You are on page 1of 2

*X86537* Reg. No.

Question Paper Code : X86537


M.E./M.Tech. Degree Examinations, April/may 2021
Second Semester
Construction Engineering and Management
CN5201 – Advanced construction techniques
(Regulations 2017)

Time : Three Hours Maximum : 100 Marks

Answer all questions

Part – A (10×2=20 Marks)

1. Distinguish Cofferdams and Caissons ; substructure construction techniques.

2. List two factors influencing choice of sheet piles and diaphragm wall construction.

3. Mention a merit and a limitation of metal deck concrete flooring with applicability.

4. Write the merits and an application of concrete paving technology.

5. List two safety points in the erection of lattice towers.

6. Name two support structures for heavy equipment in heavy industries.

7. Differentiate between retrofitting and rehabilitation of structures.

8. Define underpinning. Mention its purpose.

9. Name two explosives used in the demolition of structures.

10. Write two advantages of using robotic machines in demolition techniques.

Part – B (5×13=65 Marks)

11. a) List the various methods of tunnel construction. Explain in detail any two
methods bringing out its salient features, applicability with merits and
limitations if any. (2+4+4+3=13)
(or)
b) List the types of shoring for deep cutting. Explain any two of its types
mentioning its features with suitability. (2+4+4+3=13)
X86537 *X86537*

12. a) Bring out the construction details of vacuum dewatering technique for concrete
flooring with merits and limitations. (5+5+3=13)
(or)
b) Compare post tensioning with in-situ prestressing in high rise structure.
Discuss any one of the two methods with details, applicability, merits and
limitations. (2+4+4+3=13)

13. a) Discuss in detail the construction sequence of sky scrapers. By what ways
they are unique from the conventional construction techniques ? Discuss.
(6+4+3=13)
(or)
b) Discuss the sequence of construction of break water structure. Mention the
special equipments and processes used in its construction. (5+5+3=13)

14. a) List the various methods of strengthening structural members. Discuss any
two methods of strengthening RCC beams and columns. Bring out the special
features of the methods. (3+4+4+2=13)
(or)
b) Give a detailed discussion on the various techniques of soil stabilization with
their features and applicability. (5+5+3=13)

15. a) A commercial complex made of framed structure is having 15 floors. It is under


heavy distress and hence has to be demolished fully. Identify and discuss the
demolition sequence with suitable justification. (2+4+4+3=13)
(or)
b) A highway bridge in the heart of a busy city is to be demolished and dismantled
due to heavy distress. Discuss the safety precautions you would undertake as
an engineer to the workers at the site and the common public. Discuss with
suitable reasoning. (2+4+4+3=13)

Part – C (1×15=15 Marks)

16. a) A tall concrete chimney is to be constructed for a thermal power plant.


Identify the technique you would recommend for its construction. Discuss its
construction details with suitability and advantages. (2+5+5+3=15)
(or)
b) A 25 storey framed structure is required to be constructed in Bangalore.
Discuss the process of handling and erecting light weight components on the
structure with precautions you should take. (5+5+5=15)