2020 - 2021 ANSWER FOUR QUESTIONS ONLY Total Mark 100%

Q1: (a) Find the total dura on and the cri cal path of the project (15 marks)  

   Activity Duration(days) Precedence


A 5 ----
B 10 A
 C 8 A
D 4 B
E 3 B
 F 15 D&E
 G 2 F&C
(b) Graph the bar chart of the project in (a).  (10 marks)  

Q2: Give answers for the following questions with brief description. (25 marks)   

 (a)  Which is smaller : angle of repose of sand or clay? Why? 

   (b) 40 BCM , how much will be in loose for a load factor of 0.7 ?  

   (c) Which data is best : 2,11,8  or 20,110,80 ? 

 (d)  What is the effective productivity  of a machine working 55 min every hour and 
produce 200 LCM per hour? 

(e)  What is the difference between risk and hazard? give an example

Q3 (a)  Draw the LOB for an activity having 200 man.hr , 4 labors in each unit , 5 
working days in a week , 8 working hours in a day . The rate of produc on is 4 units 
per week and the total unit number is 150 .  (15 marks)
 (b)  A contractor wants to increase the capacity  of his company and needs to make 
decision according to the following data knowing that probability of high demand is 
0.70  and  that  of  low  demand  is  0.30.  Using  sensitivity  analysis  as  a  tool  ,which 
  alternative will be the best?      (10marks)                                                                                                  
 
 
 
 
 
 
Revenue
  Alternative Low  High 
  Demand   Demand
Do nothing $50000 $60000
Expand        $20000 $80000
Subcontract $40000 $70000

Q4 (a)  :  Fixed cost of a machine is $9000and variable cost is $100 / unit . The 
expected revenue is $ 170 / unit . What is the number of units to be produced to 
make this process feasible ? (15 marks)  
 (b)  Calculate the Internal Revenue Rate ( IRR) for a project whose cash flow  as in 
the figure . Is the project feasible knowing that the rate of interest is 15% ? ( 10 
marks)                                                                   

  
4000 4500 5000

 
1 2 3
 

10000$ 

Q5 (a)  :  Simulate  the breakdowns for next three months according to  data in the 
table .Use ( 18 , 77 , 90 ) as random numbers  (15marks)

  Breakdowns f
0 18
1 22
2 27
3 13

 (b)  List the major functions of the management and describe briefly? ( 10 marks)           

Examiner Head of Department