You are on page 1of 37

STEEL RECEIVED AT SITE (EIGHTEEN APARTMENT BUILDING PAVILION-06 & 07)

S.# Dia (mm) Manufacture

STEEL RECEIVED IN FEB-2019


1 10 mm
2 12 mm
3 16 mm PAK Steel
4 20 mm
5 25 mm
6 16 mm PAK Steel
STEEL RECEIVED IN Mar-2019
7 16 mm
8 16 mm PAK Steel
9 16 mm
STEEL RECEIVED IN Apr-2019
10 10 mm
11 12 mm
12 16 mm
PAK Steel
13 20 mm
14 25 mm
15 12 mm
16 10 mm PAK Steel
STEEL RECEIVED IN May-2019
17 10 mm
PAK Steel
18 12 mm
19 10 mm
20 10 mm PAK Steel
21 12 mm
22 20 mm
PAK Steel
23 25 mm
STEEL RECEIVED IN AUGUST-2019 (PAVILION-06 & 07)
29 10 mm
PAK Steel
30 20 mm
STEEL RECEIVED IN SEPTEMBER-2019 (PAVILION-06 & 07)
31 10 mm PAK Steel
32 10 mm
PAK Steel
33 20 mm
STEEL RECEIVED IN October-2019 (PAVILION-06 & 07)
34 16 mm
35 20 mm PAK Steel
36 25 mm
37 10 mm PAK Steel
38 10 mm
PAK Steel
39 12 mm
STEEL RECEIVED IN December-2019 (PAVILION-06 & 07)

SQS:Khan Page 1 of 37
STEEL RECEIVED AT SITE (EIGHTEEN APARTMENT BUILDING PAVILION-06 & 07)

S.# Dia (mm) Manufacture

34 12 mm
35 16 mm PAK Steel
36 25 mm
37 12 mm
PAK Steel
38 20 mm
STEEL RECEIVED IN January-2020 (PAVILION-06 & 07)
39 10 mm PAK Steel
STEEL RECEIVED IN March-2020 (PAVILION-06 & 07)
40 10mm PAK Steel
TOTAL STEEL RECEIVED FOR P# 6 & 7 & Provisonaly Buildings
STEEL RECEIVED IN JULY-2019 (MOCKUP VILLA)
1 10 mm
2 12 mm
3 16 mm PAK Steel
4 20 mm
5 25 mm
STEEL RECEIVED IN SEPTEMBER-2019 (MOCKUP VILLA)
1 10 mm
2 12 mm

3 20 mm PAK Steel

4 25 mm

TOTAL STEEL RECEIVED (Mockup Villa)


GRAND TOTAL STEEL RECEIVED

SQS:Khan Page 2 of 37
Date: February-20
Steel Received Steel Received
Date (Ton)

19.998
23.035
4-Feb-19 59.430
30.548
16.915
12-Feb-19 32.595

17-Mar-19 34.910
21-Mar-19 80.690
22-Mar-19 61.360

35.065
12-Apr-19 4.360
30.775
30.030
14-Apr-19
40.000
22-Apr-19 31.715
30-Apr-19 15.040

101.085
15-May-19
12.280
36.150
21-May-19 12.990
18.355
50.090
27-May-19
21.000

11.140
21-Aug-19
40.280

8-Sep-19 20.335
75.960
19-Sep-19
18.160

4.070
1-Oct-19 79.465
24.285
5-Oct-19 123.360
28.800
7-Oct-19
29.740

SQS:Khan Page 3 of 37
Date: February-20
Steel Received Steel Received
Date (Ton)
22.050
10-Dec-19 16.930
19.930
26.718
18-Dec-19
78.728

20-Jan-20 72.860

22-Mar-20 46.305
1,537.531

1.000
14.000
30-Jul-19 1.000
3.000
1.000

11.100
6.605

14-Sep-19 7.425

0.320

45.450
1,582.981

SQS:Khan Page 4 of 37
Steel Justification Pavilion-06 & 07
Sr. Description Steel Wt. Ton
IPA # 4 Quantity
1 Approved upto IPA # 4 650
Pavilion-06
2 Approved upto IPA # 4 618
Pavilion-07
3 Approved upto IPA # 4 42
Mockup Villa
Total 1310

Approved steel Quantity


4 Remaining work 79.27
5 Approved BBS Quantity #REF!
Extra Steel Usage
Total 86.43
Wastage % #REF!

#REF!
Total Steel Consumed Including Wastage
Steel Transfer
6 Steel Received till date 1582.98

7 Steel in Hand #REF!


8 Steel Required for Ramp & UGWT 20.00
9 Steel present at yard 78.75
10 Return to EEPL (20mm, 700 full lengths) -21.05
11
Shifted to Cluster-G (12mm,20mm.25mm) -7.5
Steel Justification Pavilion-06 & 07
Sr. Description Steel Wt. Ton
IPA # 5 Quantity
1 Approved upto IPA # 5 668
Pavilion-06
2 Approved upto IPA # 5 658.854
Pavilion-07

3 Approved upto IPA # 5 45.788


Mockup Villa
Sub Total - 1 1372.642
Chairs & Pins 45.187

Estimated Balance Works


4 Remaining work Ramp & UGWT 20.00

5 Total Steel Consumption 1383.27


Extra Steel Usage Estimated
6 Chairs in Raft Foundation Pavilion-06 13.5
7 Chairs in Raft Foundation Pavilion-07 13.6
8
Chairs in Slabs Pavilion-06 (upto Mumty) 6.4
9
Pins in beams Pavilion-06 (upto Mumty) 1.1736
10
Chairs in Slabs Pavilion-07 (upto Mumty) 6.4
11
Pins in beams Pavilion-07 (upto Mumty) 1.1736
12 Pins for block work Pavilion-06 1.47
13 Pins for block work Pavilion-07 1.47
14 Estimated Chairs in Ramp 0.3
15 Estimated Chairs in UGWT 0.2
16 Scrap at yard Approx. 37
Total 82.6872
Wastage % 5.98

1465.96
Total Steel Consumed Including Wastage
Steel Transfer
18 Steel Received till date 1582.98

19 Steel in Hand 117.02


20 Steel Required for Ramp & UGWT 20.00
20 Steel present at yard 50.70
21 Return to EEPL (20mm, 700 full lengths) -21.05
22
Shifted to Cluster-G (12mm,20mm,25mm) -7.5
23 Shifted to Pavilion-04 (25mm) -4.6
PAVILION 06 & 07 AVERAGE WEIGHT FROM STEEL TEST
REPORTS
Weight Avg. Weight Weight
Sr. # Dia (mm) Weight given by EEPL
lbs/ft lbs/ft kg/m
1 10mm 0.402
2 10mm 0.393
3 10mm 0.408
4 10mm 0.409
5 10mm 0.411
6 10mm 0.418
7 10mm 0.408
8 10mm 0.409
0.405 0.602 0.617
9 10mm 0.405
10 10mm 0.405
11 10mm 0.403
12 10mm 0.402
13 10mm 0.398
14 10mm 0.399
15 10mm 0.402
16 10mm 0.403
17 12mm 0.582
18 12mm 0.568
19 12mm 0.585
20 12mm 0.586
21 12mm 0.613
22 12mm 0.617
23 12mm 0.606
0.603 0.897 0.888
24 12mm 0.607
25 12mm 0.609
26 12mm 0.608
27 12mm 0.615
28 12mm 0.613
29 12mm 0.619
30 12mm 0.612
31 16mm 1.080
32 16mm 1.081
33 16mm 1.055
34 16mm 1.056
35 16mm 1.054
36 16mm 1.058
37 16mm 1.054
1.049 1.561 1.578
38 16mm 1.055
39 16mm 1.047
40 16mm 1.044
41 16mm 1.022
42 16mm 1.023
43 16mm 1.033
44 16mm 1.028
45 20mm 1.654
46 20mm 1.652
47 20mm 1.655
48 20mm 1.651
49 20mm 1.612
50 20mm 1.613
51 20mm 1.635
52 20mm 1.638
1.622 2.414 2.466
53 20mm 1.608
54 20mm 1.607
55 20mm 1.608
56 20mm 1.608
57 20mm 1.604
58 20mm 1.608
59 20mm 1.608
60 20mm 1.596
61 25mm 2.440
62 25mm 2.465
63 25mm 2.588
64 25mm 2.610
65 25mm 2.672
66 25mm 2.671
67 25mm 2.654
2.600 3.869 3.853
68 25mm 2.652
69 25mm 2.637
70 25mm 2.633
71 25mm 2.515
72 25mm 2.514
73 25mm 2.668
74 25mm 2.685
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 7" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:

Grade 60 Re Bars

Description Submital & Date Total Length Activity Wise #10 #12 #16 #20 #25 #32 Line Length

Raft 117.204

Zone-1 Raft PCL-P18-DS-073 100% 0.000 0.000 39.853 0.000 0.000 0.000 39.853

Zone-2 Raft PCL-P18-DS-084 100% 0.000 0.000 36.539 0.000 0.000 0.000 36.539

Zone-3 Raft PCL-P18-DS-098 100% 0.000 0.000 38.646 0.000 0.000 0.000 38.646

Plumbing drain PCL-P18-DS-080 100% 0.000 0.000 1.857 0.000 0.000 0.000 1.857

Sump pit PCL-P18-DS-107 100% 0.102 0.000 0.207 0.000 0.000 0.000 0.309

Retaining Wall 14.53

Retaining Wall PCL-P18-DS-075 100% 5.60 8.92 0.00 0.00 0.00 0.00 14.529

Lift Well & S.Wall 47.05

PCL-P18-DS-084, dated Mar 26, 2019


Raft Dowels Zone-2 100% 0.705 0.537 1.039 0.40 0.00 0.00 2.685

PCL-P18-DS-098, dated April 18, 2019


Raft Dowels Zone-3 100% 0.705 0.537 1.039 0.40 0.00 0.00 2.685

PCL-P18-DS-086, dated Mar 28, 2019


Basement ~Ground Floor Zone-2 100% 1.236 0.755 0.000 0.68 0.00 0.00 2.667

Basement ~Ground Floor Zone-3 PCL-P18-DS-101, dated Apr 16, 2019 100% 1.236 0.755 0.000 0.68 0.00 0.00 2.667

PCL-P18-DS-135, dated May 23, 2019


Ground Floor Zone-2 100% 1.236 0.755 0.000 0.68 0.00 0.00 2.667

Ground Floor Zone-3 PCL-P18-DS-144, dated June 13, 2019 100% 1.236 0.755 0.000 0.68 0.00 0.00 2.667

PCL-P18-DS-135, dated May 23, 2019


First Floor Zone-2 100% 1.236 0.755 0.000 0.68 0.00 0.00 2.667

SQS:Khan Page 10 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 7" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:

Grade 60 Re Bars

Description Submital & Date Total Length Activity Wise #10 #12 #16 #20 #25 #32 Line Length

First Floor Zone-3 PCL-P18-DS-144, dated June 13, 2019 100% 1.236 0.755 0.000 0.68 0.00 0.00 2.667

PCL-P18-DS-135, dated May 23, 2019


Second Zone-2 100% 1.236 0.755 0.000 0.68 0.00 0.00 2.667

Second 5 Zone-3 PCL-P18-DS-144, dated June 13, 2019 100% 1.236 0.755 0.000 0.68 0.00 0.00 2.667

PCL-P18-DS-135, dated May 23, 2019


Third Floor Zone-2 100% 1.236 0.755 0.000 0.68 0.00 0.00 2.667

Third Floor Zone-3 PCL-P18-DS-144, dated June 13, 2019 100% 1.236 0.755 0.000 0.68 0.00 0.00 2.667

PCL-P18-DS-135, dated May 23, 2019


Forth Floor Zone-2 100% 1.236 0.755 0.000 0.68 0.00 0.00 2.667

Forth Floor Zone-3 PCL-P18-DS-144, dated June 13, 2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667

PCL-P18-DS-135, dated May 23, 2019


Fifth Floor Zone-2 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667

Fifth Floor Zone-3 PCL-P18-DS-144, dated June 13, 2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667

PCL-P18-DS-285, dated Nov 14, 2019


Sixth Floor Zone-2 100% 0.98 0.48 0.00 0.47 0.00 0.00 1.936

PCL-P18-DS-285, dated Nov 14, 2019


Sixth Floor Zone-3 100% 1.24 0.64 0.00 0.52 0.00 0.00 2.402

PCL-P18-DS-1???, dated ??
Mumty 0% 0.00 0.00 0.00 0.00 0.00 0.00 -

Columns 76.82

Raft Dowel Zone-1 PCL-P18-DS-073, dated Mar 16, 2019 100% 0.57 0.00 0.00 0.60 1.15 0.00 2.317

Raft Dowel Zone-2 PCL-P18-DS-084, dated Mar 26, 2019 100% 0.24 0.00 0.00 1.09 0.34 0.00 1.675

Raft Dowel Zone-3 PCL-P18-DS-098, dated Apr 18, 2019 100% 0.19 0.00 0.00 0.92 0.45 0.00 1.567

SQS:Khan Page 11 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 7" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:

Grade 60 Re Bars

Description Submital & Date Total Length Activity Wise #10 #12 #16 #20 #25 #32 Line Length

Columns Zone-1 PCL-P18-DS-081, dated Mar 25, 2019 100% 0.23 0.00 0.00 0.75 2.05 0.00 3.031

Columns Zone-2 PCL-P18-DS-086, dated Mar 28, 2019 100% 0.77 0.00 0.00 2.08 0.79 0.00 3.639

Columns Zone-3 PCL-P18-DS-101, dated Apr 16, 2019 100% 0.84 0.00 0.00 2.13 1.06 0.00 4.031

Columns Zone-1 PCL-P18-DS-108, dated Apr 20, 2019 100% 0.67 0.00 0.00 0.58 1.33 0.00 2.573

Columns Zone-2 PCL-P18-DS-134, dated May 23, 2019 100% 0.78 0.00 0.00 2.08 0.72 0.00 3.583

Columns Zone-3 PCL-P18-DS-143, dated June 13, 2019 100% 0.89 0.00 0.00 2.13 0.97 0.00 3.985

Columns Zone-1 PCL-P18-DS-124, dated May 10, 2019 100% 0.67 0.00 0.00 0.75 1.69 0.00 3.108

Columns Zone-2 PCL-P18-DS-134, dated May 23, 2019 100% 0.78 0.00 0.00 2.08 0.72 0.00 3.583

Columns Zone-3 PCL-P18-DS-143, dated June 13, 2019 100% 0.89 0.00 0.00 2.13 0.97 0.00 3.985

Columns Zone-1 PCL-P18-DS-142, dated June 12, 2019 100% 0.68 0.00 0.00 1.34 1.16 0.00 3.178

Columns Zone-2 PCL-P18-DS-134, dated May 23, 2019 100% 0.79 0.00 0.00 2.33 0.50 0.00 3.613

Columns Zone-3 PCL-P18-DS-143, dated June 13, 2019 100% 0.90 0.00 0.00 2.46 0.66 0.00 4.024

Columns Zone-1 PCL-P18-DS-142, dated June 12, 2019 100% 0.52 0.00 0.00 1.80 0.00 0.00 2.319

Columns Zone-2 PCL-P18-DS-134, dated May 23, 2019 100% 0.72 0.00 0.00 2.53 0.00 0.00 3.245

Columns Zone-3 PCL-P18-DS-143, dated June 13, 2019 100% 0.81 0.00 0.00 2.73 0.00 0.00 3.534

Columns Zone-1 PCL-P18-DS-142, dated June 12, 2019 100% 0.52 0.00 0.07 1.68 0.00 0.00 2.260

SQS:Khan Page 12 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 7" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:

Grade 60 Re Bars

Description Submital & Date Total Length Activity Wise #10 #12 #16 #20 #25 #32 Line Length

Columns Zone-2 PCL-P18-DS-134, dated May 23, 2019 100% 0.72 0.00 0.00 2.51 0.00 0.00 3.223

Columns Zone-3 PCL-P18-DS-143, dated June 13, 2019 100% 0.81 0.00 0.07 2.62 0.00 0.00 3.496

Columns Zone-1 PCL-P18-DS-142, dated June 12, 2019 100% 0.48 0.00 0.49 0.75 0.00 0.00 1.719

Columns Zone-2 PCL-P18-DS-134, dated May 23, 2019 100% 0.70 0.00 0.18 1.72 0.00 0.00 2.596

Columns Zone-3 PCL-P18-DS-143, dated June 13, 2019 100% 0.78 0.00 0.24 1.82 0.00 0.00 2.838

Columns Zone-1 PCL-P18-DS-142, dated June 12, 2019 100% 0.50 0.00 0.30 0.77 0.00 0.00 1.561

Columns Zone-2 PCL-P18-DS-134, dated May 23, 2019 100% 0.19 0.00 0.00 0.51 0.00 0.00 0.700

Columns Zone-3 PCL-P18-DS-143, dated June 13, 2019 100% 0.26 0.00 0.00 0.69 0.00 0.00 0.953

Columns Mumty Zone-3 PCL-P18-DS-143, dated June 13, 2019 100% 0.13 0.00 0.00 0.36 0.00 0.00 0.488

Slab & Beams 398.85

Ground Slab Floor -1 PCL-P18-DS-104,16 Apr, 18,2019 100% 11.59 2.48 0.00 0.00 0.00 0.00 14.068

Ground Beams Floor -1 PCL-P18-DS-102,16 Apr, 18,2019 100% 1.33 0.00 0.69 4.08 0.99 0.00 7.093

Ground Floor Slab -2 PCL-P18-DS-125, May, 15,2019 100% 9.37 0.96 0.00 0.00 0.00 0.00 10.330

Ground Floor Beams -2 PCL-P18-DS-123, May, 09,2019 100% 1.33 0.00 0.91 3.92 0.00 0.00 6.164

Ground Floor Beams -2 PCL-P18-DS-154, July, 01,2019 100% 0.02 0.10 0.42 0.04 1.04 0.00 1.614

Ground Slab Floor -3 PCL-P18-DS-177, July, 18,2019 100% 10.79 0.60 0.00 0.00 0.00 0.00 11.395

SQS:Khan Page 13 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 7" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:

Grade 60 Re Bars

Description Submital & Date Total Length Activity Wise #10 #12 #16 #20 #25 #32 Line Length

Ground Beams Floor -3 PCL-P18-DS-131, May, 21,2019 100% 1.66 0.00 0.94 4.74 1.88 0.00 9.217

First Floor Slab-1 PCL-P18-DS-116, April, 30,2019 100% 8.08 2.48 0.00 0.00 0.00 0.00 10.563

First Floor Beams-1 PCL-P18-DS-117, May, 02,2019 100% 1.03 0.00 0.33 2.54 2.70 0.00 6.592

First Floor Slab-2 PCL-P18-DS-159, July, 03,2019 100% 6.98 0.95 0.00 0.00 0.00 0.00 7.935

First Floor Beams-2 PCL-P18-DS-158, July, 03,2019 100% 1.33 0.00 1.09 4.14 0.00 0.00 6.558

First Floor Slab-3 PCL-P18-DS-204, August, 21,2019 100% 7.78 0.60 0.00 0.00 0.00 0.00 8.386

First Floor Beams-3 PCL-P18-DS-203, August, 21,2019 100% 1.55 0.00 1.31 3.88 1.20 0.00 7.934

Seconed Floor Slab -1 PCL-P18-DS-130, May, 18,2019 100% 8.50 2.48 0.00 0.00 0.00 0.00 10.982

Seconed Floor Beams -1 PCL-P18-DS-129, May, 18,2019 100% 1.02 0.00 0.33 2.31 2.96 0.00 6.614

Seconed Floor Slab -2 PCL-P18-DS-161, July, 03,2019 100% 7.53 0.95 0.00 0.00 0.00 0.00 8.483

Seconed Floor Beams -2 PCL-P18-DS-161, July, 03,2019 100% 1.34 0.00 1.15 4.05 0.00 0.00 6.534

Seconed Floor Slab -3 PCL-P18-DS-222, August, 29,2019 100% 8.21 0.60 0.00 0.00 0.00 0.00 8.814

Seconed Floor Beams -3 PCL-P18-DS-221, August, 29,2019 100% 1.55 0.00 1.31 3.64 1.58 0.00 8.070

Third Floor Slab-1 PCL-P18-DS-130, May, 18,2019 100% 8.50 2.48 0.00 0.00 0.00 0.00 10.982

Third Floor Beams-1 PCL-P18-DS-129, May, 18,2019 100% 1.02 0.00 0.33 2.31 2.96 0.00 6.614

Third Floor Slab-2 PCL-P18-DS-161, July, 03,2019 100% 7.53 0.95 0.00 0.00 0.00 0.00 8.483

SQS:Khan Page 14 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 7" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:

Grade 60 Re Bars

Description Submital & Date Total Length Activity Wise #10 #12 #16 #20 #25 #32 Line Length

Third Floor Beams-2 PCL-P18-DS-161, July, 03,2019 100% 1.34 0.00 1.15 4.05 0.00 0.00 6.534

Third Floor Slab-3 PCL-P18-DS-222, August, 29,2019 100% 8.21 0.60 0.00 0.00 0.00 0.00 8.814

Third Floor Beams-3 PCL-P18-DS-221, August, 29,2019 100% 1.55 0.00 1.31 3.64 1.58 0.00 8.070

Forth Floor Slab-1 PCL-P18-DS-130, May, 18,2019 100% 8.50 2.48 0.00 0.00 0.00 0.00 10.982

Forth Floor Beams -1 PCL-P18-DS-129, May, 18,2019 100% 1.02 0.00 0.33 2.31 2.96 0.00 6.614

Forth Floor Slab-2 PCL-P18-DS-161, July, 03,2019 100% 7.53 0.95 0.00 0.00 0.00 0.00 8.483

Forth Floor Beams-2 PCL-P18-DS-161, July, 03,2019 100% 1.34 0.00 1.15 4.05 0.00 0.00 6.534

Forth Floor Slab-3 PCL-P18-DS-222, August, 29,2019 100% 8.21 0.60 0.00 0.00 0.00 0.00 8.814

Forth Floor Beams -3 PCL-P18-DS-221, August, 29,2019 100% 1.55 0.00 1.31 3.64 1.58 0.00 8.070

Fifth Floor Slab -1 PCL-P18-DS-130, May, 18,2019 100% 8.50 2.48 0.00 0.00 0.00 0.00 10.982

Fifth Floor Beams-1 PCL-P18-DS-129, May, 18,2019 100% 1.02 0.00 0.33 2.31 2.96 0.00 6.614

Fifth Floor Slab-2 PCL-P18-DS-161, July, 03,2019 100% 7.53 0.95 0.00 0.00 0.00 0.00 8.483

Fifth Floor Beams-2 PCL-P18-DS-161, July, 03,2019 100% 1.34 0.00 1.15 4.05 0.00 0.00 6.534

Fifth Floor Slab -3 PCL-P18-DS-222, August, 29,2019 100% 8.21 0.60 0.00 0.00 0.00 0.00 8.814

Fifth Floor Beams -3 PCL-P18-DS-221, August, 29,2019 100% 1.55 0.00 1.31 3.64 1.58 0.00 8.070

Sixth Floor Slab PCL-P18-DS-277, Nov, 01,2019 100% 22.31 3.91 0.00 0.00 0.00 0.00 26.224

SQS:Khan Page 15 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 7" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:

Grade 60 Re Bars

Description Submital & Date Total Length Activity Wise #10 #12 #16 #20 #25 #32 Line Length

Sixth Floor Beams PCL-P18-DS-275, Oct, 29,2019 100% 3.82 0.18 2.93 10.65 4.83 0.00 22.407

Roof Slab PCL-P18-DS-288, Nov, 26,2019 100% 12.09 1.85 1.43 0.00 0.00 0.00 15.365

RoofBeams PCL-P18-DS-287, Nov, 20,2019 100% 2.00 0.08 1.37 5.78 2.21 0.00 11.439

Mumty Roof Slab PCL-P18-DS-294, Dec, 06,2019 100% 1.06 0.00 0.00 0.00 0.00 0.00 1.056

Mumty Roof Beam PCL-P18-DS-294, Dec, 06,2019 100% 0.26 0.00 0.19 0.64 0.00 0.00 1.089

Stair Case

Basement-2 PCL-P18-DS-109, April, 22,2019 100% 0.15 0.22 0.00 0.00 0.00 0.00 0.363

Basement-3 PCL-P18-DS-109, April, 22,2019 100% 0.15 0.22 0.00 0.00 0.00 0.00 0.363

Ground Floor PCL-P18-DS-109, April, 22,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

Ground Floor PCL-P18-DS-147, June, 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

First Floor PCL-P18-DS-109, April, 22,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

First Floor PCL-P18-DS-147, June, 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

Seconed Floor PCL-P18-DS-109, April, 22,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

Seconed Floor PCL-P18-DS-147, June, 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

Third Floor PCL-P18-DS-109, April, 22,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

SQS:Khan Page 16 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 7" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:

Grade 60 Re Bars

Description Submital & Date Total Length Activity Wise #10 #12 #16 #20 #25 #32 Line Length

Third Floor PCL-P18-DS-147, June, 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

Forth Floor PCL-P18-DS-109, April, 22,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

Forth Floor PCL-P18-DS-147, June, 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

Fifth Floor PCL-P18-DS-109, April, 22,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

Fifth Floor PCL-P18-DS-147, June, 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

Sixth Floor -3 PCL-P18-DS-147, June, 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

Lintels

Basement PCL-P18-DS-226 ,Oct 17,19 0.03 0.07 0.00 0.00 0.00 0.00 -

Ground Floor PCL-P18-DS-226 ,Oct 17,19 100% 0.58 0.87 0.00 0.04 0.00 0.00 1.482

First Floor PCL-P18-DS-226 ,Oct 17,19 100% 0.58 0.89 0.00 0.04 0.00 0.00 1.503

Seconed Floor PCL-P18-DS-226 ,Oct 17,19 100% 0.58 0.89 0.00 0.04 0.00 0.00 1.503

Third Floor PCL-P18-DS-226 ,Oct 17,19 100% 0.58 0.89 0.00 0.04 0.00 0.00 1.503

Forth Floor PCL-P18-DS-226 ,Oct 17,19 100% 0.58 0.89 0.00 0.04 0.00 0.00 1.503

Fifth Floor PCL-P18-DS-226 ,Oct 17,19 100% 0.58 0.89 0.00 0.04 0.00 0.00 1.503

Sixth Floor PCL-P18-DS-226 ,Oct 17,19 100% 0.25 0.40 0.00 0.00 0.00 0.00 0.654

Mumty PCL-P18-DS-226 ,Oct 17,19 100% 0.01 0.02 0.00 0.00 0.00 0.00 0.031

SQS:Khan Page 17 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 7" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:

Grade 60 Re Bars

Description Submital & Date Total Length Activity Wise #10 #12 #16 #20 #25 #32 Line Length

U.G.W Tanks 10.57

U.G.W Tanks PCL-P18-DS-248,9/26/2019 100% 2.70 3.84 0.00 0.00 0.00 0.00 6.540

O.H.W Tanks PCL-P18-DS-248,9/26/2019 100% 1.34 2.68 0.00 0.00 0.00 0.00 4.026

Parapet Wall 2.07

Parapet Wall PCL-P18-DS-227 , 01 Nov, 19 100% 1.03 0.00 0.00 0.00 0.00 0.00 1.028

Parapet Wall PCL-P18-DS-288 , 26 Nov, 19 100% 1.04 0.00 0.00 0.00 0.00 0.00 1.038

Parapet Wall MUMTY & OHWT 100% 0.40 0.396


-
LENGTH
(Metre) 0.000 0.000 0.000 0.000 667.085 272.945 68.058 143.270 135.767 47.545 0.000 667.481

SQS:Khan Page 18 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Mock up Villa" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Villa Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level,
Slab & Beam, Retaining Wall, Parapet Wall Revised by:

Grade 60 Re Bars
Total Weight
Description Submittal With date of Activity #10 #12 #16 #20 #25 #32 Line Weight
PCL-P18-DS-217, DATE 29-08-2019
Raft 10.494

Raft 100% 0.000 10.494 0.000 0.000 0.000 0.000 10.494


PCL-P18-DS-219, DATE 03-09-2019
RCC Wall 2.370 0.000 0.000 0.000 0.000 0.000 -

Basement Wall 100% 2.370 0.000 0.000 0.000 0.000 0.000 2.370
Plinth Beams PCL-P18-DS-220, DATE 29-08-2019 0.900 -

Ground Floor 100% 0.232 0.000 0.198 0.471 0.000 0.000 0.900
Columns Dowels PCL-P18-DS-217, DATE 29-08-2019 6.317 -

Basement to Ist Lap 100% 0.040 0.000 0.000 0.691 0.000 0.000 0.731
Columns (BASEMENT-1LF) PCPL-P18-DS-199, DATE 31-08-2019 -

Basement ist Lap to Ground 100% 0.280 0.000 0.000 1.669 0.000 0.000 1.949
Columns (1LF-2LF) PCPL-P18-DS-199, DATE 31-08-2019 -

Ground to Ist Floor 100% 0.280 0.000 0.000 1.609 0.000 0.000 1.889
Columns (2LF-TOP ROOF) PCPL-P18-DS-199, DATE 31-08-2019 -

Ist Floor to Roof 100% 0.244 0.000 0.000 1.234 0.000 0.000 1.478

SQS:Khan Page 19 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Mock up Villa" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Villa Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level,
Slab & Beam, Retaining Wall, Parapet Wall Revised by:

Grade 60 Re Bars
Total Weight
Description Submittal With date of Activity #10 #12 #16 #20 #25 #32 Line Weight

Columns (TOP ROOF-MUMTY) PCPL-P18-DS-199, DATE 31-08-2019 -

Roof to Mumty 100% 0.047 0.011 0.000 0.211 0.000 0.000 0.270
SOG PCL-P18-DS-218, DATE 29-08-2019 0.793 -

SOG 100% 0.000 0.793 0.000 0.000 0.000 0.000 0.793


Slab & Beams 19.335 -

PCL-P18-DS-226, DATE 03-09-2019


Basement Beams Floor 100% 0.122 0.000 0.000 0.536 0.000 0.000 0.658

PCL-P18-DS-227, DATE 03-09-2019


Slab 100% 0.446 1.165 0.000 0.000 0.000 0.000 1.611

PCL-P18-DS-200, DATE 21-08-2019


Ground Beams Floor 100% 0.608 0.044 0.000 2.282 0.755 0.000 3.689

PCL-P18-DS-273, DATE 29-10-2019


Beams 100% 0.118 0.098 0.000 0.000 0.000 0.000 0.215

PCL-P18-DS-201, DATE 21-08-2019


Slab 100% 2.756 1.384 0.000 0.000 0.000 0.000 4.140

PCL-P18-DS-230, DATE 11-09-2019


First Floor Beams 100% 0.559 0.000 0.000 2.183 0.515 0.000 3.258

SQS:Khan Page 20 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Mock up Villa" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Villa Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level,
Slab & Beam, Retaining Wall, Parapet Wall Revised by:

Grade 60 Re Bars
Total Weight
Description Submittal With date of Activity #10 #12 #16 #20 #25 #32 Line Weight

PCPL-P18-DS-274, DATE 29-10-2019


Slab 100% 2.427 1.157 0.000 0.000 0.000 0.000 3.583

PCL-P18-DS-232, DATE 11-19-2019


Mumty Floor Beams 100% 0.079 0.045 0.000 0.208 0.000 0.000 0.332

PCL-P18-DS-233, Dated 11-09-2019


Slab 100% 0.229 0.046 0.000 0.000 0.000 0.000 0.275
Stair Case (B TO 1 LEVEL) PCL-P18-DS-246, DATE 24-09-2019 -

Stair Case (B TO 1 LEVEL) 100% 0.044 0.507 0.000 0.000 0.000 0.000 0.551
Stair Case (1ST TO 2ND LEVEL) PCL-P18-DS-246, DATE 24-09-2019 0.000 0.000 0.000 0.000 0.000 0.000 -

Stair Case (1ST TO 2ND LEVEL) 100% 0.044 0.293 0.000 0.000 0.000 0.000 0.337
Stair Case (2 ND
LEVEL TO MUMTY) PCL-P18-DS-246, DATE 24-09-2019 0.000 0.000 0.000 0.000 0.000 0.000 -

Stair Case(2ND LEVEL TO MUMTY) 100% 0.043 0.293 0.000 0.000 0.000 0.000 0.336
Lintels -

PCL-P18-DS-331, DATE 13,Feb 2020


Basement Floor 100% 0.028 0.045 0.000 0.000 0.000 0.000 0.072

PCL-P18-DS-331, DATE 13,Feb 2020


Ground Floor 100% 0.058 0.062 0.000 0.029 0.000 0.000 0.149

SQS:Khan Page 21 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Mock up Villa" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Villa Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level,
Slab & Beam, Retaining Wall, Parapet Wall Revised by:

Grade 60 Re Bars
Total Weight
Description Submittal With date of Activity #10 #12 #16 #20 #25 #32 Line Weight

PCL-P18-DS-331, DATE 13,Feb 2020


Ist Floor 100% 0.048 0.068 0.000 0.000 0.000 0.000 0.117

PCL-P18-DS-331, DATE 13,Feb 2020


Mumty Floor 100% 0.005 0.005 0.000 0.000 0.000 0.000 0.010

UGWT PCL-P18-DS-244, DATE 24-09-2019 4.258 -

U G W Tank 100% 0.000 0.000 0.000 0.000 0.000 0.000 -


OHWT PCL-P18-DS-244, DATE 24-09-2019 -

O H W Tank 100% 0.576 0.149 0.000 0.000 0.000 0.000 0.725


Swimming Pool PCL-P18-DS- -

Swimming Pool 100% 0.862 2.671 0.000 0.000 0.000 0.000 3.533
Parapet PCPL-P18-DS-201, DATE 21-08-2019 1.319 -

Parapet 100% 0.390 0.000 0.000 0.000 0.000 0.000 0.390


Parapet PCPL-P18-DS-233, DATE 11-09-2019 -

Parapet 100% 0.198 0.000 0.000 0.000 0.000 0.000 0.198


Parapet PCPL-P18-DS-274, DATE 29-10-2019 -

Parapet 100% 0.732 0.000 0.000 0.000 0.000 0.000 0.732


Weight
(Tons) 0.000 0.000 0.000 0.000 0.000 45.787 13.863 19.333 0.198 11.124 1.270 0.000 45.788

Principal QS Checked By (Consultant) Approved By Consultant Manger

SQS:Khan Page 22 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:

Grade 60 Re Bars

Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight

Raft 119.816

Raft-1 PCL-P18-DS-078-March 21,2019 100% 0.00 0.00 36.64 0.00 0.00 0.00 36.638

Extra -1 PCL-P18-DS-072-April 05,2019 100% 0.00 0.00 4.49 0.00 0.00 0.00 4.485

Raft-2 PCL-P18-DS-079-March 21,2019 100% 0.00 0.04 36.51 0.00 0.00 0.00 36.555

Raft-3 PCL-P18-DS-069-April 05,2019 100% 0.00 0.00 39.97 0.00 0.00 0.00 39.971

Plumbing drain PCL-P18-DS-080-April 05,2019 100% 0.00 0.00 1.86 0.00 0.00 0.00 1.857

Sump pit PCL-P18-DS-107-April 24,2019 100% 0.10 0.00 0.21 0.00 0.00 0.00 0.309

Ramp With Foundation PCL-P18-DS-304 Dec 19,2019 2.83 9.67 0.00 0.00 0.00 0.00 -

Retaining Wall 15.605 -

PCL-P18-DS-075 March 25,2019 100% 6.11 9.49 0.00 0.00 0.00 0.00 15.605

SQS:Khan Page 23 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:

Grade 60 Re Bars

Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight

Lift Wall Shear Wall 46.983 -

Found to Raft -2 PCL-P18-DS-079 - March21,2019 100% 0.74 0.75 1.03 0.49 0.00 0.00 3.010

Found to Raft -3 PCL-P18-DS-101 - April 16,2019 100% 0.70 0.54 1.04 0.40 0.00 0.00 2.685

Raft to Ground-2 PCL-P18-DS-086 - March28,2019 100% 1.12 0.56 0.00 0.59 0.00 0.00 2.275

Raft to Ground-3 PCL-P18-DS-101 - April 16,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667

Ground to Ist -2 PCL-P18-DS-135 - May 23,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667

Ground to Ist -3 PCL-P18-DS-144 - June 13,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667

Ist ~2nd-2 PCL-P18-DS-135 - May 23,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667

Ist ~2nd-3 PCL-P18-DS-144 - June 13,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667

2nd T o 3rd -2 PCL-P18-DS-135 - May 23,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667

2nd T o 3rd -3 PCL-P18-DS-144 - June 13,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667

SQS:Khan Page 24 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:

Grade 60 Re Bars

Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight

3rd to 4th-2 PCL-P18-DS-135 - May 23,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667

3rd to 4th-3 PCL-P18-DS-144 - June 13,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667

4th to 5th-2 PCL-P18-DS-135 - May 23,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667

4th to 5th-3 PCL-P18-DS-144 - June 13,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667

5th to 6th-2 PCL-P18-DS-135 - May 23,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667

5th to 6th-3 PCL-P18-DS-144 - June 13,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667

6th to Mumty -2 PCL-P18-DS-285 - Nov 14,2019 100% 0.98 0.48 0.00 0.47 0.00 0.00 1.936

6th to Mumty -3 PCL-P18-DS-285 - Nov 14,2019 100% 1.24 0.64 0.00 0.52 0.00 0.00 2.402

Columns 76.286 -

Columns Raft Dowel-1 PCL-P18-DS-078 March 21,2019 100% 0.57 0.00 0.00 0.60 1.15 0.00 2.317

Columns Raft Dowel-2 PCL-P18-DS-079 March 21 ,2019 100% 0.17 0.02 0.00 0.90 0.34 0.00 1.431

SQS:Khan Page 25 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:

Grade 60 Re Bars

Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight

Columns Raft Dowel-3 PCL-P18-DS-069 April 05 ,2019 100% 0.19 0.00 0.00 0.92 0.45 0.00 1.567

Columns Raft to Ground-1 PCL-P18-DS-081 March 25,2019 100% 0.23 0.00 0.00 0.75 2.05 0.00 3.031

Columns Raft to Ground-2 PCL-P18-DS-086 March 28 ,2019 100% 0.77 0.00 0.00 2.08 0.79 0.00 3.639

Columns Raft to Ground-3 PCL-P18-DS-101 April 16 ,2019 100% 0.84 0.00 0.00 2.13 1.06 0.00 4.031

Ground to Ist Floor-1 PCL-P18-DS-108 April 20,2019 100% 0.67 0.00 0.00 0.58 1.33 0.00 2.573

Ground to Ist Floor-2 PCL-P18-DS-134 May 23 ,2019 100% 0.78 0.00 0.00 2.08 0.72 0.00 3.583

Ground to Ist Floor-3 PCL-P18-DS-143 June 13 ,2019 100% 0.89 0.00 0.00 2.13 0.97 0.00 3.985

Ist to 2nd Floor-1 PCL-P18-DS-124 May 10 ,2019 100% 0.67 0.00 0.00 0.75 1.69 0.00 3.108

Ist to 2nd Floor-2 PCL-P18-DS-134 May 23 ,2019 100% 0.78 0.00 0.00 2.08 0.72 0.00 3.583

Ist to 2nd Floor-3 PCL-P18-DS-143 June 13 ,2019 100% 0.89 0.00 0.00 2.13 0.97 0.00 3.985

2nd to 3rd Floor-1 PCL-P18-DS-142 June 12 ,2019 100% 0.68 0.00 0.00 1.34 1.16 0.00 3.178

SQS:Khan Page 26 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:

Grade 60 Re Bars

Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight

2nd to 3rd Floor-2 PCL-P18-DS-134 May 23 ,2019 100% 0.79 0.00 0.00 2.33 0.50 0.00 3.613

2nd to 3rd Floor-3 PCL-P18-DS-143 June 13 ,2019 100% 0.90 0.00 0.00 2.46 0.66 0.00 4.024

3rd to 4th Floor-1 PCL-P18-DS-142 June 12 ,2019 100% 0.52 0.00 0.00 1.80 0.00 0.00 2.319

3rd to 4th Floor-2 PCL-P18-DS-134 May 23 ,2019 100% 0.72 0.00 0.00 2.53 0.00 0.00 3.245

3rd to 4th Floor-3 PCL-P18-DS-143 June 13 ,2019 100% 0.81 0.00 0.00 2.73 0.00 0.00 3.534

4th to 5th Floor-1 PCL-P18-DS-142 June 12 ,2019 100% 0.52 0.00 0.07 1.68 0.00 0.00 2.260

4th to 5th Floor-2 PCL-P18-DS-134 May 23 ,2019 100% 0.72 0.00 0.00 2.51 0.00 0.00 3.223

4th to 5th Floor-3 PCL-P18-DS-143 June 13 ,2019 100% 0.81 0.00 0.07 2.62 0.00 0.00 3.496

5th to 6th Floor-1 PCL-P18-DS-142 June 12 ,2019 100% 0.48 0.00 0.49 0.75 0.00 0.00 1.719

5th to 6th Floor-2 PCL-P18-DS-134 May 23 ,2019 100% 0.70 0.00 0.18 1.72 0.00 0.00 2.596

5th to 6th Floor-3 PCL-P18-DS-143 June 13 ,2019 100% 0.78 0.00 0.24 1.82 0.00 0.00 2.838

SQS:Khan Page 27 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:

Grade 60 Re Bars

Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight

Columns 6th to Mumty-1 PCL-P18-DS-142 June 12 ,2019 100% 0.50 0.00 0.30 0.77 0.00 0.00 1.561

Columns 6th to Mumty-2 PCL-P18-DS-284 Nov 14 ,2019 100% 0.15 0.00 0.00 0.39 0.00 0.00 0.537

Columns 6th to Pent House-3 PCL-P18-DS-143 June 13 ,2019 100% 0.26 0.00 0.00 0.69 0.00 0.00 0.953

Columns Pent House to Mumty-3 PCL-P18-DS-284 Nov 14 ,2019 100% 0.05 0.00 0.00 0.31 0.00 0.00 0.357

Slab & Beam,Lintles,Stair 405.073 -

Ground Floor Slab-1 PCL-P18-DS-096 April 10 ,2019 100% 14.53 2.31 0.00 0.00 0.00 0.00 16.845

Ground Floor Beam-1 PCL-P18-DS-094 April 08 ,2019 100% 1.39 0.30 1.50 4.30 3.54 0.00 11.028

Ground Floor Slab-2 PCL-P18-DS-125 May 15 ,2019 100% 9.28 0.96 0.00 0.00 0.00 0.00 10.237

Ground Floor Beam-2 PCL-P18-DS-123 May 09 ,2019 100% 1.32 0.00 0.90 3.90 0.00 0.00 6.120

Ground Floor Slab-3 PCL-P18-DS-177 July 18 ,2019 100% 11.16 0.60 0.00 0.00 0.00 0.00 11.761

Ground Floor Beam-3 PCL-P18-DS-131 May 21 ,2019 100% 1.70 0.00 0.95 4.80 1.88 0.00 9.332

SQS:Khan Page 28 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:

Grade 60 Re Bars

Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight

Ist Floor Slab-1 PCL-P18-DS-116 April 30 ,2019 100% 8.08 2.48 0.00 0.00 0.00 0.00 10.563

Ist Floor Beam-1 PCL-P18-DS-117 May 2 ,2019 100% 1.03 0.00 0.33 2.54 2.70 0.00 6.592

Ist Floor Slab-2 PCL-P18-DS-159 July03 ,2019 100% 6.98 0.95 0.00 0.00 0.00 0.00 7.935

Ist Floor Beam-2 PCL-P18-DS-158 July 03 ,2019 100% 1.34 0.00 1.09 4.13 0.00 0.00 6.566

Ist Floor Slab-3 PCL-P18-DS-204 August 21 ,2019 100% 7.78 0.60 0.00 0.00 0.00 0.00 8.386

Ist Floor Beam-3 PCL-P18-DS-203 August 21 ,2019 100% 1.55 0.00 1.31 3.88 1.20 0.00 7.934

2nd Floor Slab-1 PCL-P18-DS-130 May 18 ,2019 100% 8.50 2.48 0.00 0.00 0.00 0.00 10.982

2nd Floor Beam-1 PCL-P18-DS-129 May 18 ,2019 100% 1.02 0.00 0.33 2.31 2.96 0.00 6.614

2nd Floor Slab-2 PCL-P18-DS-161 July 31 ,2019 100% 7.53 0.95 0.00 0.00 0.00 0.00 8.483

2nd Floor Beam-2 PCL-P18-DS-160 July 03 ,2019 100% 1.34 0.00 1.15 4.05 0.00 0.00 6.534

2nd Floor Slab-3 PCL-P18-DS-222 August 29, ,2019 100% 8.21 0.60 0.00 0.00 0.00 0.00 8.814

SQS:Khan Page 29 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:

Grade 60 Re Bars

Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight

2nd Floor Beam-3 PCL-P18-DS-221 August 29, ,2019 100% 1.55 0.00 1.31 3.64 1.58 0.00 8.070

3rd Floor Slab-1 PCL-P18-DS-130 May 18 ,2019 100% 8.50 2.48 0.00 0.00 0.00 0.00 10.982

3rd Floor Beam-1 PCL-P18-DS-129 May 18 ,2019 100% 1.02 0.00 0.33 2.31 2.96 0.00 6.614

3rd Floor Slab-2 PCL-P18-DS-161 July 31 ,2019 100% 7.53 0.95 0.00 0.00 0.00 0.00 8.483

3rd Floor Beam-2 PCL-P18-DS-160 July 03 ,2019 100% 1.34 0.00 1.15 4.05 0.00 0.00 6.534

3rd Floor Slab-3 PCL-P18-DS-222 August 29, ,2019 100% 8.21 0.60 0.00 0.00 0.00 0.00 8.814

3rd Floor Beam-3 PCL-P18-DS-221 August 29, ,2019 100% 1.55 0.00 1.31 3.64 1.58 0.00 8.070

4th Floor Slab-1 PCL-P18-DS-130 May 18 ,2019 100% 8.50 2.48 0.00 0.00 0.00 0.00 10.982

4th Floor Beam-1 PCL-P18-DS-129 May 18 ,2019 100% 1.02 0.00 0.33 2.31 2.96 0.00 6.614

4th Floor Slab-2 PCL-P18-DS-161 July 31 ,2019 100% 7.53 0.95 0.00 0.00 0.00 0.00 8.483

4th Floor Beam-2 PCL-P18-DS-160 July 03 ,2019 100% 1.34 0.00 1.15 4.05 0.00 0.00 6.534

SQS:Khan Page 30 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:

Grade 60 Re Bars

Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight

4th Floor Slab-3 PCL-P18-DS-222 August 29, ,2019 100% 8.21 0.60 0.00 0.00 0.00 0.00 8.814

4th Floor Beam-3 PCL-P18-DS-221 August 29, ,2019 100% 1.55 0.00 1.31 3.64 1.58 0.00 8.070

5th Floor Slab-1 PCL-P18-DS-130 May 18 ,2019 100% 8.50 2.48 0.00 0.00 0.00 0.00 10.982

5th Floor Beam-1 PCL-P18-DS-129 May 18 ,2019 100% 1.02 0.00 0.33 2.31 2.96 0.00 6.614

5th Floor Slab-2 PCL-P18-DS-161 July 31 ,2019 100% 7.53 0.95 0.00 0.00 0.00 0.00 8.483

5th Floor Beam-2 PCL-P18-DS-160 July 03 ,2019 100% 1.34 0.00 1.15 4.05 0.00 0.00 6.534

5th Floor Slab-3 PCL-P18-DS-222 August 29, ,2019 100% 8.21 0.60 0.00 0.00 0.00 0.00 8.814

5th Floor Beam-3 PCL-P18-DS-221 August 29, ,2019 100% 1.55 0.00 1.31 3.64 1.58 0.00 8.070

6th Floor Slab PCL-P18-DS-277 Nov01 ,2019 100% 22.31 3.91 0.00 0.00 0.00 0.00 26.224

6th Floor Beam PCL-P18-DS-275 Oct 29 ,2019 100% 3.82 0.18 2.93 10.65 4.83 0.00 22.407

Roof Slab PCL-P18-DS-288 Nov 26 ,2019 100% 12.09 1.85 1.43 0.00 0.00 0.00 15.365

SQS:Khan Page 31 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:

Grade 60 Re Bars

Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight

Roof Beams PCL-P18-DS-287 Nov 20 ,2019 100% 2.00 0.08 1.37 5.78 2.21 0.00 11.439

Mumty Slab PCL-P18-DS-294 Dec 06 ,2019 100% 1.06 0.00 0.00 0.00 0.00 0.00 1.056

Mumty Beam PCL-P18-DS-294 Dec 06 ,2019 100% 0.26 0.00 0.19 0.64 0.00 0.00 1.089
Lintles -

Basement PCL-P18-DS-109 April 22,19 0% 0.03 0.07 0.00 0.00 0.00 0.00 -

Ground Floor PCL-P18-DS-109 April 22,19 100% 0.58 0.87 0.00 0.04 0.00 0.00 1.482

First Floor PCL-P18-DS-109 April 22,19 100% 0.58 0.89 0.00 0.04 0.00 0.00 1.503

Seconed PCL-P18-DS-109 April 22,19 100% 0.58 0.89 0.00 0.04 0.00 0.00 1.503

Third Floor PCL-P18-DS-109 April 22,19 100% 0.58 0.89 0.00 0.04 0.00 0.00 1.503

Forth Floor PCL-P18-DS-109 April 22,19 100% 0.58 0.89 0.00 0.04 0.00 0.00 1.503

Fifth Floor PCL-P18-DS-109 April 22,19 100% 0.58 0.89 0.00 0.04 0.00 0.00 1.503

Sixth Floor PCL-P18-DS-109 April 22,19 100% 0.25 0.40 0.00 0.00 0.00 0.00 0.654

Mumty PCL-P18-DS-109 April 22,19 100% 0.01 0.02 0.00 0.00 0.00 0.00 0.031

SQS:Khan Page 32 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:

Grade 60 Re Bars

Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight

Stairs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -

Basement Floor -2 PCL-P18-DS-109 April 22,2019 100% 0.15 0.22 0.00 0.00 0.00 0.00 0.363

Basement Floor -3 PCL-P18-DS-109 April 22,2019 100% 0.15 0.22 0.00 0.00 0.00 0.00 0.363

Ground Floor -2 PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

Ground Floor -3 PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

First Floor-2 PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

First Floor-3 PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

Seconed Floor PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

Seconed Floor PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

Third Floor PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

Third Floor PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

Forth Floor PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

SQS:Khan Page 33 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:

Grade 60 Re Bars

Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight

Forth Floor PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

Fifth Floor PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

Fifth Floor PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

Sixth Floor PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

Sixth Floor PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

Mumty PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387

Over Head .Water Tank 4.159 -

PCL-P18-DS-300 Dec 14,2019 100% 1.48 2.68 0.00 0.00 0.00 0.00 4.159

Parapet Wall 2.066 -

PCL-P18-DS-227 01 Nov, 19 100% 1.03 0.00 0.00 0.00 0.00 0.00 1.028

PCL-P18-DS-300 Dec 14,, 19 100% 1.04 0.00 0.00 0.00 0.00 0.00 1.038

Parapet Wall MUMTY & OHWT 100% 0.40 0.396


Weight
(Tons) #10 #12 #16 #20 #25 #32 Total(Tons)
Weight
(Tons) 0.000 0.000 0.000 0.000 0.000 670.000 0.00 277.000 75.000 146.000 136.000 49.000 0.000 670.000

SQS:Khan Page 34 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:

Grade 60 Re Bars

Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight
Principal QS Checked By (Consultant) Approved By Consultant Manger

SQS:Khan Page 35 of 37
Steel Justification Pavilion-06 & 07

Sr. Description Steel Wt. Ton

IPA # 5 Quantity

Approved upto IPA # 5


1 668
Pavilion-06
Approved upto IPA # 5
2 658.854
Pavilion-07
Approved upto IPA # 5
3 45.788
Mockup Villa

Sub Total - 1 1372.642

Chairs & Pins 45.187

Grand Total 1417.829

Estimated Balance Works

4 Remaining work Ramp & UGWT 20.00

5 Estimated chairs 0.50

6 Total Steel Consumption 1428.46

Steel Scrap

7 Scrap at yard Approx. 45

Total 45

Wastage % 3.15

Total Steel Consumed Including Wastage 1473.46

Steel Transfer

8 Steel Received till date 1582.98

9 Steel in Hand 109.52

10 Steel present at yard Approx. -76.50


(10mm,12mm,20mm,25mm)

11 Return to EEPL (20mm, 700 full lengths) -21.05

12 Shifted to Cluster-G (12mm,20mm,25mm) -7.5

13 Shifted to Pavilion-04 (25mm) -4.6

14 Missing -0.12
Steel Justification Pavilion-04

Sr. Description Steel Wt. Ton

Total Steel Consumption

Approved upto IPA # 03


1 596.93
Pavilion-04

Sub Total - 1 596.93

2 Chairs & Pins 16.771

3 Remaining works as per IPC claims 50.07

A Net Steel Consumption 663.77

Total Steel Received

4 Steel Received till date 610

5 Shifted from Pavilion-06 & 07(10mm) 36

6 Shifted from Pavilion-06 & 07 (12mm) 7.5

7 Shifted from Pavilion-06 & 07 (20mm) 29.05

8 Shifted from Pavilion-06 & 07 (25mm) 6.4

B Total Steel Received 688.95

Steel in Hand

11 Scrap at yard Approx. 25.18

Total Steel in Hand (B-A) 25.18

Wastage % (11/ A) 3.793%

You might also like