Professional Documents
Culture Documents
where a 6-year contract has been finaliz.ed to collect and analyze ozone-level
readings. Two lease options are available, each wid1 a first cost, allllual lease cost,
and deposit-retum estimates shown below. The MARR is 15% per year.
Location A Location B
PWA = ?
$15,000
l
S!S,000
$3500
l
SIS.000
Loc:1bon.~
S2000 S2 000
1 2 9 16 17 18
•
$18,000
i
SIS.000
$3100
Loc:anonB
A quarry outside of Austin, Texas wishes to evaluate two similar pieces of equip-
ment by which the company can meet new state enviromnental requirements for
dust emissions. The MARR is 12% per year. Detennine which alternative is
economically better using (a) the AW method, and (b) AW method with a 3-year
study period.
Equipment x y
Solution
a. Calculating AW values over the respective lives indicates that Y is the bet-
ter alternative.
AWx = -40,000(A/P,12%,4) - 25,000 + 10,000(A/ F,12%,4)
= $-36,077
AWy = -75,000(A/P,12%,6) - 15,000 + 7,000(A/ F ,12%,6)
= $-32,380
b. All n values are 3 years and the "salvage values" become the estimated
market values after 3 years. Now X is economically better.
AWx = -40,000(A/P,12%,3) - 25,000 + 14,000(A/ F , 12%,3)
= $-37,505
AW1· = -75,000(A/P,12%,3) - 15,000 + 20,000(A/F,12%,3)
= $-40,299
The Army Corps of Engineers wants to construct a dam on a flood-prone river.
The estimated constmction cost and average annual dollar benefits are listed
below. A 6% per year rate applies and dam life is infinite for analysis purposes.
(a) Select the one best location using the B/C method. (b) If the sites are now
considered independent projects, which sites are acceptable?
A 6 350,000
B 8 420,000
c 3 125,000
D 10 400,000
E 5 350,000
F 11 700,000
Solution
a. The capitalized cost A = Pi is used to obtain AW values of the constmction
1 cost., as shown in the first row of Table 7.2. Since benefits are estin1ated
TABLE 7.2 Use of Incremental B/C Rat io Analysis for Example 7.5 (Values in $1000)
DN c E A B D F
directly, initial comparison with DN is necessary. For the analysis, sites are
ordered by increasing AW-of-cost values. This is DN, C, E, A, B, D, and
F. The analysis between the ordered mutually exclusive alternatives is
detailed in the lower portion of Table 7.2. Since only site E is incremen-
tally justified, it is selected.
b. The dan1 site proposals are now independent projects. The site B/C ratio is
used to select from none to all six sites. h1 Table 7.2, third row, B/C > 1.0
for sites E and F only; they are acceptable.