STEEL RECEIVED AT SITE (EIGHTEEN APARTMENT BUILDING PAVILION-06 & 07)
34 12 mm
35 16 mm PAK Steel
36 25 mm
37 12 mm
PAK Steel
38 20 mm
STEEL RECEIVED IN January-2020 (PAVILION-06 & 07)
39 10 mm PAK Steel
STEEL RECEIVED IN March-2020 (PAVILION-06 & 07)
40 10mm PAK Steel
TOTAL STEEL RECEIVED FOR P# 6 & 7 & Provisonaly Buildings
STEEL RECEIVED IN JULY-2019 (MOCKUP VILLA)
1 10 mm
2 12 mm
3 16 mm PAK Steel
4 20 mm
5 25 mm
STEEL RECEIVED IN SEPTEMBER-2019 (MOCKUP VILLA)
1 10 mm
2 12 mm
3 20 mm PAK Steel
4 25 mm
SQS:Khan Page 2 of 37
Date: February-20
Steel Received Steel Received
Date (Ton)
19.998
23.035
4-Feb-19 59.430
30.548
16.915
12-Feb-19 32.595
17-Mar-19 34.910
21-Mar-19 80.690
22-Mar-19 61.360
35.065
12-Apr-19 4.360
30.775
30.030
14-Apr-19
40.000
22-Apr-19 31.715
30-Apr-19 15.040
101.085
15-May-19
12.280
36.150
21-May-19 12.990
18.355
50.090
27-May-19
21.000
11.140
21-Aug-19
40.280
8-Sep-19 20.335
75.960
19-Sep-19
18.160
4.070
1-Oct-19 79.465
24.285
5-Oct-19 123.360
28.800
7-Oct-19
29.740
SQS:Khan Page 3 of 37
Date: February-20
Steel Received Steel Received
Date (Ton)
22.050
10-Dec-19 16.930
19.930
26.718
18-Dec-19
78.728
20-Jan-20 72.860
22-Mar-20 46.305
1,537.531
1.000
14.000
30-Jul-19 1.000
3.000
1.000
11.100
6.605
14-Sep-19 7.425
0.320
45.450
1,582.981
SQS:Khan Page 4 of 37
Steel Justification Pavilion-06 & 07
Sr. Description Steel Wt. Ton
IPA # 4 Quantity
1 Approved upto IPA # 4 650
Pavilion-06
2 Approved upto IPA # 4 618
Pavilion-07
3 Approved upto IPA # 4 42
Mockup Villa
Total 1310
#REF!
Total Steel Consumed Including Wastage
Steel Transfer
6 Steel Received till date 1582.98
1465.96
Total Steel Consumed Including Wastage
Steel Transfer
18 Steel Received till date 1582.98
Grade 60 Re Bars
Description Submital & Date Total Length Activity Wise #10 #12 #16 #20 #25 #32 Line Length
Raft 117.204
Zone-1 Raft PCL-P18-DS-073 100% 0.000 0.000 39.853 0.000 0.000 0.000 39.853
Zone-2 Raft PCL-P18-DS-084 100% 0.000 0.000 36.539 0.000 0.000 0.000 36.539
Zone-3 Raft PCL-P18-DS-098 100% 0.000 0.000 38.646 0.000 0.000 0.000 38.646
Plumbing drain PCL-P18-DS-080 100% 0.000 0.000 1.857 0.000 0.000 0.000 1.857
Sump pit PCL-P18-DS-107 100% 0.102 0.000 0.207 0.000 0.000 0.000 0.309
Retaining Wall PCL-P18-DS-075 100% 5.60 8.92 0.00 0.00 0.00 0.00 14.529
Basement ~Ground Floor Zone-3 PCL-P18-DS-101, dated Apr 16, 2019 100% 1.236 0.755 0.000 0.68 0.00 0.00 2.667
Ground Floor Zone-3 PCL-P18-DS-144, dated June 13, 2019 100% 1.236 0.755 0.000 0.68 0.00 0.00 2.667
SQS:Khan Page 10 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 7" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:
Grade 60 Re Bars
Description Submital & Date Total Length Activity Wise #10 #12 #16 #20 #25 #32 Line Length
First Floor Zone-3 PCL-P18-DS-144, dated June 13, 2019 100% 1.236 0.755 0.000 0.68 0.00 0.00 2.667
Second 5 Zone-3 PCL-P18-DS-144, dated June 13, 2019 100% 1.236 0.755 0.000 0.68 0.00 0.00 2.667
Third Floor Zone-3 PCL-P18-DS-144, dated June 13, 2019 100% 1.236 0.755 0.000 0.68 0.00 0.00 2.667
Forth Floor Zone-3 PCL-P18-DS-144, dated June 13, 2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667
Fifth Floor Zone-3 PCL-P18-DS-144, dated June 13, 2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667
PCL-P18-DS-1???, dated ??
Mumty 0% 0.00 0.00 0.00 0.00 0.00 0.00 -
Columns 76.82
Raft Dowel Zone-1 PCL-P18-DS-073, dated Mar 16, 2019 100% 0.57 0.00 0.00 0.60 1.15 0.00 2.317
Raft Dowel Zone-2 PCL-P18-DS-084, dated Mar 26, 2019 100% 0.24 0.00 0.00 1.09 0.34 0.00 1.675
Raft Dowel Zone-3 PCL-P18-DS-098, dated Apr 18, 2019 100% 0.19 0.00 0.00 0.92 0.45 0.00 1.567
SQS:Khan Page 11 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 7" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:
Grade 60 Re Bars
Description Submital & Date Total Length Activity Wise #10 #12 #16 #20 #25 #32 Line Length
Columns Zone-1 PCL-P18-DS-081, dated Mar 25, 2019 100% 0.23 0.00 0.00 0.75 2.05 0.00 3.031
Columns Zone-2 PCL-P18-DS-086, dated Mar 28, 2019 100% 0.77 0.00 0.00 2.08 0.79 0.00 3.639
Columns Zone-3 PCL-P18-DS-101, dated Apr 16, 2019 100% 0.84 0.00 0.00 2.13 1.06 0.00 4.031
Columns Zone-1 PCL-P18-DS-108, dated Apr 20, 2019 100% 0.67 0.00 0.00 0.58 1.33 0.00 2.573
Columns Zone-2 PCL-P18-DS-134, dated May 23, 2019 100% 0.78 0.00 0.00 2.08 0.72 0.00 3.583
Columns Zone-3 PCL-P18-DS-143, dated June 13, 2019 100% 0.89 0.00 0.00 2.13 0.97 0.00 3.985
Columns Zone-1 PCL-P18-DS-124, dated May 10, 2019 100% 0.67 0.00 0.00 0.75 1.69 0.00 3.108
Columns Zone-2 PCL-P18-DS-134, dated May 23, 2019 100% 0.78 0.00 0.00 2.08 0.72 0.00 3.583
Columns Zone-3 PCL-P18-DS-143, dated June 13, 2019 100% 0.89 0.00 0.00 2.13 0.97 0.00 3.985
Columns Zone-1 PCL-P18-DS-142, dated June 12, 2019 100% 0.68 0.00 0.00 1.34 1.16 0.00 3.178
Columns Zone-2 PCL-P18-DS-134, dated May 23, 2019 100% 0.79 0.00 0.00 2.33 0.50 0.00 3.613
Columns Zone-3 PCL-P18-DS-143, dated June 13, 2019 100% 0.90 0.00 0.00 2.46 0.66 0.00 4.024
Columns Zone-1 PCL-P18-DS-142, dated June 12, 2019 100% 0.52 0.00 0.00 1.80 0.00 0.00 2.319
Columns Zone-2 PCL-P18-DS-134, dated May 23, 2019 100% 0.72 0.00 0.00 2.53 0.00 0.00 3.245
Columns Zone-3 PCL-P18-DS-143, dated June 13, 2019 100% 0.81 0.00 0.00 2.73 0.00 0.00 3.534
Columns Zone-1 PCL-P18-DS-142, dated June 12, 2019 100% 0.52 0.00 0.07 1.68 0.00 0.00 2.260
SQS:Khan Page 12 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 7" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:
Grade 60 Re Bars
Description Submital & Date Total Length Activity Wise #10 #12 #16 #20 #25 #32 Line Length
Columns Zone-2 PCL-P18-DS-134, dated May 23, 2019 100% 0.72 0.00 0.00 2.51 0.00 0.00 3.223
Columns Zone-3 PCL-P18-DS-143, dated June 13, 2019 100% 0.81 0.00 0.07 2.62 0.00 0.00 3.496
Columns Zone-1 PCL-P18-DS-142, dated June 12, 2019 100% 0.48 0.00 0.49 0.75 0.00 0.00 1.719
Columns Zone-2 PCL-P18-DS-134, dated May 23, 2019 100% 0.70 0.00 0.18 1.72 0.00 0.00 2.596
Columns Zone-3 PCL-P18-DS-143, dated June 13, 2019 100% 0.78 0.00 0.24 1.82 0.00 0.00 2.838
Columns Zone-1 PCL-P18-DS-142, dated June 12, 2019 100% 0.50 0.00 0.30 0.77 0.00 0.00 1.561
Columns Zone-2 PCL-P18-DS-134, dated May 23, 2019 100% 0.19 0.00 0.00 0.51 0.00 0.00 0.700
Columns Zone-3 PCL-P18-DS-143, dated June 13, 2019 100% 0.26 0.00 0.00 0.69 0.00 0.00 0.953
Columns Mumty Zone-3 PCL-P18-DS-143, dated June 13, 2019 100% 0.13 0.00 0.00 0.36 0.00 0.00 0.488
Ground Slab Floor -1 PCL-P18-DS-104,16 Apr, 18,2019 100% 11.59 2.48 0.00 0.00 0.00 0.00 14.068
Ground Beams Floor -1 PCL-P18-DS-102,16 Apr, 18,2019 100% 1.33 0.00 0.69 4.08 0.99 0.00 7.093
Ground Floor Slab -2 PCL-P18-DS-125, May, 15,2019 100% 9.37 0.96 0.00 0.00 0.00 0.00 10.330
Ground Floor Beams -2 PCL-P18-DS-123, May, 09,2019 100% 1.33 0.00 0.91 3.92 0.00 0.00 6.164
Ground Floor Beams -2 PCL-P18-DS-154, July, 01,2019 100% 0.02 0.10 0.42 0.04 1.04 0.00 1.614
Ground Slab Floor -3 PCL-P18-DS-177, July, 18,2019 100% 10.79 0.60 0.00 0.00 0.00 0.00 11.395
SQS:Khan Page 13 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 7" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:
Grade 60 Re Bars
Description Submital & Date Total Length Activity Wise #10 #12 #16 #20 #25 #32 Line Length
Ground Beams Floor -3 PCL-P18-DS-131, May, 21,2019 100% 1.66 0.00 0.94 4.74 1.88 0.00 9.217
First Floor Slab-1 PCL-P18-DS-116, April, 30,2019 100% 8.08 2.48 0.00 0.00 0.00 0.00 10.563
First Floor Beams-1 PCL-P18-DS-117, May, 02,2019 100% 1.03 0.00 0.33 2.54 2.70 0.00 6.592
First Floor Slab-2 PCL-P18-DS-159, July, 03,2019 100% 6.98 0.95 0.00 0.00 0.00 0.00 7.935
First Floor Beams-2 PCL-P18-DS-158, July, 03,2019 100% 1.33 0.00 1.09 4.14 0.00 0.00 6.558
First Floor Slab-3 PCL-P18-DS-204, August, 21,2019 100% 7.78 0.60 0.00 0.00 0.00 0.00 8.386
First Floor Beams-3 PCL-P18-DS-203, August, 21,2019 100% 1.55 0.00 1.31 3.88 1.20 0.00 7.934
Seconed Floor Slab -1 PCL-P18-DS-130, May, 18,2019 100% 8.50 2.48 0.00 0.00 0.00 0.00 10.982
Seconed Floor Beams -1 PCL-P18-DS-129, May, 18,2019 100% 1.02 0.00 0.33 2.31 2.96 0.00 6.614
Seconed Floor Slab -2 PCL-P18-DS-161, July, 03,2019 100% 7.53 0.95 0.00 0.00 0.00 0.00 8.483
Seconed Floor Beams -2 PCL-P18-DS-161, July, 03,2019 100% 1.34 0.00 1.15 4.05 0.00 0.00 6.534
Seconed Floor Slab -3 PCL-P18-DS-222, August, 29,2019 100% 8.21 0.60 0.00 0.00 0.00 0.00 8.814
Seconed Floor Beams -3 PCL-P18-DS-221, August, 29,2019 100% 1.55 0.00 1.31 3.64 1.58 0.00 8.070
Third Floor Slab-1 PCL-P18-DS-130, May, 18,2019 100% 8.50 2.48 0.00 0.00 0.00 0.00 10.982
Third Floor Beams-1 PCL-P18-DS-129, May, 18,2019 100% 1.02 0.00 0.33 2.31 2.96 0.00 6.614
Third Floor Slab-2 PCL-P18-DS-161, July, 03,2019 100% 7.53 0.95 0.00 0.00 0.00 0.00 8.483
SQS:Khan Page 14 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 7" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:
Grade 60 Re Bars
Description Submital & Date Total Length Activity Wise #10 #12 #16 #20 #25 #32 Line Length
Third Floor Beams-2 PCL-P18-DS-161, July, 03,2019 100% 1.34 0.00 1.15 4.05 0.00 0.00 6.534
Third Floor Slab-3 PCL-P18-DS-222, August, 29,2019 100% 8.21 0.60 0.00 0.00 0.00 0.00 8.814
Third Floor Beams-3 PCL-P18-DS-221, August, 29,2019 100% 1.55 0.00 1.31 3.64 1.58 0.00 8.070
Forth Floor Slab-1 PCL-P18-DS-130, May, 18,2019 100% 8.50 2.48 0.00 0.00 0.00 0.00 10.982
Forth Floor Beams -1 PCL-P18-DS-129, May, 18,2019 100% 1.02 0.00 0.33 2.31 2.96 0.00 6.614
Forth Floor Slab-2 PCL-P18-DS-161, July, 03,2019 100% 7.53 0.95 0.00 0.00 0.00 0.00 8.483
Forth Floor Beams-2 PCL-P18-DS-161, July, 03,2019 100% 1.34 0.00 1.15 4.05 0.00 0.00 6.534
Forth Floor Slab-3 PCL-P18-DS-222, August, 29,2019 100% 8.21 0.60 0.00 0.00 0.00 0.00 8.814
Forth Floor Beams -3 PCL-P18-DS-221, August, 29,2019 100% 1.55 0.00 1.31 3.64 1.58 0.00 8.070
Fifth Floor Slab -1 PCL-P18-DS-130, May, 18,2019 100% 8.50 2.48 0.00 0.00 0.00 0.00 10.982
Fifth Floor Beams-1 PCL-P18-DS-129, May, 18,2019 100% 1.02 0.00 0.33 2.31 2.96 0.00 6.614
Fifth Floor Slab-2 PCL-P18-DS-161, July, 03,2019 100% 7.53 0.95 0.00 0.00 0.00 0.00 8.483
Fifth Floor Beams-2 PCL-P18-DS-161, July, 03,2019 100% 1.34 0.00 1.15 4.05 0.00 0.00 6.534
Fifth Floor Slab -3 PCL-P18-DS-222, August, 29,2019 100% 8.21 0.60 0.00 0.00 0.00 0.00 8.814
Fifth Floor Beams -3 PCL-P18-DS-221, August, 29,2019 100% 1.55 0.00 1.31 3.64 1.58 0.00 8.070
Sixth Floor Slab PCL-P18-DS-277, Nov, 01,2019 100% 22.31 3.91 0.00 0.00 0.00 0.00 26.224
SQS:Khan Page 15 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 7" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:
Grade 60 Re Bars
Description Submital & Date Total Length Activity Wise #10 #12 #16 #20 #25 #32 Line Length
Sixth Floor Beams PCL-P18-DS-275, Oct, 29,2019 100% 3.82 0.18 2.93 10.65 4.83 0.00 22.407
Roof Slab PCL-P18-DS-288, Nov, 26,2019 100% 12.09 1.85 1.43 0.00 0.00 0.00 15.365
RoofBeams PCL-P18-DS-287, Nov, 20,2019 100% 2.00 0.08 1.37 5.78 2.21 0.00 11.439
Mumty Roof Slab PCL-P18-DS-294, Dec, 06,2019 100% 1.06 0.00 0.00 0.00 0.00 0.00 1.056
Mumty Roof Beam PCL-P18-DS-294, Dec, 06,2019 100% 0.26 0.00 0.19 0.64 0.00 0.00 1.089
Stair Case
Basement-2 PCL-P18-DS-109, April, 22,2019 100% 0.15 0.22 0.00 0.00 0.00 0.00 0.363
Basement-3 PCL-P18-DS-109, April, 22,2019 100% 0.15 0.22 0.00 0.00 0.00 0.00 0.363
Ground Floor PCL-P18-DS-109, April, 22,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
Ground Floor PCL-P18-DS-147, June, 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
First Floor PCL-P18-DS-109, April, 22,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
First Floor PCL-P18-DS-147, June, 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
Seconed Floor PCL-P18-DS-109, April, 22,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
Seconed Floor PCL-P18-DS-147, June, 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
Third Floor PCL-P18-DS-109, April, 22,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
SQS:Khan Page 16 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 7" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:
Grade 60 Re Bars
Description Submital & Date Total Length Activity Wise #10 #12 #16 #20 #25 #32 Line Length
Third Floor PCL-P18-DS-147, June, 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
Forth Floor PCL-P18-DS-109, April, 22,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
Forth Floor PCL-P18-DS-147, June, 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
Fifth Floor PCL-P18-DS-109, April, 22,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
Fifth Floor PCL-P18-DS-147, June, 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
Sixth Floor -3 PCL-P18-DS-147, June, 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
Lintels
Basement PCL-P18-DS-226 ,Oct 17,19 0.03 0.07 0.00 0.00 0.00 0.00 -
Ground Floor PCL-P18-DS-226 ,Oct 17,19 100% 0.58 0.87 0.00 0.04 0.00 0.00 1.482
First Floor PCL-P18-DS-226 ,Oct 17,19 100% 0.58 0.89 0.00 0.04 0.00 0.00 1.503
Seconed Floor PCL-P18-DS-226 ,Oct 17,19 100% 0.58 0.89 0.00 0.04 0.00 0.00 1.503
Third Floor PCL-P18-DS-226 ,Oct 17,19 100% 0.58 0.89 0.00 0.04 0.00 0.00 1.503
Forth Floor PCL-P18-DS-226 ,Oct 17,19 100% 0.58 0.89 0.00 0.04 0.00 0.00 1.503
Fifth Floor PCL-P18-DS-226 ,Oct 17,19 100% 0.58 0.89 0.00 0.04 0.00 0.00 1.503
Sixth Floor PCL-P18-DS-226 ,Oct 17,19 100% 0.25 0.40 0.00 0.00 0.00 0.00 0.654
Mumty PCL-P18-DS-226 ,Oct 17,19 100% 0.01 0.02 0.00 0.00 0.00 0.00 0.031
SQS:Khan Page 17 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 7" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:
Grade 60 Re Bars
Description Submital & Date Total Length Activity Wise #10 #12 #16 #20 #25 #32 Line Length
U.G.W Tanks PCL-P18-DS-248,9/26/2019 100% 2.70 3.84 0.00 0.00 0.00 0.00 6.540
O.H.W Tanks PCL-P18-DS-248,9/26/2019 100% 1.34 2.68 0.00 0.00 0.00 0.00 4.026
Parapet Wall PCL-P18-DS-227 , 01 Nov, 19 100% 1.03 0.00 0.00 0.00 0.00 0.00 1.028
Parapet Wall PCL-P18-DS-288 , 26 Nov, 19 100% 1.04 0.00 0.00 0.00 0.00 0.00 1.038
SQS:Khan Page 18 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Mock up Villa" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Villa Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level,
Slab & Beam, Retaining Wall, Parapet Wall Revised by:
Grade 60 Re Bars
Total Weight
Description Submittal With date of Activity #10 #12 #16 #20 #25 #32 Line Weight
PCL-P18-DS-217, DATE 29-08-2019
Raft 10.494
Basement Wall 100% 2.370 0.000 0.000 0.000 0.000 0.000 2.370
Plinth Beams PCL-P18-DS-220, DATE 29-08-2019 0.900 -
Ground Floor 100% 0.232 0.000 0.198 0.471 0.000 0.000 0.900
Columns Dowels PCL-P18-DS-217, DATE 29-08-2019 6.317 -
Basement to Ist Lap 100% 0.040 0.000 0.000 0.691 0.000 0.000 0.731
Columns (BASEMENT-1LF) PCPL-P18-DS-199, DATE 31-08-2019 -
Basement ist Lap to Ground 100% 0.280 0.000 0.000 1.669 0.000 0.000 1.949
Columns (1LF-2LF) PCPL-P18-DS-199, DATE 31-08-2019 -
Ground to Ist Floor 100% 0.280 0.000 0.000 1.609 0.000 0.000 1.889
Columns (2LF-TOP ROOF) PCPL-P18-DS-199, DATE 31-08-2019 -
Ist Floor to Roof 100% 0.244 0.000 0.000 1.234 0.000 0.000 1.478
SQS:Khan Page 19 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Mock up Villa" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Villa Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level,
Slab & Beam, Retaining Wall, Parapet Wall Revised by:
Grade 60 Re Bars
Total Weight
Description Submittal With date of Activity #10 #12 #16 #20 #25 #32 Line Weight
Roof to Mumty 100% 0.047 0.011 0.000 0.211 0.000 0.000 0.270
SOG PCL-P18-DS-218, DATE 29-08-2019 0.793 -
SQS:Khan Page 20 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Mock up Villa" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Villa Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level,
Slab & Beam, Retaining Wall, Parapet Wall Revised by:
Grade 60 Re Bars
Total Weight
Description Submittal With date of Activity #10 #12 #16 #20 #25 #32 Line Weight
Stair Case (B TO 1 LEVEL) 100% 0.044 0.507 0.000 0.000 0.000 0.000 0.551
Stair Case (1ST TO 2ND LEVEL) PCL-P18-DS-246, DATE 24-09-2019 0.000 0.000 0.000 0.000 0.000 0.000 -
Stair Case (1ST TO 2ND LEVEL) 100% 0.044 0.293 0.000 0.000 0.000 0.000 0.337
Stair Case (2 ND
LEVEL TO MUMTY) PCL-P18-DS-246, DATE 24-09-2019 0.000 0.000 0.000 0.000 0.000 0.000 -
Stair Case(2ND LEVEL TO MUMTY) 100% 0.043 0.293 0.000 0.000 0.000 0.000 0.336
Lintels -
SQS:Khan Page 21 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Mock up Villa" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Villa Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level,
Slab & Beam, Retaining Wall, Parapet Wall Revised by:
Grade 60 Re Bars
Total Weight
Description Submittal With date of Activity #10 #12 #16 #20 #25 #32 Line Weight
Swimming Pool 100% 0.862 2.671 0.000 0.000 0.000 0.000 3.533
Parapet PCPL-P18-DS-201, DATE 21-08-2019 1.319 -
SQS:Khan Page 22 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:
Grade 60 Re Bars
Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight
Raft 119.816
Raft-1 PCL-P18-DS-078-March 21,2019 100% 0.00 0.00 36.64 0.00 0.00 0.00 36.638
Extra -1 PCL-P18-DS-072-April 05,2019 100% 0.00 0.00 4.49 0.00 0.00 0.00 4.485
Raft-2 PCL-P18-DS-079-March 21,2019 100% 0.00 0.04 36.51 0.00 0.00 0.00 36.555
Raft-3 PCL-P18-DS-069-April 05,2019 100% 0.00 0.00 39.97 0.00 0.00 0.00 39.971
Plumbing drain PCL-P18-DS-080-April 05,2019 100% 0.00 0.00 1.86 0.00 0.00 0.00 1.857
Sump pit PCL-P18-DS-107-April 24,2019 100% 0.10 0.00 0.21 0.00 0.00 0.00 0.309
Ramp With Foundation PCL-P18-DS-304 Dec 19,2019 2.83 9.67 0.00 0.00 0.00 0.00 -
PCL-P18-DS-075 March 25,2019 100% 6.11 9.49 0.00 0.00 0.00 0.00 15.605
SQS:Khan Page 23 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:
Grade 60 Re Bars
Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight
Found to Raft -2 PCL-P18-DS-079 - March21,2019 100% 0.74 0.75 1.03 0.49 0.00 0.00 3.010
Found to Raft -3 PCL-P18-DS-101 - April 16,2019 100% 0.70 0.54 1.04 0.40 0.00 0.00 2.685
Raft to Ground-2 PCL-P18-DS-086 - March28,2019 100% 1.12 0.56 0.00 0.59 0.00 0.00 2.275
Raft to Ground-3 PCL-P18-DS-101 - April 16,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667
Ground to Ist -2 PCL-P18-DS-135 - May 23,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667
Ground to Ist -3 PCL-P18-DS-144 - June 13,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667
Ist ~2nd-2 PCL-P18-DS-135 - May 23,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667
Ist ~2nd-3 PCL-P18-DS-144 - June 13,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667
2nd T o 3rd -2 PCL-P18-DS-135 - May 23,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667
2nd T o 3rd -3 PCL-P18-DS-144 - June 13,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667
SQS:Khan Page 24 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:
Grade 60 Re Bars
Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight
3rd to 4th-2 PCL-P18-DS-135 - May 23,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667
3rd to 4th-3 PCL-P18-DS-144 - June 13,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667
4th to 5th-2 PCL-P18-DS-135 - May 23,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667
4th to 5th-3 PCL-P18-DS-144 - June 13,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667
5th to 6th-2 PCL-P18-DS-135 - May 23,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667
5th to 6th-3 PCL-P18-DS-144 - June 13,2019 100% 1.24 0.76 0.00 0.68 0.00 0.00 2.667
6th to Mumty -2 PCL-P18-DS-285 - Nov 14,2019 100% 0.98 0.48 0.00 0.47 0.00 0.00 1.936
6th to Mumty -3 PCL-P18-DS-285 - Nov 14,2019 100% 1.24 0.64 0.00 0.52 0.00 0.00 2.402
Columns 76.286 -
Columns Raft Dowel-1 PCL-P18-DS-078 March 21,2019 100% 0.57 0.00 0.00 0.60 1.15 0.00 2.317
Columns Raft Dowel-2 PCL-P18-DS-079 March 21 ,2019 100% 0.17 0.02 0.00 0.90 0.34 0.00 1.431
SQS:Khan Page 25 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:
Grade 60 Re Bars
Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight
Columns Raft Dowel-3 PCL-P18-DS-069 April 05 ,2019 100% 0.19 0.00 0.00 0.92 0.45 0.00 1.567
Columns Raft to Ground-1 PCL-P18-DS-081 March 25,2019 100% 0.23 0.00 0.00 0.75 2.05 0.00 3.031
Columns Raft to Ground-2 PCL-P18-DS-086 March 28 ,2019 100% 0.77 0.00 0.00 2.08 0.79 0.00 3.639
Columns Raft to Ground-3 PCL-P18-DS-101 April 16 ,2019 100% 0.84 0.00 0.00 2.13 1.06 0.00 4.031
Ground to Ist Floor-1 PCL-P18-DS-108 April 20,2019 100% 0.67 0.00 0.00 0.58 1.33 0.00 2.573
Ground to Ist Floor-2 PCL-P18-DS-134 May 23 ,2019 100% 0.78 0.00 0.00 2.08 0.72 0.00 3.583
Ground to Ist Floor-3 PCL-P18-DS-143 June 13 ,2019 100% 0.89 0.00 0.00 2.13 0.97 0.00 3.985
Ist to 2nd Floor-1 PCL-P18-DS-124 May 10 ,2019 100% 0.67 0.00 0.00 0.75 1.69 0.00 3.108
Ist to 2nd Floor-2 PCL-P18-DS-134 May 23 ,2019 100% 0.78 0.00 0.00 2.08 0.72 0.00 3.583
Ist to 2nd Floor-3 PCL-P18-DS-143 June 13 ,2019 100% 0.89 0.00 0.00 2.13 0.97 0.00 3.985
2nd to 3rd Floor-1 PCL-P18-DS-142 June 12 ,2019 100% 0.68 0.00 0.00 1.34 1.16 0.00 3.178
SQS:Khan Page 26 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:
Grade 60 Re Bars
Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight
2nd to 3rd Floor-2 PCL-P18-DS-134 May 23 ,2019 100% 0.79 0.00 0.00 2.33 0.50 0.00 3.613
2nd to 3rd Floor-3 PCL-P18-DS-143 June 13 ,2019 100% 0.90 0.00 0.00 2.46 0.66 0.00 4.024
3rd to 4th Floor-1 PCL-P18-DS-142 June 12 ,2019 100% 0.52 0.00 0.00 1.80 0.00 0.00 2.319
3rd to 4th Floor-2 PCL-P18-DS-134 May 23 ,2019 100% 0.72 0.00 0.00 2.53 0.00 0.00 3.245
3rd to 4th Floor-3 PCL-P18-DS-143 June 13 ,2019 100% 0.81 0.00 0.00 2.73 0.00 0.00 3.534
4th to 5th Floor-1 PCL-P18-DS-142 June 12 ,2019 100% 0.52 0.00 0.07 1.68 0.00 0.00 2.260
4th to 5th Floor-2 PCL-P18-DS-134 May 23 ,2019 100% 0.72 0.00 0.00 2.51 0.00 0.00 3.223
4th to 5th Floor-3 PCL-P18-DS-143 June 13 ,2019 100% 0.81 0.00 0.07 2.62 0.00 0.00 3.496
5th to 6th Floor-1 PCL-P18-DS-142 June 12 ,2019 100% 0.48 0.00 0.49 0.75 0.00 0.00 1.719
5th to 6th Floor-2 PCL-P18-DS-134 May 23 ,2019 100% 0.70 0.00 0.18 1.72 0.00 0.00 2.596
5th to 6th Floor-3 PCL-P18-DS-143 June 13 ,2019 100% 0.78 0.00 0.24 1.82 0.00 0.00 2.838
SQS:Khan Page 27 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:
Grade 60 Re Bars
Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight
Columns 6th to Mumty-1 PCL-P18-DS-142 June 12 ,2019 100% 0.50 0.00 0.30 0.77 0.00 0.00 1.561
Columns 6th to Mumty-2 PCL-P18-DS-284 Nov 14 ,2019 100% 0.15 0.00 0.00 0.39 0.00 0.00 0.537
Columns 6th to Pent House-3 PCL-P18-DS-143 June 13 ,2019 100% 0.26 0.00 0.00 0.69 0.00 0.00 0.953
Columns Pent House to Mumty-3 PCL-P18-DS-284 Nov 14 ,2019 100% 0.05 0.00 0.00 0.31 0.00 0.00 0.357
Ground Floor Slab-1 PCL-P18-DS-096 April 10 ,2019 100% 14.53 2.31 0.00 0.00 0.00 0.00 16.845
Ground Floor Beam-1 PCL-P18-DS-094 April 08 ,2019 100% 1.39 0.30 1.50 4.30 3.54 0.00 11.028
Ground Floor Slab-2 PCL-P18-DS-125 May 15 ,2019 100% 9.28 0.96 0.00 0.00 0.00 0.00 10.237
Ground Floor Beam-2 PCL-P18-DS-123 May 09 ,2019 100% 1.32 0.00 0.90 3.90 0.00 0.00 6.120
Ground Floor Slab-3 PCL-P18-DS-177 July 18 ,2019 100% 11.16 0.60 0.00 0.00 0.00 0.00 11.761
Ground Floor Beam-3 PCL-P18-DS-131 May 21 ,2019 100% 1.70 0.00 0.95 4.80 1.88 0.00 9.332
SQS:Khan Page 28 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:
Grade 60 Re Bars
Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight
Ist Floor Slab-1 PCL-P18-DS-116 April 30 ,2019 100% 8.08 2.48 0.00 0.00 0.00 0.00 10.563
Ist Floor Beam-1 PCL-P18-DS-117 May 2 ,2019 100% 1.03 0.00 0.33 2.54 2.70 0.00 6.592
Ist Floor Slab-2 PCL-P18-DS-159 July03 ,2019 100% 6.98 0.95 0.00 0.00 0.00 0.00 7.935
Ist Floor Beam-2 PCL-P18-DS-158 July 03 ,2019 100% 1.34 0.00 1.09 4.13 0.00 0.00 6.566
Ist Floor Slab-3 PCL-P18-DS-204 August 21 ,2019 100% 7.78 0.60 0.00 0.00 0.00 0.00 8.386
Ist Floor Beam-3 PCL-P18-DS-203 August 21 ,2019 100% 1.55 0.00 1.31 3.88 1.20 0.00 7.934
2nd Floor Slab-1 PCL-P18-DS-130 May 18 ,2019 100% 8.50 2.48 0.00 0.00 0.00 0.00 10.982
2nd Floor Beam-1 PCL-P18-DS-129 May 18 ,2019 100% 1.02 0.00 0.33 2.31 2.96 0.00 6.614
2nd Floor Slab-2 PCL-P18-DS-161 July 31 ,2019 100% 7.53 0.95 0.00 0.00 0.00 0.00 8.483
2nd Floor Beam-2 PCL-P18-DS-160 July 03 ,2019 100% 1.34 0.00 1.15 4.05 0.00 0.00 6.534
2nd Floor Slab-3 PCL-P18-DS-222 August 29, ,2019 100% 8.21 0.60 0.00 0.00 0.00 0.00 8.814
SQS:Khan Page 29 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:
Grade 60 Re Bars
Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight
2nd Floor Beam-3 PCL-P18-DS-221 August 29, ,2019 100% 1.55 0.00 1.31 3.64 1.58 0.00 8.070
3rd Floor Slab-1 PCL-P18-DS-130 May 18 ,2019 100% 8.50 2.48 0.00 0.00 0.00 0.00 10.982
3rd Floor Beam-1 PCL-P18-DS-129 May 18 ,2019 100% 1.02 0.00 0.33 2.31 2.96 0.00 6.614
3rd Floor Slab-2 PCL-P18-DS-161 July 31 ,2019 100% 7.53 0.95 0.00 0.00 0.00 0.00 8.483
3rd Floor Beam-2 PCL-P18-DS-160 July 03 ,2019 100% 1.34 0.00 1.15 4.05 0.00 0.00 6.534
3rd Floor Slab-3 PCL-P18-DS-222 August 29, ,2019 100% 8.21 0.60 0.00 0.00 0.00 0.00 8.814
3rd Floor Beam-3 PCL-P18-DS-221 August 29, ,2019 100% 1.55 0.00 1.31 3.64 1.58 0.00 8.070
4th Floor Slab-1 PCL-P18-DS-130 May 18 ,2019 100% 8.50 2.48 0.00 0.00 0.00 0.00 10.982
4th Floor Beam-1 PCL-P18-DS-129 May 18 ,2019 100% 1.02 0.00 0.33 2.31 2.96 0.00 6.614
4th Floor Slab-2 PCL-P18-DS-161 July 31 ,2019 100% 7.53 0.95 0.00 0.00 0.00 0.00 8.483
4th Floor Beam-2 PCL-P18-DS-160 July 03 ,2019 100% 1.34 0.00 1.15 4.05 0.00 0.00 6.534
SQS:Khan Page 30 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:
Grade 60 Re Bars
Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight
4th Floor Slab-3 PCL-P18-DS-222 August 29, ,2019 100% 8.21 0.60 0.00 0.00 0.00 0.00 8.814
4th Floor Beam-3 PCL-P18-DS-221 August 29, ,2019 100% 1.55 0.00 1.31 3.64 1.58 0.00 8.070
5th Floor Slab-1 PCL-P18-DS-130 May 18 ,2019 100% 8.50 2.48 0.00 0.00 0.00 0.00 10.982
5th Floor Beam-1 PCL-P18-DS-129 May 18 ,2019 100% 1.02 0.00 0.33 2.31 2.96 0.00 6.614
5th Floor Slab-2 PCL-P18-DS-161 July 31 ,2019 100% 7.53 0.95 0.00 0.00 0.00 0.00 8.483
5th Floor Beam-2 PCL-P18-DS-160 July 03 ,2019 100% 1.34 0.00 1.15 4.05 0.00 0.00 6.534
5th Floor Slab-3 PCL-P18-DS-222 August 29, ,2019 100% 8.21 0.60 0.00 0.00 0.00 0.00 8.814
5th Floor Beam-3 PCL-P18-DS-221 August 29, ,2019 100% 1.55 0.00 1.31 3.64 1.58 0.00 8.070
6th Floor Slab PCL-P18-DS-277 Nov01 ,2019 100% 22.31 3.91 0.00 0.00 0.00 0.00 26.224
6th Floor Beam PCL-P18-DS-275 Oct 29 ,2019 100% 3.82 0.18 2.93 10.65 4.83 0.00 22.407
Roof Slab PCL-P18-DS-288 Nov 26 ,2019 100% 12.09 1.85 1.43 0.00 0.00 0.00 15.365
SQS:Khan Page 31 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:
Grade 60 Re Bars
Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight
Roof Beams PCL-P18-DS-287 Nov 20 ,2019 100% 2.00 0.08 1.37 5.78 2.21 0.00 11.439
Mumty Slab PCL-P18-DS-294 Dec 06 ,2019 100% 1.06 0.00 0.00 0.00 0.00 0.00 1.056
Mumty Beam PCL-P18-DS-294 Dec 06 ,2019 100% 0.26 0.00 0.19 0.64 0.00 0.00 1.089
Lintles -
Basement PCL-P18-DS-109 April 22,19 0% 0.03 0.07 0.00 0.00 0.00 0.00 -
Ground Floor PCL-P18-DS-109 April 22,19 100% 0.58 0.87 0.00 0.04 0.00 0.00 1.482
First Floor PCL-P18-DS-109 April 22,19 100% 0.58 0.89 0.00 0.04 0.00 0.00 1.503
Seconed PCL-P18-DS-109 April 22,19 100% 0.58 0.89 0.00 0.04 0.00 0.00 1.503
Third Floor PCL-P18-DS-109 April 22,19 100% 0.58 0.89 0.00 0.04 0.00 0.00 1.503
Forth Floor PCL-P18-DS-109 April 22,19 100% 0.58 0.89 0.00 0.04 0.00 0.00 1.503
Fifth Floor PCL-P18-DS-109 April 22,19 100% 0.58 0.89 0.00 0.04 0.00 0.00 1.503
Sixth Floor PCL-P18-DS-109 April 22,19 100% 0.25 0.40 0.00 0.00 0.00 0.00 0.654
Mumty PCL-P18-DS-109 April 22,19 100% 0.01 0.02 0.00 0.00 0.00 0.00 0.031
SQS:Khan Page 32 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:
Grade 60 Re Bars
Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight
Basement Floor -2 PCL-P18-DS-109 April 22,2019 100% 0.15 0.22 0.00 0.00 0.00 0.00 0.363
Basement Floor -3 PCL-P18-DS-109 April 22,2019 100% 0.15 0.22 0.00 0.00 0.00 0.00 0.363
Ground Floor -2 PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
Ground Floor -3 PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
First Floor-2 PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
First Floor-3 PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
Seconed Floor PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
Seconed Floor PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
Third Floor PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
Third Floor PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
Forth Floor PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
SQS:Khan Page 33 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:
Grade 60 Re Bars
Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight
Forth Floor PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
Fifth Floor PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
Fifth Floor PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
Sixth Floor PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
Sixth Floor PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
Mumty PCL-P18-DS-147 June 21,2019 100% 0.14 0.25 0.00 0.00 0.00 0.00 0.387
PCL-P18-DS-300 Dec 14,2019 100% 1.48 2.68 0.00 0.00 0.00 0.00 4.159
PCL-P18-DS-227 01 Nov, 19 100% 1.03 0.00 0.00 0.00 0.00 0.00 1.028
PCL-P18-DS-300 Dec 14,, 19 100% 1.04 0.00 0.00 0.00 0.00 0.00 1.038
SQS:Khan Page 34 of 37
PROJECT NAME: Apartment Buildings at Eighteen, Islamabad
Job No. IPA# SCHED "Pavilion 6" CONTRACTOR: Principal Constructor Pvt.Ltd.
CLIENT DWG No./P/ S-01 TO 22
CONSULTANT: Prepared by: Muhammad Akram Khan
PHASE # Pavilion 7 Checked by:
Rev No. 0 Date:
Steel for Raft, Columns , Plinth Beams, Stair ,SOG Level, Slab & Beam, Retaining Wall & Shear wall, Lift Well Revised by:
Grade 60 Re Bars
Description Total Weight of Activity Wise #10 #12 #16 #20 #25 #32 Line Weight
Principal QS Checked By (Consultant) Approved By Consultant Manger
SQS:Khan Page 35 of 37
Steel Justification Pavilion-06 & 07
IPA # 5 Quantity
Steel Scrap
Total 45
Wastage % 3.15
Steel Transfer
14 Missing -0.12
Steel Justification Pavilion-04
Steel in Hand