T.Y.B.Sc.

IT SEM V SPM MCQ - Unit - 2


1. RAD stands for ___________.

a. Rapid Application Development


b. Repeated Application Development
c. Ready Application Development
d. Relative Application Development

2. SDLC stands for?

a. Software Design Life Cycle


b. Software Development Life Cycle
c. System design Life Cycle
d. System Development Life Cycle

3. Waterfall Model also called as

a. Linear Sequential Model


b. Classic Life Cycle Model
c. One Shot
d. All of These

4. The Spiral Model of software development

a. Ends with the delivery of the software product


b. Is more chaotic than Incremental Model
c. Includes project risks evaluation during each stage
d. All of These

5. Evolutionary Software Process Model

a. Alternative in nature
b. Can Easily accommodate product requirement change
c. Do not generally Throw Away Approach
d. All of These

6. What are the four framework activities found in Extreme Programming (XP) process model

a. Analysis, Design ,Coding, Testing


b. Planning ,Analysis, Design ,Coding
c. Planning ,Analysis, Design ,Testing
d. Planning ,Design ,Coding, Testing

7. Important artefact for scrum methodology

a. Product Backlog
b. Sprint Backlog
c. Sprint Burndown Chart
d. All of these

For Queries / Assistance / Sharing document on Campus Orbit - email us at


campus.connect59@gmail.com or www.campusorbit.com
T.Y.B.Sc. IT SEM V SPM MCQ - Unit - 2
8. What is Pair Programming?

a. It is a programming process, wherein a programmer writes the program twice just in case.
b. A development method, where two developers work on the same workstation.
c. It is an algorithm that finds pair numbers in a set of integers.
d. It is a way of rectifying errors in programs by looking for pairs of errors.

9. Which of the following is NOT a practice of Extreme Programming?

a. Test-Driven Development
b. Small Releases
c. Shared Code and Responsibility
d. Empower Customers

10. Function count method was developed by

a. B. Boehm
b. B. Beizer
c. Alan Albrecht
d. M. halstead

11. What is related to the overall functionality of the delivered software?

a. Function-related metrics
b. Product-related metrics
c. Size-related metrics
d. LOC-related metrics

12. Which technique is applicable when other projects in the same analogy application domain have been
completed?

a. Algorithmic cost modelling


b. Expert judgement
c. Estimation by analogy
d. Parkinson’s Law

13. Which model is used during early stages of the system design after the requirements have been
established?

a. An application-composition model
b. A post-architecture model
c. A reuse model
d. An early design model

14. Which model is used to compute the effort required to integrate reusable components or program code
that is automatically generated by design or program translation tools?

a. An application-composition model
b. A post-architecture model
c. A reuse model
d. An early design model
For Queries / Assistance / Sharing document on Campus Orbit - email us at
campus.connect59@gmail.com or www.campusorbit.com
T.Y.B.Sc. IT SEM V SPM MCQ - Unit - 2

15. COCOMO-II estimation model is based on

a. Algorithm approach
b. Complex approach
c. Bottom up approach
d. Top down approach

16. Function point analysis (FPA) method decomposes the system into functional units. The total numbers
of functional units are

a. 5
b. 4
c. 3
d. 2

17. What is the meaning of Software Scope?

a. It describes the Off-the-shelf component.


b. It describes the functions and features that are to be delivered to end users.
c. It describes the software risk.
d. It describes the project risk.

18. What is the first activity in Software Project Planning?

a. Determination of software scope


b. Determination of budget
c. Find out the team size
d. Find out the program size

19. LOC Based techniques requires problem decomposition based on

a. Information Domain Values


b. Project Schedule
c. Software functions
d. Process activities

20. Process Based techniques requires problem decomposition based on

a. Information Domain Values


b. Project Schedule
c. Project cost
d. Process activities

For Queries / Assistance / Sharing document on Campus Orbit - email us at


campus.connect59@gmail.com or www.campusorbit.com

You might also like