater deflection of
the floor and a surface that is less wear-resistant than it
Fig. 14-10. Effect of freezing and thawing on strength of
concrete that does not contain entrained air (cured 7 days might have been.
before first freeze) (Powers 1956).
TEMPERATURE OF CONCRETE
Air entrainment should always be used for construc-
tion during the freezing months. The exception is concrete Temperature of Concrete as Mixed
work done under roof where there is no chance that rain,
snow, or water from other sources can saturate the concrete The temperature of fresh concrete as mixed should not be
and where there is no chance of freezing. less than shown in Lines 1, 2, or 3 of Table 14-1 for the
The likelihood of water saturating a concrete floor respective thickness of section. Note that lower concrete
during construction is very real. Fig. 14-11 shows con- temperatures are recommended for more massive
ditions in the upper story of an apartment building during concrete sections because heat generated during hydra-
winter construction. Snow fell on the top deck. When tion is dissipated less rapidly in heavier sections. Also
heaters were used below to warm the deck, the snow note that at lower ambient air temperatures more heat is
melted. Water ran through floor openings down to a level lost from concrete during transporting and placing; hence,
that was not being heated. The water-saturated concrete the recommended concrete temperatures as mixed are
froze, which caused a strength loss, particularly at the higher for colder weather.
243
Design and Control of Concrete Mixtures ◆ EB001
There is little advantage in using fresh concrete at a material) can be assumed as 0.925 kJ (0.22 Btu) compared
temperature much above 21°C (70°F). Higher concrete to 4.187 kJ (1.0 Btu) for water.
temperatures do not afford proportionately longer protec- Fig. 14-12 shows the effect of temperature of materials
tion from freezing because the rate of heat loss is greater. on temperature of fresh concrete. The chart is based on the
Also, high concrete temperatures are undesirable since equation
they increase thermal shrinkage after hardening, require
0.22(Ta M a + Tc Mc ) + Tw Mw + Twa Mwa
more mixing water for the same slump, and contribute to T =
the possibility of plastic-shrinkage cracking (caused by 0.22( M a + Mc ) + Mw + Mwa
rapid moisture loss through evaporation). Therefore, the where
temperature of the concrete as mixed should not be more T = temperature in degrees Celsius (Fahrenheit) of
than 5°C (10°F) above the minimums recommended in the fresh concrete
Table 14-1.
Ta , Tc , Tw , and Twa = temperature in degrees Celsius
Aggregate Temperature. The temperature of aggregates (Fahrenheit) of the aggregates, cement, added mixing
varies with weather and type of storage. Aggregates usu- water, and free moisture on aggregates, respectively;
ally contain frozen lumps and ice when the temperature is generally Ta = Twa
below freezing. Frozen aggregates must be thawed to Ma , Mc , Mw , and Mwa = mass in kilograms
avoid pockets of aggregate in the concrete after batching, (pounds) of the aggregates, cement, free moisture on
mixing, and placing. If thawing takes place in the mixer, aggregates, and mixing water, respectively
excessively high water contents in conjunction with the If the weighted average temperature of aggregates
cooling effect due to the ice melting must be avoided. and cement is above 0°C (32°F), the proper mixing-water
At temperatures above freezing it is seldom necessary temperature for the required concrete temperature can be
to heat aggregates, the desired concrete temperature can selected from Fig. 14-12. The range of concrete tempera-
usually be obtained by heating only the mixing water. At tures in the chart corresponds with the recommended
temperatures below freezing, in addition to heating the values given in Lines 1, 2, and 3 of Table 14-1.
mixing water, often only the fine aggregate needs to be
heated to produce concrete of the required temperature,
provided the coarse aggregate is free of frozen lumps.
Three of the most common methods for heating Weighted average temperature of
aggregates and cement, °F
aggregates are: (1) storing in bins or weigh hoppers heated 40 50 60 70
by steam coils or live steam; (2) storing in silos heated by 180
Mix data:
hot air or steam coils; and (3) stockpiling over heated 78 Aggregate = 1360 kg (3000 lb)
Moisture in aggregate = 27 kg (60 lb)
slabs, stem vents or pipes. Although heating aggregates Added mixing water = 108 kg (240 lb)
stored in bins or weigh hoppers is most commonly used, Portland cement = 256 kg (564 lb)
70 160
the volume of aggregate that can be heated is often limited
Mixing water temperature, °C
244
Chapter 14 ◆ Cold-Weather Concreting
Gasket stopper
Surface of concrete
CONTROL TESTS
Thermometers are needed to check the concrete tempera-
tures as delivered, as placed, and as maintained. An inex-
Water or
pensive pocket thermometer is shown in Fig. 14-13. alcohol
After the concrete has hardened, temperatures can be
checked with special surface thermometers or with an
Drilled or
ordinary thermometer that is kept covered with insulating preformed
blankets. A simple way to check temperature below the hole
245
Design and Control of Concrete Mixtures ◆ EB001
246
Chapter 14 ◆ Cold-Weather Concreting
appropriate exposure classification. Because of the risk of Before placing concrete, the heaters under a formed
surface imperfections that might occur on exterior concrete deck should be turned on to preheat the forms and melt
placed in late fall and winter, many concrete contractors any snow or ice remaining on top. Temperature require-
choose to delay concrete placement until spring. By waiting ments for surfaces in contact with fresh concrete are the
until spring, temperatures will be more favorable for ce- same as those outlined in the previous section “Concreting
ment hydration; this will help generate adequate strengths
on Ground.” Metallic embedments at temperatures below
along with sufficient drying so the concrete can resist
the freezing point may result in local freezing that
freeze-thaw damage.
decreases the bond between concrete and steel reinforce-
ment. ACI Committee 306 suggests that a reinforcing bar
CONCRETING ABOVEGROUND having a cross-sectional area of about 650 mm2 (1 in.2)
Working aboveground in cold weather usually involves should have a temperature of at least -12°C (10°F) immedi-
several different approaches compared to working at ately before being surrounded by fresh concrete at a tem-
ground level: perature of at least 13°C (55°F). Caution and additional
1. The concrete mixture need not be changed to generate study are required before definitive recommendations can
more heat because portable heaters can be used to be formulated. See ACI 306 for additional information.
heat the undersides of floor and roof slabs. When slab finishing is completed, insulating blankets
Nevertheless, there are advantages to having a mix or other insulation must be placed on top of the slab to
that will produce a high strength at an early age; for ensure that proper curing temperatures are maintained.
example, artificial heat can be cut off sooner (see Table
The insulation value (R) necessary to maintain the
14-3), and forms can be recycled faster.
2. Enclosures must be constructed to retain the heat concrete surface temperature of walls and slabs above-
under floor and roof slabs. ground at 10°C (50°F) or above for 7 days may be esti-
3. Portable heaters used to warm the underside of mated from Fig. 14-16. To maintain a temperature for
formed concrete can be direct-fired heating units longer periods, more insulation is required. ACI 306 has
(without venting). additional graphs and tables for slabs placed on ground at
Table 14-3.
A. Recommended Duration of Concrete Temperature in Cold Weather–Air-Entrained Concrete*
Protection from early-age freezing For safe stripping strength
Conventional High-early strength Conventional High-early-strength
Service category concrete,** days concrete,† days concrete,** days concrete,† days
No load, not exposed‡
2 1 2 1
favorable moist-curing
No load, exposed, but later
3 2
has favorable moist-curing
Partial load, exposed 3 2 6 4
Fully stressed, exposed See Table B below
B. Recommended Duration of Concrete Temperature for Fully Stressed, Exposed, Air-Entrained Concrete
247
Design and Control of Concrete Mixtures ◆ EB001
R
(4
R
=
)
=
0.
-5
R
0.
70
70
=
20
(4
1.
Minimum ambient temperature, °C
)
-10
=1
(6
) 10
.06
R
R=
=1
-15
(6)
.41
1.0
0
R=
6
(8)
-20
(6)
1.4
-10
1(
-25
R=
8)
1.4
-20
-30
1 (8
)
-30
-35
-40 -40
Cement content Cement content Cement content
-45 237 kg/m3 296 kg/m3 356 kg/m3
-50
(400 lb/yd3) (500 lb/yd3) (600 lb/yd3)
-50 -60
0 100 200 300 400 500 600 0 100 200 300 400 500 600 0 100 200 300 400 500 600
Wall or slab thickness, mm
Fig. 14-16. Thermal resistance (R) of insulation required to maintain the concrete surface temperature of walls and slabs
aboveground at 10°C (50°F) or above for 7 days. Concrete temperature as placed: 10°C (50°F). Maximum wind velocity:
24 km/h (15 mph). Note that in order to maintain a certain minimum temperature for a longer period of time, more insulation
or a higher R value is required (adapted from ACI 306).
a temperature of 2°C (35°F). Insulation can be selected Corners and edges are particularly vulnerable during
based on R values provided by insulation manufacturers cold weather. As a result, the thickness of insulation for
or by using the information in Table 14-4. these areas, especially on columns, should be about three
When concrete strength development is not deter- times the thickness that is required to maintain the same
mined, a conservative estimate can be made if adequate for walls or slabs. On the other hand, if the ambient
protection at the recommended temperature is provided temperature rises much above the temperature assumed
for the duration of time found in Table 14-3. However, the in selecting insulation values, the temperature of the
actual amount of insulation and length of the protection concrete may become excessive. This increases the proba-
period should be determined from the monitored in-place bility of thermal shock and cracking when forms are
concrete temperature and the desired strength. A correla- removed. Temperature readings of insulated concrete
tion between curing temperature, curing time, and com- should therefore be taken at regular intervals and should
pressive strength can be determined from laboratory not vary from ambient air temperatures by more than the
testing of the particular concrete mix used in the field (see values given in ACI 306. In addition, insulated concrete
“Maturity Concept” discussed later in this chapter). ACI temperatures should not be allowed to rise much above
306 states that with a compressive strength of 3.5 MPa (500 27°C (80°F). In case of a sudden increase in concrete tem-
psi), concrete will normally have sufficient strength to perature, up to say 35°C (95°F), it may be necessary to
resist early frost damage. If the concrete will be in a satu- remove some of the insulation or loosen the formwork.
rated condition when frozen, the concrete should be prop- The maximum temperature differential between the con-
erly air entrained and must have developed a compressive crete interior and the concrete surface should be about
strength of 28 MPa (4000 psi). 20°C (35°F) to minimize cracking. The weather forecast
248
Chapter 14 ◆ Cold-Weather Concreting
ENCLOSURES
Heated enclosures are very effective for protecting
concrete in cold weather, but are probably the most expen-
sive too (Fig. 14-17). Enclosures can be of wood, canvas
tarpaulins, or polyethylene film (Fig. 14-18). Prefabricated, Fig. 14-17. Even in the winter, an outdoor swimming pool
rigid-plastic enclosures are also available. Plastic enclo- can be constructed if a heated enclosure is used. (43453)
249
Design and Control of Concrete Mixtures ◆ EB001
INSULATING MATERIALS
Heat and moisture can be retained in the concrete by
covering it with commercial insulating blankets or batt
insulation (Fig. 14-19). The effectiveness of insulation can
be determined by placing a thermometer under it and in Fig. 14-20. Insulating concrete forms (ICF) permit con-
contact with the concrete. If the temperature falls below creting in cold weather. (69699)
250
Chapter 14 ◆ Cold-Weather Concreting
Air
Air Air,
supply CO,
CO2,
Air
Fan Flame
a) Direct-fired heater
Air,
CO,
CO2,
Enclosure
Air
Clean
Air heated
supply air
only
Air
Fan Flame
b) Indirect-fired heater
Fig. 14-21. With air temperatures down to -23°C (-10°F),
concrete was cast in this insulated column form made of Fig. 14-22. Two types of air heaters.
19-mm (3⁄4-in.) high-density plywood inside, 25-mm (1-in.)
rigid polystyrene in the middle, and 13-mm (1⁄2-in.) rough
plywood outside. R value: 1.0 m2 · °C/W (5.6 [°F · hr · ft2]
/Btu). (43461)
HEATERS
Three types of heaters are used in cold-weather concrete
construction: direct fired, indirect fired, and hydronic
systems (Figs. 14-22 to 14-25). Indirect-fired heaters are
vented to remove the products of combustion. Where heat
is to be supplied to the top of fresh concrete— for example, Fig. 14-23. An indirect-fired heater. Notice vent pipe that
a floor slab—vented heaters are required. Carbon dioxide carries combustion gases outside the enclosure. (43459)
251
Design and Control of Concrete Mixtures ◆ EB001
252
Chapter 14 ◆ Cold-Weather Concreting
A salamander is an inexpensive combustion heater cement type and amount, whether accelerating admix-
without a fan that discharges its combustion products into tures were used, and the loads that must be carried.
the surrounding air; heating is accomplished by radiation Recommended minimum periods of protection are given
from its metal casing. Salamanders are fueled by coke, oil, in Table 14-3. The duration of heating structural concrete
wood, or liquid propane. They are but one form of a that requires the attainment of full service loading before
direct-fired heater. A primary disadvantage of salaman- forms and shores are removed should be based on the
ders is the high temperature of their metal casing, a defi- adequacy of in-place compressive strengths rather than an
nite fire hazard. Salamanders should be placed so that arbitrary time period. If no data are available, a conserva-
they will not overheat formwork or enclosure materials. tive estimate of the length of time for heating and protec-
When placed on floor slabs, they should be elevated to tion can be made using Table 14-3.
avoid scorching the concrete.
Some heaters burn more than one type of fuel. The Moist Curing
approximate heat values of fuels are as follows:
No. 1 fuel oil 37,700 kJ/L (135,000 Btu/gal) Strength gain stops when moisture required for curing is
Kerosene 37,400 kJ/L (134,000 Btu/gal) no longer available. Concrete retained in forms or covered
Gasoline 35,725 kJ/L (128,000 Btu/gal) with insulation seldom loses enough moisture at 5°C to
Liquid-propane gas 25,500 kJ/L (91,500 Btu/gal) 15°C (40°F to 55°F) to impair curing. However, a positive
Natural gas 37,200 kJ/m3 (1,000 Btu/ft3) means of providing moist curing is needed to offset
drying from low wintertime humidities and heaters used
The output rating of a portable heater is usually the heat
in enclosures during cold weather.
content of the fuel consumed per hour. A rule of thumb is
Live steam exhausted into an enclosure around the
that about 134,000 kJ are required for each 100 m3 (36,000
concrete is an excellent method of curing because it
Btu for 10,000 ft3) of air to develop a 10°C (20°F) tempera-
provides both heat and moisture. Steam is especially prac-
ture rise.
tical in extremely cold weather because the moisture
Electricity can also be used to cure concrete in winter.
provided offsets the rapid drying that occurs when very
The use of large electric blankets equipped with thermo-
cold air is heated.
stats is one method. The blankets can also be used to thaw
Liquid membrane-forming compounds can be used
subgrades or concrete foundations.
for early curing of concrete surfaces within heated
Use of electrical resistance wires that are cast into the
enclosures.
concrete is another method. The power supplied is under
50 volts, and from 7.0 to 23.5 MJ (1.5 to 5 kilowatt-hours)
of electricity per cubic meter (cubic yard) of concrete is Terminating the Heating Period
required, depending on the circumstances. The method
Rapid cooling of concrete at the end of the heating period
has been used in the Montreal, Quebec, area for many
should be avoided. Sudden cooling of the concrete surface
years. Where electrical resistance wires are used, insula-
while the interior is still warm may cause thermal crack-
tion should be included during the initial setting period. If
ing, especially in massive sections such as bridge piers,
insulation is removed before the recommended time, the
abutments, dams, and large structural members; thus
concrete should be covered with an impervious sheet and
cooling should be gradual. A safe temperature differential
the power continued for the required time.
between a concrete wall and the ambient air temperature
Steam is another source of heat for winter concreting.
can be obtained from ACI 306R-88. The maximum uni-
Live steam can be piped into an enclosure or supplied
form drop in temperature throughout the first 24 hours
through radiant heating units. In choosing a heat source, it
after the end of protection should not be more than the
must be remembered that the concrete itself supplies heat
amounts given in Table 14-2. Gradual cooling can be
through hydration of cement; this is often enough for
accomplished by lowering the heat or by simply shutting
curing needs if the heat can be retained within the
off the heat and allowing the enclosure to cool to outside
concrete with insulation.
ambient air temperature.
253
Design and Control of Concrete Mixtures ◆ EB001
should be left in place. Before shores and forms are With these limitations in mind, the maturity concept has
removed, fully stressed structural concrete should be gained greater acceptance for representing the compres-
tested to determine if in-place strengths are adequate, sive strength of the concrete for removal of shoring or
rather than waiting an arbitrary time period. In-place opening a pavement to traffic; but it is no substitute for
strengths can be monitored using one of the following: quality control and proper concreting practices (Malhotra
(1) field-cured cylinders (ASTM C 31 or AASHTO T 23); 1974 and ACI Committee 347).
(2) probe penetration tests (ASTM C 803); (3) cast-in-place To monitor the strength development of concrete in
cylinders (ASTM C 873); (4) pullout testing (ASTM C 900); place using the maturity concept, the following informa-
or (5) maturity testing (ASTM C 1074). Many of these tests tion must be available:
are indirect methods of measuring compressive strength;
they require correlation in advance with standard cylin- 1. The strength-maturity relationship of the concrete used
ders before estimates of in-place strengths can be made. in the structure. The results of compressive strength
tests at various ages on a series of cylinders made of
If in-place compressive strengths are not documented,
a concrete similar to that used in the structure; this
Table 14-3B lists conservative time periods in days to
must be done to develop a strength-maturity curve.
achieve various percentages of the standard laboratory-
These cylinders are cured in a laboratory at 23°C ± 2°C
cured 28-day strength. The engineer issuing project draw-
(73°F ± 3°F).
ings and specifications in cooperation with the formwork
2. A time-temperature record of the concrete in place.
contractor must determine what percentage of the design
Temperature readings are obtained by placing expend-
strength is required (see ACI Committee 306). Side forms
able thermistors or thermocouples at varying depths in
can be removed sooner than shoring and temporary false-
the concrete. The location giving the lowest values pro-
work (ACI Committee 347).
vides the series of temperature readings to be used in
the computation (Fig. 14-26).
MATURITY CONCEPT See ACI 306R-88 for sample calculations using the
maturity concept.
The maturity concept is based on the principle that
strength gain in concrete is a function of curing time and
temperature. The maturity concept, as described in ACI
306R-88 and ASTM C 1074 can be used to evaluate
strength development when the prescribed curing
temperatures have not been maintained for the required
time or when curing temperatures have fluctuated. The
concept is expressed by the equation:
Metric: M = ∑ (C + 10) ∆t
Inch-Pound Units: M = ∑ (F – 14) ∆t
where
M = maturity factor
∑ = summation
C = concrete temperature, degrees Celsius
F = concrete temperature, degrees Fahrenheit
∆t = duration of curing at temperature C (F), usually
in hours
The equation is based on the premise that concrete
gains strength (that is, cement continues to hydrate) at
temperatures as low as -10°C (14°F).
Before construction begins, a calibration curve is
drawn plotting the relationship between compressive
strength and the maturity factor for a series of test cylin-
ders (of the particular concrete mixture proportions) cured
in a laboratory and tested for strength at successive ages.
The maturity concept is not precise and has some
limitations. But, the concept is useful in checking the
curing of concrete and estimating strength in relation to
time and temperature. It presumes that all other factors
affecting concrete strength have been properly controlled.
254
Chapter 14 ◆ Cold-Weather Concreting
REFERENCES
255
Design and Control of Concrete Mixtures ◆ EB001
256