Proposed Project

Screening by Project Proponent


1. Is the project subject to section 34A, First and Second Schedule?
2. Is the project in line with Development Plan & Policies?

First Schedule Activities Second Schedule


(5 Weeks EIA Reviewing Activities (12 Weeks EIA
Procedure) Reviewing Procedure)

PRE-SUBMISSION
OF EIA REPORT Scoping Process
STAGE (Formulation of Terms of Reference) Ends

Revised TOR
Submission of TOR
not submitted

EIATRC TOR Revised,


TORAC
No Re-submitted in
time
MEETING
(TRC, AIs, Gas)

Yes
If Conformed
Submission of EIA Report Submission of EIA Report

EIA
TRC Report
TRC RAC
RAC
Rejected
Rejected
DURING
Yes
SUBMISSION
OF EIA REPORT Public Display
STAGE

No EIATRC EIATRC
REVIEW Approved REVIEW
MEETING MEETING
(TRC, AIs & (TRC, AIs & No
GAs) AND Yes GAs)
DECISION AND
MAKING(ST DECISION
ATE MAKING(DG)
DIRECTOR
Notes:
OR DG)
Approved With Conditions TRC : DOE Technical Review Committee
(Team of DOE officers at DOE State or
Headquarters)
- Submission of EMP TORAC: Terms Of Reference Adequacy Check
- Presentation of COA RAC: Report Adequacy Check
POST Execution Plan EIATRC: EIA Technical Review Committee at
SUBMISSION DOE State or Headquarters
OF EIA REPORT GAs: Government Agencies
STAGE AIs: Appointed Individuals on case by case
-Compliance Monitoring (CM) basis and may include Non-Governmental
-Impact Monitoring (IM) Organization (NGOs)
-Performance Monitoring (PM)
rd
-3 Party Audit

Figure 1.1 General Overview of EIA Procedure in Malaysia